HomeMy WebLinkAboutUtilities 2015-11-24 Item 2E - Contract Supplement #1 - 2015 Central Business District Sanitary Sewer Rehabilitation Construction Management with RH2 EngineeringCity of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Utilities Committee FROM: Bob Giberson, Public Works Directo By: Peter Lau, Senior Program Manager DATE: November 20, 2015 SUBJECT: 2015 CBD Sanitary Sewer Rehabilitation Project Project No. 91541201, Contract No. 15 -074 Construction Management Supplemental Agreement No. 1 ISSUE Approve Supplemental Agreement No. 1 to Contract No. 15 -074 with RH2 Engineering, Inc. (RH2). BACKGROUND Consultant Contract No. 15 -074 with RH2 provided design engineering services for the 2015 Central Business District (CBD) Sanitary Sewer Rehabilitation. Two separate construction projects were generated after the design was completed; the 2015 Sanitary Sewer Manhole Rehabilitation Project and the 2015 CBD Sanitary Sewer Rehabilitation Project. Supplemental Agreement No. 1 with RH2 will provide construction management (CM) support for these two sanitary sewer construction projects. City Council awarded the 2015 Sanitary Sewer Manhole Rehabilitation Project to Olson Brothers Pro -Vac, LLC, and the construction contract for the 2015 CBD Sanitary Sewer Rehabilitation project was awarded to Michels Corporation at the November 2, 2015 Council meeting. DISCUSSION To properly manage these two sanitary sewer construction projects, the City will need CM support during the construction phase. Through this Supplement No. 1, RH2 will provide construction inspections, review of material submittals and change order requests, and assist with monthly payments. RH2 staff has expertise in construction inspection for sewer pipe relining and manhole construction and has performed the design work for these two projects. Tukwila CM staff will still provide the majority of the CM work and the remaining share of field inspections. BUDGET SUMMARY This Supplemental Agreement was carefully reviewed and is reasonable for cost and scope of work. Contract 2016 CM Budget RH2 Design Contract 15 -074 $ 16,136.00 $ 20,000.00 RH2 Contract 15 -074 Supplement #1 96,574.00 120,000.00 Total $ 112,710.00 $ 140,000.00 RECOMMENDATION Council is being asked to approve Supplemental Agreement No. 1 to Contract No. 15 -074 with RH2 Engineering, Inc. in the amount of $96,574.00 for the construction management of the 2015 Sanitary Sewer Manhole Rehabilitation Project and 2015 CBD Sanitary Sewer Rehabilitation Project and to consider this item on the Consent Agenda at the December 7, 2015 Regular Meeting. Attachment: Page 71, 2015 CIP RH2 Supplemental Agreement No. 1 17 W: \PW Eng \ PROJECTS \A- SW Projects \CBD Sewer Rehabilitation (91140203)\2015 CBD Sewer \Construction\#.100 - Contract Documents \RH2 \Info Memo for RH2 Supplement #1 CM, #15 -074, 11 -20 -15 gl- sb.doc CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2015 to 2020 PROJECT: CBD Sanitary Sewer Rehabilitation Project No. 91140203 DESCRIPTION: JUSTIFICATION: STATUS: MAINT. IMPACT: COMMENT: The asbestos concrete pipe in the CBD (commercial business district) is approximately 45 years old and becoming soft. Slip lining the pipe will reinforce the strength with little impact to roadways and minimal excavation. If the pipe collapses, the street will have to be excavated and the cost of the repairs will be significant. In the last five years we have had two major pipe failures on Andover Park West. A Public Works Trust Fund loan was successfully obtained in 2012 for construction. Reduced maintenance and repair costs. The limits of the 2013 project is APW to APE from Minkler Blvd to S 180th St and will now include the repair to the sewer under the railroad tracks. FINANCIAL Through Estimated (in $000's) 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL EXPENSES 0 Project Location 4 -s•' , iiii MAI OM. . 1 MIA IMII Design 159 33 20 20 20 20 20 Vpl. 292 Land (R /W) i . °' Ma 0 Const. Mgmt. 87 120 120 120 120 120 687 Construction 639 900 900 900 900 900 5,139 TOTAL EXPENSES 159 759 1,040 1,040 1,040 1,040 1,040 0 0 6,118 FUND SOURCES Awarded Grant 0 PWTF /Proposed PW1 45 250 455 750 Mitigation Actual 0 Mitigation Expected 0 Utility Revenue 114 509 585 1,040 1,040 1,040 1,040 0 0 5,368 TOTAL SOURCES 159 759 1,040 1,040 1,040 1,040 1,040 0 0 6,118 2015 - 2020 Capital Improvement Program 71 18 0 Project Location 4 -s•' , iiii MAI OM. . 1 MIA IMII Most F )' 'I�I ll .: Pkwy �..': r ILI W 'al AA E NN�r Vpl. y7:41 i . °' Ma 2015 - 2020 Capital Improvement Program 71 18 SUPPLEMENTAL AGREEMENT NUMBER 1 to CONSULTANT AGREEMENT NUMBER 15 -074 THIS SUPPLEMENTAL AGREEMENT is entered into between the City of Tukwila, Washington, herein -after referred to as "the City ", and RH2 Engineering hereinafter referred to as "the Consultant ", in consideration of the mutual benefits, terms, and conditions hereinafter specified. The City desires to supplement the agreement entered into with the Consultant and executed on, April 6, 2015, and identified as Agreement No. 15 -074. All provisions in the basic agreement remain in effect except as expressly modified by this supplement. The changes to the agreement are described as follows: Task 1 — Additional CIP Planning Objective: Revise project to fit into modified 2015 budget. Approach: 1.1. Iteratively eliminate portions of completely designed project until the revised project is within the City's reduced 2015 budget. RH2 Deliverables: • Cost estimates of alternative design packages that meet the City's revised budget, and email and phone correspondence with City regarding scheduling the pipe segments with the greatest criticality. Task 2 — Bid Document Modifications Objective: Modify previously completed set of plans and bid documents to be consistent with reduced scope project consistent with revised CIP determined in Task 1. Approach: 2.1. Delete portions of project from completed plan set and specifications and move some to additive bid alternative. Produce plans and bid documents in the revised format. RH2 Deliverables: • Revised plans and bidding documents. Task 3 — Services During Construction (SDC) for Central Business District Sanitary Sewer Rehabilitation Objective: Assist the City with technical efforts during construction of the Central Business District Sanitary Sewer Rehabilitation project, including on -site construction observation. Approach: 3.1 Pre - construction Meeting — Prepare for and attend one (1) pre - construction conference. Prepare an agenda and meeting minutes for the pre - construction conference. 19 3.2 Submittal Review — Review shop drawings, submittals, and change order proposals of those items requested in the technical specifications. Provide a written response to the contractor and the City for each shop drawing and submittal reviewed. 3.3 Requests for Information and Pay Requests — Review written requests for information (RFIs) and quantities for pay requests and provide written responses to the City. 3.4 Construction Observation — Provide on -site construction observation (see assumed construction duration below) and associated administrative duties, including: observation of the contractor and its subcontractors, bid item quantity tracking, communications with City staff, and other tasks required in the field. Participation or Information Needed from the City: • Provide RFI responses to the contractor. • Help to process the contractor's pay requests. RH2 Deliverables: • Pre - construction conference administration and documentation, including pre - construction conference meeting agenda and minutes. • Limited on -site construction observation and associated reports. • Meetings and correspondence with the City and contractor, as needed, within the budgeted hours identified in Exhibit A — Estimate of Time and Expense. Assumptions: • The City is performing the lead role in construction management and administration. • For Task 3.4, construction is assumed to last approximately ten (10) hours each day for twenty -five (25) days. An RH2 Engineering, Inc., (RH2) team member will be present at all times during construction. • Construction phase services are variable in nature and depend in part on the contractor awarded the project. RH2 's estimate is based upon an experienced and reasonable contractor being awarded the construction contract. RH2 recommends that the City budget the amount shown for services during construction in the fee estimate plus a contingency amount. The contingency would cover additional services if a more intensive level of observation and technical support becomes necessary. • Record Drawing work may be required. Task 4 — Project Management for Central Business District Sanitary Sewer Rehabilitation Objective: Coordinate with City staff; monitor scope, budget, and schedule; review and issue invoices; and maintain project files and records for the Central Business District Sanitary Sewer Rehabilitation project. Approach: 4.1. Coordinate with City staff on schedule, progress, and technical questions. 20 4.2. Prepare for and attend two (2) construction progress meetings. Prepare an agenda and meeting minutes for the construction progress meetings. 4.3. Prepare invoices. Review for consistency and monitor budget spent. Provide monthly status updates. Participation or Information Needed from the City: • Attendance at construction meetings by members of the City's staff. Task 5 — SDC for Sanitary Sewer Manhole Rehabilitation Objective: Assist the City with technical efforts during construction of the Sanitary Sewer Manhole Rehabilitation project, including on -site construction observation. Approach: 5.1. Pre - construction Meeting — Prepare for and attend one (1) pre - construction conference. Prepare an agenda and meeting minutes for the pre - construction conference. 5.2. Submittal Review — Review shop drawings, submittals, and change order proposals of those items requested in the technical specifications. Provide a written response to the contractor and the City for each shop drawing and submittal reviewed. 5.3. Requests for Information and Pay Requests — Review written RFIs and quantities for pay requests and provide written responses to the City. 5.4. Construction Observation — Provide on -site construction observation (see assumed construction duration below) and associated administrative duties, including: observation of the contractor and its subcontractors, bid item quantity tracking, communications with City staff, and other tasks required in the field. Participation or Information Needed from the City: • Provide RFI responses to the contractor. • Help to process the contractor's pay requests. RH2 Deliverables: • Pre - construction conference administration and documentation, including pre - construction conference meeting agenda and minutes. • Limited on -site construction observation and associated reports. • Meetings and correspondence with the City and contractor, as needed, within the budgeted hours identified in Exhibit A — Estimate of Time and Expense. Assumptions: • The City is performing the lead role in construction management and administration. • For Task 5.4, construction is assumed to last approximately ten (10) hours each day for twelve (12) days. An RH2 team member will be present at all times during construction. • Construction phase services are variable in nature and depend in part on the contractor awarded the project. RH2 's estimate is based upon an experienced and reasonable 21 contractor being awarded the construction contract. RH2 recommends that the City budget the amount shown for services during construction in the fee estimate plus a contingency amount. The contingency would cover additional services if a more intensive level of observation and technical support becomes necessary. • Record Drawing work may be required. Task 6 — Project Management for Sanitary Sewer Manhole Rehabilitation Objective: Coordinate with City staff; monitor scope, budget, and schedule; review and issue invoices; and maintain project files and records for the Sanitary Sewer Manhole Rehabilitation project. Approach: 6.1. Coordinate with City staff on schedule, progress, and technical questions. 6.2. Prepare for and attend two (2) construction progress meetings. Prepare an agenda and meeting minutes for the construction progress meetings. 6.3. Prepare invoices. Review for consistency and monitor budget spent. Provide monthly status updates. Participation or Information Needed from the City: • Attendance at construction meetings by members of the City's staff. 1. Time for Performance, the completion date of the work shall be August 31, 2016. 2. Payment, shall be as follows: o Payment for the work provided by the Consultant as part of this supplement shall be made for an additional $96,574.00. The total amount for the Consultant for this contract shall not exceed $112,710.00 without express written modification of the Agreement signed by the City. DATED this CITY OF TUKWILA day of , 2015. Jim Haggerton, Mayor CONSULTANT By: Printed Name: Richard L. Ballard Title: Director 22 EXHIBIT A City of Tukwila Supplemental Agreement No. 1 to Agreement No. 15 -074 2015 Central Business District Sewer Rehabilitation SDC Estimate of Time and Expense Tony V. Pardi John D. Hendron Kenneth D. Schonberger Zachary W. Schrempp Maureen A. Schueren $214.00 $206.00 5161.00 $150.00 5129.00 Steve Fletcher Hours 5138 Task 1 ADDITIONAL CIP PLANNING Descri p tion Principal Project Manager Project Engineer Staff Engineer Administrative Support pport Total Hours Total Labor Sub Cost Total Su6consultant Total Expense Total Cost Classification Professional IX Professional VII Professional III Professional II Administrative V Technician IV Tony V. Pardi John D. Hendron Kenneth D. Schonberger Zachary W. Schrempp Maureen A. Schueren $214.00 $206.00 5161.00 $150.00 5129.00 Steve Fletcher Hours 5138 Task 1 ADDITIONAL CIP PLANNING 1.1 Reduce scope of project to fit within the City's reduced 2015 budget - 2 3 - - 5 $ 895 $ - $ - $ 37 $ 932 Subtotal - 2 3 - - 5 $ 895 - $ - $ - $ 37 $ 932 Task 2 BID DOCUMENT MODIFICATIONS 2.1 Revise bidding documents to remove work and move portions to additive bid alternative 1 2 2 2 2 9 $ 1,506 $ - $ - $ 53 $ 1,559 Subtotal 1 2 2 2 2 9 $ 1,506 - $ - $ - $ 53 $ 1,559 Task 3 SDC FOR CENTRAL BUSINESS DISTRICT SANITARY SEWER REHABILITATION 3.1 Prepare for and attend one (1) pre- construction conference - - 4 2 6 5 - 16 - - 10 $ 1,790 $ - $ - $ 144 $ 1,934 3.2 Review shop drawings, submittals, and change order proposals 23 $ 3,617 16 $ 2,208 $ 2,208 $ 92 $ 5,917 3.3 Review RFIs and pay requests, and provide written response(s) to the City - 6 6 12 - 24 $ 4,002 2 $ 276 $ 276 $ 102 $ 4,380 3.4 Provide on -site construction observation - 8 40 40 - 88 $ 14,088 170 $ 23,460 $ 23,460 $ 1,419 $ 38,967 Subtotal - 20 57 68 - 145 $ 23,497 188 $ 25,944 $ 25,944 $ 1,758 $ 51,199 Task 4 PROJECT MANAGEMENT FOR CENTRAL BUSINESS DISTRICT SANITARY SEWER REHABILITATION 4.1 Coordinate with City staff regarding schedule, progress, and technical questions - 2 2 2 2 8 $ 1,292 $ - $ - $ 34 $ 1,326 4.2 Prepare for and attend two (2) construction progress meetings - 6 8 - 2 16 $ 2,782 6 $ 828 $ 828 $ 143 $ 3,753 4.3 Prepare invoices and monitor project budget - 2 2 - - 4 $ 734 $ - $ - $ 19 $ 753 Subtotal - 10 12 2 4 28 $ 4,808 6 $ 828 $ 828 $ 196 $ 5,832 Task 5 SDC FOR SANITARY SEWER MANHOLE REHABILITATION 5.1 Prepare for and attend one (1) pre - construction meeting - 4 6 - - 10 $ 1,790 $ - $ - $ 144 $ 1,934 5.2 Review shop drawings, submittals, and change order proposals - 2 6 16 - 24 $ 3,778 16 $ 2,208 $ 2,208 $ 96 $ 6,082 5.3 Review RFis and pay requests, and provide written response(5) to the City - 6 6 12 - 24 $ 4,002 3 $ 414 $ 414 $ 102 $ 4,518 5.4 Provide on -site construction observation - 8 20 20 - 48 $ 7,868 80 $ 11,040 $ 11,040 $ 815 $ 19,723 Subtotal - 20 38 48 - 106 $ 17,438 99 $ 13,662 $ 13,662 $ 1,158 $ 32,258 Task 6 PROJECT MANAGEMENT FOR SANITARY SEWER MANHOLE REHABILITATION - 1 1 1 1 6.1 Coordinate with City staff regarding schedule, progress, and technical questions 4 $ 646 $ - $ - $ 18 $ 664 6.2 Prepare for and attend two (2) construction progress meetings - 6 8 - 2 16 $ 2,782 6 $ 828 $ 828 $ 143 $ 3,753 6.3 Prepare invoices and monitor project budget - 1 1 - - 2 $ 367 $ - $ - $ 10 $ 377 Subtotal - 8 10 1 3 22 $ 3,795 6 $ 828 $ 828 $ 171 $ 4,794 PROJECT TOTAL 1 62 122 121 9 315 $ 51,939 299 $ 41,262 $ 41,262 $ 3,373 $ 96,574 J:\Uata\TUK\113 .05612015 CBD\Cordract\2015 SDC Ca,,tract\S,,pp AgmtNa. 1_FEE 2015 050 Rehab - SE C.dax 11/17/20155:21 PM