HomeMy WebLinkAboutTIC 2017-11-14 Item 2G - Final Settlement - Change Order #9 for Interurban Avenue South (South 143rd - Fort Dent Way) with Walsh ConstructionCity Tukwila Public Works Deportment - Bob Giberson, Director INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure FROM: Robin Tischmak, Acting Public Works Director CC: Mayor Ekberg DATE: November 9, 2017 SUBJECT: Interurban Avenue South — S 143rd St to Fort Dent Way Project Number 90310402 Contract 14-067, Change Order No. 9 Allan Ekberg, Mayor ISSUE Approve the final settlement and Change Order No. 9 for the Interurban Ave S Project with Walsh Construction. BACKGROUND Change Order No. 9 settles the additional compensation request and subsequent mediation effort between the City and Walsh Construction commenced on June 16, 2017, and all other disclosed or undisclosed disputes on the construction contract. Change Order No. 9 also increases the contract time by 141.5 calendar days and will allow the Interurban Ave S Project to be closed out. DISCUSSION Walsh Construction has asserted that, during construction, the project encountered unexpected impacts to the Contractor's work. The Contractor has itemized requests for additional compensation that include: 1) unpaid bid items, 2) extra work orders, 3) gravel borrow, 4) sub -contractor costs for Pearson Drilling and ADP Electric and 5) additional costs for inefficiencies and overhead. The City responded to these requests for additional compensation and disputed the Contractor's analysis of cost impacts. On June 16, 2017, the City and Walsh Construction entered mediation to resolve the disputed contract compensation amounts. Several additional settlement conferences were held throughout the summer to negotiate and discuss specific merits of the Contractor's request. Item by item negotiations were set aside in favor of a global settlement discussion. The City Attorney, PW staff, and our construction management consultant met with the Contractor's authorized representatives and discussed the settlement terms to formally close out the project. The discussed settlement terms included that the City shall increase the current contract time by 141.5 calendar days, making the total Contract time 1,067.5 calendar days. As a result of the contract time increase, the City shall rescind the assessed liquidated damage of $358,364.32, which were assessed, but never collected by the City from the Contractor. On top of the liquidated damage reimbursement, the City shall also pay the Contractor a total of $1,425,000.00, in addition to other amounts already paid, to arrive at a final settlement amount for the Interurban Ave S Project. FISCAL IMPACT The total contract amount was $7,836,662.16. With the remaining contract balance of $343,740.85, Change Order No. 9 is for $1,081,259.15 for a total balance owing of $1,425,000 to Walsh Construction. The Transportation Improvement Board has approved an additional $750,000 in grant funds. We are over the 2017 CIP budgeted amount by $950,000, but with the additional $750,000 TIB funds and $35,000 in traffic impact fees for signal improvements, the City overage is $165,000. The total final contract amount is now $8,917,921.31. RECOMMENDATION Council is being asked to approve Walsh Construction's Contract No. 14-067's final settlement Change Order No. 9 for $1,081,259.15 with a contract time extension of 141.5 calendar days and consider this item at the November 27, 2017 Committee of the Whole and the December 4, 2017 Regular Meeting. Attachments: Change Order No. 9 Interurban Ave S Project CIP Overview W:\PW Eng\PROJECTS\A- RW & RS Projects\Interurban Ave S (90310402)\Info Memo for CO #9, Final CA 110717 gl.docx 153 Sheet 1 of 1 CITY OF TUKWILA CONTRACT CHANGE ORDER NO. 9 DATE: November 6, 2017 BUDGET NO.: 104.98.595.300.65.00 PROJECT NO.: 90310402 CONTRACT NO.: 14-067 PROJECT NAME: Tukwila Urban Center Transit Center Project, Andover Park West Street and Water Improvement Project TO: Walsh Construction You are hereby directed to make the herein described changes to the plans and specifications or do the following described work not included in the plans and specifications on this contract: NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued. Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and covenants; B. The rights of the "Owner" are not prejudiced; C. All claims against the "Owner" which are incidental to or as a consequence of this change are waived; and D. The Contractor must submit all Field Overhead and Home Office Overhead Rates for approval in advance of all change orders. CHANGE: See Attached Exhibit "A" We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above and below. ACCEPTED: Date Contractor By Title Original Contract (with tax) $ 7,597,833.39 APPROVED BY THE CITY OF TUKWILA Previous Change Orders $ 238,828.77 Date This Change Order(withouttax) $ 1,081,259.15 By Mayor REV. CONTRACT AMOUNT $ 8,917,921.31 Original Contract Time: 450 Calendar Days Additional Contract Time for this Change Order: 141.5 Days Updated Contract Time: 1,067.5 Calendar Days City Engineer ORIGINAL: City Clerk (1 of 2) Contractor (2 of 2) PW Project Finance File cc: Finance Department (w/encumbrance) Project Management File 154 (11/2014) EXHIBIT "A" CHANGE: This Change Order settles the Contractor's request for additional compensation and is meant to settle all dispute, both disclosed and undisclosed, on the Contract. This Change Order also increases the Contract time by 141.5 calendar days, and will allow this Project to be closed out. Change Order Details: The Contractor, Walsh Construction, has asserted that, during construction, the project encountered unexpected impacts to the Contractor's work that resulted in significant additional expense to the Contractor. The Contractor has itemized requests for additional compensation that include: 1) unpaid bid items, 2) extra work orders, 3) gravel borrow, 4) sub -contractor costs for Pearson Drilling and ADP Electric and 5) additional costs for inefficiencies and overhead. The City responded to these requests for additional compensation and disputed the Contractor's analysis of cost impacts. On June 16, 2017, the City and Walsh Construction entered mediation to resolve the disputed contract compensation amounts. Several additional settlement conferences were held to negotiate and discuss specific merits of the Contractor's request. Item by item negotiations were set aside in favor of a global settlement discussion. The City's project representatives met with the Contractor's authorized representatives, and discussed the settlement terms to formally close out this project. The discussed settlement terms are as follow: Included in this Change Order #9, the City shall increase from the current Contract time by 141.5 calendar days, making the total Contract time at 1,418 calendar days. As a result of the Contract time increase, the City shall rescind the assessed liquidated damage of $358,364.32, which was assessed, but never collected by the City from the Contractor. On top of the liquidated damage reimbursement, the City shall also pay the Contractor $1,425,000.00 as a final settlement amount for all outstanding compensation claims. Once this Change Order #9 is executed, the final payment will be issued, and the Release of Claims form will be completed by the Contractor. Thereafter, the construction project can be closed out by the City Council. Page 1 of 1 155 CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2017 to 2022 PROJECT: Interurban Ave S (S 143 St - Fort Dent Way) Project No. 90310402 DESCRIPTION: Design and construct sidewalks, pavement restoration, drainage, and lighting. JUSTIFICATION: Pedestrian traffic is forced to walk in traveled way, lighting is substandard, drainage is poor and pavement failure is accelerating. STATUS: Completed final design in 2013. Construction awarded on 5/5/14 and construction completed in 2016. MAINT. IMPACT: Reduce annual pavement repairs and increase pedestrian safety. COMMENT: Federal Hwy STP Grant of $389,000 for design. State TIB grant of $5m, Federal STP grant of $2.145m, and developer mitigation of $260,000. City Bond for $3.465m in 2014/15. FINANCIAL Through Estimated (in $000's) EXPENSES 2005-11 2012 2013 2014 2015 2016 2017 TOTAL Design Land (R/VV) Const. Mgmt. Construction TOTAL EXPENSES FUND SOURCES Awarded TIB Grant Awarded STP Grant 389 Mitigation/Traffic Impact Bond City Oper. Revenue 75 TOTAL SOURCES 464 464 464 2 2 369 209 578 87 760 1,494 2,341 74 1,395 4,868 6,337 577 1,139 1,716 71 1,425 1,496 996 209 2,803 8,926 12,934 2 2 578 578 296 1,571 99 375 2,341 2,847 552 85 3,558 (705) 6,337 779 937 1,716 966 530 1,496 4,888 2,512 184 3,558 1,792 12,934 BUDGET Diff 996 :aS 209 TM 2 2r1IF hill 2,455 (348) 8,324 (602) 11,984 (950) 4,138 750 2,512 149 35 3,558 1,627 165 11,984 950 156 W.IPW Eng1PROJECTSIA- RW & RS Projectsllnterurban Ave S (90310402)IGrants & Bondllnterurban Final CIP sheet 110617 Y Project Location :aS TM 2 2r1IF hill s III i S 139 ®$ 94 W 5744 Strii �52 /v0i //'' OCL Y®r J/. St g N m ,,. o 1 ���++"�� � Iii -�- 3'156 St ___ a '":. rh ricA .. cera r� i�►`I'I '� ��_/ GISi. stsast it'll�r Tukwila PoavY 156 W.IPW Eng1PROJECTSIA- RW & RS Projectsllnterurban Ave S (90310402)IGrants & Bondllnterurban Final CIP sheet 110617