HomeMy WebLinkAboutTIC 2017-06-13 Item 2C - Bid Award - McCann Construction Enterprises for 2017 Annual Small Drainage ProgramCity of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Comm'
FROM: Bob Giberson, Public Works Director
BY: Ryan Larson, Senior Program Manager
CC: Mayor Ekberg
DATE: June 9, 2017
SUBJECT: 2017 Annual Small Drainage Program
Project No. 91741201
Bid Award
ISSUE
Award a contract to McCann Construction Enterprises, Inc. for construction of the 2017 Annual Small Drainage Program.
BACKGROUND
The Small Drainage Program constructs drainage projects throughout the City that are too large for City staff to complete, but are
smaller than a typical capital improvement project. The projects originate from citizen complaints and maintenance staff
recommendations and are compiled on the Small Drainage Project List. Each year the projects are prioritized based on need,
expense, permitting requirements, and length of time on the list. The highest priority projects are then designed and constructed.
The 2017 Annual Small Drainage Program was advertised to provide drainage improvements at up to four locations. One project
includes a water quality treatment device.
1) 48th Ave S between S 160nd and S 162th St 2) Strander Blvd Sidewalk (in front of Target)
3) 58th Ave S, 14423 to 14455 4)4-1-50th
(Schedule B - Additive Alternate Project)
DISCUSSION
The 2017 Annual Small Drainage Program was advertised for bids on May 18 and May 25, 2017. Two bids were received and
opened on June 6, 2017. The bids were checked, tabulated, and no errors were found. McCann Construction is the apparent low
bidder with an overall bid of $508,988.75. The engineer's estimate was $527,030.00. McCann Construction successfully completed
the Duwamish Gardens construction project. Since the overall bid is above available funding, it is recommended that the additive
alternate project be eliminated and construction of the first three projects that make up Bid Schedule A be awarded in the amount
of $451,823.75.
BUDGET AND BID SUMMARY (All amounts include sales tax)
Bid Results Estimate 2017 Budget
Bid Amount (Schedule A only) $ 451,823.75 $ 464,555.00 $ 290,000.00
Contingency (10 %) 45,182.38 46,455.50
Water Quality Retrofit (pg. 83) 110,000.00
Excess SDP Design Funds 41,000.00
Excess Gilliam Creek Culvert Funds 56,006.13
Total $ 497,006.13 $ 511,010.50 $ 497,006.13
RECOMMENDATION
Council is being asked to award Schedule A of the construction contract for the 2017 Annual Small Drainage Program to McCann
Construction Enterprises in the amount of $451,823.750 and consider this item on the Consent Agenda at the June 19, 2017
Regular Meeting.
Attachments: CIP Pages 96 & 97
Project Location Map
Bid Tabulation
1PWStare\PW Common$WW Eng1PROJECTS\A- DR Projects\Annual Small Drainage Programs■2017 SDP (91741201)1Design InfoMemo Bid Award 2017 koc
31
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Annual Small Drainage Program Project No. 9XX41201
DESCRIPTION: Select, design, and construct small drainage projects throughout the City.
JUSTIFICATION: Provide drainage corrections for existing /ongoing drainage problems throughout the City, including culvert
replacements, drain extensions, and pavement upgrades.
STATUS: Projects for this annual program are taken from Small Drainage Project List.
MAINT. IMPACT: Reduces maintenance.
COMMENT: Ongoing project, only one year shown in first column. Construction expenses may occur over two calendar
years.
FINANCIAL Through Estimated
(in $000's)
2015 2016 2017
2018
2019
2020
2021
2022
BEYOND TOTAL
EXPENSES
Design
74
80
80
80
80
80
80
80
80
714
Streamgages /Monitor
10
10
35
35
36
36
36
36
40
274
Const. Mgmt.
62
80
80
80
80
80
80
80
80
702
Construction
255
515
515
515
514
514
514
513
513
4,368
TOTAL EXPENSES
401
685
710
710
710
710
710
709
713
6,058
FUND SOURCES
Awarded Grant
0
Proposed Grant
0
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
401
685
710
710
710
710
710
709
713
6,058
TOTAL SOURCES
401
685
710
710
710
710
710
709
713
6,058
2017 - 2022 Capital Improvement Program
96
32
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Storm Water Quality Retrofit Program Project No. 91241202
DESCRIPTION: Design and install water quality improvements at selected drainage locations throughout the City.
JUSTIFICATION: Most surface water is discharged directly to receiving water bodies untreated.
STATUS: Additional water quality is being added to Interurban Ave S in 2015 and 53rd Ave S in 2017.
MAINT. IMPACT: Expected to increase maintenance.
COMMENT: Combine with other CIP projects for design and construction, where feasible.
FINANCIAL Through Estimated
(in $000's)
2015 2016 2017
2018
2019
2020
2021
2022
BEYOND TOTAL
EXPENSES
Design
9
15
15
15
15
15
15
15
15
129
Land (R /W)
0
Const. Mgmt.
15
15
15
15
15
15
15
15
120
Construction
80
80
80
80
80
80
80
80
640
TOTAL EXPENSES
9
110
110
110
110
110
110
110
110
889
FUND SOURCES
Awarded Grant
0
Proposed Grant
0
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
9
110
110
110
110
110
110
110
110
889
TOTAL SOURCES
9
110
110
110
110
110
110
110
110
889
Project Location:
Entire System
GIS
2017 - 2022 Capital Improvement Program
97
33
Q �'
2017 Annual Neighborhood
Drainage Program
48th Ave S
Date: June 7, 2017 By: R. Linsao
W: \PW Eng \GIS \Projects \RyanL \CIP Storm Drainage \2017 drainage program.mxd
s
Not to Scale
58th Ave S
Strander Blvd
cis
Tuk`r,,ila
CITY OF TUKWILA - DEPARTMENT OF PUBLIC WORKS
2017 Small Drainage Program
BID TABS
06/6/17
Total
Engineer's Estimate
McCann
R.W. Scott Construction
No.
Section on
Item
Quantity
Unit
Unit Cost
Total Cost
Unit Cost
Total Cost
Unit Cost
Total Cost
ROADWAY (SCHEDULE A)
1
1 -04
Unexpected Site Changes
1
FA
$8,000.00
$ 8,000
$8,000.00
$ 8,000
$8,000.00
$ 8,000
2
1 -09
Mobilization
1
LS
$42,000.00
$ 42,000
$45,000.00
$ 45,000
$65,000.00
$ 65,000
3
1 -10
Project Temporary Traffic Control
1
LS
$32,000.00
$ 32,000
$21,000.00
$ 21,000
$60,000.00
$ 60,000
4
2 -01
Clearing and Grabbing
1
LS
$18,000.00
$ 18,000
$6,500.00
$ 6,500
$40,000.00
$ 40,000
5
2 -02
Pavement Removal Incl. Haul
420
SY
$25.00
$ 10,500
$25.00
$ 10,500
$24.00
$ 10,080
6
2 -03
Unsuitable Foundation Excavation Incl. Haul
40
CY
$35.00
$ 1,400
$35.00
$ 1,400
$100.00
$ 4,000
7
2 -03
Gravel Borrow Incl. Haul
110
TN
$35.00
$ 3,850
$25.00
$ 2,750
$46.00
$ 5,060
8
4 -04
Crushed Surfacing Top Course
320
TN
$45.00
$ 14,400
$45.00
$ 14,400
$60.00
$ 19,200
9
5 -04
HMA Cl. 1/2" PG 64 -22
180
TN
$175.00
$ 31,500
$185.00
$ 33,300
$225.00
$ 40,500
10
5 -04
HMA Thickened Edge
530
LF
$10.00
$ 5,300
$5.50
$ 2,915
$10.00
$ 5,300
11
8 -01
Temporary Water Pollution / Erosion Control
1
LS
$10,000.00
$ 10,000
$3,500.00
$ 3,500
$4,000.00
$ 4,000
12
8 -04
Cement Conc. Traffic Curb and Gutter
20
LF
$60.00
$ 1,200
$65.00
$ 1,300
$110.00
$ 2,200
13
8 -14
Cement Conc. Sidewalk
200
SY
$75.00
$ 15,000
$105.00
$ 21,000
$84.00
$ 16,800
ROADSIDE DEVELOPMENT (SCHEDULE A)
14
8 -02
Topsoil Type A
70
CY
$50.00
$ 3,500
$60.00
$ 4,200
$180.00
$ 12,600
15
8 -02
Hydroseed
540
SY
$4.00
$ 2,160
$5.00
$ 2,700
$5.00
$ 2,700
16
8 -02
Property Restoration
1
FA
$10,000.00
$ 10,000
$10,000.00
$ 10,000
$10,000.00
$ 10,000
STORM DRAINAGE (SCHEDULE A)
17
7 -04
Storm Sewer Pipe 12 In. Diam
546
LF
$75.00
$ 40,950
$85.00
$ 46,410
$100.00
$ 54,600
18
7 -04
Storm Sewer Pipe 8 In. Diam
312
LF
$70.00
$ 21,840
$60.00
$ 18,720
$85.00
$ 26,520
19
7 -04
Storm Sewer Pipe 6 In. Diam
68
LF
$50.00
$ 3,400
$60.00
$ 4,080
$100.00
$ 6,800
20
7 -04
Storm Sewer Pipe 4 In. Diam
65
LF
$50.00
$ 3,250
$60.00
$ 3,900
$90.00
$ 5,850
21
7 -04
Ductile Iron Storm Sewer Pipe 12 In. Diam.
146
LF
$120.00
$ 17,520
$130.00
$ 18,980
$120.00
$ 17,520
22
7 -04
Ductile Iron Storm Sewer Pipe 8 In. Diam.
155
LF
$100.00
$ 15,500
$85.00
$ 13,175
$110.00
$ 17,050
23
7 -04
Remove /Abandon Existing Storm Sewer Pipe
365
LF
$20.00
$ 7,300
$15.00
$ 5,475
$100.00
$ 36,500
24
7 -04
Remove /Abandon Existing Storm Sewer Structure
6
EA
$1,000.00
$ 6,000
$750.00
$ 4,500
$800.00
$ 4,800
25
7 -05
Connection to Drainage Structure
7
EA
$1,000.00
$ 7,000
$1,750.00
$ 12,250
$1,000.00
$ 7,000
26
7 -05
Connection to Drainage Pipe
3
EA
$500.00
$ 1,500
$1,200.00
$ 3,600
$750.00
$ 2,250
27
7 -05
Storm Cleanout
2
EA
$500.00
$ 1,000
$950.00
$ 1,900
$500.00
$ 1,000
28
7 -05
Concrete Inlet
8
EA
$1,500.00
$ 12,000
$1,450.00
$ 11,600
$1,500.00
$ 12,000
29
7 -05
Catch Basin, Type 1
11
EA
$2,000.00
$ 22,000
$1,650.00
$ 18,150
$1,750.00
$ 19,250
30
7 -05
Catch Basin, Type 1L
5
EA
$2,250.00
$ 11,250
$1,700.00
$ 8,500
$1,900.00
$ 9,500
31
7 -05
Catch Basin Type 248 In. Diam.
1
EA
$3,500.00
$ 3,500
$4,500.00
$ 4,500
$4,500.00
$ 4,500
32
7 -05
Trench Drain
1
LS
$4,000.00
$ 4,000
$5,000.00
$ 5,000
$6,000.00
$ 6,000
33
7-06
Pothole Existing Utilities
11
EA
$800.00
$ 8,800
$750.00
$ 8,250
$600.00
$ 6,600
34
7 -10
4' X 15' Modular Wetland Unit
1
EA
$60,000.00
$ 60,000
$65,000.00
$ 65,000
$65,000.00
$ 65,000
35
8 -30
Resolution of Utility Conflicts
1
FA
$8,000.00
$ 8,000
$8,000.00
$ 8,000
$8,000.00
$ 8,000
TRAFFIC CONTROL DEVICES (SCHEDULE A)
36
8 -22
Plastic Stop Line
15
LF
$25.00
$ 375
$28.25
$ 424
$40.00
$ 600
37
8 -22
Plastic Crosswalk Line
70
SF
$8.00
$ 560
$13.50
$ 945
$20.00
$ 1,400
$ 464,555
$ 451,823.75
$ 618,180
CITY OF TUKWILA - DEPARTMENT OF PUBLIC WORKS
2017 Small Drainage Program
BID TABS
05/13/17
Total
Engineer's Estimate
McCann
R.W. Scott Construction
No.
Section
°n
Item
Quantity
Unit
Qty
Total Cost
ROADWAY (SCHEDULE B)
38
1 -04
Unexpected Site Changes
1
FA
$2,000.00
$ 2,000
$2,000.00
$ 2,000
$2,000.00
$ 2,000
39
1 -09
Mobilization
1
LS
$10,000.00
$ 10,000
$5,000.00
$ 5,000
$10,000.00
$ 10,000
40
1 -10
Project Temporary Traffic Control
1
LS
$10,000.00
$ 10,000
$6,500.00
$ 6,500
$12,000.00
$ 12,000
41
2 -01
Clearing and Grubbing
1
LS
$6,000.00
$ 6,000
$3,500.00
$ 3,500
$10,000.00
$ 10,000
42
2 -02
Remove and Replace Handrail
1
LS
$4,000.00
$ 4,000
$3,000.00
$ 3,000
$2,500.00
$ 2,500
43
2 -02
Pavement Removal Incl. Haul
30
SY
$25.00
$ 750
$25.00
$ 750
$100.00
$ 3,000
44
2 -03
Unsuitable Foundation Excavation Incl. Haul
5
CY
$35.00
$ 175
$35.00
$ 175
$150.00
$ 750
45
2 -03
Gravel Borrow Incl. Haul
5
TN
$35.00
$ 175
$25.00
$ 125
$150.00
$ 750
46
4 -04
Crushed Surfacing Top Course
5
TN
$45.00
$ 225
$45.00
$ 225
$150.00
$ 750
47
5 -04
HMA Cl. 1/2" PG 64 -22
10
TN
$175.00
$ 1,750
$185.00
$ 1,850
$300.00
$ 3,000
48
8 -01
Temporary Water Pollution / Erosion Control
1
LS
$4,000.00
$ 4,000
$650.00
$ 650
$2,000.00
$ 2,000
49
8 -04
Cement Conc. Traffic Curb and Gutter
20
LF
$60.00
$ 1,200
$65.00
$ 1,300
$200.00
$ 4,000
50
8 -14
Cement Conc. Sidewalk
20
SY
$75.00
$ 1,500
$105.00
$ 2,100
$200.00
$ 4,000
ROADSIDE DEVELOPMENT (SCHEDULE B)
51 8 -02 Property Restoration 1 FA $2,000.00
$ 2,000
$2,000.00
$ 2,000
$2,000.001 $ 2,000
STORM DRAINAGE (SCHEDULE B)
I(
52
7 -04
Class III Reinforced Concrete Sewer Pipe 36 In. Diam
6
LF
$450.00
$ 2,700
$665.00
$ 3,990
$350.00
$ 2,100
53
7 -05
Connection to Drainage Pipe
1
EA
$500.00
$ 500
$2,500.00
$ 2,500
$1,600.00
$ 1,600
54
7 -05
Debris Barrier
1
EA
$500.00
$ 500
$1,800.00
$ 1,800
$3,000.00
$ 3,000
55
7 -05
Catch Basin Type 2 60 In. Diam. W /Overflow Cage
1
EA
$7,000.00
$ 7,000
$12,500.00
$ 12,500
$9,000.00
$ 9,000
56
7 -20
Temporary Water Bypass System
1
LS
$5,000.00
$ 5,000
$2,500.00
$ 2,500
$4,500.00
$ 4,500
57
8 -15
Light Loose Riprap
20
CY
$150.00
$ 3,000
$235.00
$ 4,700
$100.00
$ 2,000
$ 62,475
$ 57,165
$ 78,950
$ 527,030.00
$ 508,988.75
$ 697,130.00