ITEM INFORMATION
ITEM No.
1
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATE: 06/15/15
AGENDA ITLW TITLE 2015 Annual Overlay & Repair Program
Construction Management Supplement No. 1 with KPG, Inc.
CATEGORY ❑ Discussion
AN Dale
l /
Motion
Date 06/15/15
❑ Resolution
RI1,g Date
• Ordinance
❑ Bid Award
AI/gage
❑ Public Hearing
AN Date
❑ Other
Mtg Date
I A•Itg
Mtg Date
SPONSOR ❑ Council • Major ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police • PTV
SPONSOR'S KPG, Inc. is currently the design consultant for the 2015 Annual Overlay & Repair Program
SUMMARY with Contract No. 14-157. Three engineering firms were evaluated for construction
management services and KPG was chosen as the most qualified. The construction bid
opening was 6 /3 /15 and will be forthcoming. Council is being asked to approve
Supplemental Agreement No. 1 to Contract No. 14 -157 with KPG for construction
management services in the amount of $172,658.89.
REVIEWED BY ❑ COW Mtg. ❑ CA &P Cmte
❑ Utilities Cmte ❑ Arts Comm,
DATE: 06/01/15
❑ F &S Cmte
Comm.
CHAIR: ]OE
►1 Transportation
Cmte
• Parks
Planning Comm.
COMIVII1'I'EE
DUFFIE
RECOMMENDATIONS:
SPONSOR /ADMIN.
COMMITTEE
Public Works Department
unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$172,658.89 $175,000.00 $0.00
Fund Source: 104 ARTERIAL STREETS (PG 18, 2014 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
06/15/15
MTG. DATE
ATTACHMENTS
06/15/15
Informational Memorandum dated 05/29/15
Consultant Selection Scoring Matrix
Vicinity Map
Page 18, 2015 CIP
Contract, Scope of Work, and Fee Estimate
Minutes from the Transportation Committee meeting of 06/01/15
1
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
TO: Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
BY: David Sorensen, Project Manager
DATE: May 29, 2015
SUBJECT: 2015 Overlay and Repair Program
Project No. 91510401, Contract No. 14 -157
Supplement No. 1 for Construction Management Services
ISSUE
Execute Supplement No. 1 with KPG, Inc. to provide construction management services for the 2015
Overlay and Repair Program.
BACKGROUND
Three (3) engineering firms were evaluated to provide construction management services for the
City's 2015 Overlay and Repair Program (see attached scoring and selection matrix). Each consulting
firm provides services with expertise in multiple engineering disciplines. All of the firms are qualified,
however KPG, Inc. possesses a knowledge and understanding of the City's program that provides
efficiency and benefits which cannot be matched at this time by any other firm. KPG, Inc. has
prepared preliminary plans for several of the project segments as part of the 2014 Overlay and Repair
Program and has also performed very well on previous City projects, including the preliminary design
of the 2015 Overlay and Repair Program. The selection of a consultant to provide these services will
continue to be evaluated annually as a consultant's staffing and expertise changes over time.
DISCUSSION
KPG, Inc. has provided a Supplement, scope of work, and fee estimate for construction management
services for the 2015 Overlay and Repair Program for $172,658.89. Construction bid opening is
scheduled for June 3, 2015.
FISCAL IMPACT
Sup No. 1 CM Budget
Construction Management Sup No. 1 $ 172,658.89 S 175,QQ0.00
RECOMMENDATION
Council is being asked to approve Supplement No. 1 to Contract 14 -157 for construction management
services with KPG, Inc. for the 2015 Overlay and Repair Program in the amount of $172,658.89 and
consider this item on the Consent Agenda at the June 15, 2015 Regular Meeting.
Attachments: Consultant Selection Scoring Matrix
Vicinity Map
Page 18, 2015 CIP
Contract, Scope of Work and Fee Estimate
W:WW Enq,PROJECTSVk- RW & RS Prei ce Aa ual Overlay 8 Repair Prograna2015 Overlay 8 Repair Pregrarn,Canslruclion ManagemenrAocs to TC
3
4
2{}15 Overlay Program — Contract tor Construction Management
Services
DEA Associate
d
c
0
3..
CH2M Hill, Inc.
Paving project design/ constuction experience.
2
5
3
Current Knowledge olf`FHWA, State, and Tukwila Standards and Procedures
2
4
3
Environmental Experience
2
2
2
Experience with similar federal aid projects?
2
3
3
Past Postive Experience on City Paving Projects
1
5
0
Small Scale Projects
3
4
2
Utilities Coordination
2
4
3
Coniruction Inspection
1
5
4
TOTALS
15
32
20
For each category, highest score is 5 (with the lowest or worst score 1)
Consultant with the highest score is ranked the best.
Staff: Dave Sorensen
Selection Date: 5/1/15
Selected Consultant: KPG, Inc.
'Selection Justification: This firm has demonstrated relevant pavement project design
experience including exceptional familiarity with WSDOTI FHWA standards, and a
solid DBE approach and commitment. And has performed well on previous city overlay
projects in providing design and CM services. Based on overall score KPG prevailed.
01
J
r ■r
S. BOEING ACCESS RD.
S. 124111 ST.
GATEWAY DR.
LEEL
w
emiopro
Ili
NriVit
FORT DENT PARK
SOUTHC N1ER BLVD
TUKWILA PARKWAY
ANDOVER PARK W.
2015 Overlay Program
Vicinity Map
7
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2015 to 2020
PROJECT: Annual Overlay and Repair Program Project No. 91310401
DESCRIPTION: Select, design and construct asphalt and concrete pavement overlays of arterial and residential streets,
JUSTIFICATION:
STATUS:
MAt NT. IMPACT:
COMMENT:
Preserve and maintain the street structure in a safe and useable state by resurfacing before failure which also
minimizes costs. Some individual sites may be coordinated with water, sewer, and surface water projects.
Each year various sect.ons of roadway throughout the City are designed and constructed for asphalt overlay.
Reduces annual maintenance.
Ongoing project. Only one year actuals shown in first column.
FINANCIAL Through Estimated
in $000's
2013 2014 2015
2016
2017
2018
2019
2020
BEYOND TOTAL
EXPENSES
Design
48
100
125
125
150
150
175
175
175
1,223
Land (RAM
0
Canst. Mgmt,
175
175
175
200
20D
225
225
230
1,605
Construction
1,125
1,250
1,260
1,300
1,320
1,325
1,330
1,340
10,250
TOTAL EXPENSES
48
1,400
1,550
1,560
1,650
1,670
1,725
1,730
1,745
13,078
FUND SOURCES
Awarded Grant
0
Proposed Grant
0
Mitigation Actual
0
Mitigation Expected
0
City Oper. Revenue
48
1,400
1,550
1,560
1,650
1,670
1,725
1,730
1,745
13.078
TOTAL SOURCES
48
1,400
1,550
1,560
1,650
1,670
1,725
1,730
1,745
13,078
2015 - 2020 Capital Improvement Program
18
9
SUPPLEMENTAL AGREEMENT NO. 1
AGREEMENT NO. 14 -157
PROJECT No. 91510401
City of Tukwila
Public Works Department
6300 Southcenter Boulevard #100
Tukwila, WA 98188
KPG, Inc.
753 - 9th Avenue N.
Seattle, WA 98109
PROJECT: 2015 Overlay Program — Construction Services
This SUPPLEMENTAL AGREEMENT NO. 1 is to supplement the agreement entered into with KPG,
Inc. and the City of Tukwila, which was executed on the 9th day of October, 2014.
All provisions in the basic agreement remain in effect, except as expressly modified as follows:
Article 2, Scope of Services, shall be supplemented with the following:
The Consultant agrees to provide construction services in accordance with the scope of work included as
Exhibit A.
Article 4, Payment, shall be modified as follows:
Payment for work provided by Consultant shall be made as provided on Exhibit B, attached hereto,
provided that the total amount of payment to the Consultant for this work not exceed $172,658.89 without
express written modification of the Agreement signed by the City. The new total contract shall not exceed
$309, 386.71 without express written modification of the Agreement signed by the City.
IN WITNESS WHEREOF, the parties hereto have set their hands and seals this day
of , 2015.
APPROVED: APPROVED:
CITY OF TUKWILA KPG, INC.
Jim Haggerton
Mayor
Attested:
Christy O'Flaherty, City Clerk
Nelson Davis, P.E.
Principal
11
EXHIBIT A-1
Construction Management Services
Scope of Work
May 15, 2015
City of Tukwila — 2015 Overlay Program
This work will provide construction management services for the construction contract to complete the
City of Tukwila — 2015 Overlay Program. These services will include design support, project
management, documentation control, inspection, materials testing, public involvement, and contract
administration during the construction of the project, as detailed below. KPG ( "Consultant ") will provide
to the City of Pacific ( "City ") construction management services for the project.
A detailed scope for the Contract follows:
I. INTRODUCTION
The following scope of services and associated costs are based upon the assumptions outlined below.
General Assumptions:
• The proposed project team will include one full -time documentation control specialist, a part -
time resident engineer during construction activities, one full -time inspector for each location
during construction activities where unit price work is being performed, sub - consultants
to provide services for materials testing, and other supporting tasks as deemed necessary. It is
anticipated that full- time site observation will be required for the entire of the project.
• The level of service is based on a construction project duration of approximately 60 calendar
days.
• KPG estimates a total project duration of 98 calendar days (14 weeks) including preconstruction
service, construction services, and project closeout. No suspensions or stop work periods are
anticipated during this duration.
• It is anticipated that the KPG will develop the Record of Materials (ROM). This scope of services
provides the management of the ROM and scheduling of required materials testing respectively.
• It is anticipated that the City will review and execute the insurance, bonds, and the Construction
Contract.
1. KPG will do all public outreach, and ensure affected business and residents are notified of
impending contractor activities one week prior to work by door to door and or A -board signs that
include date, hours of work, and a KPG staff phone number to call for questions.
• The design engineers from KPG will be available during construction to answer questions during
construction and review RAM's, shop drawings, and answer RFI's that require a level of
engineering expertise outside of the capabilities of the Consultant.
City of Tukwila —2015 Overlay Program Page 1 of 7 KPG
Construction ManagementServices Project Number 14117
Scope of Work 5/10/15
12
EXHIBIT A -1
• Services will be performed in accordance with the Contract plans & special provisions, and City
of Pacific engineering standards.
II. SCOPE OF WORK
The objective and purpose of this Construction Management Services Agreement is for the Consultant
to successfully deliver the construction of the Project to the City by ensuring that the improvements are
constructed in accordance with the approved Plans and Specifications, as may be amended or revised,
that all of the required Project documentation is accounted for.
TASK 1— MANAGEMENT /COORDINATION /ADMINISTRATION
Provide overall project management, coordination with the City, monthly progress reports, and
invoicing. This effort will include the following elements.
• Organize and layout work for project staff. Prepare project instructions on contract
administration procedures to be used during construction.
• Review monthly expenditures and CM team scope activities. Prepare and submit project
progress letters to the City along with invoices describing CM services provided each month.
Prepare and submit reporting required by funding source(s), if any.
Deliverables
• Monthly invoices and progress reports
TASK 2 - PRECONSTRUCTION SERVICES
2.1 Preconstruction Conference: The Consultant will prepare an agenda for, distribute notices of,
and conduct a preconstruction conference in the City's offices. The Consultant's project
manager, resident engineer, inspector, and document control specialist will attend the
preconstruction conference. The Consultant will prepare a written record of the meeting and
distribute copies of the minutes to all attendees and affected agencies, staff, etc.
At the Pre - construction conference, the Consultant shall facilitate discussions with the
Contractor concerning the plans, specifications, schedules, issues with utilities, unusual
conditions, Federal, State, and local requirements and any other items that will result in better
project understanding among the parties involved.
Deliverables
• Preconstruction conference agenda with meeting minutes
TASK 3 — CONSTRUCTION SERVICES - FIELD
3.1 On -site Observation: The Consultant shall provide the services of one full time inspector
p e r l o c a t i o n during construction activities and other tasks necessary to monitor the
progress of the work. An additional part time junior inspector, to be approved by the City,
may be incorporated as dictated by the Contractor's approach to the Work. Construction
staff shall oversee the following items of work, on the
City of Tukwila —2015 Overlay Program
Construction Management Services
Scope of Work
Page 2 of 7
KPG
Project Number 14117
5/10/15
13
EXHIBIT A -1
project site, and will observe the technical progress of the construction, including providing
day -to -day contact with the Contractor and the City:
o Preparation to include mobilization, clearing and grubbing, removal of structures
o Grading, installation of drainage and storm sewer
o Erosion Control and Planting
o HMA grinding and paving
o Driveways, curb, gutter and sidewalk
o And all incidental items necessary to complete the Work as described in the Plans
and /or Specifications.
Field inspection staff will perform the following duties as a matter of their daily activities:
Observe technical conduct of the construction, including providing day -to -day contact
with construction contractor, City, utilities, and other stakeholders, and monitor for
adherence to the Contract Documents. The Consultant's personnel will act in
accordance with Sections 1 -05.1 and 1 -05.2 of the Standard Specifications.
ii. Observe material, workmanship, and construction areas for compliance with the
Contract Documents and applicable codes, and notify construction contractor of
noncompliance. Advise the City of any non - conforming work observed during site visits.
Document all material delivered to the job site in accordance with the contract
documents.
iv. Prepare daily inspection reports, recording the construction contractor's operations as
actually observed by the Consultant; includes quantities of work placed that day,
contractor's equipment and crews, and other pertinent information.
v. Interpret Contract Documents in coordination with the City and KPG.
vi. Resolve questions which may arise as to the quality and acceptability of material
furnished, work performed, and rate of progress of work performed by the construction
contractor.
vii. Establish communications with adjacent property owners. Respond to questions from
property owners and the general public.
viii. Coordinate with permit holders on the Project to monitor compliance with approved
permits, if applicable.
ix. Prepare field records and documents to help assure the Project is administered in
accordance with the funding requirements.
x. Collect and calculate delivery tickets and salesman's daily reports of aggregate. All
tickets will be initialed with correct bid item and stationing identified (Construction
Manual 10 -2).
xi. Attend and actively participate in regular on -site weekly construction meetings.
xii. Take periodic digital photographs during the course of construction, and record
locations.
City of Tukwila — 2015 Overlay Program
Construction Management Services
Scope of Work
14
Page 3 of 7
KPG
Project Number 14117
5/10/15
EXHIBIT A-1
xiii. Coordinate with the City's maintenance personnel.
xiv. Punch list. Upon substantial completion of work, coordinate with the Client and
affected agencies, to prepare a 'punch list' of items to be completed or corrected.
Coordinate final inspection with those agencies.
Assumptions:
• Consultant will provide observation services for the days /hours that the contractor's
personnel are on -site.
• The Consultant's monitoring of the construction contractor's activities is to ascertain
whether or not they are performing the work in accordance with the Contract Documents;
in case of noncompliance, Consultant will reject non - conforming work, and pursue the
other remedies in the interests of the City, as detailed in the Contract Documents. The
Consultant cannot guarantee the construction contractors' performance, and it is
understood that Consultant shall assume no responsibility for: proper construction means,
methods, techniques; project site safety, safety precautions or programs; or for the failure
of any other entity to perform its work in accordance with laws, contracts, regulations, or
City's expectations.
3.2 Substantial Completion: Upon substantial completion of work, coordinate with the City and
other affected agencies, to perform a project inspection and develop a comprehensive list of
deficiencies or 'punchlist' of items to be completed. A punchlist and Certificate of Substantial
Completion will be prepared by the Consultant and issued by the City.
3.3 Materials Testing: Coordinate the work of the materials testing technicians and testing
laboratories in the observation and testing of materials used in the construction; document
and evaluate results of testing; and address deficiencies. Frequency of testing shall be
determined by the resident engineer.
Deliverables
• Daily Construction Reports with project photos — submitted on a weekly basis
• Punch List, Certificate of Substantial Completion
• Review test reports for compliance
TASK 4.1— CONSTRUCTION SERVICES — OFFICE
City of Tukwila —2015 Overlay Program
Construction Management Services
Scope of Work
Page 4 of 7
KPG
Project Number 14117
5/10/15
15
EXHIBIT A -1
A. Document Control. Original documentation will be housed at the Consultant's office, and
filed in accordance with standard filing protocol. A copy of working files will be maintained in
the field office.
Document Control consists of:
• Final Estimate (Approving Authority File)
• Comparison of Preliminary and Final Quantities (Approving Authority File)
• Final Records (Approving Authority File)
• Record of Material Samples and Tests
• Affidavit of Wages Paid
• Release for the Protection of Property Owners and General Contractor
B. Project Coordination: Liaison with City, construction contractor, engineer, utilities and
property owners on a regular basis to discuss project issues and status.
C. Plan Interpretations: Provide technical interpretations of the drawings, specifications, and
contract documents, and evaluate requested deviations from the approved design or
specifications. Coordinate with City for resolution of issues involving scope, schedule, and /or
budget changes.
D. Weekly Meetings: Lead weekly meetings, including preparation of agenda, meeting minutes,
and distribution of minutes to attendees. Outstanding issues to be tracked on a weekly basis.
E. Initial Schedule Review: Perform detailed schedule review of contractor provided CPM for
conformance with the contract documents.
F. Lump Sum Breakdown: Evaluate construction contractors' Schedule of Values for lump sum
items. Review the Contract Price allocations and verify that such allocations are made in
accordance with the requirements of the Contract Documents. Lump Sum Breakdowns for
payment each month will be calculated with detailed data.
G. Monthly Pay Requests: Prepare monthly requests for payment, review with the City,
contractor and approve as permitted. Utilize City provided format for pay estimates, or
Consultant format.
H. Monthly Schedule Review: At the monthly cutoff, review contractor's updated schedule and
compare with field - observed progress, as described in Section 1 -08 of the Special Provisions.
In addition, perform schedule analysis on contractor provided CPM updates and review
schedule for delays and impacts. Coordinate with Contractor in the development of recovery
schedules, as needed, to address delays caused by either events or issues within the
Contractor's control or other events or issues beyond the Contractor's control.
I. Certified Payroll: Process and track all certified payroll per State Prevailing Wage
Requirements. This includes verifying the initial payroll for compliance and 10% of all payrolls
submitted thereafter. Tracking payroll each week.
J. Weekly Statement of Working Days: Prepare and issue weekly statement of working day
report each week.
K. Subcontractor Documentation: Process / Approve all required subcontractor documentation.
Request to Sublets will be verified and logged. This includes checking System Award
Management System (SAMS), verifying business licensing, reviewing insurance
City of Tukwila — 2015 Overlay Program
Construction Management Services
Scope of Work
16
Page 5 of 7
KPG
Project Number 14117
5/10/15
EXHIBIT A -1
documentation, verifying city business licensing, Intent to Pay Prevailing Wage and Affidavit of
Wages Paid. All subcontractor documentation will be logged into KPG's subcontractor logs.
L. Record Drawings: Review record drawings prepared by the Contractor, and prepare a
conformed set of project record drawings based on Contractor provided information and from
inspection notes. Record drawings to be verified on a monthly basis, as part of the progress
payment to the Contractor. Upon project completion, contractor provided markups will be
verified for completeness and supplemented with inspection information. The Consultant will
provide the marked up plan sheets with both the contractors and inspectors as -built
information. Revisions to the CAD drawings are not included
M. Physical Completion Letter: Following completion of all punchlist work, prepare physical
completion letter to the contractor, and recommend that City and /or Utilities accept the
project.
N. Project Closeout: Transfer all project documents to the City for permanent storage.
• Schedule review comments
• As -built schedule
• Meeting agendas and notes
• Monthly Pay Estimates
• Subcontractor Packets
• Cost Projection
• Physical Completion Letter
• Final Project Documents
TASK 4.2 — SUBMITTAL/RFI PROCESSING
A. Submittals: Coordinate review process for shop drawings, samples, traffic control plans, test
reports, and other submittals from the Contractor for compliance with the contract documents.
Key submittals to be transmitted to the City for their review and approval. Submittals shall be
logged and tracked.
B. Request for Information (RFI): Review and respond to RFI's. RFI's shall be logged and tracked.
C. Record of Materials (ROM): Utilize ROM prepared by KPG and update based on Special
Provisions and Plans for use on the project, based on the contract specifications. The ROM will be
maintained by the Resident Engineer. The ROM will track all of the materials delivered to the site
including manufacturer /supplier, approved RAM's, QPL items, material compliance
documentation, and all other required documentation.
Deliverables
• Submittal log
• RFI Log
• Completed Record of Material for Material Certification
TASK 4.3 — CHANGE MANAGEMENT
A. Case Log: Develop and maintain a case log which includes change orders, RFP's, Field Work
Directives
City of Tukwila —2015 Overlay Program
Construction Management Services
Scope of Work
Page 6 of 7
KPG
Project Number 14117
5/10/15
17
EXHIBIT A-1
. Change Orders: Develop change orders and provide technical assistance to negotiate change
orders, and assist in resolution of disputes which may occur during the course of the project. Each
change order will be executed in accordance with WSDOT Standard Specifications and contain the
following:
• Change order
• Independent Cost Estimate
• Time Impact Analysis
• Contractor's Pricing
• Verbal Approval Memo
• Back up documentation
C. Field Work Directives: Prepare field work directives as necessary to keep the contractor on
schedule.
D. Minor Change Orders: Develop minor change orders per WSDOT Standard Specifications. Each
minor change order will be executed and contain the following:
• Independent Cost Estimate
• Verbal Approval Memo
• Back up documentation
E. Force Account: Track contractor force account labor, equipment and materials. All force account
calculations will be verified by the engineer and double checked by the documentation specialist.
Deliverables
• Change Order(s)
• Case Management Log
• RFI Log
• Minor Change Order(s)
• Force Account Records
City of Tukwila —2015 Overlay Program
Construction Management Services
Scope of Work
18
Page 7 of 7
KPG
Project Number 14117
5/10/15
HOUR AND FEE ESTIMATE
Project City of Tukwila
2015 Overlay Program
Construction Services
EXHIBIT B
f Arch acceurc i
Lan dac:..pe Archlteuure
✓ e Yet Engineering 4
Task
Description
Labor Hour Estimate
Project
Manager
Senior ' Project Design CAO Const b. Const
Engineer I Engineer i Engineer Technician, Inspector ; Inspector
(night)
3 130.751$ 139.13[$ 13076$ 94.29
81.72 13 106.13
3 121.20
Senior I Senior Survey Document Office
Const lnsp I Const Insp Crew Specialist Admin
(night
$ 130.75 1 $ 143.82 1 3 132.71 3 71.65 5 70.39
Total Budget
Budget
1 - Management, Coordination, Administration
Weekly level of effort by Classification
Estimated duration 16 weeks
0 0
0 0
2
Preconstruction Budget Mims
16
32 $ 4,344.50
2 - Preconstructlon Services (Estimated duration 3 weeks)
Weekly level al effect by Classification
0
0
15
0 0
a
16
0
0
10
2
Preconstructian Budget Estimate
0
0
48
0
0
0
0
40
0
30
6 $ 15,123.33
3 - Construction Services (Estimated duration 9 weeks)
Weekly Jevel al effort by Classification
0 0
16
0 0
25
4
30
10
O 16
6
Construction Period Budget Estimate
0
144
0
0
225
35
270
O
144 54 S 109,682.36
4 - Closeout/Record Dwg Services {Estimated duration 4 weeks)
Weekly level of effort by Classification 0 0
4
0 0 1 8
0
O 16
2
Closeout t Record Dwg Budget Estimate
0
0
16
0
20
0
32 _
0
0
64 8 5 13,056.71
Subtotal - Labor
0
0 224 0 20 225 35 1 350 90 0 238 100 . $ 142,408.89
Reimbursables & Subconsutiants
Material Testing Allowance $
Constr1Jction Vehicle (3 months .' $750) $
Miscellaneous - Mileage, Repro. Field Supplies $
25,000.00
2,250.00
3,000.00
Subtotal - Reimbursables
30,250,00
Total Project Budget
17 2,658.66
5/2612015
20
TRANSPORTATION COMMITTEE
Meeting Minutes
June 1, 2015— 5:15 p.m. -- Foster Conference Room, 6300 Building
City of Tukwila
Transportation Committee
PRESENT
Councilmembers: Joe Duffle, Chair; Allan Ekberg, Kathy Hougardy
Staff: David Cline, Robin Tischmak, Michael Ronda, David Sorensen, Maggie Lubov,
Peter Lau, Cyndy Knighton, Gail Labanara, Laurel Humphrey
CALL TO ORDER: Committee Chair Duffle called the meeting to order at 5:15 p.m.
I. PRESENTATIONS
II. BUSINESS AGENDA
A. Grant Acceptance: Commute Trip Reduction (CTR)
Staff is seeking Council approval to accept three grant awards relating to Transportation Demand
Management (TDM) programs. A revised informational merno was distributed to the Committee to
correct the funding level of grant no. 2.
$186,334.64 in Federal funds administered by Washington State Department of
Transportation (WSDOT) for trip reduction efforts in Tukwila's regional growth center.
$270,000.00 in Federal funds administered by WSDOT for expansion of trip reduction efforts
in South King County.
$74,500 funding renewal for the current TDM allocation for the 2015 -2017 biennium.
The first two grants are part of WSDQT's effort to reduce greenhouse gas emissions by awarding
Federal Congestion Mitigation and Air Quality Improvement (CMAQ) grants for projects in urban
growth centers and corridors. The projects propose to enhance and expand trip reduction strategies
such as online tools, trainings and incentives. Funding from the grants will completely cover costs for
one position along with marketing and material expenses. The third grant is a renewal of WSDOT
funds for the existing CTR program in the City, in place since 1991. No matching funds are required
for any of the grants.
The Committee asked clarifying questions and felt that a program overview would be helpful to the
full Council prior to considering the grant awards. NO DECISION. FORWARD TO JUNE 8, 2015
COMMITTEE OF THE WHOLE.
B. Supplemental Agreement: 2015 Overlay and Repair Program
Staff is seeking. Council approval of Supplemental Agreement No. 1 in the amount of $172,658.89
with KPG; Inc. for construction management services for the 2015 Overlay and Repair Program. The
base contract No. 14 -157 was for design services for this project. KPG was selected from a pool of
three firms for their expertise and experience in Tukwila. The bid for construction is scheduled to be
opened on June 3. 2015 and the results will be presented at the next Transportation Committee
meeting. UNANIMOUS APPROVAL. FORWARD TO JUNE 15, 2015 REGULAR CONSENT
AGENDA.