HomeMy WebLinkAboutTrans 2016-01-19 Item 2C - Discussion - 40-42 Avenue South (South 160th Street - South 131st Place) Phase III: 42nd Avenue South/South 160th Street Intersection Cost EstimateCity of Tukwila
Allan Ekberg, Mayor
TO: Mayor Ekberg
Transportation Committee
FROM: Bob Giberson, Public Works Director
BY: Cyndy Knighton, Senior Program Manager
DATE: January 15, 2016
SUBJECT: 40 -42 Ave South (S 160th — S 131 PI) Phase III
Project No. 99410303, Contract No 12 -010
42nd Avenue S/S 160th Street Intersection Cost Estimate
ISSUE
Cost estimates to improve the intersection of 42nd Ave S and S 1601h St, as part of the 42nd Avenue S Phase III Project.
I )_T41 &C %11P►1i7
On July 24, 2015, a Small Group Joint Meeting was held between the Tukwila Transportation Committee and elected officials
from the City of SeaTac. The focus of that meeting was coordination between the two jurisdictions on common issues such as
the Tukwila International Boulevard /Link Light Rail area, code enforcement, fire services, and other issues between the two
cities. Tukwila and SeaTac agreed to look at the intersection of 42nd Ave S & S 160th St and study what could be done to
improve the intersection safety, perhaps as part of Tukwila's 42nd Ave S Phase III Project, even though the actual intersection is
under SeaTac's jurisdiction. Tukwila's design work on the project is currently at the 90% level and is scheduled to begin
construction in 2016. SeaTac currently has no plans for improvements to the intersection or that portion of 42nd Ave S south of
the Tukwila city limits.
To study the potential improvements and develop planning -level cost estimates for the intersection, staff directed the design
consultant team at CH2MHill to produce conceptual drawings and cost estimates.
DISCUSSION
Two options were developed by the CH2MHill design team. Option 1 is for full intersection improvements that would include
repaving the entire intersection, improving the turning radius at the SE corner, installation of ADA compliant sidewalks, and
associated stormwater improvements (see attachment for Option 1). For this exercise, the assumption was made that the PSE
electrical pole relocation required is completed at no cost to the City. Actual costs for the PSE relocation would need to be
determined based on any franchise agreement that SeaTac has with PSE.
Option 2 would simply grind and overlay the entire intersection and sidewalks would only be installed on the north side of the
intersection, which is under Tukwila's jurisdiction (see attachment for Option 2).
FISCAL IMPACT
Due to the very preliminary nature of the cost estimates listed below, a large contingency has been factored in to provide a
buffer for budgeting considerations. The cost estimates for the two options include both design and construction costs, but do
not include any analysis for potential right -of -way acquisition. A more detailed cost estimate is included as an attachment.
Options
Cost Estimate
Option 1: Full Intersection with sidewalk improvements
$102,807.82
Option 2: Grind and Overlay Only
$19,318.00
RECOMMENDATION
For information only.
Attachments: Plan Drawings for Options 1 and 2 (2 pages)
Planning level cost estimate breakdowns for Options 1 and 2 (2 pages)
Meeting summary Small Group Joint Meeting 7/24/15 (2 pages)
11
WAPW Eng \PROJECTSIA• RW & RS Projects \42nd Ave S Phase 111 (99410303 94 -RS03) \Design \Info Memo 42nd Ave S -S 160th St Intersection Cost Estimate 1 -15 -16 gI sb.docx
IR
IR
IRR
IRR
V IN
IRU
1
1
IRI
IRR
1
IRUN IP IN
1
IRR
IRR
IMO
IRI
INN
INN
IRI
INN
IRI
1
JRU
IRI
IMO
UV
u
i-I , NrsD -
Mitlatal
.............
FULL DEPTH HMA PAVEMENT
40TH - 42ND AVENUE SOUTH - PHASE III
S 160TH ST TSIDEWALK
IMPROVEMENT OPTION 1
DATE: 01-08-16
PLANING BITUMINIOLIS PAVEMENT
AND HMA OVERLAY
1
SCALE: 1" 20'
0
N
FILL
PLANING BITUMINIOUS PAVEMENT
and HMA overlay
40TH - 42ND AVENUE SOUTH - PHASE III
S 160TH ST MILL & OVERLAY OPTION 2
DATE: 01-08-16
CA)
SCALE: 1" = 20'
40th - 42nd Ave South - Phase III
S 160th St/42nd Ave S Intersection
Option 1: Full Intersection with Sidewalk Improvements
Cost Estimate
Item No.
Sec.
No.
Item Description
Quantity
Unit
Unit Price
Total Price
SP/ST
D
1
1-09
Mobilization (assume 8% total)
1
LS
$ 3,900.00
3,900.00
STD
2
Traffic Control (assume 7% of total) not including Mobilization
1
LS
$ 3,200.00
3,200.00
SP
3
2-01
Clearing and Grubbing
0.04
AC
$ 15,000.00
533.82
STD
4
2-02
Remove Existing Drainage Structure
1
EA
$ 350.00
350.00
SP
5
2-02
Pavement Sawcutting
112
LF
2.50
280.00
SP
6
2-03
Roadway Excavation Incl. Haul
167
CY
15.00
2,505.00
STD
7
2-03
Gravel Borrow Incl. Haul
19
CY
35.00
665.00
STD
8
4-04
Crushed Surfacing Top Course (or Base Course)
26
TON
25.00
650.00
STD
9
5-04
Planing Bituminious Pavement
43
SY
10.00
430.00
STD
10
5-04
HMA Cl. 1/2-inch PG 64-22 (Class B)
54
TON
92.00
4,968.00
STD
11
5-04
HMA Cl. 1-inch PG 64-22 (Class E)
8
TON
92.00
736.00
STD
12
7-04
Corrugated polyethlyene Storm Sewer Pipe 12 In. Diam.
133
LF
38.00
5,054.00
STD
13
7-04
Corrugated polyethlyene Storm Sewer Pipe 18 In. Diam,
13
LF
42.00
546.00
STD
14
7-05
Catch Basin Type 1
4
EA
$ 1,200.00
4,800.00
STD
15
7-05
Connection to Drainage Structure
1
EA
$ 700.00
700,00
STD
16
7-05
Abandon and Fill Pipe
50.00
LF
25.00
1,250.00
SP
17
8-02
Topsoil Type A
3
CY
50.00
150.00
SP
18
8-02
Seeded Lawn Installation
42
SY
10.00
420.00
STD
19
8-04
Cement Conc. Traffic Curb and Gutter
156
LF
20.00
3,120.00
STD
20
8-14
Cement Conc Sidewalk
40
SY
32.00
1,280.00
STD
21
8-14
Cement Conc Curb Ramp Type Parallel A
4
EA
$ 1,500.00
6,000.00
STD
22
8-24
Modular Block Retaining Wall
373
SF
30.00
11,190.00
SP
Subtotal
$ 52,727.82
Contingency
I I
50%
26,360.00
Subtotal $
79,087.82
Design
15%
$ 11,860.00
Construction management
15%
11,860.00
Total Option 1
$ 102,807.82
Assume PSE pole relocation will be at no cost to City.
01 11 2016
SEATAC S 160th St -cost.xisx
40th - 42nd Ave South - Phase III
S 160th St/42nd Ave S Intersection
Option 2: Mill and Overlay Only
Cost Estimate
Item No.
1
2
3
Sec.
No.
1-09
5-04
Item Description
Mobilization (assume 8% total)
Traffic Control (assume 7% of total) not including Mobilization
Planing Bituminious Pavement
Quantity
1
1
410
Unit
LS
LS
SY
Unit Price
$ 700.00
$ 600.00
10.00
Total Price
700.00
600.00
$ 4,100.00
SP/ST
D
STD
SP
STD
4
5-04
HMA Cl. 1/2-inch PG 64-22 (Class B)
49
TON
92.00
$ 4,508.00
STD
Subtotal
$ 9,908.00
Contingency
I I
50%
$ 4,950.00
01/11/2016
Subtotal
$ 14,858.00
SEATAC S 160th St -cost.xlsx
Design
15%
$ 2,230.00
Construction management
15%
$ 2,230.00
Total Option 2 $19,318.00
SEATAC S 160th St -cost.xlsx
Small Group Joint Meeting
Meeting Summary
Small Group Joint Meeting Tukwila /SeaTac
Location:
SeaTac City Hall, McMicken Room
Date:
July 24, 2015
Begin Time:
9:00 a.m.
End Time:
10:27 a.m.
PRESENT
From SeaTac: Mia Gregerson, Mayor; Tony Anderson and Pam Fernald, Councilmembers;
Todd Cutts, City Manager; Joe Scorcio, Community and Economic
Development Director
From Tukwila: Joe Duffie, Dennis Robertson, Kathy Hougardy Councilmembers; David
Cline, City Administrator; Laurel Humphrey, Council Analyst
Welcome & Introductions
The meeting began with a welcome from Mayor Gregerson and self- introductions of attendees.
Tukwila International Boulevard Light Rail Station Area Update
Mr. Scorcio provided an update on planning in the South 154th Street station area, including
land assembly and infrastructure investment. The vision is for mixed -use, transit and pedestrian
friendly redevelopment with localized retail and high density housing. The development
community is aware of future opportunities in this area. Additionally, SeaTac is working with
the State on cleanup of the Betty Brite property. SeaTac will receive 1.25 million in State capital
funding for the International Marketplace project, which will be included in the development
concept for the area. Development in this area will include improvements to the intersection at
152nd and TIB. In its assessment of this area, the Urban Land Institute recommended fee -
based parking in support of light rail ridership and local business. He distributed copies of the
Station Area Project Background and Urban Land Institute recommendations.
Councilmember Robertson shared that current efforts toward the Tukwila International
Boulevard Comprehensive Plan update are focusing on a vision of a walkable area with main
street character. A consultant hired by the City advised that the market is not quite ready for
new housing.
Attendees discussed the importance of having a unified vision for this area, with common goals
and elimination of service redundancies. Leadership and planners from both cities are in
regular communication toward this effort. Councilmembers agreed that it would be useful to
have shared talking points when lobbying for funding or describing the common vision, and are
11111
supportive of staff collaboration with regular updates to Councils. Mayor Gregerson would like
this group to meet again on this topic with each group respectively reporting back to their
Councils on the outcome.
Code Compliance /Enforcement Update
Mr. Scorcio provided an update on code enforcement strategies in the City of SeaTac. The
program was adjusted during the last budget cycle and is currently undergoing review by a
dedicated, cross - departmental working group. There will be more focus on proactive practices
and community outreach than in the past. Their code was originally based on King County's
code and has evolved over time to better meet their needs. Substantial code amendments are
being developed now and expected to be reviewed by Council in September, Code
Enforcement staff from both cities regularly meet to share best practices. SeaTac is
considering a rental housing inspection program of their own. Councilmember Hougardy noted
that Tukwila's Strategic Plan was instrumental in giving staff the guidance to put resources into
strengthening code enforcement.
Fire Services Update
Mr. Cline provided an update on Tukwila's current examination of the possibility of annexing to
the Kent Regional Fire Authority. There is a steering committee, a finance committee, and a
governance committee evaluating various aspects, and the steering committee is on track to
make a recommendation to Council by the end of the year. Depending on the outcome and
Council approval there is possibility of a public vote in April 2016, concurrent with Kent RFA's
next vote. He noted that regardless of the outcome, the close proximity of SeaTac's Station
47 and Tukwila's Station 54 present a valuable opportunity for partnership and he would like to
continue that conversation.
Other
Mr. Cline noted the award of $1 billion in funding from the Legislature for the SR 509 extension
project. The project will benefit the whole area and is worth celebrating.
He also shared that Tukwila's Transportation Committee recently receive an update on the
intersection at 42nd Avenue South and South 160th Street. Tukwila is in the design phase of a
project that will construct ADA improvements in the northern corner. At that meeting Public
Works staff shared that SeaTac has no plans regarding the southern corners of the intersection.
He brought this to Mr. Cutts' attention and the two will have further discussions about
possibilities for aligning improvements for a cohesive intersection.
Mayor Gregerson thanked Tukwila for its participation in regional transportation planning efforts
and noted the Sustainable Airport Master Plan currently being developed by the Port.
Stakeholders in South King County are meeting regularly and cities should ensure their
transportation plans are written to accommodate impacts from the projected future airport
expansion.
Councilmember Duffle noted that as 2016 Council President, he would like to have two Tukwila -
SeaTac cooperative meetings,
Meeting Summary by LH
Joint Meeting: Tukwila/ SeaTac ................................................................................................... ............................... July 24, 2015 — Page 2 17