HomeMy WebLinkAboutTrans 2016-02-01 Item 2C - Contract Supplement #3 - Boeing Access Road over Burlington Northern Railroad Bridge Rehabilitation with Jacobs Engineering Group'0" 0 ty of Tuk *1a
Li Wi Allan Ekberg, Mayor
Public Works Department - Bob Giberson, Director
TO: Mayor Ekberg
Transportation Committee
FROM: Bob Giberson, Public Works DirectorIffi-
BY: Robin Tischmak, City Engineer
DATE: January 29, 2016
SUBJECT: Boeina Access Rd over BNRR Bridae Rehabilitation Proiect
Project No. 99410408, Contract No. 13-161
Supplemental Agreement No. 3 with Jacobs Engineering Group, Inc
ISSUE
Approve Supplemental Agreement No. 3 with Jacobs Engineering Group, Inc. (Jacobs) for
additional design services.
1:7-IT63 1201 T1111 i7
In October 2013, the City contracted with Jacobs to provide the design for the rehabilitation of the
Boeing Access Rd over BNRR Bridge. Jacobs' progress has been per schedule, but delays caused
by the railroad plan reviews and the preparation of a Construction and Maintenance (C&M)
Agreement with BNSF have put the project behind schedule. The design contract completion date
was extended to December 31, 2016 by Supplement No. 2.
ANALYSIS,
Supplemental Agreement No. 3 is for approved additional design services that include survey and
mapping, geotechnical investigations, and adjustments to the final bid documents. See attached
Supplemental Agreement No. 3, Exhibit A-1 for the project scope changes and Exhibit E2-A for the
fee proposal.
FISCAL IMPACT
Supplemental Agreement No. 3 is within the approved design budget that includes a contingency
for unanticipated work.
Contract Budget
Jacobs Original Contract $1,017,772.00 $1,353,000.00
Supplement No. 3 52,805.00
Total $1,070,577.00 $1,353,000.00
Council is being asked to approve Supplemental Agreement No. 3 with Jacobs Engineering Group,
Inc. for the Boeing Access Rd over BNRR Rehabilitation Project for $52,805.00 and consider this
item on the Consent Agenda at the February 16, 2016 Regular Meeting.
Attachment: Page 11, 2015 CIP
Supplemental Agreement No. 3 with Scope and Costs
WTW EngTROJECTS�A- RW & RS Projects\Boeing Access Rd Bridge Rehab (99410408)TE\JacGbs Submittals\lnfo Memo Jacobs Sup #3 01-29-16 gi sb.docx
I'll
PROJECT:
DESCRIPTION:
JUSTIFICATION:
STATUS:
MAINT. IMPACT:
COMMENT:
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2015 to 2020
Boeing Access Rd over BNRR Bridge Rehabilitation Project No. 99410408
Rehabilitate the existing bridge with a 340' long concrete or steel bridge structure. It will be 1 10' wide curb to
curb and have sidewalks on both sides.
The existing bridge is structurally and seismically deficient. Several pedestals are leaning, have concrete
spalls, exposed rusty anchor bolts and reinforcements and some cracks. The existing railings do not meet
current bridge standards.
Type, size, and location draft report (specifically required for bridges) was completed in 2005. Federal grant
applications were submitted in 2008 and 2010 and the bridge rehabilitation was successful for funding in
2012 for federal bridge funds. A Public Works Trust Fund (PWTF) loan was rescinded in 2013.
Maintenance will be reduced.
Bridge will be rehabilitated in phases to allow continued traffic use. Federal bridge grant of $9,745,600
requires a 20% local match. A bond issue will be used for the City match.
FINANCIAL Through Estimated
tin $000's) 2013 2014 2015 2016 2017 2018 2019 2020 BEYOND TOTAL
EXPENSES
Design
198
867
288
1,353
Land(R/W)
100
100
Const. Mgmt.
563
561
1,124
Construction
4,850
4,850
9,700
TOTAL EXPENSES
1 1981
967
1 5,701
1 5,411
1 01
01
01
01
01
12,277
FUND SOURCES
Awarded Grant
109
773
4,670
4,193
9,745
Proposed Grant
0
Bond
2,500
2,500
Mitigation
0
City Oper. Revenue
89
194
(1,469)
1,218
0
0
0
0
0
32
TOTAL SOURCES
1 1981
967
1 5,7011
5,4111
01
01
0
01
01
12,277
2015 - 2020 Capital Improvement Program 11
52
Adft
Washington State
Department of Transportation
Supplemental Agreement
Organization and Address
Number 3
Jacobs Engineering Group, Inc.
600-108th Ave. NE, Suite 700
Bellevue, WA 98004
Original Agreement Number
13-161
Phone: (425) 452-8000
Project Number
Execution Date
Completion Date
99410408, BHM 1380(003)
10/10/2013
12/31/2016
Project Title
New Maximum Amount Payable
Boeing Access Road Over BNRR Bridge Rehabilitation
$ 1,070,577.00
Description of Work
Add survey work, provide funds for additional costs and equipment added to the geotechnical boring, provide
funds for additional design, utility investigation work, project management, and printing as detailed in
Exhibit A-1.
The Local Agency of City
desires ho supplement the agreement entered in1owith Jacobs Engineering Group, Inc.
and executed on and identified ae Agreement No.
All provisions in the basic agreement remain in effect except 8s expressly modified bv this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
See attached Exhibit A,l for Supplement Scope o[Work.
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read: No Change
Section \( PAYMENT, shall be amended oefollows:
See attached summary of payment, Exhibit A, and the fee proposal, Exhibit E2-A.
as set forth int eh attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
spaces below and return [0 this office for final action.
By: By:
ate
DOT Form 11000n
Revised 09/2005
53
Exhibit A
Summary of Payments
54
Basic Agreement
Supplement #3
Total
Direct Salary Cost (DSC)
$314,532
$13,972
$328,504
Overhead (Including
Payroll Additives)
$372,501
$16,547
$389,048
Direct Non - Salary Costs
$4,540
$1,000
$5,540
Subconsultants
$231,839
$17,095
$248,934
Fixed Fee (30% DSC)
$94,360
$4,191
$98,551
Total
$1,017,772
$52,805
$1,070,577
54
Scope of Work
EXHIBIT A-1
City of Tukwila
Scope of Services
Supplement No, 3
1.0 Project Management
The CONSULTANT will continue providing project nnanagernentsemi[9sforthe extended project
duration which was necessitated by delay in Obtaining the Construction and Maintenance (C&K4)
Agreement from B0SF. The contract was extended from the original contract end date of June 15,
2015 to December 31, 2015 by Supplement No. 1 and then again to December 31, 2016 by
Supplement No. 2.
The CONSULTANT will continue to provide assistance in coordinating with BSNF through completion
of the C&M Agreement.
• Monthly Invoices and Progress Reports
• Project schedule update
2.0 Survey and Mapping
The CONSULTANT /1 Alliance Geonoati[3\ provided additional field surveying 8ndmmappingforth2
area along the south side of the Boeing Access Road for new retaining walls and the new drainage
area near Airport Way. (Approved with Change Log dated 2/4/2015)
The CONSULTANT (1 Alliance Geomatics) performed investigation of the right of way boundaries at
the request of the WSDOT Local Programs. (Approved with Change Log dated 5/7/2015)
E Electronic AutoCAD Civil 3D topographic base map
4.0 Geotechnical Investigation
The CONSULTANT (Shannon & Wilson and driller) had to shift the work window to meet the permit
Tukwila Boeing Access Road Bridge over 8NRR Rehabilitation—Supplement Nb3 1 55
Scope of Work
/[onUnupo0
conditions prescribed 6v the City and the Railroads. The early work hours also required a light plant
for safe field operation. (Approved with Change Log dated 12/5/2013)
During the second phase offield drilling (8-3) the CONSULTANT (Shannon & Wilson and driller) had
to work during weekend 10 meet conditions prescribed by the Railroad. This weekend operation
required surcharge for driller. (Approved with Change Log dated 3/6/2015)
12.0 100%PS&E Documents
The CONSULTANT performed additional drainage design to address the right of way conflict at the
southwest corner near Airport Way. (Approved with Change Log dated 8/5/2015)
The CONSULTANT performed additional underground utilities coordination and field verification to
resolve potential conflict with the final design. (Approved with Change Log date 10/1/2015)
The CONSULTANT performed extensive analyses and design efforts for the 10-foot wide sidewalk
widening along the south side ofthe bridge. The final design was significantly more complex and
difficult than anticipated, and required a substantial increase in effort beyond the original scope
and budget; vve request o total of1OO hours for this work effort.
9 Design elements are included in the 100% Plans, Specifications and Estimate
Tukwila Boeing Access Road Bridge over BNRR Rehabilitation—Supplement No3 2 56
EXHIBIT E -2A
Supplement No 3
City of Tukwila
Fee Proposal
South Boeing Access Road Bridge Rehabilitation Project
Task
Description
Project
Manager
Sr.
Civil /Str
Eng
Des.
Engineer
CADD
Project
Admin
Total
Hours
Total Cost
forlacobs
Tota/Cost
for Subs
1.0
Project Management & Coordination
72
0
0
0
6
78
$16,356
PM due to project extention (12 mo)
72
6
78
$16,356
2.0
Inspection & Load Rating (TranTech)
0
$0
3.0
Survey & Mapping (1 Alliance)
0
$0
$10,795
Add survey for retaining wall & drainage (approved 214115)
$4,474
Add survey for defining ROW (approved 517115)
$6,321
4.0
Geotechnical Investigation (Shannon & Wilson)
0
$0
$6,300
Shift work window for B -1 & e -2 (approved 1215113)
$3,800
Driller weekend charge (approved 316114)
$2,500
5.0
Environmental Planning & Permitting (Widener)
0
$0
6.0
Railroad Coordination (MCRail Logistics)
0
$0
7.0
Roadway, Drainage, Pedestrian /Bike & Traffic Control
0
$0
8.0
Bridge Rehabilitation and Seismic Analysis
0
$0
9.0
Final Seismic Analysis & Structural Design
0
$o
9.0
Conceptual Design (30 %) Plans
0
$0
10.0
60% Design Plans
0
$0
11.0
90% Design Plans, Specs & Estimate
0
$0
12.0
100% PS &E Documents
0
86
60
4
0
150
$18,354
Additional drainage at SW corner (approved 815115)
10
8
4
22
$2,584
Underground utility adjustment (approved 1011115)
16
12
28
$3,394
Design complexity (10'sidewalk & ground improvements)
60
40
100
$12,375
13.0
Ad -Ready Contract Documents
0
$0
14.0
Assistance during Bid Period
1
0
$0
Total Hours
72
86
60
4
6
228
Billing Rate (Estimated)
$220.10
$159.04
$70.82
$106.86
$84.72
JACOBS Total Labor Cost
$15,847
$13,677
$4,249
$427
$508
$34,710
Direct Expenses (production, copying, etc.)
$1,000
Subtotal:
$35,710
$17,095
TOTAL (Jacobs + Subs) for Supplement No 3: $52,805
C: VserslkimksVesktop1Tukwila BoeingiScopingiSupplement #31Boeing Access Road Br Supplment #3