HomeMy WebLinkAboutTIC 2018-02-26 Item 2A - Final Acceptance - 2016 Andover Park East Sewer Repair with Gary Harper ConstructionSIN City of Tukwila Public Works Department - Henry Hash, Director Allan Ekberg, Mayor INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Henry Hash, Public Works Director /7/ BY: Peter Lau, Senior Program Manager CC: Mayor Allan Ekberg DATE: February 23, 2018 SUBJECT: 2016 Andover Park East Sewer Repair Project Project No. 91140203, Contract No. 17-092 Project Completion and Acceptance ISSUE Accept construction contract as complete and authorize release of retainage. BACKGROUND The Notice to Proceed for Contract Number 17-092 with Gary Harper Construction, Inc. of Snohomish, Washington was issued on June 19, 2017. This construction project replaced approximately 435 lineal feet of asbestos -cement sewer main with PVC pipe within the City right- of-way on Andover Park East (APE). DISCUSSION The 2016 APE Sewer Repair project was physically completed on November 8, 2017. No change orders were executed for this construction project. FISCAL IMPACT The construction budget for the 2016 APE Sewer Repair Project was $1,100,000.00. The contract bid amount was $413,935.50 and the final amount was $365,443.64. Unit price under -runs were mainly due to under -utilization on backfill crushed rocks and a force account bid item to pay for minor changes. An escrow agreement for the retainage is $16,611.07. Expenses $376,305.00 ($44,083.51) $33,222.15 Construction Contract Amount (pre-tax) Unit Price Under -runs WA State Sales Tax Total Contract Amount $365,443.64 RECOMMENDATION Council is being asked to formally accept the 2016 Andover Park East Sewer Repair contract with Gary Harper Construction, Inc. in the amount of $365,443.64 as complete, and authorize the release of the retainage subject to standard claim and lien release procedures, and to consider this item on the Consent Agenda at the March 5, 2018 Regular Council Meeting. Attachment: Notice of Completion, Contract #17-092 W:1PW Eng1PROJECTSIA- SW Projects\CBD Sewer Rehabilitation (91140203)12016 APE Sewer Repair,Construction9i.700 - Post Construction & CloseoutlInfo Memo 2016 APE Sewer Repair close out 022318 gl.docx 1 Date: V Original ❑ Revised # NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT Contractor's UBI Number: 601606620 Name & Mailing Address of Public Agency City of Tukwila 6200 Southcenter Boulevard Tukwila, WA 98188 UBI Number: 179000208 Department Use Only Assigned to: Date Assigned: Notice is hereby given relative to the completion of contract or project described below Project Name 2016 Andover Park East Sewer Repair, 91140203 Contract Number 17-092 Job Order Contracting ❑ Yes V No Description of Work Done/Include Jobsite Address(es) Replacement of approximately 435 linear feet of asbestos -cement sewer main with PVC pipe, and other necessary works associated with this pipe replacement, within the City right-of-way on Andover Park East. Federally funded transportation project? ❑ Yes No (if yes, provide Contract Bond Statement below) Contractor's Name E-mail Address Affidavit ID* Gary Harper Construction, Inc. gary@garyharperconst.com 747289 Contractor Address Te ephone # 14831 223rd Street SE, Snohomish, WA 98296 360-863-1955 If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number. ❑ Retainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects) Name: Bond Number: Date Contract Awarded Date Work Commenced Date Work Completed Date Work Accepted May 15, 2017 July 31, 2017 November 8, 2017 Were Subcontracters used on this project? If so, please complete Addendum A. VY es ❑ No Affidavit ID* - No L&I release will be granted until all affidavits are listed. Contract Amount Additions (+ ) Reductions (- ) Sub -Total Sales Tax Rate 10.0 % (If various rates apply, please send a breakdown) Sales Tax Amount $ 413935.50 $ 0.00 Liquidated Damages $ 0.00 $ 81,714.00 $ 332,221.50 $ 33222.14 TOTAL $ 366_443 64 Amount Disbursed $ 348832.57 Amount Retained $ 16611.07 NOTE: These two totals must be equal TOTAL $ 365,443.64 Comments: Note: The Disbursing Officer must submit this con I leted notice immediately after acceptance of the work done under this contract. NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates. Submitting Form: Please submit the completed form by email to all three agencies below. Contact Name: Diane Jaber Email Address: diane.jaber@tukwilawa.gov Dep of Revenue Public Works Section C.ra (360) 704-5650 PWC@dor.wa.gov 0 Washington State Department of Labor & Industries Contract Release (855) 545-8163, option # 4 ContractRelease@LNI. WA.GOV REV 31 0020e (10/26/15) F215-038-000 10-2014 Title: Fiscal Specialist Phone Number: (206) 433-1871 X 1871 Employment Security Department Registration, Inquiry, Standards & Coordination Unit (360) 902-9450 publicworks@esd.wa.gov 2 Addendum A: Please List all Subcontractors and Sub -tiers Below This addendum can be submitted in other formats. Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed. Subcontractor's Name: UBI Number: (Required) Affidavit ID* Apply A Line, Inc. 600553941 738669 Harlow Construction Company, Inc. 601762618 740645 Olson Brothers PRO -VAC, LLC 602170975 744620 PLS, Inc. 601979933 729980 Prime Electric, Inc. 601004783 749733 Puget Paving & Construction, Inc. 600403309 738611 Sea -Tac Sweeping Service 601735583 739516 Silverstreak, Inc. 600432781 739289 For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the Washington Relay Service by calling 711. REV 31 0020e Addendum (10/26/15) F215-038-000 10-2014 3