HomeMy WebLinkAboutReg 2016-07-18 Item 3C - Resolution - Reject All Bids for South 144th Street Phase II Street ImprovementsCOUNCIL AGENDA SYNOPSIS
nitials
Meeting Date
Prepared by
Mayor's review
C cil review
07/18/16
BG
❑ Resolution
Mtg Date 07118116
.
E].B&Aivard
Mtg Date
EIPublic Hearing
Mtg Date
-
SPONSOR ❑ Council ❑ Mayor [:] HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police Z PW'
SPONSOR'S Council is being asked to approve the Resolution rejecting all bids for the South 144th St
SUMMARY Phase 11 Street Improvement Project. This project includes street improvements on S 144th
St from 42nd Ave S to Tukwila Int'l Blvd. Both bids were significantly over budget. Cost
savings measures will be looked at that include design revisions and closing the road
during construction. Rebidding is now scheduled for later this year with construction in
2017.
RLVILWT,D BY ❑ cow mtg. ❑ CA&P Cmte ❑ F&S Cmte Z Transportation Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 07/OS/16 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works Department
COMMITTEE' Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT/ FUND SOURCE
ExPEINDITuRF. REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
07/18/16
ITEM INFORMATION
3.C.
STAFF SPONSOR: BOB GIBERSON
I ORIGINAL AGENDA DATE: 07/18/16
AGENDA ITI,',m Tri'LLz South 144th Street Phase II Street Improvements
Resolution Rejecting All Bids
CXfEGORY F-1 Discussion
Mtg Date
❑ Motion
Mtg Date
❑ Resolution
Mtg Date 07118116
❑ Ordinance
Mtg Date
E].B&Aivard
Mtg Date
EIPublic Hearing
Mtg Date
❑ Other
Altg Date
SPONSOR ❑ Council ❑ Mayor [:] HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police Z PW'
SPONSOR'S Council is being asked to approve the Resolution rejecting all bids for the South 144th St
SUMMARY Phase 11 Street Improvement Project. This project includes street improvements on S 144th
St from 42nd Ave S to Tukwila Int'l Blvd. Both bids were significantly over budget. Cost
savings measures will be looked at that include design revisions and closing the road
during construction. Rebidding is now scheduled for later this year with construction in
2017.
RLVILWT,D BY ❑ cow mtg. ❑ CA&P Cmte ❑ F&S Cmte Z Transportation Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
DATE: 07/OS/16 COMMITTEE CHAIR: DENNIS ROBERTSON
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works Department
COMMITTEE' Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT/ FUND SOURCE
ExPEINDITuRF. REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source:
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
07/18/16
MTG. DATE
ATTACHMENTS
07/18/16
Informational Memorandum dated 07/01/16
Draft Resolution Rejecting All Bids
Page IS, 201S CIP
Bid Tabulation
Minutes from the Transportation Committee meeting of 07/OS/16
TO:
FROM
BY:
CC:
DATE:
City of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
Transportation Committee
Bob Giberson, Public Works Director
Cyndy Knighton, Senior Program Manager
Mayor Ekberg
July 1, 2016
SUBJECT: S 144"' St - Phase II (42nd Ave S — Tukwila Int'I Blvd)
Project No. 99510402
Resolution to Reject all Bids
ISSUE
Resolution to reject all bids on the S 144th St - Phase II Project.
BACKGROUND
The S 144th St - Phase II Project was advertised starting on May 18, 2016 and bids were opened on June
7, 2016. Two bids were received and the results are shown on the attached bid tabulation. The
construction budget in the 2015 -2020 CIP is summarized below and includes $180,000.00 for
construction management:
Construction Funding Source Amount
TIB Grant $820,000.00
_.. ................____......___.............._.._..........................................................__............_..__.._.._-__.....__- �_._........_.. .......------ ....----- ......... __......-..__............................._. ................._........_....
Tukwila Village Frontage Contribution 700,000.00
.._ ................._..........._............. .__..- ......_..................
Traffic Impact .. ................._............_ . _ . _.._...... ....................................... 25,000.00
_..........---..........-----
General Fund 37,000.00
......................._.............._................._......._....................................................._..............__..........----........_................_.._..........__........---............__.._..............................................__... .....__........................
Construction Mana ement 180,000.00
2015 — 2016 CIP Construction Budget $1,402,000.00
ANALYSIS
Staff has certified the bids and found only one minor error on the low bid of$ 2,017,684.10 and no errors
on the second bid of $2,400.256.55. As both bids were significantly higher than the Engineer's Estimate
of $1,788,471.30, an analysis of the project design, funding package, and bid prices was conducted.
Staff recommends rejecting all bids at this time and rebidding the project in the fall or early winter. In the
interim, the project design can be analyzed in detail to look for cost savings. Cost saving measures to be
considered may include: extended closure of S 144th St between Tukwila International Blvd and 42nd Ave
S during construction; value engineering the project to include design revisions to reduce costs; and
reducing coordination costs with the Tukwila Village contractor. Bidding later this year with work starting
in early 2017 would also mean a single construction season for the street improvements. Addressing all
of these reasons are anticipated to result in a better bidding climate.
FINANCIAL IMPACT
Additional design costs will be incurred to repackage the project, as well as additional costs for a second
advertising. In the long run, a redesign and repackaging of the project is anticipated to save the City
money. The 2017 CIP budget for this project will be evaluated to ensure there is adequate funding
available. The Transportation Improvement Board (TIB) has indicated there may be up to $150,000 in
additional grant money that could be made available, pending the final accepted bid amount.
3
INFORMATIONAL MEMO
Page 2
RECOMMENDATION
Council is being asked to approve the Resolution rejecting all bids received for the S 1441h St Phase 11
Project and consider this item on the Consent Agenda at the July 18, 2016 Regular Meeting.
ATTACHMENTS
Bid Rejection Resolution
Page 15, 2015 Cl P
Bid Tabulation
WAPW Eng\PROJECTS\A- RW & RS Projects\S 144th St Phase 11 TIB - 42nd Ave S (99510402 95-RW02)\Design\INFO MEMO Resolution Bid Reject 07-01-16 rrt.docx
4
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
TUKWILA, WASHINGTON, REJECTING ALL BIDS SUBMITTED
FOR THE SOUTH 144TH STREET PHASE 11 PROJECT.
WHEREAS, sealed bids were solicited for the South 144th Street Phase 11 Project; and
WHEREAS, bids were received from two bidders and were publicly opened and read aloud
on June 7, 2016; and
WHEREAS, a budget was set for the construction of the street improvements; and
WHEREAS, the low bid received was over the budgeted amount for construction of the
South 144th Street Phase 11 Project; and
WHEREAS, the City reserved the right to reject all bids in its call for bids, and RCW
35.23.352 provides for the rejection of any or all bids by resolution of the City Council; and
WHEREAS, the City wishes to reject all bids due to budget limitations;
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,, WASHINGTON,
HEREBY RESOLVES AS FOLLOWS:
All bids for the South 144th Street Phase 11 Project are hereby rejected due to budget
limitations.
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at a
Regular Meeting thereof this day of 12016.
ATTEST/AUTHENTICATED:
Christy O'Flaherty, MMC, City Clerk Joe Duffle, Council President
APPROVED AS TO FORM BY:
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
Rachel B. Turpin, City Attorney
WAWord Processing\ResolLitions\Reject bids for S 144th Street Project 6-27-16
CK:bjs Page 1 of 1
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2015 to 2020
PROJECT:
S 144 St Phase II (42 Ave S - Tukwila Int'I Blvd) * Project No. 99510402 Zone 3
DESCRIPTION:
Construct curb, gutter, sidewalk, bike lanes, pavement restoration, illumination, drainage and utility
undergrounding from Tukwila Int'I Blvd to 42nd Ave S. Also add a signal at 42nd Ave S.
JUSTIFICATION:
Provide pedestrian and vehicle safety, drainage and neighborhood revitalization.
Phase I - Tukwila Int'I Blvd to Military Rd, project completed in 2007 for $3.1 million with $1 million in grants.
STATUS:
Phase II - 42 Ave S to Tukwila International Blvd.
MAINT. IMPACT:
Reduce pavement, drainage repairs, and maintenance costs.
25
Awarded Transportation Improvement Board's Arterial Improvement Program (AIP) grant of $1 million.
COMMENT:
Project is on Impact Fee list. Design and construction related to the Tukwila Village project.
FINANCIAL Through Estimated
tin -4tnnn's1 2n13 2n1d 2n15 2niA 2n17 MR 2n19 2n2n RFYOND TOTAL
EXPENSES
Design
286
25
311
Land (RNV)
40
40
Const. Mgmt.
180
180
Construction
1,402
1,402
TOTAL EXPENSES
1 0
326
1 1,607
1 0
0
0
0
0
0
1,933
FUND SOURCES
Awarded Grant
180
820
1,000
Proposed Grant
0
Proposed Mitigation
100
700
800
Traffic Impact Fees
133
13
25
171
City Oper. Revenue
(133)
33
62
0
0
0
0
0
0
(38)
TOTAL SOURCES
0
326
1 1,607
0
0
0
0
0
0
1 1,933
Project Location
2015 - 2020 Capital Improvement Program
r
15
v
Certified Bid Tab
1 Engineer's Estimate
Gary Merlino Construction Co., Inc.
1 DPK, Inc.
Bid Item Item Quantity Unit Unit Price Total Cost
No.
Unit Price Total Cost
Unit Price Total Cost
SCHEDULE A - ROADWAY IMPROVEMENTS
ROADWAY
■
1
Unexpected Site Changes
1
EST
$ 50,000.00
$ 50,000.00
$ 50,000.00
$ 50,000.00
$ 50,000.00
$ 50,000.00
2
Roadway Surveying
1
LS
$ 21,100.00
$ 21,100.00
$ 18,000.00
$ 18,000.00
$ 25,000.00
$ 25,000.00
3
SPCC Plan
1
LS
$ 1,000.00
$ 1,000.00
$ 300.00
$ 300.00
$ 6,000.00
$ 6,000.00
4
Resolution of Utility Conflicts
1
EST
$ 25,000.00
$ 25,000.00
$ 25,000.00
$ 25,000.00
$ 25,000.00
$ 25,000.00
5
Utility Potholing
1
EST
$ 6,000.00
$ 6,000.00
$ 6,000.00
$ 6,000.00
$ 6,000.00
$ 6,000.00
6
Type B Progress Schedule
1
LS
$ 5,000.00
$ 5,000.00
$ 300.00
$ 300.00
$ 15,000.00
$ 15,000.00
7
Mobilization
1
LS
$ 131,800.00
$ 131,800.00
$ 235,000.00
$ 235,000.00
$ 86,000.00
$ 86,000.00
8
Project Temporary Traffic Control
1
LS
$ 122,100.00
$ 122,100.00
$ 187,000.00
$ 187,000.00
$ 100,000.00
$ 100,000.00
9
Clearing and Grubbing
1
LS
$ 11,000.00
$ 11,000.00
$ 20,000.00
$ 20,000.00
$ 50,000.00
$ 50,000.00
10
Removal of Structure and Obstruction
1
LS
$ 25,000.00
$ 25,000.00
$ 25,000.00
$ 25,000.00
$ 40,000.00
$ 40,000.00
11
Roadway Excavation Incl. Haul
980
CY
$ 25.00
$ 24,500.00
$ 110.00
$ 107,800.00
$ 40.00
$ 39,200.00
12
Unsuitable Foundation Excavation Incl. Haul
110
CY
$ 30.00
$ 3,300.00
$ 58.00
$ 6,380.00
$ 45.00
$ 4,950.00
13
Gravel Borrow Incl. Haul
1440
TON
$ 20.00
$ 28,800.00
$ 31.00
$ 44,640.00
$ 30.00
$ 43,200.00
14
Crushed Surfacing Base Course
1280
TON
$ 22.00
$ 28,160.00
$ 46.00
$ 58,880.00
$ 40.00
$ 51,200.00
15
HMA CI 1/2" PG 64 -22
620
TON
$ 100.00
$ 62,000.00
$ 105.00
$ 65,100.00
$ 110.00
$ 68,200.00
16
HMA CI 1/2" PG 64 -22 for Overlay
340
TON
$ 90.00
$ 30,600.00
$ 105.00
$ 35,700.00
$ 105.00
$ 35,700.00
17
Planing Bituminous Pavement
690
SY
$ 7.00
$ 4,830.00
$ 10.00
$ 6,900.00
$ 10.00
$ 6,900.00
18
Cement Conc. Pavement
65
CY
$ 220.00
$ 14,300.00
$ 500.00
$ 32,500.00
$ 580.00
$ 37,700.00
19
Decorative Stamped Finish
25
SY
$ 100.00
$ 2,500.00
$ 260.00
$ 6,500.00
$ 230.00
$ 5,750.00
20
Concrete Steps
1
LS
$ 5,000.00
$ 5,000.00
$ 1,600.00
$ 1,600.00
$ 8,000.00
$ 8,000.00
21
Cast -in -Place Wall
1
LS
$ 2,000.00
$ 2,000.00
$ 8,000.00
$ 8,000.00
$ 13,000.00
$ 13,000.00
22
Modular Block Wall
310
SF
$ 35.00
$ 10,850.00
$ 40.00
$ 12,400.00
$ 46.00
$ 14,260.00
23
Erosion Control and Water Pollution Prevention
1
LS
$ 61,000.00
$ 61,000.00
$ 30,000.00
$ 30,000.00
$ 15,000.00
$ 15,000.00
24
Cement Conc. Traffic Curb and Gutter
1640
LF
$ 25.00
$ 41,000.00
$ 50.00
$ 82,000.00
$ 26.00
$ 42,640.00
25
Cement Conc. Gutter
510
LF
$ 25.00
$ 12,750.00
$ 50.00
$ 25,500.00
$ 28.00
$ 14,280.00
26
Roundabout Cement Concrete Curb and Gutter
280
LF
$ 27.00
$ 7,560.00
$ 70.00
$ 19,600.00
$ 45.00
$ 12,600.00
27
Extruded Curb Type 6
40
LF
$ 10.00
$ 400.00
$ 30.00
$ 1,200.00
$ 25.00
$ 1,000.00
28
Cement Conc. Driveway Entrance Type 1
320
SY
$ 70.00
$ 22,400.00
$ 135.00
$ 43,200.00
$ 60.00
$ 19,200.00
29
Cement Conc. Driveway Entrance Type 2
30
SY
$ 70.00
$ 2,100.00
$ 135.00
$ 4,050.00
$ 140.00
$ 4,200.00
30
Cement Conc. Driveway Entrance Type 3
50
SY
$ 70.00
$ 3,500.00
$ 135.00
$ 6,750.00
$ 100.00
$ 5,000.00
31
Adjust Monument Case and Cover
1
EA
$ 500.00
$ 500.00
$ 500.00
$ 500.00
$ 600.00
$ 600.00
32
Mailbox Support
1
EA
$ 350.00
$ 350.00
$ 500.00
$ 500.00
$ 400.00
$ 400.00
33
Railing
1
LS
$ 5,000.00
$ 5,000.00
$ 4,000.00
$ 4,000.00
$ 4,000.00
$ 4,000.00
Subtotal Roadway $ 771,400.00
$ 1,170,300.00
$ 849,980.00
SIDEWALK
34
Cement Conc. Sidewalk
1650
SY
$ 40.00
$ 66,000.00
$ 70.00
$ 115,500.00
$ 50.00
$ 82,500.00
35
Thickened Edge Sidewalk
130
LF
$ 45.00
$ 5,850.00
$ 27.00
$ 3,510.00
$ 100.00
$ 13,000.00
36
Cement Conc. Curb Ramp Type Perpendicular A
8
EA
$ 1,500.00
$ 12,000.00
$ 2,000.00
$ 16,000.00
$ 1,700.00
$ 13,600.00
37
Cement Conc. Curb Ramp Type Perpendicular B
2
EA
$ 1,500.00
$ 3,000.00
$ 2,000.00
$ 4,000.00
$ 1,900.00
$ 3,800.00
38
Cement Conc. Curb Ramp Type Parallel A
1
EA
$ 1,500.00
$ 1,500.00
$ 2,000.00
$ 2,000.00
$ 2,000.00
$ 2,000.00
39
Detectable Warning Surface
40
SF
$ 45.00
$ 1,800.00
$ 32.00
$ 1,280.00
$ 30.00
$ 1,200.00
Subtotal Sidewalk $ 90,150.00
$ 142,290.00
$ 116,100.00
STORM DRAINAGE
40
Shoring or Extra Excavation Cl. B
3290
SF
$ 1.00
$ 3,290.00
$ 1.00
$ 3,290.00
$ 0.10
$ 329.00
41
Gravel Backfill Incl. Haul for Storm Trench
440
TN
$ 18.00
$ 7,920.00
$ 25.00
$ 11,000.00
$ 30.00
$ 13,200.00
42
Ductile Iron Storm Sewer Pipe 12 In. Diam.
420
LF
$ 100.00
$ 42,000.00
$ 105.00
$ 44,100.00
$ 175.00
$ 73,500.00
43
Solid Wall PVC Storm Sewer Pipe 18 In. Diam.
50
LF
$ 40.00
$ 2,000.00
$ 117.00
$ 5,850.00
$ 175.00
$ 8,750.00
44
Solid Wall PVC Storm Sewer Pipe 12 In. Diam.
560
LF
$ 50.00
$ 28,000.00
$ 77.00
$ 43,120.00
$ 140.00
$ 78,400.00
45
Storm Drainage Television Inspection
1
LS
$ 2,000.00
$ 2,000.00
$ 2,000.00
$ 2,000.00
$ 1,000.00
$ 1,000.00
46
Concrete Inlet
3
EA
$ 800.00
$ 2,400.00
$ 1,400.00
$ 4,200.00
$ 1,500.00
$ 4,500.00
47
Catch Basin Type 1
6
EA
$ 1,000.00
$ 6,000.00
$ 1,700.00
$ 10,200.00
$ 1,800.00
$ 10,800.00
I. of3
03
Certified Bid Tab
1 Engineer's Estimate
1 Gary Merlino Construction Co., Inc.
DPK, Inc
Bid Item
Item Quantity Unit Unit Price Total Cost
No.
Unit Price Total Cost
Unit Price Total Cost
48
Catch Basin Type 1 L
1
EA
$ 2.000D0
$ 2.000.00
$ 2,000.00
$ 2.000.00
$ 1.850.O0
$ 1.850.00
49
Catch Basin Type 2 48 In. Dam.
6
EA
$ 3.000D0
$ 18.000.00
$ 4.200.00
$ 25.200D0
$ 2.500.00
$ 15.000.00
50
Adjust Catch Basin
8
EA
$ 500.00
$ 4.000.00
* 400.00
$ 3.200o0
$ 700.00
$ 5.800D0
51
Connectto Existing Drainage Structure
3
EA
$ 1.000.00
$ 3.000.00
$ 1.200.00
$ 3.600.00
$ 4.000.00
$ 12.000.00
52
Connect Drainage Structure to Existing Pipe
1
EA
$ 800.00
$ 800.00
$ 1.200.00
$ 1.200.00
$ 5.000.00
$ 5.000.00
53
Stormwater Treament Vault, 4'x8'
1
EA
$ 22.500.00
$ 22.500.00
20.000.00
$ 20.000.00
$ 40.000.00
$ 40.000.00
54
Stormwater Treatment Vault, 4'x13'
1
EA
$ 38.000.00
$ 83.000.00
$ 31.000.00
$ 81.000.00
$ 50.000.00
$ 50.000.00
Subtotal Storm Drainage $ 178.910.00
$ 209.000.00
$ 319.929.00
WATER
55
Ductile Iron Pipe for Water Main 4 In. Diam.
10
LF
$ 130.00
$ 1.300.00
$ 180.00
$ 1.300.00
$ 250.00
$ 2.500.00
56
Adjust Water Valve
10
EA
$ 500.00
$ 5.000.00
$ 400.00
$ 4.000.00
$ 000.00
$ 8.000.00
57
Relocate FDC, PiV and associated appurtenances
1
LS
$ 7.000.00
$ 7.000o0
$ 3.000.00
$ 3.000.00
$ 8.000.00
$ 8.000.00
58
Adjust Water Meter Box
3
EA
$ 400.00
$ 1.200.00
$ 300.00
$ 800.00
$ 850.00
$ 1.050.00
59
Service Connection 1 In. Diam.
1
EA
$ 1.000D0
$ 1.000.00
$ 4.000.00
$ 4.000.00
$ 5.000.00
$ 5.000.00
60
Relocate Water Meter, Setter and Box
2
EA
$ 700.00
$ 1.400.00
$ 600.00
$ 1.200.00
$ 1.500.00
$ 3.000.00
Subtotal Water $ 16.900D0
$ 14.400.00
$ 25.550.00
SANITARY SEWER
61
Adjust Sewer Manhoe j 3
EA |* 500.00
$ 1.500.00
$ OUU.UO|$ 1.800.00
$ 800.00 1 * 2.400.00
Subtotal Sanitary Sewer $ 1.500.00
$ 1.800.00
$ 2.400.00
JLLUMINATION AND SIGNAL SYSTEMS
62
Illumination System, Complete
1
LS
$ 215.000.00
$ 215.000.00
$ 190.000.00
$ 190.000.00
$ 170.000.00
$ 170.000D0
63
Traffic Signal System, Complete (S 144th St and 42nd Ave S)
1
LS
$ 258.000.00
$ 259.000.00
$ 215.000.00
$ 215.000.00
$ 185.000.00
$ 185.000.00
64
Signal Loop Modifications, Complete (Tukwila Intl Blvd &S144thSt)
1
LS
$ 16'000o0
$ 10.000.00
$ 15.000.00
$ 15.000.00
$ 15.000.00
$ 15.000.00
65
Rectangular Rapid Flashing Beacon (RRFB) System, Complete
1
LS
$ 25.000.00
$ 25.000.00
$ 11.000.00
$ 11.000.00
* 12.000.00
$ 12.000.00
Subtotal lilumination & Signal Systems $ 515.000.00
$ 431.000.00
$ 382.000.00
TRAFFIC CONTROL DEVICES
06
Storm Dram Marker
13
EA
$ 50D0
$ 650.00
$ 35.00
$ 456.00
$ 25.80
$ 325.00
67
Raised Pavement Marker Type 1
3.5
HUND
* 300.00
$ 1.050.00
$ 300.00
$ 1.050.00
$ 450.00
$ 1.575.00
68
Raised Pavement Marker Type 2
0.5
HUND
$ 400.00
$ 200.00
$ 420.00
$ 210.00
$ 1.000D0
$ 500.00
69
Permanent Signing
1
LS
$ 4.000D0
$ 4.000.00
$ 8.000.00
$ 9.000.00
$ 5.000.00
$ 5.000.00
70
Plastic Line, 4 In.
1920
LF
$ 2.00
$ 8.840.00
$ 1.20
$ 2.304.00
$ 2.00
$ 3.840.00
71
Plastic Stop Line
90
LF
$ 8.00
$ 720.00
$ 3.00
$ 270.00
$ 8.00
$ 720.00
72
Plastic Crosswalk Line
490
SF
$ 8.00
$ 3.920.00
$ 3.30
$ 1.617.00
$ 6.00
$ 2.940.00
73
Plastic Traffic Arrow
2
EA
$ 100.00
$ 200.00
$ 220.00
$ 440.00
$ 50.00
$ 100.00
74
Plastic Bicycle Lane Symbol
4
EA
$ 100.00
* 400.00
$ 420.00
$ 1.680.00
$ 300.00
$ 1.200.00
75
P|astiuBicyc|oLane8ymbo|forLoopDetaction
2
EA
$ 75.00
$ 150.00
$ 280.00
$ 500.00
$ 140.00
$ 280.00
76
Plastic Access Parking Space Symbol
4
EA
$ 100.00
$ 400.00
$ 390.00
$ 1.560.00
$ 360.00
$ 1.440.00
77
Paint Line, 4In.
290
LF
$ 1.00
$ 290.00
$ 1.10
$ 319.00
$ 0.025
$ 7.25
Subtotal Traffic Control Devices $ 15.820.00
$ 19.465D0
$ 17.927.25
ROADSIDE DEVELOPMENT
78
Property Restoration
1
EST
$ 5.500.00
$ 5,500.00
$ 5.500.00
$ 5.500.00
$ 5.500o0
$ 5.500.00
79
Topsoil Type A
150
CY
$ 40.00
$ 8.000.00
$ 40u0
$ 6.000.00
$ 35.00
$ 5.250.00
80
Bark Mulch
15
CY
$ 40.00
$ 600.00
$ 33.00
$ 495.00
$ 60.00
$ 900.00
81
Seeded Lawn lnstallation
115
8Y
$ 3.00
$ 345.00
* 1.30
$ 149.50
$ 5.00
$ 575D0
82
P8|PETi|io|omen|ooa'PN|GO51Y Green Mountain Linden; 2.5^Co}..12''14'Ht.
13
EA
$ 400.00
$ 5.200D0
$ 870.00
$ 4.810.00
$ 350.00
$ 4.550.00
83
PG|PECornuokouooxnuttuUii'KN4-43Y Starlight Dogwood; 2.5^Cu|'.12'-14'Ht.
11
EA
$ 350.00
$ 3.850.00
$ 370.00
$ 4.070.00
$ 350.00
$ 3.850.00
84
PSIPEAbo|iaxgnundiUom'Ka|eidoaoopeYKa|oidoocopeAbe|ie;2Ga||onCont
18
EA
$ 22.00
$ 396.00
$ 19.00
$ 34280
$ 20.00
$ 880.00
85
PSIPE Berberis thunbergii 'Concorde'/ Concorde Japanese Barberry; 2 Gallon Cont.
86
EA
$ 22.00
$ 1.882.00
$ 21.00
$ 1.806.00
$ 20.00
$ 1.720.00
86
PSI PESpinooe japonica 'YVa|bumeY Magic Carpet Spinuo;2 Gallon Cont.
60
EA
$ 22.00
$ 1.320.00
$ 21.00
$ 1.260.00
$ 20.00
$ 1.200D0
87
PSIPE Calluna vulgaris Spring Torch'! Spring Torch Heather; 1 Gauon Cont.
68
EA
$ 18.00
$ 1.134.00
$ 14.00
* 882.00
$ 20.00
$ 1.200.00
88
PSIPE Teucrium chamaedrys Wall Germander; 1 GalIon Cont.
85
EA
$ 18.00
$ 1.530.00
$ 11.00
$ 935.00
* 10.00
$ 850.00
89
PSIPE Pennisetum Alopecuroides 'Little Bunny'/ Little Bunny Dwarf Fountain Grass; 1 Gallon Cont.
91
EA
$ 12.00
$ 1.092.00
$ 10.00
$ 910.00
$ 10.00
$ 310D0
90
PG|PEGnhizochyriumecoporium 'The B|uooY The Blues Little 8/uastnm
51
EA
$ 12.00
$ 012.00
$ 14D0
$ 714.00
$ 10.00
$ 510.00
91
PSI PE Veronica peduncularis 'Georgia BlueY Georgia Blue Speedwell; 1 Gallon Cont.
210
EA
$ 10.00
$ 2.100.00
14.00
$ 2.940.00
$ 10.00
$ 2.100.00
CO
O
Certified Bid Tab
Engineer's Estimate
Gary Merlino Construction Co., Inc.
I DPK, Inc.
Bid Item
Item Quantity Unit Unit Price Total Cost
No.
Unit Price Total Cost
Unit Price Total Cost
92
PSIPE Geum 'Mango Lassi'/ Mango Lassi Avens; 1 Gallon Cont.
290
EA
$ 10.00
$ 2,900.00
$ 14.00
$ 4,060.00
10.00
$ 2,900.00
93
Root Barrier
400
LF
15.00
$ 6,000.00
$ 9.00
$ 3,600.00
$ 4.00
$ 1,600.00
94
Automatic Irrigation System, Complete
1
LS
$ 35,000.00
$ 35,000.00
41,000.00
$ 41,000.00
$ 40,000.00
$ 40,000.00
95
Bench
4
EA
$ 1,800.00
$ 7,200.00
$ 2,200.00
$ 8,800.00
$ 2,500.00
$ 10,000.00
96
Trash Receptacle
2
EA
$ 2,000.00
$ 4,000.00
$ 2,200.00
$ 4,400.00
$ 1,500.00
$ 3,000.00
LF
Subtotal Roadside Development $ 86,671.00
$ 92,673.50
$ 87,035.00
FRANCHISE UTILITY ITEMS
$ 29.00
$ 62,930.00
97
Franchise Utility Coordination
1
LS
$ 5,000.00
$ 5,000.00
$ 2,000.00
$ 2,000.00
$ 25,000.00
$ 25,000.00
98
Adjust Gas Valve
2
EA
$ 500.00
$ 1,000.00
$ 400.00
$ 800.00
$ 600.00
$ 1,200.00
Subtotal Franchise Utility Items $ 6,000.00
$ 2,800.00
$ 26,200.00
Sub-Total
Schedule A $ 1,680,351.00
2,084,688.50
$ 1,827,121.25
SCHEDULE B - SEATTLE CITY LIGHT IMPROVEMENTS
99
Adjust Utility Vault
1
EA
$ 500.00
$ 500.00
$ 1,300.00
$ 1,300.00
$ 2,900.00
$ 2,900.00
100
Adjust Handole
1
EA
$ 300.00
$ 300.00
$ 300.00
$ 300.00
$ 900.00
$ 900.00
101
Furnish and Install 507LA Vault
1
EA
$ 9,000.00
$ 9,000.00
$ 13,000.00
$ 13,000.00
$ 8,000.00
$ 8,000.00
102
Furnish and Install 577LA Vault
1
EA
$ 11,000.00
$ 11,000.00
$ 19,000.00
$ 19,000.00
10,000.00
$ 10,000.00
103
Furnish and Install 712LA Vault
1
EA
$ 25,000.00
$ 25,000.00
$ 42,000.00
$ 42,000.00
$ 15,000.00
$ 15,000.00
104
Furnish and Install PVC Conduit, 4 In. Diam.
2170
LF
$ 12.00
$ 26,040.00
$ 47.00
$ 101,990.00
$ 29.00
$ 62,930.00
105
Furnish and Install PVC Conduit, 5 In. Diam.
1700
LF
$ 15.00
$ 25,500.00
$ 58.00
$ 98,600.00
$ 39.00
$ 66,300.00
106
Replace Frame and Cover, 42 In. Round
2
EA
$ 700.00
$ 1,400.00
$ 6,000.00
$ 12,000.00
$ 4,000.00
$ 8,000.00
Schedule B Subtotal
Sales Tax (9.5%)
$ 98,740.00
$ 9,380.30
$ 288,190.00
$ 27,378.05
$ 174,030.00
$ 16,532.85
Sub-Total
$ 108 ' 120.30
Schedule B
315,568.05
$ 190,562.85
TOTAL CONSTRUCTION BID/ESTIMATE (Schedule A + B) $ 1,788,471.30
$ 2,400,256.55
$ 2,017,684.10
Miscalculations in Contractor Bid Proposals:
(1) Amount entered on Proposal for Total Cost was $72.50. Calculating the unit price times the quantity is $7.25. Error carried through to bid amount on Schedule A and the Total Bid.
Certified by
Cyndy
Date
June 7, 2016
3 of 3
12
TRANSPORTATION COMMITTEE
Meeting Minutes
City of Tu kwi la
City Council Transportation Committee
July 5, 2016 - 5:30 p.m. -Foster Conference Room, 6300 Building
Councilmembers: Dennis Robertson, Chair; Verna Seal, De'Sean Quinn
Staff: David Cline, Gail Labanara, Pat Brodin, Peter Lau, Robin Tischmak, Laurel
Humphrey
CALL TO ORDER: Committee Chair Robertson called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. BUSINESS AGENDA
A. Bid Rejection Resolution: South 144th Street Phase II (42nd Avenue South - TO
Staff is seeking Council approval of a resolution to reject all bids on the South 144th Street -
Phase II Project. Two bids were received in June and were both significantly higher than the
Engineer's Estimate of $1,788,471.30. Staff recommends rejecting the bids and rebidding in
fall or early winter after a cost savings analysis is conducted. UNANIMOUS APPROVAL.
FORWARD TO JULY 18, 2016 REGULAR CONSENT AGENDA.
B. Contract; Tukwila Urban Center - Pedestrian /Bicycle Bridge
Staff is seeking Council approval of a contract with AKANA for construction management
services for the Tukwila Urban Center Pedestrian /Bicycle Bridge in the amount of $700,669.00.
The contract will include field engineering, inspection, documentation compliance support,
and on -call specialty consultation. The fee is reasonable and under the budget of $850,000.
UNANIMOUS APPROVAL. FORWARD TO JULY 18, 2016 REGULAR CONSENT AGENDA.
III. SCATBd
No report was given.
IV. MISCELLANEOUS
The Transportation Committee Meeting adjourned at 5:40 p.m.
Next meeting: Monday, July 18, 2016
Committee Chair Approval
Minutes,by LH, Reviewed by GL
13