HomeMy WebLinkAboutTrans 2015-08-17 Item 2B - Agreement - 53rd Avenue South (South 137th Street-South 144th Street) Design with KPG IncCity of Tukwila
Jim Haggerton, Mayor
INFORMATIONAL MEMORANDUM
TO: Mayor Naggerton
Transportation Committee
FROM: Bob Giberson, Public Works Director
By: Ryan Larson, Senior Program Manager
DATE: August 14, 2015
SUBJECT: 53rd Ave South (S 137th St — S 144th St)
Project No. 99110301
Consultant Selection and Agreement
ISSUE
Approve a Consultant Agreement with KPG, Inc. to provide engineering design services for the 53rd Ave S project.
BACKGROUND
This design contract is for the reconstruction of 53rd Ave S from S 137th St to S 144th St. The 53rd Ave S Project's
design will include reconstructing the roadway, drainage, sidewalks, illumination, water main and sewer upgrades,
and undergrounding of overhead utilities. City Residential Street, Water, Sewer, and Surface Water funds will be
used to fund the design effort. Transportation Improvement Board (TIB) Funding and other grant sources are being
sought to fund a large portion of the construction phase.
ANALYSIS
A Request for Proposals was sent via email on June 16, 2015 to all firms listed on the MSRC Consultant Roster
advertising Civil, Construction Management, and Roadway, Bikeway, and Walkway Design Services. Ten proposals
were received on July 2, 2015. The consultant qualifications were reviewed and scored and three firms, Perteet,
KPG, and KPFF, were selected for interviews and further consideration. Interviews were conducted on July 23, 2015
and KPG was selected as the firm that best met the requirements for this type of project. KPG's approach to the
project included a proposal to use public meetings similar to those they used on the Cascade View Drainage Project
where they were able to affectively work with multiple property owners. KPG also excelled with a proven track record
of helping jurisdictions obtain grant funding, including State TIB grants.
BUDGET SUMMARY
Contract Budget
KPG $ 575,731.49
Contingency 10% 57,573.15
Residential Streets
193,000.00
Residential Streets ROW portion
23,000.00
Water (401)
125,000.00
Sewer (402)
100,000.00
Surface Water (412)
200.000.00
Total $ 633,304.64
$&4i 000-00
RECOMMENDATION
Council is being asked to approve the contract with KPG Inc. in the amount of $575,731.49 to perform design
engineering services for the 53rd Ave S Project and consider this item on the Consent Agenda at the September 8,
2015 Regular Meeting.
Attachments: Scoring Matrix
2015 CIP Pages 6, 62, 77 and 87, 2015 CIP
Consultant Agreement
WAPW Eng \PROJECTS\A- RW & RS Projects \53rd Ave S (99110301)\Design Consultant Selection \Info Memo KPG PE 08 -14 -15 gl - sb.docx
53rd Ave S.
Consultant
Scoring Matrix
Total Possible Points
G
o
42 b
Nr o
a
o
i`0 0 w0
■
V G
1
S 0
io �o o1
150
200
200
100
150
200
1000
KPG
145
190
187
95
145
197
959
1
Perteet
138
188
183
65
145
187
906
2
KPFF
120
180
177
78
145
187
887
3
Reviewer Name: Combined Average Scores from three Reviewers
Ryan Larson, Robin Tischmak, Scott Bates
Date: 7/23/15
W: \PW Eng \PROJECTS\A- RW & RS Projects \53rd Ave S (99110301) \Design Consultant Selection \Scoring Matrix.xlsScoring Matrix.xls
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2015 to 2020
PROJECT: 53rd Ave S (S 137th St - S 144th St) Project No. 99110301
EXPENSES
Design and construct urban residential street improvements that include curb, gutter, sidewalk, undergrounding,
DESCRIPTION:
and illumination. Street will coordinate with Water $1.1 m, Sewer $830k, and Surface Water $1.5m CIP projects.
JUSTIFICATION:
Provide pedestrian and vehicle safety, drainage, and neighborhood revitalization.
STATUS:
Undergrounding is included in the estimate at this time. Grant applications in 2014 for 2015/16.
MAINT. IMPACT:
Reduce pavement, shoulder, and drainage work.
State TIB & Pedestrian Safety grants are proposed with Water, Sewer and Surface Water as match.
COMMENT:
See additional pages in Enterprise funds under 53rd Ave S Projects. Seattle City Light is now negotiating
190
a 60/40 underground split and undergrounding costs have been added to project.
FINANCIAL
Through Estimated
rn annn's1
2n13 2n14 2n15 2018 2n17 2n18 2n19 2n2n BEYOND TOTAL
EXPENSES
Design
190
3
193
Land(R/W)
100
100
Const. Mgmt.
120
120
240
Construction
800
800
1,600
Undergrounding
2,250
2,250
TOTAL EXPENSES
1 0
1 01
290
1 3,173
1 920
1 0
1 01
0
1 0
1 4,383
FUND SOURCES
Awarded Grant
0
Proposed Grant
174
1,082
507
1,763
Seattle City Light
1,350
1,350
Bond
0
City Oper. Revenue
0
0
116
741
413
0
0
0
0
1,270
TOTAL SOURCES
1 0
1 01
290
1 3,173
1 920
1 01
0
0
1 0
1 4,383
2015 - 2020 Capital improvement Program 6 5
CITY OFTUKVVLA CAPITAL PROJECT SUMMARY
2015 to 2020
PROJECT
53rd Ave S Water Main Replacement Project No. 90540106
O�8CR|PT|�N�
�ong*dhRns�enUa|s�ee and oudaoewa�rimpmvemama.ino�||appmxm�a�3.00OLFofnew
12^ water line along 53rd Ave G from Interurban Ave SmS144thSt.
JUSTIFICATION:
Thispm�dosaneaded|nupwithinthodi��bmioneya�mandwiUimpmv*wueroomicaand�m
'
flows m the north side of Tukwila Hill.
STATUS:
Design in2O15. with construction in2010 and 2O1T.
mmmT.|MpACT:
COMMENT:
The wa�rma�m�o*iUbea�ng53� Ave Shnm|n�m�an Ave S and 52nd Ave 8to53� Ave G.
then along S 137th St to 53rd south to S 144th St.
RmxmCv«L Through Estimated
onS000'so 2nix 2n14 2n 15 2n10 mn mm nom m2n Rpymmn rOTx/
EXPENSES
Design
125
125
Const. Mgmt.
67
68
135
Construction
450
450
900
TOTAL EXPENSES
1 01
01
125
1 517
1 518
1 01
01
01
01
1,160
FUND SOURCES
Awarded Grant
0
Proposed Grant
0
Mitigation Actual
0
Mitigation Expected
0
TOTAL SOURCES
1 01
01
1251
517
1 518
1 01
01
01
01
1,160
,lect Location
oo10-0000 Capital Improvement Program 62
^
CITY OF TUKVVLA CAPITAL PROJECT SUMMARY
2015 to 2020
PROJECT: 53md Ave S Sewer Rehabilitation Project No. 91440205
RahabUhebnnof2.1O0LF+�ofaun�a�ee*e �a was ins�|�d�1S72�53� Ave 5fmmS137�St
DBS�0�OON�
' to S 144th St. Coordinate with Street, Water, and Surface Water improvements.
JUSTIFICATION: The rehabilitation of the sanitary sewer will reduce the need to disturb the new roadway.
STATUS:
MA|NT IMPACT: Expected (u decrease maintenance.
COMMENT:
FINANCIAL Through snbmoteu
(inmmo's) 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL
EXPENSES
VV
Design
UO
100
mw
100
200
Const. Mgmt.
100
1,000
1,100
Construction
630
6,000
6,630
TOTAL EXPENSES
1 01
01
100
1 730
1 01
01
01
01
7,100
1 7,930
FUND SOURCES
Awarded Grant
0
Proposed Bond/ULID
7,100
7,100
Mitigation Actual
0
Mitigation Expected
0
(DProject Location
VV
UO
mw
;VN
W V,
2015 2020 Capital Improvement Program 77 7
CITY OFTUKVVLA CAPITAL PROJECT SUMMARY
2015 to uVoV
PROJECT:
53rd Ave S Surface Water Drainage System Project No. 90341213
Replace existing storm drainage system. Provide bioswales along 53rd Ave S and a water quality structure
DESCRIPTION:
aL the downstream end nf the system totreat storm water runoff. Purchase hght-o#may.if required, for
binawa|e construction and provide asphalt overlay.
JUSTIFICATION:
New conveyance system wiUn,duco#oodingunhghto#way and phvatepmpeny.Exiohngsystem iainpoor
condition and street runoff flows onto private property.
STATUS:
In conjunction with Street and Water improvements.
MA|NT.|MRACT:
Expected 0o decrease maintenance.
COMMENT:
FINANCIAL Through Estimated
(in $000's) 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL
EXPENSES
SL
Design
S 139
200
200
Const. Mgmt.
100
95
195
Construction
500
569
1,069
TOTAL EXPENSES
1 01
01
200
1 600
1 664
1 01
01
01
01
1,464
FUND SOURCES
Awarded Grant
0
Proposed Grant
120
360
398
878
Mitigation Actual
0
Mitigation Expected
0
TOTAL SOURCES
1 01
01
200
1 600
1 664
1 01
01
01
0
1 1,464
Project Location
SL
S 139
tro s'
xmo'zmoo Capital Improvement Program 87 8
City of Tukwila Contract Number,
2
6200 Southcenter Boulevard, Tukwila WA 98188
CONSULTANT AGREEMENT FOR
ENGINEERING SERVICES
THIS AGREEMENT is entered into between the City of Tukwila, Washington, hereinafter
referred to as "the City", and KPG, Inc., hereinafter referred to as "the Consultant", in consideration
of the mutual benefits, terms, and conditions hereinafter specified.
1. 11roiect Designation. The Consultant is retained by the City to perform engineering services
in connection with the project titled '53'd Avenue South (S 144"' Street to S 137"' Street)'.
2, Scope of Services. The Consultant agrees to perform the services, identified on Exhibit "A"
attached hereto, including the provision of all labor, materials, equipment and supplies.
3. I -ation of Agreement, Time i- Performance. This Agreement shall be in full force and
)ui fo
effect for a period commencing upon execution and ending December 31, 2016, unless sooner
terminated under the provisions hereinafter specified, Work Linder this Agreement shall
commence, upon written notice by the City to the Consultant to proceed. The Consultant shall
perform all services and provide all work product required pursuant to this Agreement no
Later than December 31, 2016 unless an extension of such time is granted in writing by the
City.
4, Payment. The Consultant shall be paid by the City for completed work and for services
rendered under this Agreement as follows:
A. Payment for the work provided by the Consultant shall be made as provided on Exhibit
"B" attached hereto, provided that the total amount of payment to the Consultant shall
not exceed $575,731.49 without express written modification of the Agreement signed
by the City.
B. The Consultant may submit vouchers to the City once per month during the progress of
the work for partial payment for that portion of the project completed to date. Such
vouchers will be checked by the City and, upon approval thereof, payment shall be made
to the Consultant in the amount approved.
C. Final payment of any balance due the Consultant of the total contract price earned will be
made promptly upon its ascertainment and verification by the City after the completion
of the work tinder this Agreement and its acceptance by the City.
D. Payment as provided in this section shall be full compensation for work performed,
services rendered, and for all materials, supplies, equipment and incidentals necessary to
complete the work.
E. The Consultant's records and accounts pertaining to this Agreement are to be kept
available for inspection by representatives of the City and the state of Washington for a
period of three (3) years after final payments, Copies shall be made available upon
request.
01
5. Ownership and Use of Documents. All documents, drawings, specifications and other
materials produced by the Consultant in connection with the services rendered under this
Agreement shall be the property of the City -whether the project for which they are made is
executed or not. The Consultant shall be permitted to retain copies, including reproducible
copies, of drawings and specifications for information, reference and use in connection with
the Consultant's endeavors. The Consultant shall not be responsible for any use of the said
documents, drawings, specifications or other materials by the City on any project other than
the project specified in this Agreement.
6. Compliance with Laws. The Consultant shall, in performing the services contemplated by
this Agreement, faithfully observe and comply with all federal, state, and local laws,
ordinances and regulations, applicable to the services rendered under this Agreement.
7. Indemnification. The Consultant shall defend, indemnify and hold the City, its officers,
officials, employees and volunteers harmless from any and all claims, injuries, damages,
losses Or Suits including attorney fees, arising Out of or resulting from the acts, errors or
omissions of the Consultant in performance of this Agreement, except for injuries and
damages caused by the sole negligence of the City.
Should a court of cornpetent.jurisdiction determine that this Agreement is subject to RCW
4.24.115, then, in the event of liability for damages arising Out of bodily injury to persons or
damages to property caused by or resulting from the concurrent negligence of the Consultant
and the City., its officers, officials, employees, and volunteers, the Consultant's liability
hereunder shall be only to the extent of the Consultant's negligence. It is further specifically
and expressly understood that the indemnification provided herein constitutes the Consultant's
waiver Of immunity under Industrial Insurance, Title 51 RCW., solely for the purposes of this
indemnification. This waiver has been mutually negotiated by the parties. The provisions of
this section shall survive the expiration or termination of this Agreement.
8. Insurance. The Consultant shall procure and maintain for the duration of the Agreement,
insurance against claims for injuries to persons or damage to property which may arise from
or in connection with the performance of the work- hereunder by the Consultant, its agents,
representatives, or employees. Consultant's maintenance of insurance as required by the
agreement shall not be construed to limit the liability of the Consultant to the coverage
provided by such insurance,, or otherwise limit the City's recourse to any remedy available at
law, or in equity.
A. Minimum Amounts and Scope of Insurance. Consultant shall obtain insurance of the
types and with the limits described below:
CA revised: 1-2013
1. A1.1101110 bile Liability insurance with a minimum combined single Iii-nit for bodily
- Ly
injury and property damage of $1,000,000 per accident. Automobile Liability
insurance shall cover all owned, non-owned, hired and leased vehicles. Coverage
shall be written on Insurance Services Office (LSO) ISO) form CA 00 01 or a substitute
form providing equivalent liability coverage. If necessary, the policy shall be
endorsed to provide contractual liability coverage.
Page 2
i1s]
2. Commercial General -Liability insurance with limits no less than $1.000.000 each
occurrence, $22,000,000 general aggregate. Commercial General Liability
insurance shall be written on ISO occurrence form CG 00 01 and shall cover
liability arising from premises, operations, independent contractors and personal
injury and advertising injury. The City shall be named as an insured under the
Consultant's Commercial General Liability insurance policy with respect to the
work performed for the City.
W -kers* Coijij2�Lj s ti( Ln coverage as required by the Industrial Insurance laws of
t,)r--- _L:a
the State of Washington.
4. I)rofessional Liability with limits no less than $1,000,000 per claim and
$1.000,000 policy aggregate limit. Professional Liability insurance shall be
appropriate to the Consultant's profession.
13. Other Insurance Provision. The Consultant's Automobile Liability and Commercial
General Liability insurance policies are to contain, or be endorsed to contain that they
shall be primary insurance with respect to the City. Any Insurance, self-insurance, or
insurance pool coverage maintained by the City shall be excess of the Consultant's
insurance and shall not be contributed or combined with it.
C. Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M,
Best rating of not less than A:VlI,
1). Verification of Coverage. Consultant shall ffirnish the City with original certificates and
a copy of the amendatory endorsements, including but not necessarily limited to the
additional insured endorsement, evidencing the insurance requirements or the Consultant
before commencement of the work. Certificates of coverage and endorsements as
required by this section shall be delivered to the City within fifteen (15) days of execution
of this Agreement.
E. Notice of Cancellation. The Consultant shall provide the City with written notice of any
policy cancellation, within two business days of their receipt of such notice.
E Failure to Maintain Insurance. Failure on the part of the Consultant to maintain the
insurance as required shall constitute a material breach of contract, upon which the City
may, after giving five business days notice to the Consultant to correct the breach,
immediately terminate the contract or, at its discretion, procure or renew such insurance
and pay any and all premiums in connection therewith, with any sums so expended to be
repaid to the City on demand, or at the sole discretion of the City, offset against funds due
the Consultant from the City.
9. Independent Contractor. The Consultant and the City agree that the Consultant is an
independent contractor with respect to the services provided pursuant to this Agreement.
Nothing in this Agreement shall be considered to create the relationship of employer and
employee between the parties hereto. Neither the Consultant nor any employee of the
Consultant shall be entitled to any benefits accorded City employees by virtue of the services
provided under this Agreement. The City shall not be responsible for withholding or
otherwise deducting federal income tax or social security or for contributing to the state
industrial insurance program, otherwise assuming the duties of an employer with respect to
the Consultant, or any employee of the Consultant.
CA revised: 1-2013
am
ilil
Ik Covenant Against Contingent, Fees. The Consultant warrants that bc has not employed or
reiobocd any 000zpuoy or puraou, other than u booafidc employee working solely for the
Consultant, to solicit or secure this contract, and that he has not paid or agreed to pay any
company or person, other than abonuOde employee working solely for the Cnomnitau|, any
fee, commission, percentage, brokerage ��c, gifts, or any other consideration contingent upon
or resulting from the award or making of this contract. For breach or violation of this
vvanrooL the City shall have the right to annul this contract vvi1bon1 liability, or in its
diocn:1iVo to deduct from the 0001coo1 ydco or consideration, or n1bcrxdae recover, the full
amount ofsuch fee, commission. percentage, brokerage fee.
gift, or contingent fee,
ll. Discrimination Prohibited. The Consultant., with regard to the work performed 6»itunder
this /\gruczuezu, will not diocrinn{oolc on the grounds of race, religion, urco6 color, nn1ioomo
origin, ugo° veteran status, sex, sexual orientation,, gender identity, ueuritu| status, political
affiliation or the presence of any disability in the selection and retention of employees or
procurement of materials or supplies.
iZ Assignment. The Consultant shall not sublet m assign any of the services covered by this
Agreement without the express written consent o(1bcCity.
13. Waiver Fw the City o[muy provision mfthis Agreement or ally tbnolimitation
provided for in this Agreement shall not constitute o waiver o( any other provision.
\4.
A. The City reserves the right to terminate this Agreement at any time by giving ' tell (10)
days written notice ha the Consultant.
B. In the event of the death of member, partner m officer ofthe Consultant, or any of' its
supervisory personnel assigned Nthe prqject, the surviving members u[(he Consultant
hereby agree to complete the work under the terms ofthis Aorccn)cut, if requested to do
so by the City. This section nbuU not be u hmo to renegotiations of this Agreement
between surviving members o[ the Consultant and the City, i[ the City aochooses.
15. This Agreement shall be «xkjcci to, and the
Consultant shall at all times comply with, all nnn6cubke federal, state and local laws,
regulations, and rules, the provisions of the 0 of Tukwila Municipal Lmdo and
ordinances of1�[` of Tukwila. In the event any suit, arbitration, or other proceeding is
instituted to enforce any term of this Agreement, the parties specifically understand and agree
that venue shall be properly laid in King County, Washington. The prevailing party io any
such action ubol} be cndUcd to its attorney's fees and costs of suit. \/eouo for any action
arising from or related to this Agreement obu|| be exclusively in King County Superior Court.
|h. Severabilitv and Survival. If any term, condition or provision ofthis Agreement is declared
void or unen6orccable or limited in its application or effect, such event shall not af , feet any
other provisions hereof and all other provisions shall remain fully enforceable. The
provisions of this Agreement, which by their sense and context are reasonably intended to
survive the completion, expiration or cancellation of this Agreement, shall survive
termination of this Agreement.
Cx revised : 1-2013
iw
17. Notices,. Notices to the City of'l'ukwila shall be sent to the following address:
City Clerk
City of Tukwila
6200 Southeenter Boulevard
Tukwila, WA 98188
Notices to Consultant shall be sent to the following address:
KPG
753 9"' Avenue North
Seattle, WA 98109
18. Entire Agreement; Modification. This Agreement, together with attachments or addenda,
represents the entire and integrated Agreement between the City and the Consultant and
supersedes all prior negotiations, representations, or agreements written or oral. No
amendment or modification of this Agreement shall be of any force or effect unless it is in
writing and signed by the parties.
DATED this .--- day of
CITY OFTUKWILA
Mayor, Jim Ilaggeiton
Attest/Authenticated:
City Clerk, Christy O'Flaberty
CA revised : 1-2013
2015.
CONSUVVANT
Printed Narne:Nelson Davis, KPG
Title:_ Principal
Approved as to Form:
Office of the City Attorney
Im
13
City of Tukwila
53rd Avenue South
S 144 th Street to S 137th Street
KPG
Scope of Work
August 11, 2016
PURPOSE:
This project includes preparation of final Plans, Specifications and Estimates for the 53rd
Avenue South Project. Project elements include:
Roadway (Project No. 9910301)
Pavement restoration, minor widening; curb, gutter, and sidewalk; shared bicycle
markings; channelization; ADA upgrades; illumination-, franchise utility
underg rounding, retaining walls, and landscape restoration between S 144th Street
and S 137th Street.
Surface Water (Project No. 90341213)
Installation of new conveyance system from S 144th Street to S 137th Street,
including water quality and flow control measures as required to mitigate roadway
project. Opportunities to retrofit existing roadway will be evaluated and implemented
where practical based on cost effectiveness and available right of way.
Water (Project No. 90540106)
Installation of new water main and appurtenances between S 144th Street and
Interurban Avenue South.
Sewer (Project No. 91440205)
Provide necessary utility adjustments to match new roadway grades, install a side
street extension to the vacant S 142nd Street right of way, and evaluate pipe
inspection videos for potential spot repairs to existing sewer and/or manholes.
Work includes necessary base mapping, design, State Environmental Protection Agency
(SEPA) documentation, Cultural Resources, and franchise utility coordination.
City of Tukwila Page 1of9 KPG
53"1 Avenue South 8/11/15 14
SCOPE OF WORK:
Task I Project Management/Coordination/Administration.
1.1 Provide project management administrative services including:
♦ Project set-up and execute agreement
♦ Execution of subconsultant agreements
+ Preparation of monthly progress reports and invoices
♦ Record keeping and project closeout
1.2 Provide overall project management including:
♦ Project staff management and coordination
+ Subconsultant management and coordination
+ Prepare and update project schedule
♦ Schedule and budget monitoring
1.3 Coordinate with City staff, including preparation and attendance of up to 8
coordination meetings throughout the duration of the project. Level of effort for this
task is based on an average of 2 Consultant staff at each of the following meetings:
+ One formal kickoff meeting at project start
+ Monthly meetings at the City throughout the project duration (estimate 7).
1.4 Provide QA / QC reviews by senior staff of all major deliverables prior to submittal to
the City.
Deliverables
♦ Project Schedule and necessary updates
♦ Monthly progress reports and invoicing
+ Meeting agendas and minutes including a summary of decisions made / needed
resulting from design coordination meetings.
Task 2 Survey and Base Mapping.
Limits of survey- 53rd Avenue S (Approximately 60 feet wide plus additional at driveways
and side streets) from the south side of S 1,14 th Street to the north side of S 137th Street
and from S '137th Street to Interurban Avenue S along the proposed water line replacement
route.
2.1 Establish horizontal and vertical control points along the corridor for field topographic
survey. Basis of control will be City of Tukwila Datum. The CONSULTANT will
locate, field survey, and calculate positions for all monuments and control points
throughout the project limits, using the Washington State plane coordinate system.
Conventional or GPS surveying methods will be used on this project. Monuments or
corners to be located and field surveyed include the following:
• Section Corners
• Side street monuments
• Property Corners
City of Tubvila Page 2 of 9 KPG
53"'A venue South 8111115
W
2.2 Field Survey and Note Reduction. Perform note reduction of the field survey data.
2.3 Mapping work to prepare 1"=20' topographic base map and digital terrain model
(DTM) in AutoCAD format of the project within the limits described above.
2.4 The Consultant will retain the services of a firm to field locate and paint all utility
locations within the project corridor so that they can be surveyed and incorporated
into the base maps. Service line locations and gravity storm and sewer will not be
field located. Perform field survey to locate paint marks including surface features
(valves, manholes, catch basins, junction boxes, vaults, etc). Irrigation systems will
not be included.
2.5 Perform observation and measure-downs of existing storm drain catch basins and
manholes. The approximate size, type (brick, concrete), and general condition of the
structures to confirm suitability for continued use, and approximate size and location
of storm drainage pipes will be documented. These observations will be made from
the surface.
2.6 The Consultant shall survey the utility potholes performed by franchise utilities
and/or subconsultant. The budget includes a $10,000 allowance for potholing of City
owned facilities.
Deliverables
♦ Electronic copies of the completed field topographic base map in PIDF and
AutoCAD.
Task 3 Public Outreach / License to Construct
3.1 Prepare flyer describing project and to obtain rights of entry for survey and mapping
to ensure smooth transition with adjacent improvements. Mailing and postage will
be provided by the City.
3.2 Prepare for and attend up to two (2) community open house meetings. Mailing
meeting notices and room arrangements will be provided by the City.
3.3 Prepare license to construct forms and exhibits for each property along the corridor.
Conduct up to 20 one-on-one meetings with adjacent residents to describe the
project and obtain right of entry signatures.
Deliverables
♦ Camera-ready mailings and flyers.
+ Open house meeting graphics
♦ Right of entry forms and exhibits (40 parcels)
♦ Summary Notes from open house meetings.
City of Tukwila
53"1 Avenue South
Page 3 of 9
KPG
8111,115
11.1
Task 4 Stormwater Preliminary Design and Alternatives Analysis
The Consultant shall prepare preliminary engineering of stormwater management and
conveyance facilities required for the project. Preliminary engineering will include the
following sub-tasks:
4.1 Compile and review existing stormwater data, including GIS data, record drawings,
and previous storm drainage reports for projects in the vicinity of the proposed
roadway improvements.
4.2 Perform an offsite analysis in accordance with Section 2.3.1 of the 2009 King County
Surface Water Design Manual (KCSWDM). The analysis will extend downstream
from the approximately 1/4 mile to the Duwamish River outfall.
4.3 Analyze all applicable Core and Special Requirements of the KCSWDM to determine
stormwater management requirements that will apply to the project.
4.4 Identify potential alternatives for meeting stormwater management requirements of
the KCSWDM, and a full retrofit of the roadway for water quality treatment. Perform
preliminary calculations for sizing alternatives facilities and prepare conceptual
drawings to illustrate each alternative.
4.5 Perform alternatives evaluation, consisting of planning-level cost estimates and
evaluation of advantages and disadvantages for each alternative for use in
alternative selection by the City.
4.6 Prepare and submit a Draft Stormwater Design Report to document the preliminary
stormwater design activities performed in the above subtasks. The report will identify
a recommended alternative for the stormwater management design.
4.7 Prepare a Final Stormwater Design Report.
Deliverables
♦ Conceptual Drawings to illustrate each stormwater alternative., 1 electronic file
in PDF format
♦ Draft Stormwater Design Report, 2 bound copies of report and 1 electronic file
in PDF format
o Final Stormwater Design Report, 2 bound copies of report and 1 electronic copy
in PDF format
♦ The storm drainage design will be in accordance with the standards of the City
of Tukwila Municipal Code (14.30,060), including the 2009 King County Surface
City of Takwila Page 4 of 9 KPG
53" A venue South 8111115
HFA
Water Design Manual (KCSWDM) and the City's 2010 Infrastructure Design and
Construction Standards.
♦ The King County Runoff Time Series (KCRTS) will be used for hydrologic
modeling and design of stormwater management facilities.
♦ XP Storm software by XP Solutions will be used for hydraulic modeling if
required for offsite analysis.
♦ Water quality treatment alternatives will include a full retrofit of the roadway,
even if Core Requirement 8 of the KCSWDM requires less than a full retrofit.
Task 5 Geotechnical Report
The Consultant shall coordinate with a qualified geotechnical firm to complete field
investigations to support the project as follows:
51 Review existing preliminary plans and geotechnical, geological and environmental
reports for the immediate area.
5.2 Plan, coordinate, and manage the field investigation, which will include the following:
• Obtain right-of-way permits from the City for the field investigation.
• Mark core/boring exploration locations and request public utility locates. A
separate trip to the site will be necessary to mark the exploration locations in
order to get the utility locates completed, and a second trip will be necessary
to observe locates and verify no conflicts exist or to select an alternate
exploration location.
• Complete up to eight borings at an average of approximately 15 feet to
explore the existing pavement section, underlying subgrade conditions,
infiltration capacity, and to determine wall design parameters. Up to 3 wells
will be left in place in order to monitor seasonal groundwater fluctuations.
5.3 Complete geotechnical laboratory analyses on disturbed soil samples obtained from
the explorations, including up to four moisture content determinations, up to four
grain-size determinations, up to four cation exchange capacity tests, and up to four
organic matter content determinations.
5.4 Prepare a draft (electronic PDF copy) and final report summarizing our findings,
conclusions, and recommendations related to the following:
• Subsurface soil and groundwater conditions and results the of laboratory
testing
• Feasibility of stormwater infiltration potential of native soil based on
City of Tukwila Page 5of9 KPG
53 "" Avenue South 8111115
18
subsurface conditions encountered, and limited laboratory testing that
includes grain-size analyses
0 Potential of existing soil to provide water quality treatment
Foundation recommendations for luminaires based on Washington State
Department of Transportation Chapter 17
0 Provide recommendations for wall design and pavement section
Deliverables
+ Draft and Final Geotechnical letter report
Task 6 Final Plans, Specifications and Estimates
The Consultant shall prepare Final Plans, Specifications and Estimates for advertisement
and award by the City. Plans shall be formatted to provide sufficient detail for convenient
field layout of all proposed facilities. City standard details and WSDOT standard plans will
be supplemented with project specific details as required. Final bid documents will be
signed by a licensed professional engineer in the State of Washington.
6.1 Coordinate with Seattle City Light, CenturyLink and Comcast Cable to develop a
preliminary undergrounding of overhead utilities plan. Each utility company will
provide a schematic design of their proposed undergrounding facilities, including
vaults, number and size of conduits, temporary pole relocations, and terminal pole
locations. The Consultant shall incorporate the utility provided information into a
preliminary aerial conversion plan compatible with proposed corridor improvements,
The Consultant will prepare a summary table of existing connection type by parcel
and provide the City with a summary of properties that need to be converted to
underground service.
6.2 Analyze illumination to provide levels consistent with the current City illumination
standards. Prepare a preliminary layout of the street illumination system and include
supporting calculations in a brief technical memorandum.
6.3 Develop retaining, wall cross section alternatives (plan and typical section) and
comparative level of opinion of cost. In determining the type of wall to use, the
Consultant will analyze cost and constructability of each wall system. As the
structural design needs for walls is unknown, the budget includes a $30,000
allowance for structural / geostructural design services.
6.4 Prepare draft Technical Information Report in accordance with City stormwater
requirements to include additional water quality facilities approved in task 4.
6.5 The Consultant shall prepare 30% Plans and Estimate for City review and comment.
Plans will contain a roadway profile and sufficient plan view information to allow
verification of scope by City departments prior to final design. Draft TIR, urban
design/landscape memorandum, and illumination calculations will be included with
City of Tukwila Page 6 of 9 KPG
53" Avenue South 8111115
iN
the 30% submittal,
6.6 The Consultant shall incorporate City comments and prepare 60% Plans, and
Estimate for City review and comment.
6.7 The Consultant shall address City comments and finalize TIR.,
6.8 The Consultant shall incorporate City comments and prepare 90% Plans,
Specifications, and Estimate for City review and comment. Specifications will be
based on WSDOT /APWA and City Standards.
6.9 Prepare contract specifications for the 90% and Bid submittals based on
WSDOT /APWA standards (English), grant funding requirements, and applicable
LAG standards.
6.10 Perform 30 %, 60 %, 90% and Bid Document quantity take -offs and opinion of costs.
6.11 The Consultant shall incorporate comments and finalize bid documents. Bid
documents will be uploaded to bxwa.com for advertisement by the City. It is
anticipated that final plans will include the following sheets. Sheets may be
combined or separated for clarity:
Cover sheet
(1 sheet)
Sheet Index, Survey Control & Alignment Data
(1 sheet)
Legend and Abbreviations
(1 sheet)
Roadway Sections
(1 sheet)
Paving Details
(2 sheets)
Drainage Details
(4 sheets)
Right of Way Plans
(5 sheets)
Site Preparation and Erosion Control Plans
(6 sheets)
Roadway Plans
(5 sheets)
Roadway Profiles
(5 sheets)
Drainage Plans
(5 sheets)
Drainage Profiles (5 sheets)
Water Plans and Details (9 sheets)
Sanitary Sewer Plans and Details
(3 sheets)
Driveway Plan and Profiles
(10 sheets)
Retaining Wall Plan and Elevations
(8 sheets)
Retaining Wall Details
(4 sheets)
Landscape Restoration Plans and Details
(8 sheets)
Illumination Plans and Details
(6 sheets
Channelization and Signing Plans and Details
(6 sheets)
Joint Utility Plans and Details
7 sheets)
TOTAL = 102 sheets
6.12 The Consultant shall provide bid period services to include responses to bidder
inquiries, preparation of addenda, attendance at bid opening, preparation of bid
City of Tukwila Page 7 of 9 KPG
53 "'.Avenue South 8111115
`11
tabulation, and recommendation to award or reject the apparent low bidder. The
budget assumes a straight forward review process with the low bidder receiving the
contract award.
Deliverables
♦ 30% Plans (1/2 size) & estimate, 5 bound, 1 unbound copy, 1 electronic file in
PDF format
60% Plans (1/2 size), specifications & estimate, 5 bound, 1 unbound copy, 1
electronic file in PDF format
♦ 90% Plans (Y2 size), specifications & estimate, 5 bound, 1 unbound copy, 1
electronic file in PDF format
♦ Final Bid Documents, 10 bound copies 1/2 size Plans, 1 electronic file in PDF
format.
Task 7 Environmental.
7.1 Cultural Resources Investigation. The Consultant will conduct the required cultural
resources assessment in compliance with Washington State E005-05.
7.2 SEPA Checklist:The Consultant will prepare a SEPA checklist for the project
improvements for based on the reviewed 30% Plans.
Deliverables:
♦ An electronic copy of the draft Cultural Resources report in Adobe PDF.
♦ An electronic copy in Adobe PDF and three (3) paper copies of the final Cultural
Resources report..
♦ SEPA submittal copies as required.
Task 8 Right of Way Calculations
Perform the following work items necessary to establish the existing right-of-way (ROW)
along the corridor based on publicly available information. Title research is not anticipated
or included in the project budget.
8.1 Research Records. Determine which existing corners and monuments should be
field located and surveyed.
8.2 Calculations for ROW lines. Using the research information and the survey work
described above, calculate location and surveyed corners, roadway features and
monuments. Incorporate existing right of way into project base maps.
8.3 Analyze right of way needs based on approved 30% Plans and develop right of way
Plans. It is anticipated that right of way and/or easements may be required at curb
returns at sidewalks, for retaining walls, and other site utilities.
8.4 Obtain title reports for up to 12 parcels and prepare up to 12 legal descriptions and
City of Tukwila Page 8 of 9 KPG
53"' Avenue South 8111115
`AI
exhibits for right of way takes, wall easements, and /or utility easements.
Deliverables.-
* Right of way information will be incorporated into the project base maps,
♦ Up to 12 legal descriptions and exhibits.
Additional Services
The City may require additional services of the Consultant in order to advance all or portions of
the project corridor through final design and construction. This work may include items
identified in the current task authorizations as well other items, which may include, but are not
necessarily limited to the following:
♦ Obtaining title reports and providing final right of way / easement legal
descriptions and exhibits beyond the quantity estimated in the scope (12
parcels)
♦ Providing property appraisals and negotiations
♦ Providing additional permitting or environmental studies
♦ Providing additional design services
♦ Providing construction services
These services will be authorized under a future contract supplement if necessary. At the
time these services are required, the Consultant shall provide a detailed scope of work and
an estimate of costs. The Consultant shall not proceed with the work until the City has
authorized the work and issued a notice to proceed.
City of Tukwila Page 9 of 9 KPG
53`4AvenueSouIh 8/11115
PA
HOUR AND FEE ESTIMATE
Project: City of Tukwila
53rd Avenue South
S 144th Street to S 137th Street
EXHIBIT B
• Architecture
Landscape Architecture
• Civil Engineering •
Task Description
*Labor Hour Estimate Total Bud
pnojec Senior Pnojoc Design ' Survey Senior Office
wanager Engineer Engineer Eng / LA Technician Crew Aumin *umm
°
'
Bud et
nasm' Management/coordination/administration
1 , Project administration 8 0 0 0
1 z Project management and coordination (12 months) 24 12 0 0
1s City staif design coordination rneetings 16 8 16 0
1 4 QA/QC reviews 8 8 0 0
Mileage
Reproduction
12
8
0
0
12 5
12 5
8 S
0 5
s
5
3 62 z1
8,039.05
7,906.83
2,735 39
Task Totals
Task 2 - Survey and Mapping
2.1 Establish alignment control
2.2 Field survey and note reductiori
zo Prepare base maps and DTM
2.4 Coordinate utility Iocate services
2.5 Storm measuredowns
2.5 Pick up utility pothole inforrnation
Utility Iocate service
Utility potholing allowance
Mileage
Reprodu
56 28 16 0 16 o 20 32 $ 22,305.48
O 2 16 0 0 10 0 o S 3,6*083
0 4 8 0 0 100 0 0 5 16,699.90
0 4 24 100 0 0 0 0 $ 13,400 32
0 0 2 8 0 4 0 0 S 1,637.45
0 0 0 12 u 24 0 0 5 4,84677
0 0 n 8 0 16 0 0 5 3,231.18
5 6.000.00
o 10,000.00
S 200.00
$ 100.00
Task Totals
O 10 50 128 0 154 0
0 59,756.45
Task a' Public Outreach
3.1 Flyer for survey 0 2 0 0 4 0
3 2 Prepare for and attend community open houses (2) 4 8 24 0 16 3
3.3 Prepare license to construct exhibits and 1 on 1 migs 8 40 24 24 40 0
Mileaoe
Task Total 12 50 48 24 60
8/11/2015
0
o
4 $ 928.97
6,594.25
$2ov 00
s sn000
20 $ 24.959.63
HOUR AND FEE ESTIMATE EXHIBIT B
Project: City of Tukwila
53rd Avenue South
S 144th Street to S 137th Street
• Architecture •
Landscape Architecture
• Civil Eruginee-ring
bor I-1 ur Es i a
Project Senior Project Design Survey Senior Office
Task Description Manager Engineer Engineer Eng / LA Technician Crew Admin Admin
184 79 $ 157.13 $ 113.12 $ 100.57 $ 81.72 $ 151.66 $ 106.86 71.96
Task 4 - Stormwater Preliminary Design and Alternatives Analysis
Total Bud
4.1 Compile and review available stormwater data 0 4 8 0
4.2 Offsite analysis 0 4 16 40
4.3 Drainage requirements analysis 0 2 4 0
4.4 Stormwater alternatives ID & development
4.5 Stormwater alternatives evaulation
4.6 Draft Stormwater Design Report
4.7 Final Stormwater Design Report
Mileage
Reproduction
2 16 24 48
2 4 8 8
I 12 24 8
1 2 4 2
0 0 0 0 $
0 0 0 0 $
0 0 0 0 $
0 0 0 0 S
C 0 0 0 S
0 0 0 8 S
0 0 0 8 3
Task Total
44 88 106
16
Budget
1,533.48
6,461.21
766.74
10,425 87
2,707 62
6,165.49
1,723 37
100.00
250.00
8.78
3,178.41
30,000.00
50.00
,228.41
Task 5 - Geotechnical Report
5.1 Coordinate Geotechnical Report
GeoDesign
Mileage
Reproduction
Task Total
Task 6 - Final Plans, Specifications, and Estimates
6.1 Coordination for utility undergrounding 8 16 40 16 16 0 0
6.2 Analyze and layout illumination system 2 8 24 0 8 0 0
6.3 Develop retaining wall recommendation 4 16 16 0 8 0 0
6.4 Prepare Draft TIR 2 4 40 20 0 47 D
6.5 Prepare 30% Plans 24 100 160 300 200 0 0
6.6 Prepare 60% Plans 24 80 160 240 180 0 0
6.7 Prepare Final TIR 0 2 8 4
0 0 0
6.8 Prepare 90% Plans 40 100 220 300 200 0 0
6.9 Prepare Specificaiions c90% Final) 4 16 40 16 8 0 0
6.10 Quantity and cost estimating (30%, 60%, 90%, Final) 4 10 24 16 16 0 0 0
6.11 Finalize Bid Documents 4 40 80 80 40 0 0 8
6.12 Bid Period Services 4 8 8 8 4 0 0 4 $
Structural wall (lesion allowance 9
Mileage
Reproduction $
8 $ 12,009 50
2 .4) 5,139 17
2 6 5860.83
2. 7.678 24
85.33&84
74,525 80
2 1 765 42
95 080 80
10,616 60
7.941 92
27,963 85
•4 320 44
30.000,00
500.00
2,500.00
Task Total 120 400 820 1000 680 0 0 60 S 371,239A1
8/11/2015
HOUR AND FEE ESTIMATE
Project: City of Tukwila
53rd Avenue South
S 144th Street to S 137th Street
EXHIBIT B
"Cr" G-
• Architecture
Landscape Architecture
4 Engineering 4
Task Description
*Labor Hour Estimate
Total Bud
Task 7 - Environmental
Project Senior Project Design Survey Senior Office
Manager Engineer Engineer Eng / LA Technician Crew Admin Admin
$ 184.79 $ 157.13 $ 113.12 $ 100.57 $ 81.72 $ 151.66 $ 106.86 $ 71.96
Budget
7 1 Cultural Resources Investigation
7.2 Prepare SEPA checklist
Widener and Associates
Mileage
Reproduction
Task Total
2
2
2
4
0
8
0
0
2
8
0
0
0
0
2 $ 991 20
4 $ 2,84465
$ 7 500 00
s
50 00
4 6 8 0 10 0 0 6 11,385.85
Task 8 - Right of Way Calculations
8 1 Research records 0 2 8 0 0 16 0 4 $ 393370
8.2 Calculations for ROW lines 0 2 16 24 0 0 0 0 $ 4,537 85
8.3 Prepare legals and exhibits (12 parcels) 0 0 24 48 8 0 0 0 $ 8.195.93
Title Reports (12 parcels) $ 6.000.00
Mileage $ -
Reproduction $ 50 00
Task Total
0 4 48 72 8 16 0 4 22,717.48
Total Estimated Fee: $ 575,731.49
8/11/2015
Exhibit B
BUDGET SUMMARY
City of Tukwila
53rd Avenue South
S 144th Street to S 137th Street
TASK
CIF' Budget Items
TOTALS
99110301
Street
Design
99110301
Street
Land (R/W)
90341213
Surface Water
Design
90540106
Water
Design
91440205
Sewer
Design
Task1 - Management/coordination /administration
$ 5,576.37
$
$ 5,576.37
$ 5,576.37
$ 5,576.37
$ 22,305.48 1
I
Task 2 - Survey and Mapping
$ 10,051.29
$
$ 13,251.29
$ 28,178.22
$ 8,275 64
$ 59,756.45
Task 3 - Public Outreach
$ 9,983.85
$
$ 7.487.89
$ 4.991,93
$ 2,495 96
$ 24,959.63
Task 4 - Stormwater Preliminary Design and Alternatives Analysis
$ -
$
$ 30,138.78
$ -
$ -
$ 30,138.78 I
Task 5 - Geotechnical Report
$ 13,291.36
$ -
$ 13,291.36
$ 3,322.84
$ 3,322.84
$ 33,228.41 I
Task 6 - Final Plans, Specifications, and Estimates
$ 185,619 70
$ -
$ 111,371 82
$ 55,685.91
$ 18,561 97
$ 371.239 41 I
Task 7 - Environmental
$ 2,846.46
$ -
$ 2,846 46
$ 2,846.46
$ 2,846.46
$ 11.385,85
Task 8 - Right of Way Calculations
$ -
$ 22,717.48
$ -
$ -
$ -
$ 22,717 48
Totals:
$ 227,369.04
$ 22,717.48
$ 183,963.98
$ 100,601.74
$ 41,079.25
$ 575,731.49
2015 - 2016 Budget:
$ 193,000.00
$ 100,000.00
$ 200,000.00
$ 125,000.00
$ 100,000.00
$ 718,000.00
8/11/2015