HomeMy WebLinkAboutCAP 2016-09-26 Item 2A - Resolution - 2017 Permit Fee Schedule: Community Development and Public WorksCity of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Community Affairs and Parks Committee
FROM: Jack Pace, DCD Director
BY: Nora Gierloff, Deputy DCD Director
CC: Mayor Ekberg
DATE: September 19, 2016
SUBJECT: Updated DCD and PW Permit Fees
ISSUE
Should Tukwila increase its land use permit fees and hourly inspection rates to reflect increased
costs to provide development review services?
BACKGROUND
Salaries for represented employees will increase in 2017 by 90% of the increase in CP1—W
(June) 2015-16. The CPI-W for that period is 2% and benefit costs have increased by an even
higher percentage.
The City's costs for processing credit card payment for permit applications have been increasing
steadily to a projected $25,000 in 2016. This is expected to sharply increase over the next few
years as we begin to allow online permit applications.
DISCUSSION
Staff is suggesting that the flat land use fees increase at the rate of the City's labor and benefit
costs. Some other permit fees are based on the valuation of the work which itself reflects
inflation so no adjustment is needed for them.
A reduced fee is proposed for temporary sign permits. We have heard that the current fee is a
barrier to small businesses in complying with the sign code. We have examined our processing
of these permits and a reduction is justified and hopefully will increase compliance rates.
The Finance and Technology Services Departments have reviewed the issue of passing
through credit card fees as a surcharge to the applicant. They have decided to start with a 3%
convenience fee and evaluate after the first year.
FINANCIAL IMPACT
The proposed fee increases will keep pace with the City's costs to provide these necessary
services.
RECOMMENDATION
The Council is being asked to approve the resolution and consider this item at the October 10
2016 Committee of the Whole meeting and subsequent October 17 Regular Meeting Consent
agenda.
ATTACHMENT
Draft Building /Electrical /Plumbing /Mechanical Permit Fee Resolution
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
TUKWILA, WASHINGTON, REPEALING RESOLUTION NO. 1867,
AND ADOPTING A CONSOLIDATED PERMIT FEE SCHEDULE.
WHEREAS, the City Council adopted Resolution No. 1867 in 2015, establishing the
City's current consolidated construction fee schedule; and
WHEREAS, the City intends to update permit fees on an annual basis, with any
increases tied to growth in City expenses for providing permit services; and
WHEREAS, the City Council wishes to recover a portion of the City's costs for
review and processing of permit applications; and
WHEREAS, the City has adopted a biennial budget process; and
WHEREAS, the City's primary cost for permit processing is employee salaries and
benefits-, and
WHEREAS, the Seattle Consumer Price Index (CPI-W) was 2% for the June 2015-
2016 period; and
WHEREAS, the cost for employee benefits has risen by an even larger percentage;
and
WHEREAS, increasing the flat fee for permits by 2% will enable revenues to track
with City costs; and
WHEREAS, as more permit applicants are paying by credit card, the surcharge on
these transactions has become a significant budget impact, and
WHEREAS, the City intends to pass this convenience fee through to the permit
applicants; and
WHEREAS, the City will evaluate its surcharge procedures after a one year trial
period;
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs Page 1 of 13
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA,
WASHINGTON, HEREBY RESOLVES AS FOLLOWS:
Section 1. Repealer. Resolution No. 1867 is hereby repealed, effective January
1, 2017.
Section 2. For 2017 and 2018, the Technology Fee shall be set at 5% of the
applicable permit fee.
Section 3. Public Works fees will be charged according to the following schedule:
PUBLIC WORKS FEE SCHEDULE
PERMIT DESCRIPTION
FEE
Type A (Short-Term Non-profit)
$ 50.00 +Technology Fee
Type B (Short-Term Profit)
$100.00 + Technology Fee
Type C
$250.00 application base fee, Technology Fee, plus
(Infrastructure and Grading on Private Property
four components based on construction value:
and City Right-of-Way and Disturbance of City
1) Plan Review
Right-of-Way)
2) Construction Inspection
3) Pavement Mitigation
4) Grading Plan Review
See Public Works Bulletin Al for fee schedule.
Type D (Long-Term)
$100.00 + Technology Fee
Type E (Potential Disturbance of
$100.00 + Technology Fee
Cit y Right-of-Wa y)
Type F (Blanket Permits)
$250.00 processing fee, plus $5,000.00 cash deposit,
withdraw $100.00 per instance for inspection
Franchise — Telecommunications
$5,000.00 administrative fee
Franchise — Cable
$5,000.00 plus 5% of total revenue
Street Vacation
$1,200.00
Latecomer's Agreements
$500.00 processing fee, plus 17% administrative fee,
plus $500.00 segregation fee
Flood Zone Control Permit
$50.00 + Technology Fee
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs Page 2 of 13
El
Section 4. Land use permit and processing fees will be charged according to the
following schedule:
LAND USE FEE SCHEDULE
All peer review fees will be passed through to the applicant per TIVIC Section 18.50.200.
Plus
2015 2016 2017 2018 Hearing Plus
Decision Type Fees Fees Fee Fee Examiner Technology
Fees Fee (TF)
Type 1, 2 and 4 Decisions
$5-94 $602
$614
$626
+ TF
SEPA MDNS Appeal
$5-94 UQ
$614
626
+ TF
Appeal of Sign Code Decision
$9194 $602
$ql 4
IQ26
+ TF
Impact Fee Appeals:
Fire
$594 $642
$614
1626
+ TF
Pole/Banner Annual Renewal
Parks
$594 $602
$614
j626
+ TF
New Billboard
Transportation
$594 $602
$614
$626
+ TF
Master Sign Program—Admin
Permanent
$24-3 $249
$253
$258
+ TF
Temporary
$406 $449
$40
41
+ TF
Pole/Banner Initial Application
$243 $24-9
$253
$258
+ TF
Special Event
$4-06 $409
$110
$112
+ TF
Pole/Banner Annual Renewal
$53 $54
$55
56
+ TF
New Billboard
$51791 $602
$614
626
+ TF
Master Sign Program—Admin
$2473 $2-�-6
$2,260
R 3_06
+ TF
Master Sign Program—BAR
$3T47-9 $3764-9
$3,620
$3,692
+ TF
W:\Word Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs
Page 3 of 13
Administrative
Public Hearing
Major Modification
Minor Modification
$2,236 $2,281
$4,()()6 $4,086
$1,370 $1,397
$&22- $635
$2,327
$2,373
$4,168
$4,251
I'lus
11-453
$648
2015 2016
2017
2018
Hearing
Plus
Decision Type
Fees Fees
Fee
Fee
Examiner
Technology
(Type 3—TMC Section 18.56.140)
Fees
Fee (TF)
Parking Standard for use not specified
$57-9 $594
$603
$615
TUC Zone, Modifications
+ TF
(TMC 18.28.250 D.4. d.1 and TMC 18.56. 100)
Modification to TUC Corridor Standards
$5-94 $602
$614
$626
Residential Parking Reduction
+ TF
(TMC Section 18.28.130. C)
$626
+HE
+ TF
(TMC Section 18.56.065)
Modification to TUC Open Space Regulations
$5994 $6.0.2
$614
$626
Shared, covenant, Complementary Parking
+ TF
(TMC Section 18.28.250 D.4.d)
$626
+ TF
Reduction (TMC Section 18.56.070)
Transit Reduction to Parking Requirements
$554 $692
$614
$626
Parking Lot Restriping
+ TF
(TMC Section 18.28.260. B. 5. b)
$626
+ TF
(TMC Section 18.56.120)
Administrative
Public Hearing
Major Modification
Minor Modification
$2,236 $2,281
$4,()()6 $4,086
$1,370 $1,397
$&22- $635
$2,327
$2,373
$4,168
$4,251
$1,425
11-453
$648
$661
• TF
• TF
• TF
• TF
Administrative Parking Variance
$5-94 $682
$614
J626
+HE
+ TF
(Type 2—TMC Section 18.56.140)
Parking Variance
$9M
$1,008
$1,028
+HE
+ TF
(Type 3—TMC Section 18.56.140)
Parking Standard for use not specified
$57-9 $594
$603
$615
+ TF
(TMC 18.28.250 D.4. d.1 and TMC 18.56. 100)
Residential Parking Reduction
W4 $602
$614
$626
+HE
+ TF
(TMC Section 18.56.065)
Shared, covenant, Complementary Parking
$6.02
$614
$626
+ TF
Reduction (TMC Section 18.56.070)
Parking Lot Restriping
$51-94 $602
$614
$626
+ TF
(TMC Section 18.56.120)
Variances
$2,825 $2,882
$2,940
$2,998
+HE
+ TF
(TMC Section 18.72)
Environmentally Sensitive Areas Deviation,
$44-95 $1,525
$1,556
$1,587
+ TF
Buffer Reduction (TMC Chapter 18.45)
Reduced fee for LDR homeowners, no
$594 $602
$614
$626
associated short plat
Reasonable Use Exception
$2,991 $3050
$3,111
$3,173
+HE
+ TF
(TMC Section 18.45.180)
Exception from Single Family Design Standard
$584 $602
$614
$626
+ TF
(TMC Section 18.50.050)
Special Permission Cargo Container
$594 $602
$614
$626
+ TF
(TMC Section 18.50.060)
Landscape Perimeter Averaging
$594 $602
$614
$626
+ TF
(TMC Section 18.52.060)
Tree and Landscape Modification Permit and
$445 $447
$109
$111
+ TF
Exceptions (TMC Chapter 18.54)
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs
Page 4 of 13
Plus
2015 2010 2017 2018 Hearing Plus
|
Decision Type | Foo» Fees | F�� | Fee | Examiner | Technology |
| ~ | | | | Foes | Fee 0F |
Boundary Line Adjustment
$1,677 $1,710
$1,744
$1,779
+ TF
(TMC Chapter 17.08)
Lot Consolidation
$62-2 $6,35
$648
$661
+ TF
(TMC Chapter 17.08)
$5-94 $6Q
$614
M26
+ TF
(TMC Chapter 17.12)
$4,986 $5,085
$5,187
$5,290
+ TF
Binding Site Improvement Plan $3,817 $3,893 $3,971 $4,050 +TF
Planned Residential Development:
Administrative (TMC Section 18.46. 110) $2,173 $2-,24-6 $2,260 12_306 + TF
Minor Modification (TMC Section 18.46. 130) $544 $&Q2 $614 Jq26 + TF
Major Modification (TMC Section 18.46.130) $2,425 $2,473 $2,522 $2,573 + TF
Checklist
$1,709 $1,743
$1,778
11_813
+ TF
SEPA Planned Action
$594 $6Q
$614
L626
+ TF
SEPA Addendum
$5-94 $6Q
$614
M26
+ TF
Sensitive Area Master Plan Overlay
(TMC 18.45.160)
$4,986 $5,085
$5,187
$5,290
+ TF
vx:\WnrdPmceso permit fee schedule 2017-2018 9-15-16
Page 5 of 13
Plus
2015 2010 2017 2018 nmunng *vua
|
Decision Type | Fouo Fees | Feu | Fee | Examiner | Technology|
Fees Fee (TF)
Substantial Development Permit: (TMC Chapter 18.44)
Permit Exemption Letter, Shoreline
$3,879
$243 $2-4-9
$253
$258
$4,117
+ TF
+ TF
(TMC Section 18.64.020)
Conditional Use Permit, Shoreline
$a797-9 $3,957
$4,036
$4,117
+HE
+ TF
(TMC 18.44,050)
+ TF
(TMC Chapter 18.66)
Shoreline Tree Permit
$4-07
$109
$111
+ TF
(TMC Chapter 18.44)
$1,008
$1,028
+ HE
+ TF
(TMC Section 18.41.060)
Shoreline Environment Redesignation
$2,991 $3,050
$3,111
$3,173
+ TF
Conditional Use Permit
$3,879
$3,957
$4,036
$4,117
+HE
+ TF
(TMC Section 18.64.020)
Unclassified Use Permit
$4,986
$5,085
$5,187
$5,290
+ TF
(TMC Chapter 18.66)
TSO Special Permission Use
$96-9
$1,008
$1,028
+ HE
+ TF
(TMC Section 18.41.060)
Compreherishie Plan Changes (TMC, Chapter 18. 8'4)
Zoning Code Text Amendment
$4,533
$4,624
$4,716
14_8 1_1
+ TF
Miscellaneous SeNices� and Charges
Development Agreement
$4T9-94
$2,034
$2,075
$2,116
+ TF
Code Interpretation (TMC Section 18.90.010)
$348
$-z55
$362
JqQ9
+ TF
Zoning Verification Letter
$-z&5
$362
1�69
+ TF
Legal Lot Verification
$55-9
$57-0
$581
$593
+ TF
Preapplication Meeting
$495
$4-94
$504
$514
+ TF
Mailing Fee to Generate Labels, per project
$458
$467
$476
$486
Public Notice Mailing Fee per address for each
$1
$1
$1
$1
mailing
vvmword permit fee schedule zn17-2o189-1u1s
Ell
Page 6 of 13
Section 5. Building permit fees will be charged according to the following
schedule:
BUILDING PERMIT FEE SCHEDULE
Total Valuation
Building Permit Fees
$1 to $500
$65.00 $66.30 + Technology Fee
$501 to $2,000
$65.00 $66.30 for the first $500, plus $4.,�G_$:j.39 for each additional
$100, or fraction thereof, to and including $2,000, + Technology Fee
$2,001 to $25,000
$129:59 -
$132.09 for the first $2,000, plus %-19 -60_$19.99 for each
additional $1,000, or fraction thereof, to and including $25,000, +
Technology Fee
$25,001 to $50,000
$600A0-_j612.41 for the first $25,000, plus $4-5-.�_$15.61 for each
additional $1,000, or fraction thereof, to and including $50,000, +
Technology Fee
$50,001 to $100,000
$993-25 -_j1 002.92 for the first $50,000, plus $40-60_110.81 for each
additional $1,000, or fraction thereof, to and including $100,000, +
Technology Fee
$100,001 to $500,000
541.83 for the first $100,000, plus $8:511$8.67 for each
additional $1,000, or fraction thereof, to and including $500,000, +
Technology Fee
$500,001 to $1,000,000
O4.43 for the first $500,000, plus $7-.--00-a7.14 for each
additional $1,000, or fraction thereof, to and including $1,000,000, +
Technology Fee
$1,000,001 to $5,000,000
$8-_443-25-_a8 61 2.12 for the first $1,000,000, plus $4:7-0 $4.79 for each
additional $1,000, or fraction thereof, to and including $5,000,000, +
Technology Fee
$5,000,001 and up
$27-,243725- $27,788.12 for the first $5,000.000, plus $4-59 $4.59 for
each $1,000 or fraction thereof, + Technology Fee
A. Non-Structural Plan Review Fee. A non-structural plan review fee shall be
paid at the time of submitting plans and specifications for review. The non-structural
plan review fee shall be 65% of the calculated permit fee as set forth in the permit fee
schedule. The non-structural plan review fee specified herein is a separate fee from the
permit fee and is in addition to the permit fee.
B. Structural Plan Review Fee. Where a structural plan review is deemed
necessary, a structural plan review fee shall be charged. The structural plan review fee
shall be 35% of the calculated non-structural plan review fee.
10YOF
NAME mm
17,4 • V im.
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs
Page 7 of 13
9
deferral of all or • it • • of a required bufldiRg permit fee for - may ♦-
provided the following Griteria are ••-
a. The property owner must submit a teGhn*Gally GOrnplete building permit
r • r • Glearly - . r • • - . •
11 and pay all required plaR review fees. • + building permit - being • • r + + . •
deferral must be greater than $300,000.
b. Before issuanGe of the building permit, the property owner must submit
triffn-& + r r .r
Mm
\ i • . • r . + gff." RM \ •
• 4 111111 + 0• .- •• .- - - -
•� . •. r- •. - - .� . .- .. ••. . -. •.
. r r •• - • r. •• i u u i r
+ • 0 • - - + a + a • . i - • r .
• • r • • - • - • + • - • - • - . - - •. - •
.+ - -.. . - r • •.+ - • • • •
interest of the City, andloF te PrOteGt the publiG welfare,
3. The budding permit fee may be deferred up to 24 months after issuanGe-ef
the building permit and must be paid before the City will issue a GertifiGate • •
for • - building.
I interest shall • +• • • deferred . permit fee. The interest
rate shall be the same as the stated interest r • the Two Year +- Treasury
• r • r building • - i . date . + . r intere-St shall
be-
GOMpounded aRRually and shall begin i a i . 'suanGe ef - building permit.
WAWord Processing\Resolutions\Consolidated permit fee schedule 1 1
NG:bjs Page i of
10
5. The building permit
+a, fra -sic -&acia�nMa,
fee deferral
A ;+k
agreemeRt be
-a firn
may GeRSOlid—ated
&r -&nrL- ivawnn+ fn,=c -no zai+1iW!,n,&i-&, %I
. . .........
111111
1W
ROURVERM MOZAPM12wit MONSO
Fee
$250 or less
Section 6. Mechanical permit fees will be charged according to the following
schedule:
MECHANICAL PERMIT FEE SCHEDULE
Valuation of
• ON F7.9rTS110W.1112
"I"MON." mv
Mechanical Permit Fee
Contract Amount)
111111
51
Fee
$250 or less
+ Technology Fee
$251 to $500
$65-.00-_1§6.30 for first $250, plus $7-.83 $7.99 for each $100 or fraction
ME
$501 to $1,000
%84:6 $86..�29 for the first $500, plus $9.70_1q 8.7 for each $100 or
fraction thereof, to and including $1,000, + Technology Fee
Section 6. Mechanical permit fees will be charged according to the following
schedule:
MECHANICAL PERMIT FEE SCHEDULE
Valuation of
Work (Total
Mechanical Permit Fee
Contract Amount)
$32—K-_113.15 for issuance of each permit (base fee) + Technology
Fee
$250 or less
+ Technology Fee
$251 to $500
$65-.00-_1§6.30 for first $250, plus $7-.83 $7.99 for each $100 or fraction
thereof, to and including $500, + Technology Fee
$501 to $1,000
%84:6 $86..�29 for the first $500, plus $9.70_1q 8.7 for each $100 or
fraction thereof, to and including $1,000, + Technology Fee
$1,001 to $5,000
$424 19_$13Q.66 for the first $1,000, plus $-9-65_59.84 for each $1,000
or fraction thereof, to and including $5,000, + Technology Fee
$5,001 to $50,000
$466-.7G-_$j70.03 for the first $5,000, plus $10..-05 $10.25 for each
$1,000 or fraction thereof, to and including $50,000, + Technology Fee
$50,001 to $250,000
$63s3 20 651.98 for the first $50,000, plus $8-40_$8.57 for each
$1,000 or fraction thereof, to and including $250,000, + Technology
Fee
$250,001 to $1,000,000
$2,3-- 2-0 for the first $250,000, plus "__$L55 for each
$1,000 or fraction thereof, to and including $1,000,000, + Technology
Fee
$1,000,001 and up
$74_ 6s3 2-0 _J8,026.58 for the first $1,000,000, plus $6_70_16_.83 for each
$1,000 or fraction thereof, + Technology Fee
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs Page 9 of 13
11
Section 7. Plumbing permit fees will be charged according to the following
schedule:
PLUMBING PERMIT FEE SCHEDULE
Permit Issuance—Issuance of each permit (base fee)
-.50--a33.15 + Technology Fee
Unit Fee Schedule (in addition to base fee above:
For one plumbing fixture (a fixture is a sink, toilet, bathtub, etc.)
W700-_$66.30 + Technology Fee
For each additional fixture
$44-.00-_$14.28 + Technology Fee
For each building sewer and each trailer park sewer
$221-80-_125.30 + Technology Fee
Rain water system - per drain (inside building)
$44-.�08_114.28 + Technology Fee
For each water heater and/or vent
$44-.00--j14.28 + Technology Fee
For each industrial waste pretreatment interceptor, including its
$2970-0-_$28.56 + Technology Fee
trap and vent, except for kitchen type grease interceptors
For each grease interceptor for commercial kitchens
$2-9:10 $29.68 +Technology Fee
For each repair or alteration of water piping and/or water treating
+ Technology Fee
equipment, each occurrence
For each repair or alteration of drainage or vent piping, each
$14.00-_$14.28 + Technology Fee
fixture
For each medical gas piping system serving one to five
$92-40-_$�a3.64 + Technology Fee
inlets/outlets for a specific gas
For each additional medical gas inlets/outlets
$4-6._116.52 + Technology Fee
For each lawn sprinkler system on any one (1) meter including
$249-..�_$29.68 + Technology Fee
backflow protection devices therefor.
For atmospheric-type vacuum breakers not included in lawn
sprinkler backflow protection:
1 to 5 ........$14.00 + Technology Fee
Over 5.......$14.00 for first 5 plus $3.25 for each additional
+ Technology Fee
For each backflow protective device other than atmospheric type
vacuum breakers:
2-inch diameter and smaller....... $29.10 + Technology Fee
Over 2-inch diameter: ....... ........ $32.25 + Technology Fee
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs Page 10 of 13
12
Section 8. Fuel Gas Piping permit fees will be charged according to the following
schedule:
FUEL GAS PIPING PERMIT FEE SCHEDULE
Permit Issuance
For issuing each permit (base fee): ($0 if permit is in conjunction with
a plumbing permit for an appliance with both plumbing and gas
connection.)
$32.50 $33.15 + Technology Fee
Unit Fee Schedule O"dd4ion4o4ten44n-svbparagraph-7-. 1)
For each gas piping system of one to five outlets
+ Technology Fee
For each additional gas piping system outlet, per outlet
$14.0)-_$14.28 + Technology Fee
Section 9. Electrical permit fees will be charged according to the following
schedule:
ELECTRICAL PERMIT FEE SCHEDULE
1. NEW SINGLE-FAMILY DWELLINGS
New single-family dwellings (including a garage)
$1,55-0-8-5, _$155.91 +Technology Fee
Garages, pools, spas and outbuildings
$91:9-0-_$8_3.54 + Technology Fee
Low voltage systems
$59-65-_J61.05 + Technology Fee
2. SINGLE-FAMILY REMODEL AND SERVICE CHANGES
Service change or alteration—no added/altered circuits
$84-.9-0-_J83.54 + Technology Fee
Service change $8 -1.90- $83.54 with added/altered circuits, plus
$�-.94- $83.54 + Technology Fee
$11.55 _$�00 for each added circuit (maximum permit fee
$4&285 $156.00 )
Circuits added/altered without service change (includes up to
$54,60.._K5.69 + Technology Fee
5 circuits)
Circuits $5460-$55.69 added/altered without service change
$54�0-_$55.69+ Technology Fee
(more than 5 circuits); $7.65 for each added circuit (maximum
permit fee $9&770 $1010.00 + Technology Fee�
Meter/mast repair
$66 .25-_J69.62 + Technology Fee
Low voltage systems
$53-9.Z5 -_$61.05 + Technology Fee
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs Page 11 of 13
13
3. MULTI-FAMILY AND COMMERCIAL (including low voltage)
Valuation of
$65&-.O�_$�6.30 + Technology Fee
Work (Total
Permit Fee
Contract Amount)
$8&-.25- $87.98 + Technology Fee
$250 or less
$65,-G0-_jq6.30 + Technology Fee
• Base fee
thereof, to and including $1,000, + Technology Fee
• Each concession fee
$4-G-W-_jj 1.02 + Technology Fee
• Each ride and generator truck
fraction thereof, to and including $5,000, + Technology Fee
Inspections or plan review not specified elsewhere (one-half hour
$66_5G�1§7 83/hour
minimum). Safety_inspe��Visions.
fraction thereof, to and including $50,000, + Technology Fee
Adult family home inspection (paid at the time of scheduling the
$66.5 )_$§7.83
inspec
fraction thereof, to and including $250,000, + Technology Fee
Disaster recovery emergency repair permit (residential structures
$20.00
or fraction thereof, to and including $1,000,000, + Technology Fee
Over $1,000,000
$10,ZIA47G-_��49�.51 plus 0.5% of cost over $1,000,000, + Technology Fee
4. MISCELLANEOUS ELECTRICAL PERMIT FEES
Temporary service (residential)
$65&-.O�_$�6.30 + Technology Fee
Temporary service/generators
$80-.90- $82.52 + Technology Fee
Manufactured/mobile home parks and RV park sites, each service
$8&-.25- $87.98 + Technology Fee
and feeder
• Base fee
+ Technology-Fee
• Each concession fee
$4-G-W-_jj 1.02 + Technology Fee
• Each ride and generator truck
$4-0� $11.02 + Technology Fee
Inspections or plan review not specified elsewhere (one-half hour
$66_5G�1§7 83/hour
minimum). Safety_inspe��Visions.
Adult family home inspection (paid at the time of scheduling the
$66.5 )_$§7.83
inspec
Disaster recovery emergency repair permit (residential structures
$20.00
vvmvom permit fee schedule 2017-2018 9-15-16
NG:bjs Page 12 of 13
Section 10. Other inspections and fees will be charged according to the following
schedule:
OTHER INSPECTIONS AND FEES
Inspections outside of normal business hours (three hour minimum charge)
$100. 0Q_$102.00/hour
Re-inspection fee
$67.83 hour
Inspection for which no fee is specifically indicated—investigations or safety
$66-50 $67.83/hour
inspections
Additional plan review required by changes, additions, or revisions to approved
$66-50 $67.83/hour
plans (minimum charge one-half hour)
Work commencing before permit issuance shall be subject to an investigation fee
100% of the permit fee
equal to 100% of the permit fee.
Plan review fee—Mechanical, Plumbing, Fuel Gas Piping and Electrical: The fee
for review shall be 25% of the total calculated permit fee. The plan review fee is a
separate fee from the permit fee and is required when plans are required in order
to document compliance with the code.
Work covered without inspection or work not ready at the time of inspection may
be charged a re-inspection fee of $66.50.
Expired permit final — includes two inspections
$133.00
Expired permit final — each additional inspection
$66-.68 _$67.83
Minor residential remodel plan review and permit (projects up to $20,000)
$20.00
Section 11. Credit Card Surcharge. If payment is made by credit card, a
processing fee of 3% will be added to the total order.
Section 12. Effective Date. This resolution and the fee schedules contained
herein shall be effective as of January 1, 2017.
PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at
a Regular Meeting thereof this day of 7 2016.
ATTEST /AUTHENTICATED:
Christy O'Flaherty, MMC, City Clerk
APPROVED AS TO FORM BY:
Rachel B. Turpin, City Attorney
Joe Duffie, Council President
Filed with the City Clerk:
Passed by the City Council:
Resolution Number:
WAWord Processing\Resolutions\Consolidated permit fee schedule 2017-2018 9-15-16
NG:bjs
Page 13 of 13
15