Loading...
HomeMy WebLinkAboutReg 2015-07-20 Item 5D - Contract Supplement #1 - Interurban Avenue South Construction Management Environmental Compliance Support with DGK Inc dba Widener & Associates for $37,280.09 (South 143rd Street to Fort Dent Way)COUNCIL AGENDA SYNOPSIS ---------------------------- - - - - -- Initials Meeting Date Prepared by Ma or'' review Council review 07/20/15 BG ITEM INFORMATION ITEM NO. 5.D. 93 STAFF SPONSOR: BOB GIBERSON ORIGINAL AGENDA DATE: 07/20/15 AGENDA ITEM TITLE Interurban Ave South Project Environmental Compliance Supplemental Agreement No. 1 with DGK, Inc. CATEGORY ❑ Discussion Mtg Date ® Motion Mtg Date 07120115 ❑ Resolution Mtg Date ❑ Ordinance Mtg Date ❑ BidAivard Mtg Date ❑ Public Hearing Mtg Date ❑ Other Mtg Date SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police ® PW SPONSOR'S Contract No. 14 -111 with DGK, Inc., dba Widener & Associates, provides construction SUMMARY management - environmental compliance for the Interurban Ave S Project. Due to construction difficulties and exposed contaminants, Widener is needed to provide additional compliance monitoring. Contingency of $1,139,675.00 will cover Widener's Supplemental Agreement No. 1. Council is being asked to approve Widener's Supplement No. 1 to Contract No. 14 -111 in the amount of $37,280.09. REVIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ® Transportation Cmte ❑ Utilities Crate ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm. DATE: 07/06/15 COMMITTEE CHAIR: )OE DUFFIE RECOMMENDATIONS: SPONSOR /ADMIN. Public Works Department COMMITTEE Unanimous Approval; Forward to Consent Agenda COST IMPACT / FUND SOURCE EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $37,280.09 $1,139,675.00 $0.00 Fund Source: 104 ARTERIAL STREET FUND (PAGE 14, 2015 CIP) Comments: MTG. DATE RECORD OF COUNCIL ACTION 07/20/15 MTG. DATE ATTACHMENTS 07/20/15 Informational Memorandum dated 07/02/15 DGK Supplement Agreement No. 1 to Contract No. 14 -111 Minutes from the Transportation Committee meeting of 07/06/15 93 City of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Transportation Committee 4-41 FROM: Bob Giberson, Public Works Director BY: Robin Tischmak, City Engineer DATE: July 2, 2015 SUBJECT: Interurban Ave South (S 143rd St to Fort Dent Way) Project No. 90310402, Contract No. 14 -111 Amendment No. 1, Construction Management - Environmental Compliance ISSUE Execute Contract Amendment No. 1 with DGK Inc., dba Widener & Associates, to monitor environmental compliance during construction of the Interurban Ave S roadway improvement project. BACKGROUND The Interurban Ave S project is in the final phase of constructing improvements to the entire corridor between 42nd Ave S and 1 -405. The improvements will include curbs, gutters, sidewalks, illumination, storm drainage, street reconstruction, and other urban roadway improvements. Several environmental permits were required for construction, including a Shoreline Permit, NPDES, and a King County Sewer Discharge Permit. Each environmental permit included certain conditions that were required to be met as well as regular monitoring and reporting of activities. Widener & Associates provided support for obtaining the permits and have and will continue to monitor compliance during construction. ANALYSIS Construction activities have exposed contaminated groundwater and soils that have specific requirements for disposal. The contaminants have caused the contractor to modify construction methods. The original contract with Widener & Associates did not include coordination efforts to deal with contaminated materials, but they have the expertise and experience to assist City staff in this effort. Contract Amendment No. 1, including the scope of work and an estimate of fees, has been prepared to perform the additional compliance monitoring to dispose of contaminated materials properly. BUDGET AND BID SUMMARY Contract Amendment No. 1 with Widener & Associates is for $37,280.09, making the total contract amount $73,019.29. The $1,139,675.00 contingency will be used for this Amendment and to date, after this amendment, there is a balance of $363,571.80. RECOMMENDATION Council is being asked to approve Contract Amendment No. 1 with DGK, Inc. in the amount of $37,280.09 for construction management environmental compliance support and consider this item on the Consent Agenda at the July 20, 2015 Regular Meeting. Attachment: Contract Amendment No. 1 W: \PW Eng\PROJECTS\A- RW & RS Projects \Interurban Ave S (90310402) \Info Memo Widener Amd #107-02-15 gl - sb.docx r1 Left OAMA City of Tukwila Agreement Number: 6200 Southcenter Boulevard, Tukwila WA 98188 CONTRACT FOR SERVICES Amendment # 1 Between the City of Tukwila and DGK Inc., Widener & Associates That portion of Contract No. 14 -111 between the City of Tukwila and DGK Inc. Widener & Associates is amended as follows: Article 2. Scope of Services, shall be supplemented with the following: The Consultant agrees to perform the services, identified on Exhibit "A" attached hereto, including the provision of all labor, materials, equipment and supplies. Article 4. Payment, shall be modified as follows: A. Payment for the work provided by the Consultant shall be made as provided on Exhibit `B" attached hereto, provided that the total amount of payment to the Consultant for this work shall not exceed $37,280.09 without express written modification of the Agreement signed by the City. The new total contract shall not exceed $73,019.29 without express written modification of the Agreement signed by the City. All other provisions of the contract shall remain in full force and effect. Dated this day of , 20 CITY OF TUKWILA CONTRACTOR Jim Haggerton, Mayor ATTEST /AUTHENTICATED City Clerk CA: 2012 Printed Name/Title: APPROVED AS TO FORM City Attorney Page 1 of 1 N11 Exhibit "A" Construction Support Interurban Avenue Project Contamination Remediation Scope of Work This supplement scope of work provides for the environmental compliance testing and monitoring on the contamination. The included the following tasks: • Coordination with King County Metro to increase discharge rates and contaminate concentration limits as needed. • Provided for the testing and monitoring of the vault site. • Coordination of the test results with King County and complete the reporting requirements. Environmental Cost Estimate Exhibit B Project Name Interurban Construction Support Client City o €Tukwila /Robin rischmak Location Interurban Blvd. Tukwila Date 5/26/2015' Project Project Manager Biologist Hours Hours Task 1 Site Contamination 79.5 36.5 Task 2 Additional Site contamination & utilty coordination 40 20 Total hours 119.5 56.5 Summary Hours Rate* Cost Project Manager 119.5 $140.00 $16,730.00 Project Biologist 56.5 $86.80 $4,904.20 Total Labor $21,634.20 Outside Services ( testing) $15,645.89 TOTAL ESTIMATED COST $37,280.09 100 City Of Tukwila • Transportation Committee TRANSPORTATION COMMITTEE Meeting Minutes July 6, 2015 — 5:15 p.m. — Foster Conference Room, 6300 Building PRESENT Councilmembers: Joe Duffie, Chair; Allan Ekberg, Kate Kruller (Absent: Kathy Hougardy) Staff: David Cline, Bob Giberson, Frank Iriarte, Robin Tischmak, Grant Griffin, Gail Labanara, Laurel Humphrey CALL TO ORDER: Committee Chair Duffie called the meeting to order at 5:15 p.m. I. PRESENTATIONS II. BUSINESS AGENDA A. Consultant Agreement: Major Maintenance on 3 Bridges 2015 Project Staff is seeking Council approval of a consultant agreement with David Evans and Associates, Inc. in the amount of $689,290.00 for design services for the Major Maintenance on 3 Bridges 2015 Project. $866,291.00 was budged for this project, funded by the Federal Bridge Program. The required 10% match will be funded by the Annual Bridge Program. The bridges involved in this project are the Frank Zepp Bridge, the Beacon Avenue S Bridge, and the Grady Way Bridge. UNANIMOUS APPROVAL. FORWARD TO JULY 20, 2015 REGULAR CONSENT AGENDA. B. Agreement Amendment: Interurban Avenue South (South 143rd Street to Fort Dent Way) Staff is seeking Council approval of Amendment No. 1 to Contract 14 -111 with DGK Inc.(dba Widener & Associates) in the amount of $37,280.90 for construction management environmental compliance support for the Interurban Avenue South roadway improvement project. This project is in the final phase of construction and required several environmental permits, including Shoreline, NPDES, and King County Sewer Discharge. Each of those permits has certain requirements, and Widener & Associates has been monitoring compliance. This amendment is to cover an increased scope of work due to the discovery of contaminated groundwater and soils. Funding for this amendment is available from the contingency budget. UNANIMOUS APPROVAL. FORWARD TO JULY 20, 2015 REGULAR CONSENT AGENDA. C. Ordinance: Tukwila Urban Center Pedestrian /Bicycle Bridge Right -of -Way Acquisition Staff is seeking Council approval of an ordinance that would authorize acquisition of property relating to the TUC Pedestrian /Bicycle Bridge Project. Final design for this project is nearly complete, and additional right -of -way is needed on the west side of the Green River. The property is currently part of the Riverview Plaza office park. Design has attempted to minimize the land encroachment but these remaining small amounts are needed in order to avoid significant impacts to the levee. The City continues to work with the property owner but this ordinance will provide the authority to condemn the property should negotiations fail. The owners have been notified of the opportunity for public hearing. UNANIMOUS APPROVAL. FORWARD TO JULY 27, 2015 COMMITTEE OF THE WHOLE FOR PUBLIC HEARING. 101