HomeMy WebLinkAboutPS 2017-02-06 Item 2D - Public Safety Plan - Format of Monthly ReportCity of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Public Safety Committee
FROM: Rachel Bianchi, Communications & Government Relations Manager
CC: Mayor Ekberg
DATE: January 31, 2017
SUBJECT: Format for Public Safety Plan Monthly Reporting to Council
ISSUE
Implementation of the Public Safety Plan is a complex project involving many planning stages,
processes, and Council actions. Staff strives to communicate frequently with the City Council
regarding the status and activities associated with the Plan.
Staff proposes a monthly written report to the City Council including information on status,
upcoming activities, and a projected annual schedule. This report will then be included in the
agenda packet of the first Regular Meeting every month.
As projects begin to take further shape, this document will ultimately morph into building-specific
updates with additional information on schedule, budget, and other updates and milestones
specific to each discrete project.
RECOMMENDATION
The Committee is asked to review and provide feedback on the draft report to ensure that it is a
successful communication tool that meets the Council's needs. The Committee of the Whole
will then be asked to review the proposal at the February 13, 2017 meeting.
ATTACHMENT
Draft monthly report to Council on the Public Safety Plan
21
22
TUKWILA PUBLIC SAFETY PLAN
Monthly Update
January, 2017
Overall Plan
Outreach
• Enviro|ssues,3hie\s[}b|etz Johnsen /SCU\and the Communications Division are finalizing
the detailed outreach plan to present tothe City Council On February 13.
• Envirolssues and the Communications Division met with Global2Local and Forterra to
develop the specific outreach program around the PSP with the CVnornunhy
Connectors.
• First Open H0V58 scheduled for March 18, 10:00 to 12:00 at Fire Station 54.
w
Recruitment period extended through February 28tOachieve a larger pool of
applicants.
Siting Advisory Committee
�
initial framework discussion with Council on January 23. Staff tasked tOgU back and
develop more detailed framework for Council review by the Public Safety Committee
February 6 and, assuming Committee concurrence, COW on February I3.
Near-term Council Decisions and Key Dates
0 February 6 — Council to be introduced to FACETS and the work they are doing on fire
station analysis — at both Public Safety Committee and full Council.
• February I3— Council presentation on the outreach plan
• February 21 —She selection and discussion of draft siting criteria begins at Public Safety
Committee; potential concurrence on draft criteria at February 27 COW
• March 6 — Council review of architect/engineering contract begins at Public Safety
Committee; potential COW on March 27 and contract approval at April 3 full Council.
Fire Stations
Siting
w Station 5l site selected; FACETS studying data to determine general areas for siting Of
52 and 54 that preserve response times and programming (size of stations).
Architecture and Programming
0 Statement of Qualifications for Architect and Engineering (A/E) services received,
interviews tO occur in February with Council action iD March and April.
Internal teams meeting to discuss programming needs and wants to be prepared when
A/E folks come on board.
Design and Permitting
• Phases scheduled to begin for 51 in May, 2017.
• Phases scheduled to begin for 52 and 54 in December, 2017.
Bidding and Construction
• Phases scheduled to begin for 51 in April, 2018.
• Phases scheduled to begin for 52 and 54 in April, 2018.
Justice Center
Siting
• Draft siting criteria in process; to be presented to Council in February, vetted through
community in March and finalized in April.
Architecture and Programming
• Phases scheduled to begin in July, 2017.
Design and Permitting
• Phases scheduled to begin in November, 2017.
Bidding and Construction
• Phases scheduled to begin in October, 2018.
Public Works Facility
Siting
Architecture and Programming
• Phases scheduled to begin in February, 2018.
Design and Permitting
• Phases scheduled to begin in June, 2018.
Bidding and Construction
• Phases scheduled to begin in September, 2019.
24
Council Action Target Next Steps — Next 12 Months
January
0 Siting Advisory Committee (January 23 COW)
February
• FACETS (fire analysis study) introduction and overview (February 6, Public Safety
Committee &Full Council)
• Monthly reporting format (February 6 Public Safety, February 13\
• Siting Advisory Committee (February 6 Public Safety Committee, February 13 COW)
• Outreach plan overview (February 13COW)
• Site Selection Process and Initial Draft OfJustice Center Siting Criteria (February 21
Public Safety Committee, February 27COW)
March
• Open House (March 18, lO:OO— 12:00 03 Fire Station 54)
• Fire Stations: Architect Selection and [Ont[8Ct (Public Safety Committee March 5, [OVV
March Z7, Final passage April 3).
• Financial Oversight Committee Appointments (March 21 Finance Committee, March 27
COW)
• Disadvantaged Business Enterprise (DBE)discussion and consensus Vndirection
April
• Siting Advisory Committee Appointments
• Finalize Justice Center siting criteria
May
• Fire Stations: GC/CM CPAR8—FS General Contractor — two rntg5 for this topic
o l) approval to pursue GC/CM process,
o 2) approval Of selected contractor and contract amount
• FACETS work complete and presented tVCouncil
June
0 Open House
July
• Justice Center: Architect Selection
• Advisory Committee Report (at minimum)
August
September
October
0 Justice Center: GC/CM CPARB—FS General Contractor — two [ntgs for this topic
o I) approval tV pursue GC/CM process,
* 2) approval of selected contractor and contract amount
• Open House
• Justice Center: Final site selection
November
9 Fire Stations 52 and 54 final sites selection
December
0 Advisory Committee Report (at minimum)