HomeMy WebLinkAboutUtilities 2016-09-13 Item 2D - Contract Supplement #1 - Andover Park East Water and Sewer Replacement with PACE EngineersTO:
FROM:
BY:
CC:
DATE:
C 0
ity of Tukwila Allan Ekberg, Mayor
Public Works Department - Bob Giberson, Director
Utilities Committee
Bob Giberson, Public Works Director A9
Mike Cusick and Peter Lau, Senior Program Managers
Mayor Ekberg
September 9, 2016
SUBJECT: Andover Park East Water and Sewer Replacement Proiect
Project No. 99940103 (and 91440204), Contract No. 15-116
PACE Engineers Supplemental Agreement No. 1
ISSUE
Approve Supplemental Agreement No. 1 with PACE Engineers Inc. (PACE).
BACKGROUND
PACE is the design consultant for the Andover Park East Water and Sewer Replacement Project with
Contract No. 15-116. On August 1, 2016 Council approved the construction contract with Titan
Earthworks. Supplemental Agreement No. 1 with PACE will provide design and construction support to
the City during construction.
DISCUSSION
PACE incurred additional costs for surveying and design of ADA sidewalk ramps, replacement of catch
basins and manhole covers, and developing a detour plan to keep local businesses in operation during
the different stages of construction. Supplemental Agreement No. 1 also includes on-call construction
management services to the City during construction to allow PACE to attend meetings, review
submittals, and answer technical questions from the City and the contractor. A time extension to
December 31, 2017 is also included in Supplemental Agreement No.l.
FINANCIAL IMPACT
The Proposed 2017 budget for construction management is $640,000 for the Andover Park East Water
and Sewer Replacement Project. AECOM was hired as the main construction management firm for
$532,893.84, leaving the remaining budget of $107,106.16 for PACE's Supplemental Agreement No. 1.
Remaining
CM Expenses CM Budget
PACE Construction Management $30,128.76
PACE Additional Design Services 24,967.56 $107,106.16
Supplement No.1 Total $_55,Q96.32 $107106.16
RECOMMENDATION
Council is being asked to approve Supplemental Agreement No. 1 to Contract No. 15-116 with PACE
Engineers, Inc. in the amount of $55,096.32 for the Andover Park East Water and Sewer Replacement
Project and consider this item at the September 26, 2016 Committee of the Whole Meeting and
subsequent October 3, 2016 Regular Meeting.
Attachments: Proposed 2017 CIP Sheets
PACE Supplemental Agreement No. I
W:\PW Eng\PROJECTS\A- WT Projects\APE Water Main Replacement (99940103)\Info Memo PACE Supp #1 09-09-16 gi sb.docx
Kul
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Andover Park E Water Main Replacement Project No. 99940103
DESCRIPTION: Design and construct 2,700 LF of new 8" & 16" ductile iron pipe along Andover Park East from Tukwila Pkwy
to Strander Blvd.
JUSTIFICATION: Support future growth within this area of the CBD as aging cast iron system has suffered frequent failures.
STATUS: Survey and design is complete. Construction is scheduled for 2016 from Strander Blvd to Tukwila Pkwy
with final paving in 2017.
MAINT. IMPACT: A new pipe will significantly reduce impact on crews from the risk of cataclysmic events.
COMMENT: PWTF loans were rescinded in 2014 & 2015 by the State Legislature.
FINANCIAL Through Estimated
tin S000'sl 2015 2016 2017 2018 2019 2020 2021 2022 BEYOND TOTAL
EXPENSES
Design
140
59
199
Land (R/W)
0
Const. Mgmt.
284
100
384
Construction
2,100
685
2,785
TOTAL EXPENSES
140
2,443
785
0
0
0
0
0
0
3,368
FUND SOURCES
Awarded Grant
0
Proposed Bond
0
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
140
2,443
785
0
0
0
0
0
0
3,368
TOTAL SOURCES
140
2,443
785
0
0
0
01
01
0
1 3,368
38
2017 - 2022 Capital Improvement Program 60
h0w IF,
38
2017 - 2022 Capital Improvement Program 60
CITY OFT0KWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Andover Park East Sewer Replacement Project No. S1440204
DESCRIPTION: Design and construct 1,600 LF of 15" and 12" sanitary sewer from Strander Blvd. to 1-405 in Andover Park E.
JUSTIFICATION: Sewer improvement will provide additional capacity for future development along Andover Park East.
STATUS: Project will overlay Andover Park East from EKnander Blvd 1o|-4O5in2O17.
YN/UNT.|K0PACT:
ConokucUon� scheduled for 2O1O[mmG�onderB�dtoTuk�|uPa�woy M�gadon�fmmVVaohin�on
��K8K0�N�'
' Place for the increased sewer capacity needed for the size of the development.
FINANCIAL Through Estimated
EXPENSES
Design
47
43
90
Const. Mgmt.
206
50
256
Construction
1,626
500
2,126
TOTAL EXPENSES
471
1,875
1 550
1 01
01
01
01
01
01
2,472
FUND SOURCES
Awarded Grant
0
Mitigation Actual
0
Mitigation Expected
290
290
39
2n1r-zos2 Capital Improvement Program 77
SUPPLEMENTAL AGREEMENT NUMBER I
to
CONSULTANT AGREEMENT NUMBER 15-116
THIS SUPPLEMENTAL AGREEMENT is entered into between the City of Tukwila,
Washington, herein-after referred to as "the City", and PACE Engineers, Inc hereinafter referred
to as "the Consultant", in consideration of the mutual benefits, terms, and conditions hereinafter
specified.
The City desires to supplement the agreement entered into with the Consultant and executed on,
June 18, 2015 and identified as Agreement No. 15-116. All provisions in the basic agreement
remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Scope of Services, for Supplemental Agreement #1 Andover Part East Water and Sewer Replacement
project for the City of Tukwila. The purpose of this supplement is to add:
1. Engineering Design Services
• Design 8 ADA ramps so that they bought up to current code requirements.
• Design for the replacement of 1960 and 1970 storm drain structures that are at end of
their design life and do not meet current City of Tukwila Infrastructure Standards.
• Survey and evaluate the existing asphalt pavement section in Andover Park East for the
replacement of the asphalt pavement after the installation of the proposed water and
sewer improvements.
• Develop a new channelization and striping plan.
• Develop a detour plan for the installation water and sewer lines that provides access to
the business in the construction
2. Construction Administration Services
• Attend the pre-construction conference.
• Review up to 10 material submittals for compliance with contract documents.
• Review and address up to 10 RFI's.
• Review up to 3 contract pay estimates as requested. We assume the City will prepare
the estimates.
• Review up to 5 change orders and prepare documents as necessary. Attend
construction meetings as requested by the City. The City will provide meeting agendas
and minutes.
• Provide up to 52 hours to assist the City as requested throughout construction.
• Prepare Record Drawings. The contractor's and City's redlines will be incorporate into
the design drawings to create Auto Cad Record Drawings.
E, to]
3. Payment, shall be amended as follows: Payment for the work provided by the Consultant as part
of this supplement shall be made for an additional $55,096.32 the total amount for the Consultant
for this contact shall not exceed $414,954.32 without express written modification of the
Agreement signed by the City
4. Time for Performance, is amended to change the number of calendar days for completion of the
work to read 930 days. The completion date will now be December 31, 2017.
DATED this -- day of , 2016.
CITY OF TUKWILA
Allan Ekberg, Mayor
I—
U
By:
Prii
E151
PACE Engineers, Inc.
Project Name
Attachment A
Project Name APE Construction Admin. Assistance
Project #: Proj Number
15412
BG
50
Project Budget Worksheet - 2016 Standard Rates
Location: (Project
ocation
City of Tukwila
Task #:
00
Prepared By:
Date:
Staff Type # (See Labor Rates Table)
Staff Type Hourly Rate
Drawing/rask Title
Pre- Construction ;M
Submittal Review
Address RFC's
Pay Requests
Change Orders
Construction Meet4
General Assistance
Prepare Record Drawl
Hours Total
Labor Total
Expenses
Labor Hours by Classification
DH
25- Jul -16
Labor
Code
Job
Title
1
$204
Senior
Senior Principal
Engineer
4
6
25
2
10 12
$192 _._.m,.M $169
Principal
Engineer
30
20
15
25
2
Project
Manager
10
70
$148
•GIS /CAD
Manager
2
74
20
Hour
Total
4.0
10.0
30.0
6.0
20.0
15.0
50.0
26.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0,0
37.0
$7,548
92.0
$17,664
10.0
$1,690
2.0
$296
20.0
$2,340
0.0
$0
0.0
$0
0.0
$0
0.0
$0
0.0
$0
0.0
$0
Postage/Courie
Plotter
PhotoNidr
Mileage/Trave
Miscellaneous
Technology Fee (2%
rate /unit
Reimbursable
Quantity Cost
Total
$590.76
File: CA Budget, Fee Worksheet
5T.'. 7t
Subconsultants
Uti
}echantcat °Engineei
Electrical Engineer
Geotechnicat Engineer
& C Engineer
iubconsultant Sub'
arkup
PACE Billed Labor Total
Reimbursable Expenses
Subconsultants
Total Project Budge
Total
Page l of 1
Rate Table Used: 2016 Standard Rates
Printed: 712512016,10:56 AM