HomeMy WebLinkAboutUtilities 2016-02-23 Item 2A - Bid Award - RL Alia Company for Central Business District Sanitary Sewer Rehabilitation:1227 Andover Park East Sewer RepairTO:
FROM
BY:
DATE:
,^ 0
Lity of Tukwila Allan Ekberg, Mayor
Public Works Department - Bob Giberson, Director
Mayor Ekberg
Utilities Committee
Bob Giberson, Public Works Director"Wi
Mike Cusick, Senior Program Manager
February 19, 2016
SUBJECT: CBD Sanitary Sewer Rehabilitation
Project No. 91140203
Bid Award for Sewer Repair at 1227 Andover Park East
ISSUE
Award contract to R. L. Alia Company for the CBD Sanitary Sewer Rehabilitation — Sewer Repair at
1227 Andover Park East.
During the cleaning and video inspection of the sanitary sewer near 1227 Andover Park East by
Michels Corporation, the contractor for the 2015 CBD Sanitary Sewer Rehabilitation Project, a section
of sewer pipe was found in a condition that could not be relined and requires excavation to repair.
ANALYSIS
The City requested quotes from five contractors for the sewer repair near 1227 Andover Park East. Two
of the five contractors returned quotes to the City. The low quote of $69,717.56 was from R.L. Alia
Company and the second highest quote of $106,471.23 was from Shoreline Construction. Both firms
have done satisfactory work for the City in the past.
BUDGET AND BID SUMMARY
Engineer's
Remaining
Estimate
Bid Amount 2016 Budget
R.L. Alia Company $60,364.72
$69,717.56 139,760.86
Contingency 20%
13,943.51
Grand Total $60364.72
$33&-61.07 $ 139,760.86
I -I : [0101 m I m I
Council is being asked to approve the contract with R. L. Alia Company in the amount of
$69,717.56 for the CBD Sanitary Rehabilitation — Sewer Repair at 1227 Andover Park East Project
and consider this item on the Consent Agenda at the March 14, 2016 Special Meeting.
W:TW Eng\PROJECTS\A- SW Projects\CBD Sewer Rehabilitation (91140203)\Info Memo CBD SEWER 1227 APE Bid Award 02-19-16 gl sb.docx