HomeMy WebLinkAboutReg 2015-06-15 Item 5A - Resolution - 2016-2021 Transportation Improvement Program COUNCIL AGENDA SYNOPSIS
-------- ------- ---------Initials--------------------------------- ITEM NO.
Meeting Date Prepared by Ma orlf review Cou cil eview
06/08/15 BG C
06/15/15 BG ' V� 5.A.
1117 ,ITEM INFORMATION
CAS NUMBER: STAFF SPONSOR: BOB GIBERSON ORIGINALAGENDA DATE: 6/08/15
AGENDA ITEM TITLE Resolution adopting the Six-Year Transportation Improvement Program 2016 - 2021
CATEGORY ® Discussion ❑Motion ® Resolution ❑ Ordinance ❑ Bid Award ®Public Hearing ❑ Other
Mtg Date 06108115 Mtg Date Mtg Date 06115115 Mtg Date Mtg Date Mtg Date 06108115 Mtg Date
SPONSOR ❑ Council ❑Mayor ❑Adm Svcs ❑ DCD ❑Finance ❑Fire ❑Legal ❑ P&R ❑ Police ❑PW
SPONSOR'S The Transportation Improvement Program (TIP) is required by the RCW to be updated
SUMMARY annually. The TIP is primarily a finanical planning document for projects competing for
federal and state grants. A Public Hearing is scheduled on June 8, 2015 for the 2016 - 2021
Transportation Improvement Program. After the Public Hearing, the TIP is adopted by City
Resolution and is then incorporated into the Regional and State TIPs.
REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte ®Transportation Cmte
❑ Utilities Cmte ❑Arts Comm. ❑Parks Comm. ❑ Planning Comm.
DATE: 6/01/15 COMMITTEE CHAIR: JOE DUFFIE
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMITTEE Unanimous Approval; Forward to Committee of the Whole
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE RECORD OF COUNCIL ACTION
6/08/15 Forward to the next Regular Meeting
6/15/15
MTG. DATE ATTACHMENTS
6/08/15 Informational Memorandum dated 05/29/15 (revised after 6/1 TC)
Draft Resolution
Draft 2016— 2021 TIP Spreadsheet
Current Adopted 2015— 2020 TIP
Minutes from the Transportation Committee meeting of 06/01/15
6/15/15 Updated summary sheet & legend for the TIP codes as requested at 6/8 C.O.W.
Resolution in final form
81
82
DRAFT 2016 - 2021 TIP SUMMARY
2016 -2021 2015 CIP Project Costs in Thousands of Dollars
TIP
PROJECT TITLE
June 10, 2015
FUNDING SOURCES
Page No. 2016 2017 2018 2019 2020 2021 TOTAL Federal State/TIB Developer Unsecured City
1 42 -42nd Ave S (S 160 St - S 131 PI)
2 53rd Ave S (S 137th St - S 144th St)
3 ADA Improvements
4 APE /Industry Dr Intersection
5 APE /Minkler Blvd Intersection
6 Annual Bridge Inspections and Repairs
7 Annual Overlay and Repair Program
8 Beacon Ave Bridge Preventative Maintenance
9 BNSF Regional Center Access
10 Boeing Access Rd Bridge Rehabilitation
11 Cascade View Safe Routes to School Phase 2
12 Frank Zepp Bridge Preventative Maintenance
13 Grady Way Bridge Preventative Maintenance
14 Multipurpose Trails
15 S 133 St /SR599 Intersection
16 S 144th St Bridge Sidewalks
17 Strander Blvd /SW 27th St St Phase III
18 TUC /TOD Pedestrian Improvements
19 TUC - Pedestrian /Bicycle Bridge
20 Walk & Roll Program
21 West Valley Highway
22 W Valley Hwy/ S 156 St Intersection
2
6
20
25
24
10
18
13
11
3
35
27
28
29
12
22
26
5,300
3,173
63
0
0
270
1,560
1,741
0
5,411
0
2,535
207
60
0
0
20
70
6,185
0
0
0
0
920
63
0
0
270
1,650
0
0
0
0
0
0
60
0
0
0
0
0
0
0
0
0
0
63
0
0
335
1,670
0
0
0
0
0
0
60
0
0
5,000
0
0
0
0
0
0
0
63
0
0
335
1,725
0
0
0
0
0
0
60
0
0
0
0
0
0
0
0
0
0
63
0
0
335
1,730
0
0
0
0
0
0
60
0
0
0
0
0
0
0
0
4360
0
63
575
622
335
1,745
0
0
0
839
0
0
280
630
1,219
52,329
1,100
0
175
630
1,032
9,660
4,093
378
575
622
1,880
10,080
1,741 1,741
0
5,411 4,193
839
2,535 2,535
207 207
580
630
1,219
57,349
1,170
6,185
175
630
1,032
580
6,000
2,939
9,660
1,154
378
575
622
1,880
10,080
0
0
1,218
750 89
0
0
0
170
1,219
28,024
650
185
175
630
592
460
29,325
20 500
440
TOTAL
PROJECTS REVISED FROM 2015 -2020 TIP
New:
42 -42nd Ave S (S 160 St - S 131 PI)
Beacon Ave Bridge Preventative Maintenance
Frank Zepp Bridge Preventative Maintenance
Grady Way Bridge Preventative Maintenance
26,595
2,963 7,128
2,183 2,188 65,934 106,991 8,676 6,580
20 34,414 57,301
Deleted:
E Marginal Way (BAR - S 112 St)
Study on the project to design and construct curb, gutter, drainage, lighting, turn lanes, and traffic control has determined
no additional capacity is necessary and only typical frontage requirements required with redevelopment will be needed.
Macadam Rd & S 144 St Intersection
Project to design and construct a northbound left turn lane from Macadam to S 144th Street has been studied and
determined to no longer be necessary.
S 144th St Phase II (42 Ave S - TIB)
Project to design and construct curb, gutter, sidewalk, bike lanes, pavement restoration, illumination, drainage,new
signal at 42nd Ave S and new pedestrian rapid flash beacon in conjuction with Tukwila Village will be completed.
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -07745
40 -42 Ave S (S 160 St - S 131 PL)
S 160th Street to Southcenter Blvd
Design and construct street improvements, drainage, sidewalks, bike facilities, and
driveway adjustments
06/08/15
06/15/15
04
C G O P S
TW
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
0
0
5,300,000
5,300,000
P
CN
2021
0
0
4,360,000
4,360,000
Totals
0
0
9,660,000
9,660,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
5,300,000
0
0
0
4,360,000
Totals
5,300,000
0
0
0
4,360,000
Report Date: June 02, 2015
Page 1
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -06601
53rd Avenue S
S 137th St to S 144th St
Design and construct urban residential street improvements that include curb, gutter,
sidewalk , illumination and undergrounding. Street portion will coordinate with Water,
Surface Water and Sewer capital improvement program projects.
06/08/15
06/15/15
04
C G O P S
TW
0.420
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2016
0
0
3,000
3,000
P
CN
2016
0
TIB
1,589,000
1,350,000
2,939,000
S
CN
2016
0
0
1,151,000
1,151,000
Totals
0
1,589,000
2,504,000
4,093,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
3,000
0
0
0
0
CN
3,170,000
920,000
0
0
0
Totals
3,173,000
920,000
0
0
0
Report Date: June 10, 2015
Page 2
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -05405
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
06/08/15
06/15/15
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2016
0
0
378,000
378,000
Totals
0
0
378,000
378,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
63,000
63,000
63,000
63,000
126,000
Totals
63,000
63,000
63,000
63,000
126,000
Report Date: June 02, 2015
Page 3
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03766
Andover Park E /Industry Drive Signal
Andover Park E
Industry Drive to
Design and construct a traffic signal and intersection improvements
06/08/15
06/15/15
05
C G O P S
TW
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
CN
2021
0
0
575,000
575,000
Totals
0
0
575,000
575,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
0
0
0
0
575,000
Totals
0
0
0
0
575,000
Report Date: June 02, 2015
Page 4
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -07746
Andover Park E /Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
06/08/15
06/15/15
03
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
0
20,000
20,000
P
CN
2021
0
0
602,000
602,000
Totals
0
0
622,000
622,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
20,000
CN
0
0
0
0
602,000
Totals
0
0
0
0
622,000
Report Date: June 02, 2015
Page 5
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03731
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi- annual inspections as well as construct necessary
repairs and maintenance
06/08/15
06/15/15
06
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2016
0
0
1,880,000
1,880,000
Totals
0
0
1,880,000
1,880,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
270,000
270,000
335,000
335,000
670,000
Totals
270,000
270,000
335,000
335,000
670,000
Report Date: June 02, 2015
Page 6
0
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -03733
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
06/08/15
06/15/15
06
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2016
0
0
10,080,000
10,080,000
Totals
0
0
10,080,000
10,080,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
1,560,000
1,650,000
1,670,000
1,725,000
3,475,000
Totals
1,560,000
1,650,000
1,670,000
1,725,000
3,475,000
Report Date: June 02, 2015
Page 7
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
TUK -57
Beacon Ave S Bridge Preventative Maintenance Project
Beacon Avenue South over South Ryan Way
S Victor St to S 170th St
Remove and replace failed bridge deck and paint structural steel.
06/08/15
06/15/15
14
0.010
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
STP(BR)
1,740,900
0
0
1,740,900
Totals
1,740,900
0
0
1,740,900
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,740,900
0
0
0
0
Totals
1,740,900
0
0
0
0
Report Date: June 02, 2015
Page 8
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA05409
BNSF Regional Center Access
New Facility
to
Construct a new access to the BNSF Regional Distribution Center, relocating the
900+ daily truck trips from residential streets in Allentown.
06/08/15
06/15/15
08
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
FMSIB
950,000
0
300,000
1,250,000
P
CN
2021
FMSIB
10,812,500
0
1,687,500
12,500,000
Totals
11,762,500
0
1,987,500
13,750,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
12,500,000
CN
0
0
0
0
1,250,000
Totals
0
0
0
0
13,750,000
Report Date: June 02, 2015
Page 9
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PIN /Project No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
/ 1380(003) TUK -52
Boeing Access Road Bridge Rehabilitation
Boeing Access Road
Interstate 5 to Airport Way South
Rehabilitate the existing bridge with a 340' long concrete or steel bridge structure. It
will be 110' wide curb to curb and have sidewalks on both sides
06/08/15
06/15/15
14
0.200
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
STP(BR)
4,193,000
0
1,218,000
5,411,000
Totals
4,193,000
0
1,218,000
5,411,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
5,411,000
0
0
0
0
Totals
5,411,000
0
0
0
0
Report Date: June 02, 2015
Page 10
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
19
WA -03795
Cascade View Safe Routes to School Phase 2
S 140th St/33rd Ave S
to
Construct an off - street paved shard use path, sidewalks, and a traffic circle at the
intersection of 33rd Ave S and S 140th Street.
06/08/15
06/15/15
28
0.190
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2021
0
WSDOT
750,000
89,000
839,000
Totals
0
750,000
89,000
839,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
839,000
Totals
0
0
0
0
839,000
Report Date: June 02, 2015
Page 11
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
TUK -55
Frank Zepp Bridge Preventative Maintenance Project
S 180th Street over the Green River
SR 181 - West Valley Highway to Sperry Drive S
Paint the structural steel, overlay deck and replace the deck joint, and install seismic
protection.
06/08/15
06/15/15
14
0.040
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
STP(BR)
2,534,812
0
0
2,534,812
Totals
2,534,812
0
0
2,534,812
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
2,534,812
0
0
0
0
Totals
2,534,812
0
0
0
0
Report Date: June 02, 2015
Page 12
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
TUK -56
Grady Way Bridge Preventative Maintenance Project
Grady Way Bridge over BN and UP Railroads
Interurban Avenue S to Longacres Drive SW, Renton
Retrofit existing bridge with seismic protection.
06/08/15
06/15/15
14
0.230
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
STP(BR)
206,500
0
0
206,500
Totals
206,500
0
0
206,500
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
206,500
0
0
0
0
Totals
206,500
0
0
0
0
Report Date: June 02, 2015
Page 13
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -03783
Multipurpose Trails
to
Wide array of necessary trail improvements to existing trail system infrastructure
06/08/15
06/15/15
28
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
0
0
360,000
360,000
Totals
0
0
360,000
360,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
60,000
60,000
60,000
60,000
120,000
Totals
60,000
60,000
60,000
60,000
120,000
Report Date: June 02, 2015
Page 14
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -07748
S 133 St/SR599 Southbound Intersection
S 133rd Street
SR 599 Southbound Ramps to S 134th PI
Construct intersection improvements including signalization or roundabout, lighting,
crosswalks, and drainage.
06/08/15
06/15/15
04
C G O P S
TW
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
0
60,000
60,000
P
CN
2021
0
0
570,000
570,000
Totals
0
0
630,000
630,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
60,000
CN
0
0
0
0
570,000
Totals
0
0
0
0
630,000
Report Date: June 02, 2015
Page 15
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA03782
S 144th St Bridge Sidewalks
S 144th Street
51st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1 -5 between 51st Ave S and 53rd Ave S
06/08/15
06/15/15
28
0.250
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2021
STP(BR)
975,200
0
243,800
1,219,000
Totals
975,200
0
243,800
1,219,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
0
0
0
0
1,219,000
Totals
0
0
0
0
1,219,000
Report Date: June 02, 2015
Page 16
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
16
WA -05410
Strander Blvd /SW 27th St Phase III
Strander Boulevard
E City Limits to West Valley Hwy /SR 181
Design and construct arterial improvements for a new roadway extending Strander
Boulevard /SW 27th St from West Valley Highway to Oaksdale Ave
06/08/15
06/15/15
01
EIS
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2018
STP
3,850,000
0
620,000
4,470,000
P
RW
2021
STP
1,150,000
0
179,000
1,329,000
P
CN
2021
FMSIB
5,000,000
0
1,000,000
6,000,000
P
CN
2021
TIGER III
20,000,000
0
25,000,000
45,000,000
Totals
30,000,000
0
26,799,000
56,799,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
20,000
0
5,000,000
0
0
RW
0
0
0
0
1,329,000
CN
0
0
0
0
51,000,000
Totals
20,000
0
5,000,000
0
52,329,000
Report Date: June 02, 2015
Page 17
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
17
WA -03772
TUC /TOD Pedestrian Improvements
Baker Blvd (if extended)
Andover Park W to E City Limits
Construct bike /pedestrian connection between the Tukwila Urban Center (TUC) and
Tukwila Station, with service by Amtrak Sounder Commuter Rail /Transit Oriented
Development (TOD) area.
06/08/15
06/15/15
28
0.750
CE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
PE
2016
0
0
70,000
70,000
P
RW
2021
STP(E)
80,000
0
0
80,000
S
RW
2021
0
0
20,000
20,000
P
CN
2021
STP(E)
420,000
0
580,000
1,000,000
Totals
500,000
0
670,000
1,170,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
70,000
0
0
0
300,000
RW
0
0
0
0
100,000
CN
0
0
0
0
700,000
Totals
70,000
0
0
0
1,100,000
Report Date: June 02, 2015
Page 18
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
/ 1320(002) TUK -50
Tukwila Urban Center Pedestrian /Bicycle Bridge over Green River
New bridge over the Green River, approximately between Baker Blvd (if extended)
and Longacres Way (if extended)
Baker Boulevard to West Valley Highway
Construct a new pedestrian /bicycle bridge over the Green River
06/08/15
06/15/15
28
0.640
DCE
Yes
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2016
0
OTHER
6,000,000
185,000
6,185,000
Totals
0
6,000,000
185,000
6,185,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
7,223,000
0
0
0
0
Totals
7,223,000
0
0
0
0
Report Date: June 02, 2015
Page 19
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
00
WA -03761
Walk & Roll Plan (Nonmotorized Transportation Plan)
Various City Streets
to
Evaluate deficiencies and create a prioritized list of projects and recommended
design standards.
06/08/15
06/15/15
28
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
0
175,000
175,000
Totals
0
0
175,000
175,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
175,000
Totals
0
0
0
0
175,000
Report Date: June 02, 2015
Page 20
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA03779
West Valley Highway
SR 181 /West Valley Highway
1 -405 to Strander Blvd
Design and construct widening to 7 lanes including curb & gutter, sidewalks,
illumination, drainage, and traffic control
06/08/15
06/15/15
03
0.500
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
0
60,000
60,000
P
CN
2021
0
0
570,000
570,000
Totals
0
0
630,000
630,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
60,000
CN
0
0
0
0
570,000
Totals
0
0
0
0
630,000
Report Date: June 02, 2015
Page 21
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Y Inside
Six Year Transportation Improvement Program
From 2016 to 2021
N Outside
Functional
Class
Priority Number
A. PINIProject No. B. STIP ID
C. Project Title
D. Road Name or Number
E. Begin & End Termini
F. Project Description G. Structure ID
m
Adopted
Amendment
Resolution No.
Improvement Type
Utility Codes
Total Length
Environmental Type
RW Required
14
WA -03765
West Valley Highway /S 156th St
SR181/West Valley Highway
Southcenter Blvd to S 158th St
Construct safety and capacity improvements at intersection.
06/08/15
06/15/15
03
O P S T W
CE
No
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
0
0
50,000
50,000
P
CN
2020
CMAQ
440,000
0
542,000
982,000
Totals
440,000
0
592,000
1,032,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
50,000
CN
0
0
0
0
982,000
Totals
0
0
0
0
1,032,000
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
52,352,912
8,339,000
59,277,300
119,969,212
Report Date: June 02, 2015
Page 22