HomeMy WebLinkAboutReg 2015-07-20 Item 5D - Contract Supplement #1 - Interurban Avenue South Construction Management Environmental Compliance Support with DGK Inc dba Widener & Associates for $37,280.09 (South 143rd Street to Fort Dent Way)COUNCIL AGENDA SYNOPSIS
---------------------------- - - - - -- Initials
Meeting Date Prepared by Ma or'' review Council review
07/20/15 BG
ITEM INFORMATION
ITEM NO.
5.D.
93
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATE: 07/20/15
AGENDA ITEM TITLE Interurban Ave South Project
Environmental Compliance Supplemental Agreement No. 1 with DGK, Inc.
CATEGORY ❑ Discussion
Mtg Date
® Motion
Mtg Date 07120115
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ BidAivard
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police ® PW
SPONSOR'S Contract No. 14 -111 with DGK, Inc., dba Widener & Associates, provides construction
SUMMARY management - environmental compliance for the Interurban Ave S Project. Due to
construction difficulties and exposed contaminants, Widener is needed to provide
additional compliance monitoring. Contingency of $1,139,675.00 will cover Widener's
Supplemental Agreement No. 1. Council is being asked to approve Widener's Supplement
No. 1 to Contract No. 14 -111 in the amount of $37,280.09.
REVIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ® Transportation Cmte
❑ Utilities Crate ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 07/06/15 COMMITTEE CHAIR: )OE DUFFIE
RECOMMENDATIONS:
SPONSOR /ADMIN. Public Works Department
COMMITTEE Unanimous Approval; Forward to Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$37,280.09 $1,139,675.00 $0.00
Fund Source: 104 ARTERIAL STREET FUND (PAGE 14, 2015 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
07/20/15
MTG. DATE
ATTACHMENTS
07/20/15
Informational Memorandum dated 07/02/15
DGK Supplement Agreement No. 1 to Contract No. 14 -111
Minutes from the Transportation Committee meeting of 07/06/15
93
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
TO: Mayor Haggerton
Transportation Committee 4-41
FROM: Bob Giberson, Public Works Director
BY: Robin Tischmak, City Engineer
DATE: July 2, 2015
SUBJECT: Interurban Ave South (S 143rd St to Fort Dent Way)
Project No. 90310402, Contract No. 14 -111
Amendment No. 1, Construction Management - Environmental Compliance
ISSUE
Execute Contract Amendment No. 1 with DGK Inc., dba Widener & Associates, to monitor environmental
compliance during construction of the Interurban Ave S roadway improvement project.
BACKGROUND
The Interurban Ave S project is in the final phase of constructing improvements to the entire corridor
between 42nd Ave S and 1 -405. The improvements will include curbs, gutters, sidewalks, illumination, storm
drainage, street reconstruction, and other urban roadway improvements. Several environmental permits
were required for construction, including a Shoreline Permit, NPDES, and a King County Sewer Discharge
Permit.
Each environmental permit included certain conditions that were required to be met as well as regular
monitoring and reporting of activities. Widener & Associates provided support for obtaining the permits and
have and will continue to monitor compliance during construction.
ANALYSIS
Construction activities have exposed contaminated groundwater and soils that have specific requirements
for disposal. The contaminants have caused the contractor to modify construction methods. The original
contract with Widener & Associates did not include coordination efforts to deal with contaminated materials,
but they have the expertise and experience to assist City staff in this effort. Contract Amendment No. 1,
including the scope of work and an estimate of fees, has been prepared to perform the additional
compliance monitoring to dispose of contaminated materials properly.
BUDGET AND BID SUMMARY
Contract Amendment No. 1 with Widener & Associates is for $37,280.09, making the total contract amount
$73,019.29. The $1,139,675.00 contingency will be used for this Amendment and to date, after this
amendment, there is a balance of $363,571.80.
RECOMMENDATION
Council is being asked to approve Contract Amendment No. 1 with DGK, Inc. in the amount of $37,280.09
for construction management environmental compliance support and consider this item on the Consent
Agenda at the July 20, 2015 Regular Meeting.
Attachment: Contract Amendment No. 1
W: \PW Eng\PROJECTS\A- RW & RS Projects \Interurban Ave S (90310402) \Info Memo Widener Amd #107-02-15 gl - sb.docx
r1
Left
OAMA
City of Tukwila Agreement Number:
6200 Southcenter Boulevard, Tukwila WA 98188
CONTRACT FOR SERVICES
Amendment # 1
Between the City of Tukwila and DGK Inc., Widener & Associates
That portion of Contract No. 14 -111 between the City of Tukwila and
DGK Inc. Widener & Associates is amended as follows:
Article 2. Scope of Services, shall be supplemented with the following:
The Consultant agrees to perform the services, identified on Exhibit "A" attached hereto,
including the provision of all labor, materials, equipment and supplies.
Article 4. Payment, shall be modified as follows:
A. Payment for the work provided by the Consultant shall be made as provided on
Exhibit `B" attached hereto, provided that the total amount of payment to the Consultant
for this work shall not exceed $37,280.09 without express written modification of the
Agreement signed by the City. The new total contract shall not exceed $73,019.29
without express written modification of the Agreement signed by the City.
All other provisions of the contract shall remain in full force and effect.
Dated this day of , 20
CITY OF TUKWILA CONTRACTOR
Jim Haggerton, Mayor
ATTEST /AUTHENTICATED
City Clerk
CA: 2012
Printed Name/Title:
APPROVED AS TO FORM
City Attorney
Page 1 of 1
N11
Exhibit "A"
Construction Support
Interurban Avenue Project
Contamination Remediation
Scope of Work
This supplement scope of work provides for the environmental compliance testing and
monitoring on the contamination. The included the following tasks:
• Coordination with King County Metro to increase discharge rates and
contaminate concentration limits as needed.
• Provided for the testing and monitoring of the vault site.
• Coordination of the test results with King County and complete the reporting
requirements.
Environmental
Cost Estimate
Exhibit B
Project Name
Interurban Construction Support
Client
City o €Tukwila /Robin rischmak
Location
Interurban Blvd. Tukwila Date
5/26/2015'
Project
Project
Manager
Biologist
Hours
Hours
Task 1 Site Contamination
79.5
36.5
Task 2 Additional Site contamination & utilty coordination
40
20
Total hours
119.5
56.5
Summary
Hours
Rate*
Cost
Project Manager
119.5
$140.00
$16,730.00
Project Biologist
56.5
$86.80
$4,904.20
Total Labor
$21,634.20
Outside Services ( testing)
$15,645.89
TOTAL ESTIMATED COST
$37,280.09
100
City Of Tukwila
• Transportation Committee
TRANSPORTATION COMMITTEE
Meeting Minutes
July 6, 2015 — 5:15 p.m. — Foster Conference Room, 6300 Building
PRESENT
Councilmembers: Joe Duffie, Chair; Allan Ekberg, Kate Kruller (Absent: Kathy Hougardy)
Staff: David Cline, Bob Giberson, Frank Iriarte, Robin Tischmak, Grant Griffin, Gail
Labanara, Laurel Humphrey
CALL TO ORDER: Committee Chair Duffie called the meeting to order at 5:15 p.m.
I. PRESENTATIONS
II. BUSINESS AGENDA
A. Consultant Agreement: Major Maintenance on 3 Bridges 2015 Project
Staff is seeking Council approval of a consultant agreement with David Evans and Associates,
Inc. in the amount of $689,290.00 for design services for the Major Maintenance on 3 Bridges
2015 Project. $866,291.00 was budged for this project, funded by the Federal Bridge
Program. The required 10% match will be funded by the Annual Bridge Program. The bridges
involved in this project are the Frank Zepp Bridge, the Beacon Avenue S Bridge, and the
Grady Way Bridge. UNANIMOUS APPROVAL. FORWARD TO JULY 20, 2015 REGULAR
CONSENT AGENDA.
B. Agreement Amendment: Interurban Avenue South (South 143rd Street to Fort Dent Way)
Staff is seeking Council approval of Amendment No. 1 to Contract 14 -111 with DGK Inc.(dba
Widener & Associates) in the amount of $37,280.90 for construction management
environmental compliance support for the Interurban Avenue South roadway improvement
project. This project is in the final phase of construction and required several environmental
permits, including Shoreline, NPDES, and King County Sewer Discharge. Each of those
permits has certain requirements, and Widener & Associates has been monitoring compliance.
This amendment is to cover an increased scope of work due to the discovery of contaminated
groundwater and soils. Funding for this amendment is available from the contingency budget.
UNANIMOUS APPROVAL. FORWARD TO JULY 20, 2015 REGULAR CONSENT AGENDA.
C. Ordinance: Tukwila Urban Center Pedestrian /Bicycle Bridge Right -of -Way Acquisition
Staff is seeking Council approval of an ordinance that would authorize acquisition of property
relating to the TUC Pedestrian /Bicycle Bridge Project. Final design for this project is nearly
complete, and additional right -of -way is needed on the west side of the Green River. The
property is currently part of the Riverview Plaza office park. Design has attempted to minimize
the land encroachment but these remaining small amounts are needed in order to avoid
significant impacts to the levee. The City continues to work with the property owner but this
ordinance will provide the authority to condemn the property should negotiations fail. The
owners have been notified of the opportunity for public hearing. UNANIMOUS APPROVAL.
FORWARD TO JULY 27, 2015 COMMITTEE OF THE WHOLE FOR PUBLIC HEARING.
101