ITEM INFORMATION
CAS NUMBER: STAFF SPONSOR: BOB GIBERSON ORIGINAL AGENDA DATE: 02/06/17
AGENDA ITEM TITLE CBD Sanitary Sewer Rehabilitation - 2015
Contract Completion and Acceptance
CATEGORY ❑ Discussion N Motion ❑ Resolution ❑ Ordinance ❑ Bid Award ❑Public Hearing ❑ Other
Mtg Date Mtg Date 02106117 Mtg Date Mtg Date Mtg Date Mtg Date Mtg Date
SPONSOR ❑ Council ❑Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police N PW
SPONSOR'S The contract with Michels Corporation of Salem, WA is complete for the Commercial
SUMMARY Business District(CBD) Sanitary Sewer Rehabilitation Project - 2015. This contract relined
6,510 lineal feet of sanitary sewer pipe. One change order was issued for$26,244.60 and
unit price under-runs totaled a credit of($43,736.50). Council is being asked to accept and
finalize the contract with Michels Corporation in the amount of$509,310.89.
REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte N Transportation Cmte
❑ Utilities Cmte ❑Arts Comm. ❑Parks Comm. ❑Planning Comm.
DATE: 01/24/17 COMMITTEE CHAIR: KATE KRULLER
RECOMMENDATIONS:
SPONSOR/ADMIN. Public Works
COMMI1-rEE Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$509,310.89 $634,157.42 $0.00
Fund Source: 402 SEWER(PG 81, 2017 CIP)
Comments:
MTG. DATE RECORD OF COUNCIL ACTION
02/13/17
MTG. DATE ATTACHMENTS
02 13/17__ Informational Memorandum dated 01/20/17
State of WA Depart of Revenue Notice of Completion 15-178
Minutes from the Transportation &Infrastructure Committee meeting of 01/24/17
331
332
City of Tukwila Allan Ekberg,Mayor
`"' • Public Works Department-Bob Giberson,Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Bob Giberson, Public Works Director ,
BY: Peter Lau, Senior Program Manager
CC: Mayor Ekberg
DATE: January 20, 2017
SUBJECT: 2015 Commercial Business District Sanitary Sewer Rehabilitation
Project No. 91140203, Contract No. 15-178
Project Completion and Acceptance
ISSUE
Accept construction contract as complete and authorize release of retainage.
BACKGROUND
The Notice to Proceed for Contract Number 15-178 with Michels Corporation of Salem, Oregon was
issued on December 7, 2015. This construction project installed approximately 6,510 lineal feet of
cured-in-place pipe (CIPP) within the right-of-way of Andover Park East, Industry Drive, Minkler
Boulevard and private easements in order to rehabilitate existing sewer pipes.
DISCUSSION
The CBD Sanitary Sewer Rehabilitation Project was physically completed on June 9, 2016. The
extended time for closeout is due to the emergency repair needed for collapsed sewer main found while
preparing to execute this slip-lining contract.
FINANCIAL IMPACT
The construction budget for the is CBD Sanitary Sewer Rehabilitation Project was $634,157.42. Only one
change order was executed in an amount of $26,244.60. Unit price under-runs were mainly due to finding
that some sections of the sewer pipe were collapsed after contract award and before construction began. A
portion of the 12-inch CIPP quantity was not installed in those collapsed sewer pipes and were repaired
under a separate contract. Retainage is being held by the City in the amount of $23,256.21.
Expenses
Construction Contract Amount (pre-tax) $482,616.00
Change Order No. 1 26,244.60
Unit Price Under-runs (43,736.50)
WA State Sales Tax 44,186.79
Total Contract Amount $509,310-89
RECOMMENDATION
Council is being asked to formally accept the 2015 Central Business District Sanitary Sewer
Rehabilitation contract with Michels Corporation in the amount of$509,310.89 as complete, and
authorize the release of retainage subject to standard claim and lien release procedures, and to
consider this item on the Consent Agenda at the February 6, 2017 Regular Council Meeting.
Attachment:Notice of Completion,Contract#15-178
WAPW Eng\PROJECTS\A-SW Projects\CBD Sewer Rehabilitation(91140203)\2015 CBD SewerlConstmction\#.700-Post Construction&Closeout\Info Memo 2015 Sewer Rehab Close 012017 gl.docx
333
334
S�"ATe
-.f M Original
^ � ❑ Revised#
Oy
�yd 7889�
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Date: January 17, 2017 Contractor's UBI Number: 601061071
Name&.Mailing:Address of Piililic.Agency. '. Department�Use,Only _
City of u I a Assigned to:
6200 Southcenter Boulevard
Tukwila, WA 98188 Date Assigned:
UBI Number: 179000208
Notice is hereby given relative to the completion of contract or project described below
Project Name Contract Number Job Order Contracting
2015 CBD Sanitary Sewer Rehabilitation Project 91140203 115-178 ❑ Yes V No
Description of Work Done/Include Jobsite Address(es)
Installation of approximately 6,510 lineal feet of cured-in-place pipe within the right-of:-way of Andover
Park East, Industry Drive, Minkler Boulevard and private easements to rehabilitate existing sewer pipes.
Federally funded transportation project? ❑ Yes S6 No (if yes,provide Contract Bond Statement below)
Contractor's Name E-mail Address Affidavit ID*
Michels Corporation ictaverni@michels.us 1656933
Contractor Address Telephone#
1715 16th Street SE, Salem, OR 97302 1503-364-1199
If Retainage is not withheld,please select one of the following and List Surety's Name&Bond Number. -
El Retainage Bond ❑ Contract/Payment bond(valid for federally funded transportation projects)
Name: jBond Number:
Date Contract Awarded Date Work Commenced Date Work Completed Date Work Accepted
November 2, 2015 December 7, 2015 June 9, 2016
Weire Sulicontracters used.on.this project?1f so;please:4 omplete Addendum=A_ Yes �Nd
Affidavit ID*-No L&I release will be-granted until all affidavits are listed.
Contract Amount $ 482,616.00
Additions (+) $ 26,244.60 Liquidated Damages $ 0.00
Reductions ( -) $ 43,736.50 Amount Disbursed $ 486,054.68
Sub-Total $ 465,124.10 Amount Retained $ 23,256.21
Amount of Sales Tax 9.5
(If various rates apply,please send a breakdown) $ 44186.79
TOTAL $ 509,310.89 TOTAL $ 509,310.89
NOTE: These two totals must beequal
Comments:
Note:The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form:Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber Title: Fiscal Specialist
Email Address: diane.jaber @tukwilawa.gov Phone Number: (206)433-1871 x 1871
Department of Revenue Washington State Dgwvnem of �Ass Employment Security
Public Works Section Labor &Industries Department
(360)704-5650 Contract Release Registration,Inquiry,
PWC @dor.wa.gov (855)545-8163,option#4 Standards&Coordination
ContractRelease @LNI.WA.GOV Unit
(360)902-9450
publicworks @esd.wa.gov
REV 31 0020e(4/28/14) F215-038-000 04-2014
335
Addendum A: Please List all Subcontractors and Sub-tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name: UBI Number: (Required) Affidavid ID*
Traffic Control Solutions, LLC 603536630 681886
For tax assistance or to request this document in an alternate format,please call 1-800-647-7706.Teletype(TTY) users may use the
Washington Relay Service by calling 711.
0020e Addendum(04/28/14) F215-038-000 04-2014
Transportation Committee Minutes.....................................................................................................................January24,2017
C. Contract Amendment:53rd Avenue South (South 137th Street through South 144th Street)
Staff is seeking Council approval of Supplement 2 to Contract 15-159 with KPG, Inc. in the
amount of$79,858.20 for real estate acquisition services for the 53rd Avenue South Project. The
design is now at 60% and 19 locations were identified where minor additional right-of-way or
easements are required. The total budget for right-of-way acquisitions is$98,000. UNANIMOUS
APPROVAL. FORWARD TO FEBRUARY 6,2017 REGULAR CONSENT AGENDA.
D. Project Update on South 160th Street Speed Cushion Pilot Project
Staff updated the committee on a plan to pilot the installation of speed cushions on South 160tH
Street from 42nd Avenue South to 51St Avenue South. Speed Yec&st ions�re humps or tables that
include wheel cutouts for emergency vehicles. Speed dat be collected both before and
after installation to assess the impact of the pilot project.�T iof�the cus hions and signs is
$33,197.40 which will come from the $75,000 Traffic Calming budget.�Staff plans to conduct
outreach with impacted residents to notify thefn of the pilot an�cNequest feedback.
Councilmember Quinn noted that traffic calmingAs requested by residents`.ibt wide and asked
that there be strong,defensible rationale for tki`e locations of pilot projects such as this. Staff is
purchasing two more mobile radar speed units as j needs around 'he city. Chair
Kruller also noted that there are speed issues around tlheZity,-particularly near schools, and is
interested in piloting the cushions in�other areas as soon as practical. DISCUSSION ONLY.
E. Purchase of Water Hydrant Saver
Staff is seeking Committee approval of a Stan ey Hy rant\\Sa-ve-r-- the amount of $6,022.50,
funded from the Water division's small tools�an��nor-quipme`nt budget. This is a hydraulic
impact wrench that will make fire�hydrant`alve seat removal.more cost effective and safer for
the operator. COMITTEE UNANIMOUS APPROVAL.
F Contract Closeout-.2015 Centra)Busin.ess District Sanita Sewer Rehabilitation
F.
Staff is seeking Coun it approval-of-contr�act�completion and release of retainage to the Michels
Corpoor, ion in the-amount off$509,310.89 for tKe 2015 Commercial Business District Sanitary
Sewer Rehabilitation Rrolec This project installed approximately 6,510 lineal feet ofcured-in-
pa c'iner within the right-of-waa�j,of Andover Park East, Industry Drive, Minkler Boulevard and
private easements. UNANIMOUS�PROVAL. FORWARD TO FEBRUARY 6, 2017 REGULAR
CON�SEN AGENDA.
G. Contract Close ut: C st l S rings Emergency Surface Water Repair
Staff is seeking Cooun�approval of contract completion and release of retainage to the Frank
Coluccio Const�c�tio/n/Company in the amount of $164,093.54 for the Crystal Springs
Emergency Surface Water Repair Construction Project. This project constructed emergency
repair of a collapsed surface water pipe, pavement and sinkhole in Crystals Springs Park and
51s' Avenue South. UNANIMOUS APPROVAL. FORWARD TO FEBRUARY 6, 2017 REGULAR
CONSENT AGENDA.