HomeMy WebLinkAboutTIC 2017-11-28 Item 4 - Dicussion - Valley View Sewer District Open HouseValley View Sewer District
Open House/Public Meeting
THE LOOP AND SURROUNDING AREA
NEW SEWER CONSTRUCTION PROJECT
SUNDAY, NOVEMBER 19, 2017
AGENDA
Project Design
Overall Project Cost Estimate and
Funding Status
Connection Costs and Payment Options
Project Schedule
Incentives for Connection in 2018
Bey 1'xlT'
ORIGINAL DESIGN
Legend
• Proposed NEanhole
• Existing Sewer Manhole
HDD Installation
- Open Trench installation
— Existing Sewer
• Manhole
Gravity plain
Potent& Service
Wetlands
1 Irch=12@iQel
re470.11. L.' PULL
..:.:t:, R j.w
Area /b1 ^e� }r.i- S
s.�' 4
w
The Loop Sewer
Valley View Sewer District
• r a-W�u •.wwttr Ca Vs
dft
1•6saa^ 1,1". pr} n lam^ ilekilatn
FINAL PROJECT DESIGN
f1F
WG wit ■
Legend
• Proposed Manhole
• Existing Sewer Manhole
— HOD Installation
— Open Trench Installation
— Emoting Sewer
1.5 Inch Farce Main
▪ Individual P rnp Stations
e Manhole
r--- Gravity Main
ni Potential Service Area
-- Wetlands
1
Age
eCal SD '7447.sw Lmx+;Lnsnen. 1.4 ANA Lax alJ.: ra :� . ac
21 Gare
ry
r. 0.811 1
12
11
ISac
pt,
The Loop Sewer - Alternate Design
Valley View Sewer District
AMP
.M.} 4b rar,r T�rq.
PROPOSED PUMP LOTS NORTH OF
S 156T" STREET
Logien!
• Proposed Manhole
e Existing Sewer MOMOIe
-1100 Installation
--�
Open Trench installation
Existing Sewer
1.3 inch Force Main
tndtvidiral Pump Stations
it Manhole
Gravity Win
Potential Service Area
Wetlands
Peso... r.l•.:..-.,' LW,ttiro6.aKi ref! to 1,co swrri3'�e �m�_.s.iconivrin�.nua sr:nyi.yson •.wosur .r
1 air'=ante.t
The Loop Sewer - Alternate Design
Valley View Sewer District
OVERALL PROJECT COST ESTIMATE
AND FUNDING STATUS
Total Project Cost (Estimate): $5,680,000.00
Grant Funded Amount: $4,535,136.00
Balance : $1,144,864.00
For Information Only!
Total Project Cost Divided Among Existing Lots: $39,172/Lot
Balance Divided Among Existing Lots : $ 7,895/Lot
Proposed Connection Charge/Existing Lot: $ 3,000 (Estimate)
*Collected from existing and future lots upon connection
VIuey '
V ,V
CONNECTION COSTS AND PAYMENT OPTIONS
CONNECTION COSTS
Connection Charge
General Facility Charge (GFC)
KC Treatment Capacity Charge (Capacity Charge)
c -:t-11 c'az .rr per- :� �� �, �`' I rw (3r `Parrrr�l-4.
J11..11,. JL. Iry %...1 1 1.1 11111, 1 Gl. .rJ i JV .VV ,1 1.1 11111.
Paid for by Grant
:A
.J1 .A 1.. .J t.. V 1..1 v14.11 1J{.1 lAl. . 1 1
Paid for by Grant
..! 1 lA
YV
i vvv
EXISTING LOT CONNECTION COSTS
CHARGE TYPE
FULL AMOUNT
AVERAGE MONTHLY FINANCE CHARGE
Connection Charge
$3,000.00 (Estimate)
$21.00
$33.00
$62.60
$0.00
$0.00
GFC
$4,033.00
Capacity Charge
$9,176.76 (Estimate)
Permit Fee
$100.00
•
, etkOO—{[slim )
Si
ALL CONNECTION CHARGES
$16,209.76
$116.60
SEWER BILL/MONTH
$58.85
`TOTAL WITH SEWER BILL/MONTH
$175.45
(1) Connection Charge and GFC annual installments for 15 years.
(2) Capacity Charge quarterly bill for 15 years.
(3) Each newly created lot will have a Connection Charge of $10,500 (Estimate).
F4LZey
$934.84 Due Upon Financing
KING COUNTY COMMUNITY
DEVELOPMENT BLOCK GRANT (CDBG)
Valley View Awarded $205,000 Grant for Low
Income Property Owner Connection Costs
Based on Income Verification and Income
Eligibility
For Qualifying Homeowners, the Block Grant Will
Pay For:
Connection Charge
General Facility Charge
King County Treatment Capacity Charge
KING COUNTY COMMUNITY
DEVELOPMENT BLOCK GRANT (CDBG)
2017 Income Guidelines
(Based on Number of Persons and Corresponding Combined Income)
Persons per
household
1
Low income
(50% and below
of median)
$33,600
or Tess
2
$ 38,400
or Tess
3 4
$43,200
or Tess
$48,000
or Tess
5
$51,850
or less
6
$55,700
or Tess
7
$59,550
or less
8
$63,400
or less
Must be owner occupied to qualify for assistance.
PROJECT SCHEDULE
PHASE I (MAINLINE CONSTRUCTION)
^'3,100 feet of 8" PVC Pipe in Public Right -of -Way
^'5,900 feet of 8" PVC Pipe in Private Easements
• —1,500 feet of 8" HDPE Pipe by Horizontal Directional Drill
c ^'4,200 feet of 6" PVC and HDPE Pipe
49 of 48" Sewer Manholes
All Street and Private Property Restoration
PHASE II (SIDE SEWER CONSTRUCTION)
• Installation of up to 138 Side Sewers
• Approximately 6,800 feet of 4" PVC Side Sewer Pipe
Installation of 7 Private Pump Systems
All Private Property Restoration
PROJECT SCHEDULE (CONT.)
PHASE SCHEDULE
January 2018
January/February 2018
March/April 2018
April/May 2018
October/November 2018
PHASE SCHEDULE
September/October 2018
October/November 2018
December 2018
"f10!"i! GIQd1,1RL+.1!Jlf1JRf,.�IPR�!.es1
Design Complete
Go Out for Public Bid
Select Contractor and Award Contract
Start Phase I Construction
Complete Phase I Construction
Go Out for Public Bid
Select Contractor(s) and Award Contract(s)
Complete Phase I Construction
PHASE 11 CONNECTION INCENTIVES
I ,
If, mow '
1 t
500 CRE100 mL
1C113115
, -T1
830 CFUi100
10113,15
• •
‘..• 290 CFU/100 mL. . _
10/13/15 • t,
•TiLt,
4500 CFU/100 mL
10/13/15 ,
500 CFU/100 mL
10/13/15
230 CFU/100 mL
10/13/15
320 CFU/100 mL
4/9/15
d
rt:44g6i
The Loop Sewer
Valley View Sewer District
1 Inch .750
NORTH
INCENTIVES FOR CONNECTION IN
2018 (PHASE II)
kitm
The Loop Connection Charge Escalation
($3,000.00 Estimate)
Year Connection Charge Year
2018
2019
2020
2021
2022
$3,000.00
$6,500.00
$6,695.00
$6,890.00
$7,085.00
Connection Charge
2023
2024
2025
2026
2027
Capacity Charge Escalation
Year
2013
2014
Capacity Charge
$6,618.26
$7,897.96
$7,280.00
$7,475.00
$7,670.00
$7,865.00
$8,060.00
Year
2017
2018
Capacity Charge
$8,912.91
$9,176.76
After 2018 Responsible for Side Sewer and Permit Fee = $7,100
VIIIMMItlyitYLCIMORTme
Va leis_
INCENTIVES FOR CONNECTION IN
2018 (PHASE II) (CONT.)
CHARGE TYPE
FULL AMOUNT
2018
2019
AVERAGE MONTHLY FINANCE CHARGE
2018
2019
Connection Charge
$3,000
$6,500
(Estimate)
$21.00
$42.00
GFC
$4,033
$4,033
$33.00
$33.00
Capacity Charge
$9,176
$9,452
(Estimate)
$62.60
1 $64.50
Permit Fee
$0
$100
N/A
N/A
Side Sewer
$0
$7,000
(Estimate)
$0.00
$57.50
ALL CONNECTION CHARGES
$16,209
$27,085
1 $116.60
1
$197.00
SEWER BILL/MONTH
$58.85
62.50 (Projected)
[TOTAL WITH SEWER BILL/MONTH
$175.45
$259.50
(1) Capacity Charge assumes 3% yearly increase.
"-WORKP. mu;1;pn.f DEFTER
SEifER DISTRICT
POSSIBLE CONNECTION
REQUIREMENTS
No District Requirement to Connect
Possible Other Agency Requirements to Connect:
City of Tukwila Ordinance
Failed Septic System
Title Transfer (Sale of Property)
Major Remodel Permit (Add Bedroom/Bathroom)
•Health Department
Failed Septic System
Bank
Upon Property Sale, the Lending Institution May Require
Connection to Sewers as a Condition of Sale
FUTURE COMMUNICATIONS
Notification of Contract Award and Start Date for Phase I
Construction.
Notification of Contract Award and Start Date for Phase II
Construction.
Notification of Availability of Application for CDBG
Assistance.
Request for Income Verification Documentation for CDBG
Applicants.
Request for Signed Right of Entry Forms for Construction
of Side Sewers on Private Property.
Request for Signed Side Sewer Easements for Those
Properties Best Served by Common Sewer Lines.