HomeMy WebLinkAboutTrans 2015-08-17 Item 2C - Contract Supplement #2 - South 144th Street Phase II (42nd Avenue South-Tukwila International Boulevard) for Right-of-Way Acquisition with KPG IncCity of Tukwila
Jim Haggerton, Mayor
TO: Mayor Haggerton
Transportation Committee
FROM: Bob Giberson, Public Works DirectorR8
BY: Cyndy Knighton, Senior Program Manager
DATE: August 14, 2015
SUBJECT: S 144th Street Phase II Project (42nd Ave S to Tukwila International Blvd)
Project No. 99510402
Supplemental Agreement No. 2 for ROW Acquisition Services
ISSUE
Execute a supplemental agreement with KPG in the amount not to exceed $27,239.99 to complete right -of -way (ROW)
acquisition services for the S 144th Street Phase II Project (42nd Avenue S to Tukwila International Boulevard).
In May 2015, the design contract with KPG was supplemented by the amount of $20,000 to begin acquiring ROW for the
S 144th St Phase II Project. ROW is needed from 4 parcels to accommodate the current design features. Legal
descriptions were developed and Administrative Offer Summaries were prepared for each parcel, as well as a Project
Funding Estimate to best estimate the remaining ROW costs.
31WRI"111[6111
KPG's ROW Supplemental Agreement No. 1 was limited to gathering property information, establishing values of property
to be acquired, and developing a Project Funding Estimate. Supplemental Agreement No. 2 will authorize the consultant
team to make the initial offers, negotiate with the property owners and execute all of the necessary paperwork associated
with ROW acquisition. KPG's Supplemental Agreement No. 2 for an additional $27,239.99 will accomplish all of the
required ROW tasks.
FINANCIAL IMPACT
The current CIP budget for ROW is $40,000, of which $20,000 has been expended under KPG's Supplemental Agreement
No. 1. Supplemental Agreement No. 2 will use the remaining $20,000 from the ROW budget and staff is proposing the use
of $7,239.99 from the construction budget. A budget amendment will be brought forward later this year to update the
project costs in the Capital Improvement Program. Once the final ROW purchase prices have been negotiated (currently
estimated to be $82K), staff will propose the use of construction funds to acquire the necessary property, if a budget
amendment has not yet been made. The budget amendment will likely include updated impact fee collections to
supplement the project budget. The King County Library System and the Tukwila Village site will be assessed traffic
impact fees once building permits have been issued.
RECOMMENDATION
Council is being asked to approve KPG's Supplemental Agreement No. 2 in the amount of $27,239.99 to complete ROW
acquisition services for the S 144th Street Phase II Project and consider this item at the August 24, 2015 Committee of the
Whole and subsequent September 8, 2015 Regular Meeting.
Attachments: 2015 CIP Page 15
Consultant Supplemental Agreement No, 2
W: \PW Eng\PROJECTS\A- RW & RS Projects \S 144th St Phase 11 TIB - 42nd Ave S (99510402 95- RW02)Tesign\ROW\INFO MEMO KPG Supp #2 ROW gl - sb -ri gi.dou 27
CITY OFTUKVNLA CAPITAL PROJECT SUMMARY
301* to 2020
PROJECT:
S144St Phase U(42Ave S' Tukwila |mt'l Blvd)° Project No. 99510402 Zone
Construct curb, gutter, sidewalk, bike lanes, pavement restoration, illumination, drainage and utility
DESCRIPTION:
undergrounding from Tukwila Int'l Blvd to 42nd Ave S. Also add a signal at 42nd Ave S.
JUSTIFICATION:
Provide pedestrian and vehicle safety, drainage and neighborhood revitalization.
Phase Tukwila |ni'| Blvd \uMi|itoryRd project million million ' � .
Phase 11 42 Ave 8k, Tukwila International Blvd.
MA|NT.|MPACT:
Reduce pavement, drainage repairs, and maintenance costs.
25
Awarded Tnanupoxahon|mpmvomontBoard's Aneha||mpmvementPmgmmV\|P)g,nn8nf$1 million. .
Project is on Impact Fee list, Design and construction related to the Tukwila Village project.
FINANCIAL Through Estimated
(in $000's) 2013 2014 2015 2016 2017 201 R 2019 2n2n npYOwn mr /
EXPENSES
Design
286
25
311
Const. Mgmt.
180
180
Construction
1,402
1,402
TOTAL EXPENSES
1 01
326
1 1,607
1 01
01
01
01
01
0
1,933
FUND SOURCES
Awarded Grant
180
820
1,000
Proposed Grant
0
Proposed Mitigation
100
700
800
Traffic Impact Fees
133
13
25
171
2015 zVoo Capital Improvement Program 15
SUPPLEMENTAL AGREEMENT No. 2
AGREEMENT No. 14-103
PROJECT No. 99510402
City of Tukwila
Public Works Department
6300 Southcenter Boulevard #100
Tukwila, WA 98188
KPG, Inc.
753 - 9th Avenue N.
Seattle, WA 98109
PROJECT: S 144"' Street Phase 11 Project - ROW Negotiation Services
This SUPPLEMENTAL AGREEMENT NO. 2 is to supplement the agreement entered into with KPG,
7'
Inc. and the City of Tukwila, which was executed on the 29h day of July, 2014.
All provisions in the basic agreement remain in effect, except as expressly modified as follows:
Article 2, Scope of Services, shall be supplemented with the following:
I
The Consultant agrees to provide right of way services in accordance with the scope of work included as
Exhibit A-2.
Article 4, Payment, shall be modified as follows:
A. Payment for work provided by Consultant shall be made as provided on Exhibit B-2, attached
hereto, provided that the total amount of payment to the Consultant for this work- not exceed
$27,239.99 without express written modification of the Agreement signed by the City. The new
total contract shall not exceed $345,153.97 without express written modification of the Agreement
signed by the City.
IN WITNESS WHEREOF, the parties hereto have set their hands and seals this day
of 2015.
APPROVED:
CITY OF TUKWfLA
Jim Hac-erton
Mayor
Attested:
Christy O'Flaberty, City Clerk
APPROVED:
KPG, INC.
Nelson Davis, P.E.
Principal
K*1
City of Tukwila
42"d S 144th Street Phase 11 Project
Avenue S to Tukwila International Boulevard
Supplement No. 2 — Right of Way Negotiation Services
KPG
Scope of Work
July 27, 2015
PURPOSE:
Following completion of base maps and completion of 50% design for S 1441h Street, it
was determined that additional right of way is necessary to complete the improvements.
Valuation and legal descriptions were prepared under supplement no. 1 to this Contract.
This supplement is provided to support negotiations for partial right of way takes on four
(4) parcels in support of the S 144th Street Phase 11 Project.
SCOPE OF WORK:
Task 8 Right of Way Calculations
8.6 Support acquisition services to be performed by Abeyta & Associates under
subcontract to the Consultant in accordance to state guidelines.
The overall objectives are:
1 Negotiate for the partial acquisitions from 4 parcels for the
completion of the proposed roadway improvements.
2. Assist the City of Tukwila with the acquisition process and
preparation of forms.
A specific list of Performance Objectives is outlined in the following paragraphs.
SPECIFIC OBJECTIVES
The key objectives of this proposal are:
Acquisitions:
1. Inspect and prepare a Preliminary Acquisition Report for each parcel,
2. Identify fee interest ownership for 4 parcels.
City of Tukwila
S 144th St Phase // Project
Page 1of3
KPG
7/27/2015
r-111
Exhibit A-2
3. Prepare and setup acquisition files for 4 parcels.
4. Prepare acquisition forms needed to obtain property rights. This
proposal does not include the preparation of Possession and Use
agreements,
5. Negotiate to acquire in fee title and easements from 4 Parcels - A
minimum of 3 attempts for each parcel.
6. Maintain diaries for 4 parcels.
7. Assist in clearing title encumbrances that will adversely impact the
rights being acquired,
8. Assist in delivering funds to each property owner,
9. Deliver completed files to the City of Tukwila.
1 •` A
1 Those services related to obtaining releases of encumbrances from
title, which require legal action;
2. The actual filing of condemnation and subsequent litigation;
3. Certain dosing costs such as transfer taxes, title reports, recording
fees, penalty costs for pre payments cost of a pre-existing mortgage,
partial reconveyance fees, the pro rate share of real property taxes
paid subsequent to vesting title to the City;
4. Relocation Services;
5. Continuing negotiations for those parcels listed for condemnation;
6. Appraisal services
City of Tukwila
S 144h St Phase // Project
Page 2 of 3
KPG
7/27/2015
Wil
Exhibit A-2
Additional Services
The City may require additional services of the Consultant in order to advance all or
portions of the project corridor through final design and construction. This work may
include items identified in the current task authorizations as well other items, which may
include, but are not necessarily limited to the following:
• Condemnation support
0 Providing additional permitting or environmental studies
* Providing construction services
These services will be authorized under a future contract supplement if necessary. At
the time these services are required, the Consultant shall provide a detailed scope of
work and an estimate of costs. The Consultant shall not proceed with the work until the
City has authorized the work and issued a notice to proceed.
City of Tukwila
S 144h St Phase // Project
Page 3 of 3
KPG
7/27/2015
r-W
HOUR AND FEE ESTIMATE
Project: City of Tukwila
S 144th Street Phase II
42nd Avenue S to Tukwila International Boulevard
Supplement No. 2 - ROW Negotiation Services
EXHIBIT B-2
• A rchitect u re •
Landscape Architecture
Ci v,1 Pri itineeri fl iz •
Task 8 - Right of Way Calculations and Acquisitions
8.6 Negotiation support
Subconsultant - Abeyta
Mileage
Reproduction
Task Total
*Labor Hour Estimate
Project = Senior Project Urban Design . Survey Senior Office
Manager-, Engineer Engineer Designer Eng / LA Techrlician Crew Admiri Admin
$ -179.26 $ 143.58 $ 115.36 $ 125.96 $ 99.44 I $ 86.18 $ 139.96 $ 112.70 $ 74.25
Total Budget
Budget
0
8
0
0
4 8 8 0 0 8
0
0
* Hourly rates are based on the following:
Direct Salary Costs
Overhead Rate
Fixed Fee
4 $ 3,774.99
23,365.00
50.00
50.00
4 $ 27,239.99
Total Estimated Fee: $ 27,239.99
$ 65.00 $ 52.06 $ 41.83 $ 45.67 $ 36.06 $ 31.25 ' $ 50.75 $ 40.87 $ 26.92
145.78%
30%
7/27/2015
Totals
1,368.84
$ 1,995.50
$ 410.65