HomeMy WebLinkAboutReg 2016-05-02 Item 4G - Final Acceptance - 6300 Building Water Service Replacement with Green River Construction for $43,307.25COUNCIL AGENDA SYNOPSIS
----------- ----------------- - - - - -- Initials
Meeting Date
Prepared bL
Ma is review
Council review
05/02/16
BG
❑ Resolution
Mt g Date
❑ Ordinance
Mt g Date
❑ Bid Award
MtS Date
F-J Public Hearing
Mt
,g Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD [:] Finance ❑ Fire E]IT ❑ P&R ❑ Police Z PV
SPONSOR'S The contract with Green River Construction, Inc. of Tukwila, WA is complete for the 6300
SUMMARY Building Water Service Replacement Project. This project installed a new water service
between the water meter and the 6300 Building. One change order was issued to replace
the connection to the fire protection line for $1,600.00. Council is being asked to accept
and finalize the contract with Green River Construction in the amount of $43,307.25.
REVIEWED BY ❑ cow Mtg. ❑ CA&P Cmte ❑ F&S Cmte ❑ Transportation Cmte
Z Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 04/26/16 COMMITTEE CHAIR: KATHY HOUGARDY
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMITTEE Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$43,307.25 $49,866.30 $0.00
Fund Source: 303 FACILITIES (PG 49, 2015 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/02/16
11114 ► I I'kl I MQ 011 T, 1-% W�4
ITEMNO.
4.G.
CAS NUMBER:
I STAFF SPONSOR: BOB GIBERSON
ORIGINALAGLNDA DATE: 05/02/16
AGENDA ITEM TITLE 6300 Building Water Service Replacement
Project Completion and Acceptance
CATEGORY ❑ Discussion
Mt g Date
Z Motion
Mtg Date 09102116
❑ Resolution
Mt g Date
❑ Ordinance
Mt g Date
❑ Bid Award
MtS Date
F-J Public Hearing
Mt
,g Date
❑ Other
Mtg Date
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD [:] Finance ❑ Fire E]IT ❑ P&R ❑ Police Z PV
SPONSOR'S The contract with Green River Construction, Inc. of Tukwila, WA is complete for the 6300
SUMMARY Building Water Service Replacement Project. This project installed a new water service
between the water meter and the 6300 Building. One change order was issued to replace
the connection to the fire protection line for $1,600.00. Council is being asked to accept
and finalize the contract with Green River Construction in the amount of $43,307.25.
REVIEWED BY ❑ cow Mtg. ❑ CA&P Cmte ❑ F&S Cmte ❑ Transportation Cmte
Z Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 04/26/16 COMMITTEE CHAIR: KATHY HOUGARDY
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMITTEE Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$43,307.25 $49,866.30 $0.00
Fund Source: 303 FACILITIES (PG 49, 2015 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/02/16
MTG. DATE
ATTACHMENTS
05/02116
Informational Memorandum dated 04/22/16
State of WA Depart of Revenue Notice of Completion 16-018
Minutes from the Utilities Committee meeting of 04/26/16
59
.1
City of Tukwila
Public Works Department - Bob Giberson, Director
TO: Mayor Ekberg
Utilities Committee
FROM: Bob Giberson, Public Works Director AVA
BY: Mike Cusick, Senior Program Manager
DATE: April 22, 2016
SUBJECT: 6300 Building Water Service Replacement
Project No. 91630202, Contract No. 16-018
Project Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of retainage.
BACKGROUND
Allan Ekberg, Mayor
The water service to the 6300 Building has broken 5 times. Costs for the last 2 repairs were
$11,639.03. The installation of the new water service between the water meter and the 6300
Building will reduce maintenance costs for the City of Tukwila.
ANALYSIS & FISCAL IMPACT
Notice to Proceed for Contract No. 16-018 with Green River Construction, Inc. of Tukwila
Washington was issued on February 17, 2016. Green River Construction replaced the water
service to the 6300 Building and completed the work on February 24, 2016.
Contract Award Amount (without sales tax) $37,950.00
Change Order No. 1 (Repair of Fire Protection) 1,600.00
Sales Tax at 9.5% 3,757.25
Total Contract Amount $43,307.25
RECOMMENDATION
Council is being asked to formally accept the project and authorize the release of retainage,
subject to standard claim and lien release procedures for the 6300 Building Water Service
Replacement Contract No.16-018 with Green River Construction, Inc., in the final amount of
$43,307.25 and consider this item on the Consent Agenda at the May 2, 2016, Regular
Meeting.
Attachment: Notice of Completion, Contract No. 16-018
wApw eng\projects\a- bg projects\6300 building water replacement (91630302)\info memo 6300 bldg water closeout 04-08-16 sb gl docx
61
62
TATS A
❑ Original
❑ Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Date: 3/30/16 Contractor's UBI Number: 600 407 115
pY 4 /. � /.,? 9 /i'r �' / %J'o /r: ,r,. 1 i,. � 3y<, . •�. ,Y; ,� , ,x r,,,�x;.:: °. r1"
f i(it ;�• S�itif 1'
t s
City ot Tukwila
6300 Southcenter Blvd #101
Tukwila, WA 98188
UBI Number:
`��� 4 %��ef i �^ ( ,Yr�'�Y k '" ' �s� Y�a�+� sy r"�" �;��' l /�� y .�.iy �s �fJ�� � ✓
,,,, f ����/i..%11,� � ' � 56�4�14/�•1.;',���,, ,.,��45, ���������.,. �''�e..�'.��€£< f6. /,.,,.... Gi
Assigned to:
Date Assigned:
lvottce is herebv liven retative to the completion of contract or proiect aescrtbea below
Project Name contract AUmDer JoD uraerr uontracttng
6300 Building Water Service Replacement 116-018 El Yes V No
Description of Work Done/Include Jobsite Address(es)
The replacement of the water service to the 6300 Building (91630302)
Federally funded transportation project? ❑ Yes V No (if yes, provide Contract Bond Statement below)
Contractor's Name E -mail Address Affidavit ID*
Green River Construction, Inc. lalison@greenriverconstructioni 634261
6402 S 144th Street, Tukwila, WA 98188 1206- 246 -9456
If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number.
❑ Retainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects)
Name: I Bond Number:
Date Contract Awarded Date Work Commenced Date Work Completed Date Work Accepted
February 17, 2016 1 February 19, 2016 February 24 2016
Contract Amount
Additions ( + )
Reductions (- )
Sub -Total
Sales Tax Rate 9.5
(If various rates apply, please send a breakdown)
Sales Tax Amount
TOTAL
$ 37,950.00
$ 1,600.00
$ 0.00
$ 39,550.00
$ 3757.25
$ 43,307.25
NuiK: Zhese two totals must he
Liquidated Damages $
0.00
Amount Disbursed $
41,329.75
Amount Retained $
1,977.50
TOTAL $ 43,307.25
Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber
Email Address: diane.jaber @tukwilawa.gov
Department of Revenue Washinom Stela Depaunem of
Public Works Section Labor & Industries
(360) 704 -5650 Contract Release
PWC@dor.wa.gov (855) 545 -8163, option # 4
ContractRelease @LNI. WA.GOV
REV 31 0020e(10/26/15) F215- 038 -000 10 -2014
Title: Fiscal Cordinator
Phone Number: 206 - 433 -1871
Employment Security
Department
Registration, Inquiry,
Standards & Coordination
Unit
(360) 902 -9450
publicworks@esd.wa.gov
63
Addendum A: Please List all Subcontractors and Sub -tiers Below
Tbis addeddum can be submitted in other formats.
Provide known affidavits at this time. No L &I release will be Qranted until all affidavits are listed.
Subcontractor's Name: UBI Number: (Required) Affidavit ID*
Evergreen Concrete Cutting, Inc. 601 605 667 632932
Action Asphalt Paving LLC 602 206 312 633153
For tax assistance or to request this document in an alternate format, please call 1- 800 - 647 -7706. Teletype (TTY) users may use the
Washington Relay Service by calling 711.
REV 31 0020e Addendum (10/26/15) F215- 038 -000 10 -2014
UTILITIES COMMITTEE
Meeting Minutes
.. r - I
City Council Utilities Committee
April26, 2016 - 5:30 p.m. - Foster Conference Room, 6300 Building
Councilmembers: Kathy Hougardy, Chair; Kate Kruller, Thomas McLeod
Staff: Bob Giberson, Frank Iriarte, Robin Tischmak, Peter Lau, Mike Cusick, Pat Brodin,
Gail Labanara, Laurel Humphrey
CALL TO ORDER: Committee Chair Hougardy called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. BUSINESSAGENDA
A. Project Completion: 2015 Sanitary Sewer Manhole Rehabilitation
Staff is seeking Council approval of project completion and release of retainage to Olson
Brothers Pro -Vac, LLC in the amount of $95,768.92 for the 2015 Sanitary Sewer Manhole
Rehabilitation Project. This project provided sewer manhole rehabilitations at 9 locations in
Tukwila and was budgeted at $126,081.72. UNANIMOUS APPROVAL. FORWARD TO MAY 2,
2016 REGULAR CONSENT AGENDA
B. Proiect Completion: 6300 Building Water Service Replacement
Staff is seeking Council approval of project completion and release of retainage to Green River
Construction, Inc., in the amount of $43,307.25 forthe 6300 Building Water Service Replacement
Contract. This project installed a new service line between the water meter and the 6300
Building, necessitated byseveral recent failures. The cost of the last two repairs was $11,639.03.
UNANIMOUS APPROVAL. FORWARD TO MAY 2, 2016 REGULAR CONSENT AGENDA
C. Consultant Selection: Central Business District Sanitary Sewer Rehabilitation
Staff informed the Committee about the selection of RI-12 Engineering, Inc. to design the 2016
CBD Sanitary Sewer Rehabilitation Project in the amount of $31,386.35. This project entails a
five year program to repair and reline the sanitary sewer pipe in the CBD, and in 2016
approximately 7,800 feet of pipe are scheduled to be relined. Additional funds for design will
come from the 2016 Construction Management Budget. INFORMATION ONLY.