HomeMy WebLinkAboutReg 2015-12-07 Item 3I - Agreement - Tukwila International Boulevard Redevelopment: Motel Demolition Construction Management with Akana for $72,646COUNCIL AGENDA SYNOPSIS --- -------------- --------- -- - - - - -- Initial, Meetin ,g Date Prepared by Mayor's review, Council review 12/07/15 BG ITEM INFORMATION ITEM NO. 3.1. CAS NUMBER: STAFF SPONSOR: BOB GIBERSON ORIGINAL,AGENDA DATE:: 12/07/15 AGENDA ITEnI TITLE Tukwila International Blvd Redevelopment Project - Demolition Construction Management Contract with AKANA CATEGORY ❑ Discussion Mtg Date ® Motion Aft g Date 12107115 ❑ Resolution g Date Mt ❑ Ordinance Aft g Date ❑ BidAward Mt g Date ❑ Public Hearing Aft g Date ❑ Other g Date Aft SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police ® PIV SPONSOR'S This contract is for construction management services for the Tukwila International SUMMARY Boulevard Redevelopment Project - Demolition. AKANA was selected from the list of three consulting firms. Construction management services will include project management, documentation, and part -time inspection for the demolition contract that the City plans to award in December 2015. Council is being asked to approve the construction management contract with AKANA for $72,646.00. R1�VIEWED BY ❑ COW Mtg. ❑ CA &P Cmte ❑ F &S Cmte ❑ Transportation Cmte ® Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm. DATE: 11/24/15 COMMITTEE CHAIR: DENNIS ROBERTSON RECOMMENDATIONS: SPONSOR /ADMIN. Public Works COMMrrrrE Unanimous Approval; Forward to Consent Agenda COST IMPACT / FUND SOURCE EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $72,646.00 $250,000.00 $0.00 Fund Source: 302 FACILITIES (PAGE 43, 2015 CIP) Comments: MTG. DATE RECORD OF COUNCIL ACTION 12/07/15 MTG. DATE ATTACHMENTS 12/07/15 Informational Memorandum dated 11/20/15 Consultant Selection Scoring Matrix Page 43, 2015 CIP AKANA Contract with Scope of Work and Fee Minutes from the Utilities Committee meeting of 11/24/15 59 AM City of Tukwila Jim Haggerton, Mayor INFORMATIONAL MEMORANDUM TO: Mayor Haggerton Utilities Committee FROM: Bob Giberson, Public Works Director BY: Robin Tischmak, City Engineer DATE: November 20, 2015 SUBJECT: Tukwila International Blvd Redevelopment Project — Motel Demolition Project No. 91330201 Construction Management Consultant Selection and Contract ISSUE Execute a construction management contract with AKANA for the demolition of the Great Bear, Boulevard, and Spruce Motels and Sam's Smoke Shop on Tukwila International Boulevard (TIB). Demolition of the Traveler's Choice is included if awarded by Council. BACKGROUND The City purchased the Great Bear, Boulevard and Traveler's Choice motels from the Federal Government in 2014 and Sam's Smoke Shop and the Spruce Motel in 2015 as part of the TIB Redevelopment Project. Bids were received and opened on October 22, 2015 for demolition of the buildings and site stabilization, which the City plans to award in December 2015. ANALYSIS Management of the construction contract will require outside consulting services to assist with project management, documentation, and part -time inspection. The City is proposing to provide an inspector from Public Works staff to cover the majority of the inspection. AKANA was selected from a list of three firms and was determined to be the most qualified consultant to provide the requested services. The proposed contract scope of work is based on the number of expected working days in the contract and is independent of whether or not the City awards the Bid Alternate No. 1 to demolish the Traveler's Choice Motel. BUDGET AND BID SUMMARY Contract Budget AKANA CM Contract $ 72,646.00 $250,000.00 RECOMMENDATION Council is being asked to approve the construction management contract for the TIB Redevelopment Project with AKANA for $72,646.00, and to consider this item on the Consent Agenda at the December 7, 2015 Regular Meeting. Attachments: Consultant Selection Scoring Matrix Page 43, 2015 CIP Contract with Scope of Work and Estimate WAPW Eng \PROJECTSW- BG Projects \Tukwila Village (90030222) \Demolition \Info Memo Demolition Motels - CM AKANA 11 -20 -15 gl- rt.docx 61 62 Tukwila International Blvd. Redevelopment Project - Motel Demolition Consultant 0 io i� 0 Cm 0 V Date: 11/4/15 H: \Scoring Matrix.xlsScoring Matrix.xls W Total Possible Points 15 20 20 10 15 20 100 AKANA 15 20 18 10 15 20 98 1 Anchor Envronmental 15 20 17 5 15 20 92 2 Harris & Associates 15 16 16 8 12 18 85 3 Date: 11/4/15 H: \Scoring Matrix.xlsScoring Matrix.xls W CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2015 to 2020 PROJECT: TIB Redevelopment Project Project No. 91330201 DESCRIPTION: This Tukwila International Blvd (TIB) Redevelopment Project is for the acquisition and disposition of properties within and adjacent to the City's Urban Renewal Area. JUSTIFICATION: Improve the neighborhood's safety by eliminating the high amounts of crime associated with the motel properties. STATUS: The City has completed appraisals and is in negotiations with the property owners and the US Attorney General's Office to purchase four motels and a smoke shop. MAINT. IMPACT: If purchased, the City will need to demolish buildings and maintain the properties until they are redeveloped. COMMENT: Land purchase costs are based on appraised value. Engineering includes legal and administrative expenses. Debt service costs are not shown (see Attachment A). FINANCIAL Through Estimated (in $000's) 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL EXPENSES Engineering 35 250 250 535 Land (R/W) 3,610 1,590 5,200 Construction 250 200 50 500 TOTAL EXPENSES 35 4,110 1 2,040 1 50 1 0 0 0 0 0 6,235 FUND SOURCES Awarded Grant 0 Proposed Grant 0 Land Sale 2,250 2,250 Bonds 3,850 2,250 6,100 City Oper. Revenue 35 260 (210) (2,200) 0 0 0 0 0 (2,115) TOTAL SOURCES 35 4,110 1 2,040 1 50 1 01 01 01 01 01 6,235 2015 - 2020 Capital Improvement Program 43 M City of Tukwila Contract Number: 6200 Southcenter Boulevard, Tukwila WA 98188 CONSULTANT AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES THIS AGREEMENT is entered into between the City of Tukwila, Washington, hereinafter referred to as "the City ", and AKANA, hereinafter referred to as "the Consultant ", in consideration of the mutual benefits, terms, and conditions hereinafter specified. 1. Proiect Designation. The Consultant is retained by the City to perform Construction management services in connection with the project titled Urban Renewal Motel Demolition. 2. Scope of Services. The Consultant agrees to perform the services, identified on Exhibit "A" attached hereto, including the provision of all labor, materials, equipment and supplies. 3. Duration of Agreement; Time for Performance. This Agreement shall be in full force and effect for a period commencing upon execution and ending 270 Calendar days from execution, unless sooner terminated under the provisions hereinafter specified. Work under this Agreement shall commence upon written notice by the City to the Consultant to proceed. The Consultant shall perform all services and provide all work product required pursuant to this Agreement no later than 270 Calendar days from NTP unless an extension of such time is granted in writing by the City. 4. Payment. The Consultant shall be paid by the City for completed work and for services rendered under this Agreement as follows: A. Payment for the work provided by the Consultant shall be made as provided on Exhibit "B" attached hereto, provided that the total amount of payment to the Consultant shall not exceed $72,646.00 without express written modification of the Agreement signed by the City. B. The Consultant may submit vouchers to the City once per month during the progress of the work for partial payment for that portion of the project completed to date. Such vouchers will be checked by the City and, upon approval thereof, payment shall be made to the Consultant in the amount approved. C. Final payment of any balance due the Consultant of the total contract price earned will be made promptly upon its ascertainment and verification by the City after the completion of the work under this Agreement and its acceptance by the City. D. Payment as provided in this section shall be full compensation for work performed, services rendered, and for all materials, supplies, equipment and incidentals necessary to complete the work. E. The Consultant's records and accounts pertaining to this Agreement are to be kept available for inspection by representatives of the City and the state of Washington for a period of three (3) years after final payments. Copies shall be made available upon request. 65 5. Ownership and Use of Documents. All documents, drawings, specifications and other materials produced by the Consultant in connection with the services rendered under this Agreement shall be the property of the City whether the project for which they are made is executed or not. The Consultant shall be permitted to retain copies, including reproducible copies, of drawings and specifications for information, reference and use in connection with the Consultant's endeavors. The Consultant shall not be responsible for any use of the said documents, drawings, specifications or other materials by the City on any project other than the project specified in this Agreement. 6. Compliance with Laws. The Consultant shall, in performing the services contemplated by this Agreement, faithfully observe and comply with all federal, state, and local laws, ordinances and regulations, applicable to the services rendered under this Agreement. 7. Indemnification. The Consultant shall defend, indemnify and hold the City, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or resulting from the acts, errors or omissions of the Consultant in performance of this Agreement, except for injuries and damages caused by the sole negligence of the City. Should a court of competent jurisdiction determine that this Agreement is subject to RCW 4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or damages to property caused by or resulting from the concurrent negligence of the Consultant and the City, its officers, officials, employees, and volunteers, the Consultant's liability hereunder shall be only to the extent of the Consultant's negligence. It is further specifically and expressly understood that the indemnification provided herein constitutes the Consultant's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement. 8. Insurance. The Consultant shall procure and maintain for the duration of the Agreement, insurance against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work hereunder by the Consultant, its agents, representatives, or employees. Consultant's maintenance of insurance as required by the agreement shall not be construed to limit the liability of the Consultant to the coverage provided by such insurance, or otherwise limit the City's recourse to any remedy available at law or in equity. A. Minimum Amounts and Scope of Insurance. Consultant shall obtain insurance of the types and with the limits described below: CA revised : 1 -2013 W% 1. Automobile Liability insurance with a minimum combined single limit for bodily injury and property damage of $1,000,000 per accident. Automobile Liability insurance shall cover all owned, non - owned, hired and leased vehicles. Coverage shall be written on Insurance Services Office (ISO) form CA 00 01 or a substitute form providing equivalent liability coverage. If necessary, the policy shall be endorsed to provide contractual liability coverage. Page 2 2. Commercial General Liabilitv insurance with limits no less than $1,000,000 each occurrence, $2,000,000 general aggregate. Commercial General Liability insurance shall be written on ISO occurrence form CG 00 01 and shall cover liability arising from premises, operations, independent contractors and personal injury and advertising injury. The City shall be named as an insured under the Consultant's Commercial General Liability insurance policy with respect to the work performed for the City. 3. Workers' Compensation coverage as required by the Industrial Insurance laws of the State of Washington. 4. Professional Liability with limits no less than $1,000,000 per claim and $1,000,000 policy aggregate limit. Professional Liability insurance shall be appropriate to the Consultant's profession. B. Other Insurance Provision. The Consultant's Automobile Liability and Commercial General Liability insurance policies are to contain, or be endorsed to contain that they shall be primary insurance with respect to the City. Any Insurance, self- insurance, or insurance pool coverage maintained by the City shall be excess of the Consultant's insurance and shall not be contributed or combined with it. C. Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M. Best rating of not less than A: VII. D. Verification of Coverage. Consultant shall furnish the City with original certificates and a copy of the amendatory endorsements, including but not necessarily limited to the additional insured endorsement, evidencing the insurance requirements of the Consultant before commencement of the work. Certificates of coverage and endorsements as required by this section shall be delivered to the City within fifteen (15) days of execution of this Agreement. E. Notice of Cancellation. The Consultant shall provide the City with written notice of any policy cancellation, within two business days of their receipt of such notice. F. Failure to Maintain Insurance. Failure on the part of the Consultant to maintain the insurance as required shall constitute a material breach of contract, upon which the City may, after giving five business days notice to the Consultant to correct the breach, immediately terminate the contract or, at its discretion, procure or renew such insurance and pay any and all premiums in connection therewith, with any sums so expended to be repaid to the City on demand, or at the sole discretion of the City, offset against funds due the Consultant from the City. 9. Independent Contractor. The Consultant and the City agree that the Consultant is an independent contractor with respect to the services provided pursuant to this Agreement. Nothing in this Agreement shall be considered to create the relationship of employer and employee between the parties hereto. Neither the Consultant nor any employee of the Consultant shall be entitled to any benefits accorded City employees by virtue of the services provided under this Agreement. The City shall not be responsible for withholding or otherwise deducting federal income tax or social security or for contributing to the state industrial insurance program, otherwise assuming the duties of an employer with respect to the Consultant, or any employee of the Consultant. CA revised : 1 -2013 Page 3 67 10. Covenant Against Contingent Fees. The Consultant warrants that he has not employed or retained any company or person, other than a bonafide employee working solely for the Consultant, to solicit or secure this contract, and that he has not paid or agreed to pay any company or person, other than a bonafide employee working solely for the Consultant, any fee, commission, percentage, brokerage fee, gifts, or any other consideration contingent upon or resulting from the award or making of this contract. For breach or violation of this warrant, the City shall have the right to annul this contract without liability, or in its discretion to deduct from the contract price or consideration, or otherwise recover, the full amount of such fee, commission, percentage, brokerage fee, gift, or contingent fee. 11. Discrimination Prohibited. The Consultant, with regard to the work performed by it under this Agreement, will not discriminate on the grounds of race, religion, creed, color, national origin, age, veteran status, sex, sexual orientation, gender identity, marital status, political affiliation or the presence of any disability in the selection and retention of employees or procurement of materials or supplies. 12. Assignment. The Consultant shall not sublet or assign any of the services covered by this Agreement without the express written consent of the City. 13. Non - Waiver. Waiver by the City of any provision of this Agreement or any time limitation provided for in this Agreement shall not constitute a waiver of any other provision. 14. Termination. A. The City reserves the right to terminate this Agreement at any time by giving ten (10) days written notice to the Consultant. B. In the event of the death of a member, partner or officer of the Consultant, or any of its supervisory personnel assigned to the project, the surviving members of the Consultant hereby agree to complete the work under the terms of this Agreement, if requested to do so by the City. This section shall not be a bar to renegotiations of this Agreement between surviving members of the Consultant and the City, if the City so chooses. 15. Applicable Law; Venue; Attorney's Fees. This Agreement shall be subject to, and the Consultant shall at all times comply with, all applicable federal, state and local laws, regulations, and rules, including the provisions of the City of Tukwila Municipal Code and ordinances of the City of Tukwila. In the event any suit, arbitration, or other proceeding is instituted to enforce any term of this Agreement, the parties specifically understand and agree that venue shall be properly laid in King County, Washington. The prevailing party in any such action shall be entitled to its attorney's fees and costs of suit. Venue for any action arising from or related to this Agreement shall be exclusively in King County Superior Court. 16. Severability and Survival. If any term, condition or provision of this Agreement is declared void or unenforceable or limited in its application or effect, such event shall not affect any other provisions hereof and all other provisions shall remain fully enforceable. The provisions of this Agreement, which by their sense and context are reasonably intended to survive the completion, expiration or cancellation of this Agreement, shall survive termination of this Agreement. CA revised : 1 -2013 MP Page 4 17. Notices. Notices to the City of Tukwila shall be sent to the following address: City Clerk City of Tukwila 6200 Southcenter Boulevard Tukwila, WA 98188 Notices to Consultant shall be sent to the following address: Jeff Faunce 3380 146" place SE, suite 105 Bellevue, Washington 98007 18. Entire Agreement; Modification. This Agreement, together with attachments or addenda, represents the entire and integrated Agreement between the City and the Consultant and supersedes all prior negotiations, representations, or agreements written or oral. No amendment or modification of this Agreement shall be of any force or effect unless it is in writing and signed by the parties. DATED this day of CITY OF TUKWILA Mayor, Jim Haggerton Attest /Authenticated: City Clerk, Christy O'Flaherty CA revised: 1 -2013 20 CONSULTANT Printed Name: Ken Valder Title: Vice President Approved as to Form: Office of the City Attorney Page 5 M 70 EXHIBIT A SCOPE OF SERVICES Construction Management Services City of Tukwila Urban Renewal Motel Demolition Akana (CONSULTANT) will provide professional Construction Management (CM) Services for the City of Tukwila (CITY). These services will include CM, contract administration, field observation, documentation, and reporting as required during the "Urban Renewal Motel Demolition Project ". All services will be provided in accordance with the Washington State Department of Transportation's (WSDOT) Local Agency Guidelines and Construction Manual. Consultant will be providing Construction Management (Jeff Faunce), Contract Administrator, and Inspection services on a Part time basis to the project to perform the duties listed below. Project Description The project includes Demolition and site reconfiguration of four (4) Motel properties and one retail property, including but not limited to: removal of site structures and improvements, cutting /capping utilities, removal of one approx. 60" Dia. retention pipe, removal of concrete and asphalt paving, installation of new chain link and cedar split rail fencing, new drainage, piping and illumination and other work necessary. Work Breakdown Structure by Tasks 100 Pre - Construction Services: 101 CONSULTANT will review bid documents to become familiar with the project. 102 City Inspector will take pre- construction photographs and burn them to a disc to include in hard -copy files. 103 CONSULTANT will conduct a site visit with City Inspector to become acquainted with the project site. 104 CONSULTANT will prepare hard -copy and electronic files for project documentation. 105 CONSULTANT will prepare Project Templates for: A. Design Changes B. Change Orders and Change Order Justifications C. Case Log and Case Log Files D. Pay Estimates, including Ledger E. Forecasted Cost to Complete F. Coordination Meeting Agendas, Minutes and Sign -In Sheets 106 CONSULTANT will prepare Project Logs for tracking: A. Design Changes B. Change Orders C. Requests for Information(RFI) D. Submittals E. Materials on Hand (will correlate with Pay Estimates) F. Employment Documentation 107 CONSULTANT will prepare for, and conduct, a Pre - Construction meeting. Duties will include: A. Preparing an agenda draft and sending it to the CITY for review /comments. B. Developing an attendees list with input from CITY. C. Conducting the meeting. D. Preparing Meeting Minutes, sending them to CITY for review /comments, revising them per comments and distributing them to attendees and affected stakeholders. 108 CONSULTANT will review the Contractor's initial Schedule against allowable Working Days. CONSULTANT will also review schedule sequencing and activity duration to check that they are reasonable. Any discrepancies, conflicts or unreasonable work durations will be brought to the attention of the Contractor and the CITY will be notified. 109 CONSULTANT will prepare up to 4 monthly CONSULTANT progress invoices for CITY review and payment. 200 Construction Management Administration: 71 201 CONSULTANT will prepare up to 4 Monthly Progress Pay Estimates for work performed by Contractor. These will be completed once CONSULTANT and Contractor have reached agreement on estimate quantities. 202 City inspector will prepare Weekly Statement of Working Day reports. 203 CONSULTANT will monitor Contractor and Sub - Contractor's employment documentation for adherence to contract requirements. Monitoring will include: A. Maintaining Employment Documentation Log. B. Collecting, reviewing and approving (or rejecting) Requests to Sublet. C. Collecting Certified Payrolls to verify that they meet contract wage requirements. D. Collecting Statements of Intent to pay prevailing wages. E. Collecting Affidavits of Wages Paid. 204 CONSULTANT will review and respond to Requests for Information (RFIs) submitted by the Contractor. Responses will include technical interpretations of the drawings, specifications, and Contract Documents. The CONSULTANT will update the RFI Log as RFIs are submitted and resolved. 205 CONSULTANT and City Inspector will monitor issues that may eventually have impacts to the project budget or schedule. These issues will be documented Information included in the Log will be: A. An assigned number that will be used to track each issue separately. B. The date the issue became known. C. A description of the issue. D. An estimate of the lowest cost necessary to resolve the issue. If resolution creates an overall decrease to the budget, this amount would be negative. E. An estimate of the highest cost necessary to resolve the issue. F. An estimate of the issue's impact on Working Days. G. A summary of project documents that relate to the issue. H. Comments relating to the issue. 206 CONSULTANT will prepare Change Orders and will include the CITY in the process of Change Order negotiation and preparation. Items tracked using the Issue Log may eventually become Change Orders. CONSULTANT Change Order work will include: A. Scheduling and conducting negotiation meetings. The CONSULTANT will create and distribute meeting agendas and minutes. B. Preparation of independent Engineer's Estimates. C. Compilation of Change Order back -up. This will include, but is not limited to: i. Engineer's Estimates ii. E -mail correspondence iii. Extra Work Orders from Contractor iv. Design Change Documents v. Meeting Minutes D. Preparation of Change Order Justifications. (1 change order included in proposal cost) Justifications will include: i. A description of the change. ii. An evaluation of what is required by the Contract. iii. An explanation as to why a Change Order is necessary. iv. Descriptions of considered alternatives to a Change Order. v. The reasons for entitlement; why the work cannot be paid for under the existing contract. vi. The names of those that approved the Change Order. vii. An evaluation of impact to Working Days. viii. Change Order back -up. E. Writing the Change Orders and providing them to CITY for edits and /or concurrence. F. Obtaining the necessary signatures for execution once concurrence has been given by the CITY. G. Maintaining the Change Order Log. 300 Construction Services - Field: Calendar Days 180: of these days 135 Calendar days compromise this contract proposal as indicated on page P -1 of the contract documents. 72 CONSULTANT will provide Part time Inspection consisting of a senior and Junior inspector depending on the skill sets needed for the days operation to assist in layout and slope verification to meet ADA and observe day -to -day conduct of construction. This will include acting as the project hub for communications, monitoring Contractor adherence to Contract Documents and documentation of Contractor's work progress for payment. Work will include the following: 301 CONSULTANT will request and review the Contractor's breakdowns of lump -sum items for accuracy and payment purposes. Breakdowns will be used to evaluate construction progress of these items for pay estimates. 302 City and Consultant Inspectors will prepare Field Note Records that detail Contractor's completed work for inclusion in monthly Pay Estimates. Field Note Records will internally be checked for accuracy prior to being entered into Pay Estimates. 303 Prior to monthly Pay Estimate completion, the City and CONSULTANT will coordinate with the Contractor to reach agreement on the Pay Estimate quantities. 304 City will review the materials delivered to the project site to ensure they are the approved construction materials. This will be done by checking them against the approved Submittals and noting materials delivered on Inspector Daily Reports (IDR). 305 The CONSULTANT Inspector(s) will prepare up to 10 Inspector's Daily Reports when city Inspector is absent. If there is more than one Inspector, each will prepare an individual report. IDRs will include: A. Weather information. B. Contractor and Subcontractors working that date, as well as the on -site representative for each. C. A work activity summary. D. Bid items worked on. E. Equipment and employees utilized and hours used /worked. F. A diary to be used as a narrative of the day's events. G. Photos. H. Materials used. 306 City and Consultant will take photos of construction progress and will maintain them electronically in an orderly fashion. Upon completion of the project, these photos will be burned to discs that will be included in the hard -copy files. 307 CONSULTANT will assist the CITY regarding Public Information by assisting the CITY with responding to project related questions from property owners and the general public. 308 City and Consultant will review the Contractor's As -Built drawings. Drawings will be checked for accuracy and to determine if they reflect as- constructed conditions. 400 Materials: City will review submittals by the Contractor. Materials that do not require testing will be rejected, approved or conditionally approved per the requirements of the City and the Contract provisions. Materials that require testing will be rejected, approved or conditionally approved per results of field evaluation and WSDOT Construction Manual requirements. The Contractor will be notified immediately of any unapproved materials or failed test results. 401 CONSULTANT will update the Submittal list as submittals are rejected, approved, or conditionally approved as well as when test results are obtained. 402 City and Consultant will inspect materials and conduct testing in accordance with the Cities direction and the WSDOT Construction Manual. 403 City and Consultant will inspect the Concrete for adherence to Contract requirements. Test cylinders will be taken as required, inspectors will inspect loads to verify that conformance with Mix design is met. 404 City and Consultant will inspect installation of Hot Mix Asphalt for adherence to Contract requirements. 405 Consultant will provide a sub consultant to perform a Minor Materials Testing to a limit of $5000.00 for Asphalt compaction, Concrete Cylinders, and backfill compaction as directed by the Inspection staff. 500 Project Completion: Assist the CITY with the close -out of the project. Items of work include the following: 73 501 CONSULTANT will coordinate with the CITY, and the Contractor to resolve outstanding project issues. This includes up to 2 Project Closeout Meetings. The CONSULTANT will prepare and distribute the agendas and minutes. 502 City will prepare and issue a Letter of Substantial Completion. Prior to being issued to the Contractor. Issuance of this letter will mark the beginning of project completion. 503 CONSULTANT will coordinate with the Contractor to obtain all outstanding project documentation. 504 City and Consultant will prepare a Punch List of work items for the Contractor. This list will be created with input from the CITY. Creation of the list will include 1 initial project walkthrough and up to 2 follow - up walkthroughs to ensure Punch List work is complete. The list may still be revised after it has been issued to the Contractor. 505 City will prepare and issue a Letter of Physical Completion. This letter will denote that the Contractor's work is completed. 506 City and Consultant will take photos of completed project and will maintain them electronically in an orderly fashion. Upon completion of the project, these photos will be burned to discs that will be included in the hard -copy files. 507 City and Consultant will receive As- Builts (Record Drawings) from the Contractor upon issuance of Physical Completion and will perform a review of the drawings for accuracy. 508 CONSULTANT will prepare the Final Pay Estimate and Voucher. Prior to being issued to the Contractor, drafts of these items will be routed to the CITY for review /approval. 509 CONSULTANT will review the project records to verify that they are complete. This will be a last check before hard -copy files are transferred to the CITY. 510 Attend a wrap up meeting with the CITY. 600 Optional Field Services: Upon written approval from the CITY, the CONSULTANT shall provide engineering services beyond the work identified above. Services may include the addition of new tasks; additional working days added to the contract or increasing the work effort of the engineering services as directed by the CITY. Such work shall be specified in a written Supplement to this Agreement. Optional services may include: additional work caused by extension of contract time due to Non - Working Days or schedule delays, additional project meetings, additional testing due to failing tests, additional surveying and mapping, additional geotechnical analysis, additional environmental documentation, document printing and overtime due to the contractor working weekends. Assumptions: • This scope and fee does not include construction support services during non - working days. A Non - Working Day is defined in the WSDOT Standard Specifications as "...unworkable because of weather or conditions caused by the weather that prevents satisfactory and timely performance of the work shown on the critical path of the Contractor's approved schedule." If the contract amount under this agreement is exceeded, the CONSULTANT may request a supplement to cover the costs incurred from work completed on Non - Working Days. • Construction will take no more than 135 Calendar days for this contract proposal as indicated on page P- 1 of the contract documents. • The Contractor will be responsible for environmental documentation requirements. • No Overtime has been estimated. • Assume the contractor will work 8:00 am to S:OOpm, working a 40 hour week, 8 hours a day, I shift. • No office space for Consultant will be provided, weekly meeting space will be assumed to be available at Public works. • Consultant will provide vehicle and fuel, cell phone, standard safety wear and laptop computer. • Mileage for PPM, PM /RE, PE, and CA, assume 40 x trips @ 60 miles round trip (includes anticipated on -site daily mileage). inspection mileage will be charged assume 65 trips at 60 miles round trip 74 Deliverables by Task: • 100 Pre - Construction Services 0 101 Sub - Consultant Agreements 0 102 Notice to Proceed Letter 0 103 Award Data Package 0 112 Pre - construction meeting agenda, sign -in sheet and minutes 0 113 Initial CPM Schedule Review with up to 2 updates 0 114 4 CONSULTANT Progress Invoices • 200 Construction Management Administration 0 201 Up to 4 Pay Estimates 0 203 Employment documentation and tracking log for Contractor and Sub - Contractors 0 204 RFI responses and RFI Log 0 205 Case Log 0 207 Change Orders (CO), a CO Log and CO justifications with back -up • 300 Construction Services — Field 0 301 Review of lump -sum breakdowns 0 302 Field Note Records 0 304 Scale Certifications, Scaleman's Daily Reports and Scale Report Log 0 306 Inspector's Daily Reports ( Consultant) 0 308 Disc of construction progress photos • 400 Materials 0 401 Approved Request for Approval of Materials (RAM), ROM and test reports • 500 Project Completion 0 501 Meeting agendas, sign -in sheets and minutes for up to 2 close -out meetings 0 502 Letter of Substantial Completion 0 504 Final Punch List 0 505 Final Change Order 0 506 Letter of Physical Completion 0 507 Disc of completed project photos 0 508 Contractor produced As- Builts (Record Drawings) 0 509 Final Pay Estimate and Voucher 0 510 Hard - copies of project files 75 76 Proposal Fee Estimate Exhibit B CLIENT Name: City of Tukwila PROJECT Description: Urban Renewal Motel Demolition phase 2 Scott inspection Proposal /Job Number: Date: 11/12/15 AKANA January 1, 2014 Rates Classification: d V 3 u - : w L N d L N -° O a d N Y .E ma Q Total CZE CZE CZE 1 Sub T 0 C7 d L c = x o H O ii. ° Sub CZE 0. 3 L to 2 R la 5 in CZE co V O CZE Q. co z V i 0 2 Total Expenses Total Labor + Expenses Hourly Rate: $72 1 $72 1$50 $40 $30 Hours Fees 143% 10% Fees Fees 5% Fees 5% Fees Task 100 - preconstruction services Preconstruction services 16 4 8 12 24 64 $3,042 $4,353 $739 $0 $0 $5,092 $8,134 $0 $0 $0 $0 $0 $0 $0 $01 $0 $0 $0 $0 $0 $0 Task 0 OI 0 $01 $0 $01 $0 $0 $0 $0 Task 100 - Subtotal 16, 4i 8 12, 24 64 $3,042 $4,353 $739 $0 $0I $0I $0 $0 $5,092 $8,134 Task 200 - Construction Services Field office Administration 48 156 204 $8,142 $11,651 $1,979 $0, $0 $1,344 $67 $15,041 $23,183 FA tracking 12 32 44 $1,825 $2,612: $3,7381 $0 $0 $6,350 $8,176 0 $0 $0 $0 $0 $0 $0 $0 0 $0 $0 $0, $0 $0 $0 $0 Task 200- Subtotal 601 OI 0 0 188 248 $9,967 $14,263, $5,717 $0 $0 $0 $1,344', $67 $21,392 $31,359 Task 300 - Construction Services Field field inspection services fa tracking 36 80 116 0 $6,596 $9,439 $1,604; $0. $0 $0 $0, $2,184 $0 $109 $0 $13,336 $0 $19,932 $0 Task 0 $0 $0 $0 $0 $0 $0 $0 0 $0; $0 $0 $0 $0 $0 $0 Task300- Subtotal 36 0 80 01 0 116 $6,5961 $9,439 $1,604 $0 $0 $0I $2,184 $109 $13,336 $19,932 Task 400 - materials materials 0 $0 $0 $0, $5,000 $250 $0 $5,250 $5,250 Task 0 $0, $01 501 $0 $0 $0 $0 Task 0 $01 $0 $0 $0 $0 $0 $0 Task 0 $0 $0 $0 $0 $0 $0 $0 Task 400 - Subtotal O1 0 0 0; 0 0 $0 $0 $0 $0 $5,000 $250', 501 $0 $5,250 $5,250 Task 500 - Project Completion closeout 16, 16,1 24 56 $2,674', $3,826: $650 $781 $39 $0 $5,296 $7,970 Task i 0 $01 $0 $0 $0 $0 $0 $0 Task ' 0 $01 $01 $0 :: $0 $0 $0 $0 Task 0 $0 $0 $0 $0 $0 $0 $0 Task 500 - Subtotal 16 0 16 01 24 56 $2,6741 $3,8261 $650 $781 1 $0i $391 $01 $0 $5,296 $7,970 hidden line - task groups end I All Phases Total 128 4', 104 121 236 484 $22,279 $31,882j $8,710, $7811 $5,000', $289 $3,528, $176 $50,367 572,646 W: \PW Eng \ OTHER \Forms \Agendas \UC Agenda Items \Exhibit E-1 Cost Estimate phase 2 2012 Cooper Zieiz Engineers, Inc. m Utilities Committee Minutes November 24, 2095 - Page 2 supplement if approved will provide construction management support for the two projects, including inspections, material review, change order requests, and payment assistance. UNANIMOUS APPROVAL. FORWARD TO DECEMBER 7, 2015 REGULAR CONSENT AGENDA. F. Consultant Selection: Tukwila International Boulevard Redevelopment Protect Staff is seeking Council approval of a construction management contract with AKANA in the amount of $72,646.00 for the Tukwila International Boulevard Redevelopment Project. This project will demolish the Sam's Smoke Shop building along with the Great Bear, Boulevard, and Spruce Motels. The proposed scope of work is based on the number of expected working days and is independent of the decision the Council makes regarding the Travelers Choice Motel. That property is currently being evaluated as a potential site for art use in partnership with 4Culture, and a decision is expected in December. UNANIMOUS APPROVAL. FORWARD TO DECEMBER 7, 2015 REGULAR CONSENT AGENDA. G. Water Sewer, and Surface Water Rates for 2016 Staff is seeking Council approval of a resolution adopting a new Public Works fee schedule to update water, sewer, and surface water rates for 2016. Committee packets include rate comparison charts for neighboring cities for each type. Water: After analyzing the needs of the water enterprise fund, staff is proposing no increase for single family or multifamily residential customers and a 5% increase for commercial /industrial. Sewer: Staff is proposing no increase for residential customers and a 5% increase for commercial /industrial. Surface Water: Staff is proposing a 15% increase for residential and commercial customers. Committee members asked clarifying questions. Committee Chair Robertson requested a 2016 work plan item to discuss financing of large projects in greater detail, including information on utility- specific local improvement districts. The Committee forwarded the resolution to the consent agenda but asked that Public Works staff be in attendance to address any questions that arise. UNANIMOUS APPROVAL. FORWARD TO DECEMBER 7, 2015 REGULAR CONSENT AGENDA. III. MISCELLANEOUS Meeting adjourned at 6:15 p.m. Next meeting: Tuesday, December 15, 2015 - 5:30 p.m. - Foster Conference Room Committee Chair Approval Minutes by L 1, Reviewed by GL 79