HomeMy WebLinkAboutRes 1882 - 2017-2022 Transportation Improvement ProgramCl*ty o u 1a
Washington
Resolution No. 1882
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUKWILA, WASHINGTON, ADOPTING A SIX-YEAR
TRANSPORTATION IMPROVEMENT PROGRAM (2017-
2022), AND DIRECTING THE SAME TO BE FILED WITH
THE STATE SECRETARY OF TRANSPORTATION AND
THE TRANSPORTATION IMPROVEMENT BOARD.
WHEREAS, pursuant to the requirements of RCW Chapters 35.77 and 47.26 as
amended, the City Council of the City of Tukwila has previously adopted a
Transportation Improvement Program and thereafter periodically modified said
Transportation Improvement Program by resolution; and
WHEREAS, the City Council has reviewed the work accomplished under said
program, determined current and future City street and arterial needs and, based upon
these findings, has prepared a Six-Year Transportation Improvement Program for the
ensuing six calendar years (2017-2022); and
WHEREAS, on June 13, 2016, a public hearing was held regarding the City's Six-
Year Transportation Improvement Program;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Program Adopted. A Six-Year Transportation Improvement Program
for the calendar years 2017 to 2022, attached hereto as Exhibit A, is hereby adopted.
Section 2. Filing of Program. The City Clerk is hereby authorized and directed to
file a copy of this resolution, together with the exhibit attached hereto, with the
Secretary of Transportation and the Transportation Improvement Board of the State of
Washington.
WAWord Processing\Resolutions\TIP 2017-2022 5-20-16
CK:bjs Page 1 of 2
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON,
at a Regular Meeting thereof this � QrO day of 7a-i7/j Q_ 12016.
ATTEST /AUTHENTICATED:
Christy O'F191herty, MMC, City Mirk
APPROVED AS TO FORM BY:
(Tulu -
Rachel B. Turpin, City Attorney
Q�� ZLLA�
Voe Duffie, C&n*cil President
Filed with the City Clerk: -is-
Passed by the City Council:
Resolution Number: ) YYA
Exhibit A: City of Tukwila Six-Year Transportation Improvement Program for 2017 to 2022
WAWord ProcessingResolutions\TIP 2017-2022 5-20-16
CK:bjs
Page 2 of 2
2017 -2022
TIP
DRAFT 2017 - 2022 TIP SUMMARY
2016 CIP
PROJECT TITLE Page No.
2017
Project Costs in Thousands of Dollars
2018 2019 2020 2021
2022
TOTAL
June 6, 2016
FUNDING SOURCES
Federal State/T113 Developer Unsecured
City
1
42 -42nd Ave S (S 160 St - S 131 PI)
2
4,807
2,031
0
0
0
4360
11,198
11,198
2
53rd Ave S (S 137th St - S 144th St)
6
2,354
2,353
0
0
0
0
4,707
2,141
2,566
3
ADA Improvements
20
200
200
200
200
200
200
1,200
1,200
4
APE /Industry Dr Intersection
25
85
657
0
0
0
0
742
742
5
APE /Minkler Blvd Intersection
24
144
1,570
0
0
0
0
1,714
1,714
6
Annual Bridge Inspections and Repairs
10
270
335
335
335
335
335
1,945
1,945
7
Annual Overlay and Repair Program
18
1,650
1,670
1,725
1,730
1,745
1,760
10,280
10,280
8
Beacon Ave Bridge Preventative Maintenance
-
1,741
0
0
0
0
0
1,741
1,741
0
9
BNSF Regional Center Access
13
0
0
0
0
0
13,750
13,750
11,763
1,987
10
Boeing Access Rd Bridge Rehabilitation
11
10,846
0
0
0
0
0
10,846
8,626
2,220
11
Cascade View Safe Routes to School Phase 2
3
783
0
0
0
0
783
700
83
12
Frank Zepp Bridge Preventative Maintenance
2,535
0
0
0
0
0
2,535
2,535
0
13
Grady Way Bridge Preventative Maintenance
149
0
0
0
0
0
149
149
0
14
Multipurpose Trails
35
60
60
60
60
60
220
520
520
15
S 133 SUSR599 Intersection
27
0
335
2,064
0
0
0
2,399
2,399
16
S 144th St Bridge Sidewalks
-
0
0
0
0
0
1,219
1,219
975
244
17
Strander Blvd /SW 27th St St Phase III
28
0
5,000
0
0
1,329
51,000
57,329
29,325
28,004
18
TUC/TOD Pedestrian Improvements
29
1,283
1,260
0
425
1,725
4,693
3,311
1,382
19
TUC - Pedestrian /Bicycle Bridge
12
6,185
0
0
0
0
0
6,185
5,289
896
20
21
Walk & Roll Program
West Valley Highway
22
-
0
0
0
0
0
0
0
374
0
1,334
175
1,500
175
3,208
1,792 150
175
1,266
TOTAL
33,092
15,471
4,384
3,124
6,728
74,519
137,318
59,125
9,222 150 -
68,821
PROJECTS REVISED FROM 2015 -2020 TIP
New:
Deleted:
None
W Valley Hwy /S 156th St
Intersection
Project has been combined with the West Valley Hightway (1 -405 - Strander Blvd) project.
Adft
W"hhVilonato
Deparb"oMt st of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
Totals
0
2,031,000
0
6,868,000
6,868,000
P
CN
2021
0
0
4,360,000
4,360,000
Totals
0
0
11,228,000
11,228,000
0
0
I
A. PIN/Project No. B. STIP ID
>
CD
0
0
<
CD
0
z
C. Project Title
X
>
RL
0
D. Road Name or Number
CL
0
CL
0
0
r-
(D
M
— a-
ty
E. Begin & End Termini
Z
9
3
CD
z
0
CL
--4
1<
c
W —
CD
F. Project Description G. Structure ID
Q .
I
P
M
CA
V
CD
a
17
WA-07745
06/13/16
06/20/16
04
C G O P S
Yes
T W
40-42 Ave S IS 160 St - S 131 PL)
S 160th Street to Southcenter Blvd
Design and construct street improvements, underground aerial utilities, drainage,
sidewalks, bike facilities, and driveway adjustments
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
Totals
0
2,031,000
0
6,868,000
6,868,000
P
CN
2021
0
0
4,360,000
4,360,000
Totals
0
0
11,228,000
11,228,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
4,807,000
2,031,000
0
0
4,360,000
Totals
4,807,000
2,031,000
0
0
4,360,000
Report Date: June 06, 2016 Page 1
Amh
WaShingtoo $1loto
Departumat of Transportation
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
Totals
0
TIB
2,141,400
2,565,600
4,707,000
Totals
0
2,141,400
2,565,600
4,707,000
X
0
0
0
A:
A. PIN/Project No. B. STIP ID
>
3
M
U)
0
C
0
%<
Z
C. Project Title
>
M
X
D. Road Name or Number
(D
0
0
0
CD
M
tr
E. Begin & End Termini
0)
M
'0
—
(D
z
-q
0
CL
C.
0)
CD
F. Project Description G. Structure ID
M
P
M
M
a
0-
17
WA-06601
06/13/16
06/20/16
04
C G O P S
0.420
CE
Yes
TW
53rd Avenue S
S 137th St to S 144th St
Design and construct urban residential street improvements that include curb, gutter,
sidewalk , illumination and undergrounding. Street portion will coordinate with Water,
Surface Water and Sewer capital improvement program projects.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
Totals
0
TIB
2,141,400
2,565,600
4,707,000
Totals
0
2,141,400
2,565,600
4,707,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
2,353,500
2,353,500
0
0
0
Totals
2,353,500
2,353,500
0
0
0
Report Date: June 06, 2016 Page 2
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
ALL
2017
Totals
0
200,000
0
1,200,000
1,200,000
Totals
0
0
1,200,000
1,200,000
0
A. PIN/Project No. B. STIP ID
>
3
0
<
0
M
Z
C. Project Title
M
>
EL
CD
0
D. Road Name or Number
CL
0
CL
0
0
r-
01
a
11 5-
rr
E. Begin & End Termini
a
M
M
z
4�
0
CL
U3
U)
CD
F. Project Description G. Structure ID
(a
M
Q.
0
M
M
CL
00
WA-05405
06/13/16
06/20/16
06
No
Americans with Disabilities Act (ADA) Improvements
Various locations
to
Design and construct ADA compliant upgrades to City infrastructure in conjunction
with a City developed plan.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2017
Totals
0
200,000
0
1,200,000
1,200,000
Totals
0
0
1,200,000
1,200,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
ALL
200,000
200,000
200,000
200,000
400,000
Totals
200,000
200,000
200,000
200,000
400,000
Report Date: June 06, 2016 Page 3
Aftk�
w0shil"ato" $11talho
Departmwit of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
PE
2017
RW
0
0
0
75,000
75,000
P
RW
2017
0
0
0
0
10,000
10,000
P
CN
2018
0
0
0
657,000
"n
0
I
A. PIN/Project No. B. STIP ID
0
>
a
M
(A
0
0
(D
C
1<
z
C. Project Title
X
>
CD
X
0
D. Road Name or Number
0.
0
CL
0
0
CD
0
M
—
0)
rr
E. Begin & End Termini
W
a
z
0
CL
to
v
S.
0
0)
M
Description G. Structure ID
F. Project De
to
Q.
0
"a
M
M
1 0
"a
W
a
Q.
16
WA-03766
06/13/16
06/20/16
05
C G O P S
0.190
CE
No
TW
Andover Park E/Industry Drive Signal
Andover Park E
Industry Drive to
Design and construct a traffic signal and intersection improvements
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2017
RW
0
0
0
75,000
75,000
P
RW
2017
0
0
0
0
10,000
10,000
P
CN
2018
0
0
657,000
657,000
1 Totals
0
0
742,000
742I000
Expenditure Schedule
Phase
list
2nd
3rd
4th
5th & 6th
PE
75,000
0
0
0
0
RW
10,000
0
0
0
0
CN
0
657,000
0
0
0
Totals
85,000
1 657,0001
01
O'l
0
Report Date: June 06, 2016 Page 4
AM.
w4shl"Oul"Swo
Depwtavent of Transportatkm
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
PE
2017
RW
0
0
0
134,000
134,000
P
RW
2017
0
0
0
0
10,000
10,000
P
CN
2018
0
0
1,570,000
-n
0
A. PIN/Project No. B. STIP ID
1 01
>
X
(D
0
0
0
<
C
0
0
X
-Z
C. Project Title
>
3
M
W
M
Z
D. Road Name or Number
m
CL
CL
0
0
(D M
E. Begin & End Termini
0
V
3
CD
z
0
CL
F. Project Description G. Structure ID
Q
0
M
(D
16
WA-07746
06/13/16
06/20/16
03
C G O P S
No
T W
Andover Park E/Minkler Blvd Intersection
Andover Park E
Minkler Blvd to
Construct left turn lanes on Andover Park East and reconstruct traffic signal
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2017
RW
0
0
0
134,000
134,000
P
RW
2017
0
0
0
0
10,000
10,000
P
CN
2018
0
0
1,570,000
1,570,000
Totals
0
1 01
1,714,0001
1,714,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
134,000
0
0
0
0
RW
10,000
0
0
0
0
CN
0
1,570,000
0
0
0
Totals
1 144,000
0
0
Report Date: June 06, 2016 Page 5
Awk,
sude
V Depwtomt of TransportnUon
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
ALL
2017
Totals
0
335,0001
0
1,945,000
L 1,945,000
0
0
0
1,945,0001
-n
0
1
1z
A. PIN/Project No. B. STIP ID
>
CD
U)
0
<
M
C
0
Z
C. Project Title
X
>
=1
M
m
X
D. Road Name or Number
CD
0
CL
0
0
r-
M
0
0
Cr
E. Begin & End Termini
M
z
0
CL
S.
U) w
F. Project Description G. Structure ID
Co
CL
P
M
U)
3
M
14
WA-03731
06/13/16
06/20/16
06
No
Annual Bridge Inspections and Repairs
Various City Street
to
Perform load ratings and bi-annual inspections as well as construct necessary
repairs and maintenance
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2017
Totals
0
335,0001
0
1,945,000
L 1,945,000
Totals
0
0
1,945,0001
1,945,000
Expenditure Schedule
Phase
1st
2nd
I 3rd
4th
5th & 6th
ALL
270,000
335,0001
335,000
335,000
670,000
Totals
270,000
335,0001
335,000
335,000
670,000
Report Date: June 06, 2016 Page 6
AM,
vrW"hingto" $tote
o .pt...t of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 202fl.
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
1
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
ALL
2017
Totals
0
1,670,0001
0
10,280,000
X
0
0
0
10,280,000
- n
0
A. PIN/Pro ect No. B. STIP ID
j
>
3
M
0
0
<
C
0
3
z
C. Project Title
>
M
C
D. Road Name or Number
so
CL
0
CL
0
0
E. Begin & End Termini
Z
0
M
(A
F. Project Description G. Structure ID
CL
0
M
(n
CD
CL
16
WA-03733
06/13/16
06/20/16
06
C G O P S
No
T W
Annual Overlay and Repair Program
Various City Streets
to
Repair, rehabilitate, and overlay City streets as needed in an annual program
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
1
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
ALL
2017
Totals
0
1,670,0001
0
10,280,000
10,280,000
Totals
0
0
10,280,000
10,280,000
Expenditure Schedule
Phase
1st
2nd
I 3rd
4th
5th & 6th
ALL
1,650,000
1,670,0001
1,725,000
1,730,000
3,505,000
Totals
1,650,000
1,670,0001
1,725,000
1,730,000
3,505,000
Report Date: June 06, 2016 Page 7
Allift
vro Departammt of Trwispartatim
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
STP(BR)
1,740,920
0
0
0
M
0
1,740,920
0
01
"n
0
1
A. PIN/Pro ect No. B. STIP ID
>
3
0
<
C
0
Z
C. Project Title
X
>
X
D. Road Name or Number
(D
0
CL
0
0
r-
M
M
.0
3
rr
E. Begin & End Termini
0)
3
z
0
M
S.
M
F. Project Description G. Structure ID
(a
0.
P
(D
Q.
19
/1320(004) TUK-57
06/13/16
06/20/16
14
0.010
CE
No
Beacon Ave S Bridge Preventative Maintenance Project
Beacon Avenue South over South Ryan Way
S Victor St to S 170th St
Remove and replace failed bridge deck and paint structural steel.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
STP(BR)
1,740,920
0
0
0
1,740,920
Totals
1,740,920
0
01
1,740,920
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
1,740,920
0
0
0
0
Totals
1,740,920
0
0
0
0
Report Date: June 06, 2016 Page 8
Adak
Washw*W" stido
Depadnwat of Transportaftm
Agency: Tukwila
County: King
MP0/RTP0: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
PE
2021
FMSIB
950,000
0
0
300,000
M
P
CN
2021
FIVISIB
10,812,500
-n
0
M
17
A. No. B. STIP ID
PIN /Project
12,500,000
Totals
>
3
(D
0
0
<
M
3
1,987,500
0
Z
C. Project Title
>
5�
CD
X
M
n
D. Road Name or Number
(D
0
0
0
M
E. Begin & End Termini
°_+
z
0
0
C.
M
F. Project Description G. Structure ID
M
0-
�L
P
"a
CD
(D
U)
5
M
00
WA05409
06/08/15
06/15/15
08
EIS
No
BNSF Regional Center Access
New Facility
to
Construct a new access to the BNSF Regional Distribution Center, relocating the
.900+ daily truck trips from residential streets in Allentown.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
FMSIB
950,000
0
0
300,000
1,250,000
P
CN
2021
FIVISIB
10,812,500
13,750,0001
0
1,687,500
12,500,000
Totals
11,762,500
0
1,987,500
13,750,000
Expenditure Schedule
Phase
list
2nd
3rd
4th
5th & 6th
PE
0
0
0
0
12,500,000
CN
0
0
0
0
1,250,000
Totals
0
0
0
0
13,750,0001
Report Date: June 06, 2016 Page 9
Adffhk,
400 washil"oolm stato
Vro Department of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
o
8,625,600
0
0
2,220,000
X
V
0
8,625,600
0
2,220,000
10,845,600
0
A. PIN/Project No. B. STIP ID
> 9
M U)
0
<
C
0
3
(D
z
C. Project Title
=
>
M
D. Road Name or Number
CD
CL
0
CL
0
0
CD
U
E. Begin & End Termini
su
M.
z
-4
0
CL
C.
F.
F. Project Description G. Structure ID
CL
0
CD
M
M
a
CL
14
/1380(003) TUK-52
06/13/16
06/20/16
14
0.200
DCE
Yes
Boeing Access Road Bridge Rehabilitation
Boeing Access Road
Interstate 5 to Airport Way South
Rehabilitate the existing Boeing Access Road bridge structure over the Burlington
Norther and Union Pacific Railroads. Work will include rehabilitation of the bridge
sub-structure, seismic retrofit, and construction of a new bridge deck including
pedestrian/bicycle amenities.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
STP(BR)
8,625,600
0
0
2,220,000
10,845,600
Totals
8,625,600
0
2,220,000
10,845,600
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
10,845,600
0
0
0
0
Totals
10,845,600
0
0
0
0
Report Date: June 06, 2016 Page 10
Aft
0" Wa6bb"llft" ftot*
vro .p..t...t of TrmsportaUw
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
SRTS
699,745
01
0
83,353
X
V
a
699,745
0
83,353
-n
0
M.
q
A. PIN/Project No. B. STIP ID
>
3
CD
0
0
<
CD
C
0
C
z
C. Project Title
=
>
Q
CD
0
c
D. Road Name or Number
(D
CL
0
CL
0
0'
E. Begin & End Termini
:3
z
0 04
to
0 0)
0 —
M
F. Project Description G. Structure ID
CL
P
CD
M
CL
00
/1320(005) TUK-58
06/13/16
06/20/16
28
0.510
CE
No
Cascade View Elementary Safe Routes to School Project - Phase 2
33rd Ave S and S 140th Street
S. 144th at 34th Ave. S. to 140th St at 34th Ave. S.
Concrete sidewalks are proposed on one side of 33rd Ave S (S 140th St to S 144th
St) and onone side of S. 140th St (Military Road South to 34th Ave S) along with a
standard curb and gutter separating the sidewalk from the roadway. A traffic circle is
proposed at the intersection of 33rd Ave S and S 140th St to assist inreducing
vehicle speeds and increase visibility and safety of pedestrians crossing the street.
Curb bulb-outs and/or pedestrian refuge islands at the east entrance/exit to the traffic
circle would be constructed to improve the safety ofcrossing S 140th St at 33rd Ave
S. There are currently no ADA facilities to connect to within the project limits. Minor
storm water improvements will be added to the general action area.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
SRTS
699,745
01
0
83,353
783,098
Totals
699,745
0
83,353
783,098
Expenditure Schedule
Phase
1st
2nd
I 3rd
4th
5th & 6th
CN
783,098
01
0
0
0
Totals
783,098
01
0
0
0
Report Date: June 06, 2016 Page 11
A111101116
W004"QU)" stave
ftp.....t of Transpwitalklica
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
STP(BR)
2,534,812
01
0
0
2,534,812
13
0
2,534,812
0
0
-n
0
-Z
A. PIN/Pro ect No. B. STIP ID
i
>
3
CD
W
0
<
C
z
C. Project Title
X
>
C
D. Road Name or Number
CL
0
0
0
r-
M
U 0
rr
E. Begin & End Termini
V
z
0
0.
to
at
F. Project Description Structure ID
ription G. Struct
to
M
CL
P
M
M
0
—
V
M
CL
16
/1274(009) TUK-55
06/13/16
06/20/16
14
0.040
CE
No
Frank Zepp Bridge Preventative Maintenance Project
S 180th Street over the Green River
SIR 181 - West Valley Highway to Sperry Drive S
Paint the structural steel, overlay deck and replace the deck joint, and install seismic
protection.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
STP(BR)
2,534,812
01
0
0
2,534,812
Totals
2,534,812
0
0
2,534,812
Expenditure Schedule
Phase
1st
2nd
I 3rd
4th
5th & 6th
CN
2,534,812
01
0
0
0'
Totals
2,534,812
01
0
0
0
Report Date: June 06, 2016 Page 12
Aft1h►
Depwt
W"h" ment Mao
of Transpwtatkm
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (Y("Federal
Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
STP(BR)
148,574
0
0
0
X
0
148,574
0
0
148,574
0
I
A. PIN/Project No. B. STIP ID
>
M
0
0
<
M
a
—
--I
0
9
z
C. Project Title
>
m
X
D. Road Name or Number
CL
0
C L
0
0
r-
M
rr
E. Begin & End Termini
go
V
M
z
-4
0
CL
to
0 -
M
F. Project Description G. Structure ID
(a
CD
CL
0
M
M
(A
M
14
/1288(005) TUK-56
06/13/16
06/20/16
14
0.230
CE
No
Grady Way Bridge Preventative Maintenance Project
Grady Way Bridge over BN and UP Railroads
Interurban Avenue S to Longacres; Drive SW, Renton
Retrofit existing bridge with seismic protection.
Funding
Status
Phase
Phase Start Year (Y("Federal
Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
STP(BR)
148,574
0
0
0
148,574
Totals
148,574
0
0
148,574
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
148,574
0
0
0
0
Totals
148,574
0
0
0
0
Report Date: June 06, 2016 Page 13
Aftil►
WWA409Stat""e
Department of Transportatka
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
o
0
60,0001
0
520,000
;a
0
0
0
520,000
-n
0
A. PIN/Project No. B. STIP ID
>
M
U)
0
<
=
0
z
z
C. Project Title
X
>
M
0
=
C
D. Road Name or Number
M
CL
0
0
-
0
0
U 0
=
a
U
E. Begin & End Termini
a)
1.
V
9
z
-1
�<
0
0.
C.
U)
RL
CD
F. Project Description G. Structure ID
a
0
M
U)
=
M
CL
00
WA -03783
06/13/16
06/20/16
28
CE
No
Multipurpose Trails
to
Wide array of necessary trail improvements to existing trail system infrastructure
Funding
Status
Phase
Phase Start Year
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
Totals
0
60,0001
0
520,000
520,000
Totals
0
0
520,000
520,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
60,000
60,0001
60,000
60,000
280,000
Totals
60,000
60,0001
60,000
60,000
280,000
Report Date: June 06, 2016 Page 14
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
PE
2018
RW
0
25,000
0
310,000
310,000
P
RW
2018
2,064,000
0
0
0
25,000
25,000
P
CN
2019
0
0
2,064,000
-n
0
z
A. PIN/Project No. B. STIP ID
1 70
>
3
CD
U)
0
<
M
—
0
0
C
z
C. Project Title
>
a
CD
--
0
=
C
D. Road Name or Number
0.
0
CL
0
0
-20.
0
U 0
=
9
rr
E. Begin & End Termini
'o
3
z
'V
0
CL
Co
0
0 aL
M
F. Project Description G. Structure ID
CL
P
M
M
M
—
M
a
CL
16
WA-07748
06/13/16
06/20/16
04
C G O P S
No
T W
S 133 StISR599 Southbound Intersection
S 133rd Street
SR 599 Southbound Ramps to S 134th PI
Construct intersection improvements including signalization or roundabout, lighting,
crosswalks, and drainage.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2018
RW
0
25,000
0
310,000
310,000
P
RW
2018
2,064,000
0
0
0
25,000
25,000
P
CN
2019
0
0
2,064,000
2,064,000
Totals
01
1 70
7 2,399,0001
2,399,0001
Expenditure Schedule
Phase
list
2nd
3rd
4th
5th & 6th
PE
0
310,000
0
0
0
RW
0
25,000
0
0
0
CN
0
0
2,064,000
0
0
Totals
1 01
335,0001
2,064,000
01
0
Report Date: June 06, 2016 Page 15
Allift
Villashirwato" state
Departnuat of Trwisportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
ALL
2021
STP(13R)
975,200
01
0
243,800
1,219,000
Totals
975,200
0
243,800
1,219,000
M
V
0
0
0
I
;W
A. PIN/Project No. B. STIP ID
>
3
M
U)
0
C
0
3
�<
z
C. Project Title
X
>
RL
D. Road Name or Number
0-
0
CL
0
0
r-
M
U 0
rr
E. Begin & End Termini
z
0
CL
%:�
S.
aL
F. Project Description G. Structure ID
to
M
0.
0
"a
M
M
CL
17
WA03782
06/13/16
06/20/17
28
0.250
No
S 144th St Bridge Sidewalks
S 144th Street
51 st Ave S to 53rd Ave S
Widen existing sidewalks on bridge over 1-5 between 51st Ave S and 53rd Ave S
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
ALL
2021
STP(13R)
975,200
01
0
243,800
1,219,000
Totals
975,200
0
243,800
1,219,000
Expenditure Schedule
Phase
1st
2nd
I 3rd
4th
5th & 6th
ALL
0
01
0
0
1,219,000
Totals
0
01
0
0
1,219,000
Report Date: June 06, 2016 Page 16
AM1►
ftwW000" $W0
Department of Transportatbm
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
PE
2017
STP
3,892,500
0
0
607,500
M
c
RW
2018
0
1,254,250
5,100,0001
0
q
A. PIN/Project No. B. STIP ID
A.
1,450,000
P
CN
M
(A
0
<
M
C
—
0
3
M
1,000,000
6,000,000
z
C. Project Title
2022
>
1 20,000,0001
(D
25,000,0001
03.
Totals
M
1 0
D. Road Name or Number
M
0.
0
0
0
ei
67
tr
E. Begin & End Termini
—
z
0
CL
to
F. Project Description G. Structure ID
F.
CL
0
M
M
U)
M
CL
16
WA-05410
06/13/16
06/20/16
01
EIS
No
Strander Blvd/SW 27th St Phase III
Strander Boulevard
E City Limits to West Valley Hwy/SR 181
Design and construct arterial improvements for a new roadway extending Strander
Boulevard/SW 27th St from West Valley Highway to Oaksdale Ave
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2017
STP
3,892,500
0
0
607,500
4,500,000
P
RW
2018
STP
1,254,250
5,100,0001
0
195,750
1,450,000
P
CN
2022
FMSIB
5,000,000
0
1,000,000
6,000,000
P
CN
2022
1 TIGER 111
1 20,000,0001
1 01
25,000,0001
45,000,000
Totals
1 30,146,7501
1 0
1 26,803,2501
56,950,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
5,000,000
0
0
0
RW
0
0
1,450,000
0
0
CN
0
0
0 .
0
5,100,0001
1 Totals
1 01
5,000,0001
1,450,0001
0
f— 5,100,000
Report Date: June 06, 2016 Page 17
Aft
Depwtnwat of Transportation
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
<
PE
2017
STP(E)
439,420
0
0
68,580
X
'0
RW
2020
0
173,000
1,725,000
o
A. PIN /Project No. B. STIP ID
200,000
S
�'
o
`�°
0
0
�
�
3
Z
C. Project Title
2018
y
m
Fi
m
286,000
m
Totals
X
1 01
D. Road Name or Number
m
o
0
c
o
n
r-
c
m
E. Begin & End Termini
�,
a
..
3
V
o
a
�
'i
E•
y m
F. Project Description G. Structure ID
a
M
o
M
y
?
a
17
WA -03772
06/13/16
06/20/16
28
0.750
CE
Yes
TUC/TOD Pedestrian Improvements
Baker Blvd (if extended)
Andover Park W to E City Limits
Construct bike /pedestrian connection between the Tukwila Urban Center (TUC) and
Tukwila Station, with service by Amtrak Sounder Commuter Rail/Transit Oriented
Development (TOD) area.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2017
STP(E)
439,420
0
0
68,580
508,000
P
RW
2020
STP(E)
173,000
1,725,000
0
27,000
200,000
S
CN
2017
0
0
1,000,000
1,000,000
P
CN
2018
STP(E)
2,699,000
0
286,000
2,985,000
Totals
3,311,420
1 01
1,381,580
4,693,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
283,000
0
0
225,000
0
RW
0
0
0
200,000
0
CN
1,000,000
1,260,000
0
0
1,725,000
Totals
1,283,000
1,260,000
0
425,000
1,725,000
Report Date: June 06, 2016 Page 18
wasm"ow stato
Depwtment of Transpartatilan
Agency: Tukwila
County: King
MPOIRTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
1
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
CN
2017
Totals
0
OTHER
5,289,000
896,000
X
0
0
0
896,000
"n
0
1
A. PIN/Project No. B. STIP ID
>
3
M
0
0
<
M
a
-I
0
CD
r-
�<
z
C. Project Title
>
:1
CD
su
M
0
a
D. Road Name or Number
CL
0
CL
0
0
r-
-
M
115.
3
rr
E. Begin & End Termini
ID
V
M
z
0
CL
S.
U)
M IM
M
F. Project Description G. Structure ID
I
(a
M
I
0
M
0
CD
00
/1320(002) TUK-50
06/13/16
06/20/16
28
0.640
DCE
Yes
Tukwila Urban Center Pedestrian/Bicycle Bridge over Green River
New bridge over the Green River, approximately between Baker Blvd (if extended)
and Longacres Way (if extended)
Baker Boulevard to West Valley Highway
Construct a new pedestrian/bicycle bridge over the Green River
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
1
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
S
CN
2017
Totals
0
OTHER
5,289,000
896,000
6,185,000
Totals
0
5,289,000
896,000
6,185,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
CN
6,185,000
0
0
0
0
Totals
6,185,000
01
0
0
0
Report Date: June 06, 2016 Page 19
Ad1bk
washito" $11liallo
Deparbnent of Transportation
Agency: Tukwila
County: King
MPO/RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
m
PE
2021
Totals
0
0
0
175,000
X
M
0
0
0
175,000
175,000
0
1
;W
A. PIN/Project No. B. STIP ID
>
M
0
0
<
a
-q
0,
z
C. Project Title
>
CD
o
a
D. Road Name or Number
CD
0
0
M
116
M
tr
E. Begin & End Termini
a)
M
(D
z
IV
0
CL
aL
M
F. Project De cture ID
Description G. Structure
0
M
M
(D
U)
00
WA-03761
06/08/15
06/15/15
28
No
Walk & Roll Plan (Nonmotorized Transportation Plan)
Various City Streets
to
Evaluate deficiencies and create a prioritized list of projects and recommended
design standards.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2021
Totals
0
0
0
175,000
175,000
Totals
0
0
175,000
175,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
01
0
0
175,000
Totals
0
0
1 0
0
175,000
Report Date: June 06, 2016 Page 20
�w .,
Agency: Tukwila
County: King
MPO /RTPO: PSRC
Six Year Transportation Improvement Program
From 2017 to 2022
Y Inside N Outside
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
3
Local Funds
Total Funds
m
<
PE
2020
RW
0
0
0
340,000
M
c
RW
2020
0
0
-�
0
A. PIN /Project No. B. STIP ID
400,000
P
CN
o
3
?
0
1,792,000
542,000
2,334,000
Totals
C. Project Title
y
eo
3,074,000
m
,�
d
M
n
c
D. Road Name or Number
o
o.
o'
n
r
°—'
>v 0
a
E. Begin & End Termini
=
V
z
,�
°c
M w
F. Project Description G. Structure ID
a
o
N
M
a
14
WA03779
06/13/16
06/20/16
03
0.500
CE
No
West Valley Highway
SR 181/West Valley Highway
1-405 to Strander Blvd
Design and construct completion of 7 lane sections of West Valley Highway with
sidewalks, curbs, gutters, storm drainage, lighting, and traffic control, including safety
and capacity improvements at the S 156th St intersection.
Funding
Status
Phase
Phase Start Year (YYYY)
Federal Fund Code
Federal Funds
State Fund Code
State Funds
Local Funds
Total Funds
P
PE
2020
RW
0
0
0
340,000
340,000
P
RW
2020
0
0
2,484,000
0
400,000
400,000
P
CN
2021
0
TIB
1,792,000
542,000
2,334,000
Totals
I
1,792,000
1,282,000
3,074,000
Expenditure Schedule
Phase
1st
2nd
3rd
4th
5th & 6th
PE
0
0
0
174,000
150,000
RW
0
0
0
200,000
200,000
CN
0
0
0
0
2,484,000
Totalsl
0
0
0
374,000
2,834,000
Report Date: June 06, 2016 Page 21
Federal Funds
State Funds
Local Funds
Total Funds
Grand Totals for Tukwila
59,945,521
9,222,400
67,666,083
136,834,004
Report Date: June 06, 2016 Page 21
Christy O'Flaherty
From: Christy O'Flaherty
Sent: Tuesday, June 21, 2016 9:20 AM
To: 'GregA@TIB.wa.gov'
Cc: Bob Giberson
Subject: Tukwila Transportation Improvement Program 2017-2022
June 21, 2016
TO: TRANSPORTATION IMPROVEMENT BOARD
RE: CITY OF TUKWILA 2017-2022 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to City of Tukwila Resolution #1882 passed June 20, 2016, adopting the Transportation
Improvement Program for 2017-2022.
Res 1882 - 2017-2022 Transportation Improvement
Program: httr)://records.tukwilawa.qovANebLink8/l/doc/271937/Pagel.aspx
Please contact me with any questions at 206 433-1855.
Please respond to this email to ensure it was received satisfactorily. Thank you.
Sincerely yours,
Christy O'Flaherty, MMC
City Clerk
Attachment
xc: Bob Giberson, Public Works Director
Christy O'Flaherty
From: Christy O'Flaherty
Sent: Tuesday, June 21, 2016 9:21 AM
To: 'millarr@wsdot.wa.gov'
Cc: Bob Giberson
Subject: Tukwila Transportation Improvement Program 2017-2022
June 21, 2016
TO: WASHINGTON STATE DEPT OF TRANSPORTATION
RE: CITY OF TUKWILA 2017-2022 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to City of Tukwila Resolution #1882 passed June 20, 2016, adopting the Transportation
Improvement Program for 2017-2022.
Res 1882 - 2017-2022 Transportation Improvement
Program: http://records.tukwilawa.govNVebLink8/1 /doc/271937/Pagel.aspx
Please contact me with any questions at 206 433-1855.
Please respond to this email to ensure it was received satisfactorily. Thank you.
Sincerely yours,
Christy O'Flaherty, MMC
City Clerk
Attachment
xc: Bob Giberson, Public Works Director
1
Christy O'Flaherty
From:
Christy O'Flaherty
Sent:
Tuesday, June 21, 2016 9:21 AM
To:
'Andi Markley'
Cc:
Bob Giberson
Subject:
Tukwila Transportation Improvement Program 2017-2022
June 21, 2016
TO: PUGET SOUND REGIONAL COUNCIL
RE: CITY OF TUKWILA 2017-2022 TRANSPORTATION IMPROVEMENT PROGRAM
Following is a link to City of Tukwila Resolution #1882 passed June 20, 2016, adopting the Transportation
Improvement Program for 2017-2022.
Res 1882 - 2017-2022 Transportation Improvement
Program: httr)://records.tukwilawa.govNVebLink8/l/doc/271937/Pagel.aspx
Please contact me with any questions at 206 433-1855.
Please respond to this email to ensure it was received satisfactorily. Thank you.
Sincerely yours,
Christy O'Flaherty, MMC
City Clerk
Attachment
xc: Bob Giberson, Public Works Director
1