SPONSOR'S The contract with Laser Underground & Earthworks, Inc. of Snohomish, WA is complete for
SUMMARY the 2015 Annual Small Drainage Program - Longacres Way. This project provided storm
drainage improvements at Longacres Way near West Valley Hwy. Construction began May
4, 2015 and was completed on June 16, 2015. Unit price over -runs were $1,307.38. Council
is being asked to accept and finalize the contract with Laser Underground & Earthworks in
the amount of $56,748.38.
REVIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ❑ Transportation Cmte
® Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 08/11/15 COMMITTEE CHAIR: DENNIs ROBERTSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMrITEI Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPINDITURI REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$56,748.38 $63,757.15 $0.00
Fund Source: 412 SURFACE WATER (PG 136, 2013 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
08/17/15
5.C.
CAS NUMBER:
STAFF SPONSOR: BOB GIBERSON
ORIGINAL AGENDA DATE: 08/17/15
AGENDA ITEM TITLE 2015 Annual Small Drainage Program - Longacres Way
Project Completion and Acceptance
CATEGORY ❑ Discussion
Mtg Date
® Motion
Mtg Date 08117115
E] Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&'R ❑ Police ® PW
SPONSOR'S The contract with Laser Underground & Earthworks, Inc. of Snohomish, WA is complete for
SUMMARY the 2015 Annual Small Drainage Program - Longacres Way. This project provided storm
drainage improvements at Longacres Way near West Valley Hwy. Construction began May
4, 2015 and was completed on June 16, 2015. Unit price over -runs were $1,307.38. Council
is being asked to accept and finalize the contract with Laser Underground & Earthworks in
the amount of $56,748.38.
REVIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ❑ Transportation Cmte
® Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 08/11/15 COMMITTEE CHAIR: DENNIs ROBERTSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMrITEI Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPINDITURI REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$56,748.38 $63,757.15 $0.00
Fund Source: 412 SURFACE WATER (PG 136, 2013 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
08/17/15
MTG. DATE
ATTACHMENTS
08/17/15
Informational Memorandum dated 08/07/15
State of WA Depart of Revenue Notice of Completion 15 -091
Minutes from the Utilities Committee meeting of 08/11/15
17
1
City of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
TO:
Mayor Haggerton
Utilities Committee
FROM:
Bob Giberson, Public Works Director -le
BY:
Peter Lau, Senior Program Manager
DATE:
August 7, 2015
SUBJECT: 2015 Small Drainage Program — Longacres Way
Project No. 91541201, Contract No. 15 -091
Project Completion and Acceptance
ISSUE
Accept construction contract as complete and authorize release of retainage.
BACKGROUND
The Notice to Proceed for Contract Number 15 -091 with Laser Underground & Earthworks,
Inc. of Snohomish, Washington was issued on May 4, 2015 for the 2015 Small Drainage
Program (SDP) — Longacres Way Project. This construction project built roughly 300 linear
feet of storm drainage improvements on Longacres Way between West Valley Highway and
Nelson Place. Other project improvements included clearing and grubbing, asphalt
pavement removal, asphalt paving, sidewalk replacement, and project site restoration.
DISCUSSION
The 2015 Small Drainage Project — Longacres Way Project was physically completed on
June 16, 2015. No change orders were executed for this project.
FINANCIAL IMPACT
The construction budget for the 2015 Small Drainage Project — Longacres Way was
$325,000.00. A small amount of unit price over -runs were due to some additional usage of
crushed surfacing top course for storm drainage trench backfill. Retainage is being held by the
City for this project in the amount of $2,837.42.
Expenses
Construction Contract Amount $55,441.00
Unit Price Over -runs 1,307.38
Total Contract $56748.38
RECOMMENDATION
Council is being asked to formally accept the 2015 Small Drainage Project — Longacres
Way construction contract as complete and authorize the release of retainage, subject to
standard claim and lien release procedures, with Laser Underground & Earthworks, Inc. in
the final amount of $56,748.38 and to consider this item on the Consent Agenda at the
August 17, 2015 Regular Council Meeting.
Attachment: Notice of Completion
WAPW EngIPROJECTSW- DR ProjectslAnnual Small Drainage Programs12015 SDP (91541201)IConstruction\Long Acres WayW.700 - Post Construction 8 Closeoutlnfo Memo Close out Longacres Laser 08 -07 -15 gLdocx
M
20
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Contractor's UBI Number: 601269998
Date:
Name & Address of Public Agency Department Use Only
City of Tukwila Assigned to:
6200 Southcenter Boulevard
Tukwila, WA 98188 Date Assigned:
UBI Number: 179 000 208
Notice is hereby given relative to the completion of contract or project described below
Project Name
Contract Number
Job Order Contracting
2015 Small Drainage Program - Lon acres Way Project #91541201
15 -091
❑ Yes 0 No
Description of Work Done /Include Jobsite Address(es)
Construction of roughly 300 linear feet of storm drainage improvements on Longacres Way between West Valley Highway and Nelson Place. Items of work
included clearing and grubbing, asphalt pavement removal, storm pipe and catch basin installations, asphalt paving, sidewalk replacement, project site
restoration, and other work necessary to complete the Work as specified and shown in the Contract Documents. Affidavit ID for Laser Underground &
Earthworks, Inc. is 585322.
Federally funded road transportation project? ❑ Yes No
Contractor's Name
Telephone Number
Laser Underground & Earthworks, Inc. 1425-251-1636
Contractor Address
20417 87th Avenue SE, Snohomish, WA 98296
If Retainage is Bonded, List Surety's Name (or attach a copy)
N /A.
Surety Agent's Address
N /A.
Date Contract Awarded
Date Work Commenced
Date Work Completed
Date Work Accepted
April 20, 2015
May 4, 2015
June 16, 2015
Contract Amount $ 55,441.00
Additions ( +) $ 1,307.38 Liquidated Damages $
Reductions ( -) $ 0.00 Amount Disbursed $
Sub -Total $ 56,748.38 Amount Retained $
Amount of Sales Tax Paid at 0.0%
(if various rates apply, please send a breakdown) $ 0.00
TOTAL $ 56,748.38 TOTAL $
NOTE. Tliese two totals must be equal
Please List all Subcontra tors Below:
0.00
53,910.96
2,837.42
56,748.38
Subcontractor's Name:
UBI Number:
Affidavit ID (if known)
Caliber Concrete Construction, Inc.
601 156 625
585446
RAM Surveying & Mapping LLC
603 071 903
585389
F215- 038 -000 08-2011
REV 31 0020e (08/25/11)
Continued on page 2
21
Please List all Subcontractors Below:
ISubcontractor's Name: IUBI Number: (Affidavit ID (if known)
Contact Name: Diane Jaber
Title: Fiscal Specialist
Email Address: Diane.Jaber @TukwilaWA.gov Ynone Number: (20b) 433 -1t5t1 xitsrt
ii ote: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form to all three agencies below. For a faster response, please submit by e -mail.
For tax assistance or to request this document in an alternate format, visit http: / /dor.wa.gov or call 1- 800 - 647 -7706.
Teletype (TTY) users may call (360) 705 -6718.
F215- 038 -000 08 -2011
REV 31 0020e (08/25/ 11)
22
Washington State
Department of Revenue
Washington State
x Department of Labor and Industries
Amllr� Washington State
Employment Security Department
-
Public Works Section
Contract Release
'�� Specialized Collections Unit
PO Box 47474
PO Box 44274
PO Box 9046
Olympia WA 98504 -7474
Olympia, WA 98504 -4272
Olympia WA 98507 -9046
(360)725 -7588
(360)902-4754
(360) 902.9780
FAX (360) 664 -4159
FAX (360) 902 -6897
Fax (360) 902 -9287
PWC @dorwa.gov
ContractRelease @lni.wa gov
publicworks @esd.wa.gov
For tax assistance or to request this document in an alternate format, visit http: / /dor.wa.gov or call 1- 800 - 647 -7706.
Teletype (TTY) users may call (360) 705 -6718.
F215- 038 -000 08 -2011
REV 31 0020e (08/25/ 11)
22
City Of Tukwila
• Utilities Committee
UTILITIES COMMITTEE
Meeting Minutes
August 11, 2015 — 5:30 p.m. — Foster Conference Room, 6300 Building
PRESENT
Councilmembers: Dennis Robertson, Chair; Verna Seal, De'Sean Quinn
Staff: Bob Giberson, Frank Iriarte, Robin Tischmak, Ryan Larson, Peter Lau, and Gail
Labanara
CALL TO ORDER: Chair Robertson called the meeting to order at 5:30 p.m
I. PRESENTATIONS
II. BUSINESS AGENDA
A. Grant Application: 531 Ave S
Staff is seeking Committee approval to submit construction grant applications for a State
Transportation Improvement Board Grant and the State Department of Ecology's 2016
Stormwater Pre - Construction Grant for 531d Ave S project funding. As previous grant
applications were unsuccessful, the budget amendment approved by Council on 8/3/15 has
allowed design funding to be covered by City funds. The grant applications will be for
construction funding in 2016 and 2017. UNANIMOUS APPROVAL.
B. Project Completion: 2015 Small Drainage Project — Longacres Way
Staff is requesting Council approval of project completion and release of retainage to Laser
Underground & Earthworks, Inc. in the amount of $56,748.38 for the 2015 Small Drainage
Project — Longacres Way. The project constructed approximately 300 linear feet of storm
drainage improvements on Longacres Way between West Valley Hwy and Nelson Place.
The project was physically completed on June 16, 2015 and WSDOT then followed with
their overlay project that included West Valley Hwy. The project budget was $63,757.15.
UNANIMOUS APPROVAL. FORWARD TO AUGUST 17, 2015 REGULAR CONSENT
AGENDA.
III. MISCELLANEOUS
Staff reported that East Marginal Way S Storm Pipe Replacement Project is under negotiation with the
Contractor for the final closeout and there have been major issues. The City may unilaterally close the
contract and prepare for a future claim.
Councilmember Seal reported the deteriorating asphalt on Bremmer's Hill (S 144th St near Showalter
Elementary School). City Engineer was just informed of the status today, so we will be investigating the
"melting" asphalt after all of the hot weather.
Committee Chair Robertson requested overgrown brush be cut back at the southeast corner of the
intersection of 42nd Ave S/ S 160th St, but was informed that the area in question is in SeaTac. Bob Giberson
will personally call SeaTac to inform them of the need to mow that area.
Meeting adjourned at 5:34 p.m.
Next meeting: Tuesday, August 25, 2015 — 5:30 p.m. — Foster Conference Room
/ 1� , F
r°'' Committee Chair Approval
Minutes by �,3L, Reviewed by BG
C:\ Users\ laurel- h\AppData \Local \Microsoft \Windows \Temporary Internet Files\ Content. Outlook \VQLVDRQW \Utilities081115.docx
23