HomeMy WebLinkAbout18-038 - JRS Engineering - Building Envelope Services for the Justice Center and Fire Stations1110011000,11
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Agreement Number:18-038(e)
CONTRACT FOR SERVICES
Amendment No. 5
Between the City of Tukwila and JRS Engineering.
That portion of Contract No. 18-038 between the City of Tukwila and JRS Engineering is
hereby amended as follows:
3. Duration of Agreement; Time for Performance. This Agreement shall be in full force
and effect for a period commencing upon execution and ending December 31, 2021,
unless sooner terminated under the provisions hereinafter specified. Work under this
Agreement shall commence upon written notice by the City to the Consultant to proceed.
The Consultant shall perform all services and provide all work product required pursuant to
this Agreement no later than December 31, 2021 unless extension of such time is granted
by writing by the City.
The duration of the contract is now through December 31, 2021, unless modified by
supplemental agreement.
All other provisions of the contract shall remain in full force and effect.
Dated this 23 day of November , 2020.
CITY OF TUKWILA
C-0~ 065e/cg
Allan Ekberg, Mayor
12/08/2020
ATTEST/AUTHENTICATE D
c134.€4t-9 6,677(cth&t.t-9
CONTRACTOR
Jeff Speed, 'nncipal
APPROVED AS TO FORM
c
Christy O'Flaherty, O'Flaherty, MMC, City Clerk Office of the City Attorney
CA Revised December 2016
Page 1 of TI
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98
Agreement Number:
18-038(d)
Council Approval N/A
CONTRACT FOR SERVICES
Amendment No. 4
Between the City of Tukwila and JRS Engineering
That portion of Contract No. 18-038 between the City of Tukwila and JRS Engin ering is
hereby amended as follows.
Section 1 - The Consultant is retained by the City to perform building
envelope consulting services in connection with the project titled Tukwila Public Safety Plan,
Fire Stations Si, 52 and Justice Center.
Section 2 Scope of Services: The Consultant agrees to perform the services, identified on
Exhibit "A" attached hereto, including the provision of all labor, materials, equipment and
supplies
Section 4 Payment: The Consultant shall be paid by the City for comp eted work and for
services rendered under this Agreement as follows:
Payment for the work provided by the Consultant shall be made as provided on Exhibit
attached hereto, provided that the total amount of payment to the Consultant shall not exceed
$186,885 (including estimated expenses) without express written modification of the
Agreement signed by the City. The total amount for this amendment is $4,400.
All other provisions of the contract shall remain in full force and effect.
Dated this 25th day of May , 2020
CITY OF TUK ILA CONTRACTOR
Prfrfd N.,, e. Jeff Speen, Principal
APPROVED AS TO FORM
Allan Ekberg, Mayor
ATTEST/AUTHENTICATED
6h4 ri.677(ah&Y t-9
Q,Selirtel.':
Christy O'Flaherty, MMC, City Clerk Office of the City Attorney
CA Revsed Deco ller 2016
Page 1 of 1
EXHIBIT A
ADDITIONAL SERVICES AGREEMENT
THIS ADDITIONAL SERVICES AGREEMENT made as of the 19th day of May, 2020, shall supplement
the Consultant Agreement for Building Envelope Consulting Services ("the Agreemenr) made as of the
21st day of March, 2018.
BETWEEN:
AND
City of Tukwila, having an office at
6200 Southcenter Boulevard
Tukwila, WA 98188
(the "Client")
JRS ENGINEERING, a Washington State Corporation having an office at
12721 30th Ave NE, 2"d Floor
Seattle, WA 98125 USA
(the "Engineer")
Subject to the terms and conditions of the Agreement, the Client agrees to hire the Engineer to provide the
additional services described in the attached Supplement to Schedule "A".
CLIENT
Per:
/Name:
Title:
JRS ENGINEERING
Per:
Name' Jeff peert
Principal
Date:
Date:
May 25, 2020
EXHIBIT A
m JRS ENGINEERING
SUPPLEMENT TO SCHEDULE A PAGE 1 OF 1
SUPPLEMENT TO SCHEDULE "A"
Services
JRS Engineering (JRS) is pleased to provide building envelope consulting services for the Fire Station 51
project in Tukwila, Washington.
SCOPE OF WORK
Window Testing: JRS Amendment No. 3 (dated 4/28/20) increased the total JRS scope for field window
testing to two days on site to conduct a total of four window tests. The intent is for one day on site to test
two aluminum storefront windows and a second day on site to test two fiberglass storefront windows.
Following conversations with the Owners representative after the leaks observed during aluminum
storefront testing on 4/29/20, JRS has been requested to provide an additional services request to cover
the additional testing the Owner has requested. The proposed fees below include the same-day retest of
the aluminum storefront that leaked on 4/29/20 and the proposed additional testing to be scheduled
(specifically, an additional day on site for a second retest of the aluminum storefront that leaked on 4/29/20
and testing of two additional aluminum storefront windows of a similar type). See Exhibit A from the
Agreement for additional information regarding this scope of work.
PROPOSED FEES
JRS Engineering proposes to undertake the services described above for the folio ing fees, subject to the
terms and conditions from the Agreement:
Fire Station 51
Phase/Title
Quantity/
Description
Anticipated
Units/Hours
Anticipated
Additional
Hourly Rate
Costs
Total
Additional
Fixed Fee
Window Testingn/a
• Same-day retest on
4/29/20 [$800/ea]
• First test per day
[$2,000/ea]
• Additional test (completed
same day) [WO/ea]
• 1 retest
4 1 mobilization
+ 1 retest
• 2 additional
tests
$4,400
SUBTOTAL
-
$4,400
END OF SUPPLEMENT TO SCHEDULE "A"
RB
City of Tukwila Agreement Number: 18-038 (c)
6200 Southcenter Boulevard, Tukwila WA 98188
CONTRACT FOR SERVICES
Amendment No. 3
Between the City of Tukwila and JRS Engineering
That portion of Contract No. 18-038 between the City of Tukwila and JRS Engineering is
hereby amended as follows:
Section 1 Proiect Designation: The Consultant is retained by the City to perform building
envelope consulting services in connection with the project titled Tukwila Public Safety Plan,
Fire Stations 51, 52 and Justice Center.
Section 2 Scope of Services: The Consultant agrees to perform the services, identified on
Exhibit "A" attached hereto, including the provision of all labor, materials, equipment and
supplies.
Section 4 Payment: The Consultant shall be paid by the City for completed work and for
services rendered under this Agreement as follows:
Payment for the work provided by the Consultant shall be made as provided on Exhibit "A"
attached hereto, provided that the total amount of payment to the Consultant shall not exceed
$182,485 (including estimated expenses) without express written modification of the
Agreement signed by the City. The total amount for this amendment is $12,600 ($5,800 +
$6,800).
All other provisions of the contract shall remain in full force and effect.
Dated this 29th April
day of , 2020
CITY OF T
Allan Ekberg, Mayor z n aow
CA Revised December 2016
CONTRACT R
pe_____
Prin ed N e: Jeff Speed, Principal
Page 1 of 1
rdi JRS ENGINEERING SUPPLEMENT roSCHEDULE A PAGE 1 OF 1
SUPPLEMENT TO SCHEDULE "A"
Services
JRS Engineering (JRS) is pleased to provide building envelope consulting services for the Fire Station 51
project in Tukwila, Washington.
SCOPE OF WORK
Window Testing: In the current contract for this pnoject. JRS has been approved for one day on site to
conduct two window tests. Following conversations with the Owner's representative regarding scope of
window testing for this project, JRS has been requested to provide an additional services request for a
second day on site for an additional two window tests; the proposed fixed fee below is for this additional
day of window testing. The current intent is to test two fiberglass storefront windows and two aluminum
storefront windows. See Exhibit A from the Agreement for additional information regarding this scope of
work.
Submittal, RFI, and Shop Drawing Reviews: As discussed with the Owner's representative, JRS has
exhausted the current budget from the Agreement for submittal, RFI, and shop drawing reviews, in part due
to the consulting regarding the C -channel detailing. The proposed hourly budget below is for additional
reviews anticipated through the remainder of construction. See Exhibit A from the Agreement for additional
information regarding this scope of work.
PROPOSED FEES
JRS Engineering proposes to undertake the services described above for the following fees, subject to the
terms and conditions from the Agreement:
Fire Sation 51
Phase/Title
Quantity/
Description
Anticipated
Units/Hours
Anticipated
�����wn�;
Hourly Rate
Costs
Total
Additional'
Fixed Fee
YV|n6o",Temingn/o
• Fi�|tegper day
($2,000/ea]'
• Additional test (completed
same day) [$800/ea]
• 1 mobilization
+lte�
• 1 test
'
$2,800
Submittal, RFI,
and Shop
Drawing Reviews
Additional consulting, as
needed, to review submittals,
RFIs, and/or shop drawings
Approx. 20 hrs
$3,000
n/a
SUBTOTAL
$3,000
$2,800
END OF SUPPLEMENT TO SCHEDULE "A"
ADDITIONAL SERVICES AGREEMENT
THIS ADDITIONAL SERVICES AGREEMENT made as of the 30th day of March, 2020, shall supplement
the Consultant Agreement for Building Envelope Consulting Services ("the Agreement") made as of the
21st day of March, 2018.
BETWEEN:
AND
City of Tukwila, having an office at
6200 Southcenter Boulevard
Tukwila, WA 98188
(the "Client")
JRS ENGINEERING, a Washington State Corporation having an office at
12721 30th Ave NE, 2nd Floor
Seattle, WA 98125 USA
(the "Engineer")
Subject to the terms and conditions of the Agreement, the Client agrees to hire the Engineer to provide the
additional services described in the attached Supplement to Schedule "A".
CLIENT
Per:
Name:
Title:
Date:
JRS ENGINEERING
Per:
Name: Jeff Speert Date:
Title: Principal
JRS ENGINEERING SUPPLEMENT TO SCHEDULE A PAGE 1 OF 1
SUPPLEMENT TO SCHEDULE "A"
Services
JRS Engineering (JRS) is pleased to provide building envelope consulting services for the Fire Station 52
project in Tukwila, Washington.
SCOPE OF WORK
Window Testing: In the current contract for this pnoject. JRS has been approved for one day on site to
conduct two window tests. Following conversations with the Owner's representative regarding scope of
window testing for this pnoject. JRS has been requested to provide an additional services request for a
second day on site for an additional two window tests; the proposed fixed fee below is for this additional
day of window testing. The current intent is to test bwo fiberglass storefront windows and bmo aluminum
storefront windows. See Exhibit A from the Agreement for additional information regarding this scope of
work.
Submittal, RFI, and Shop Drawing Reviews: As discussed with the Owner's representative, JRS has
almost exhausted the current budget from the Agreement for submittal, RFI, and shop drawing reviews, in
part due to the consulting regarding the north foundation wali The proposed hourly budget below is for
additional reviews anticipated through the remainder of construction. See Exhibit A from the Agreement for
additional information regarding this scope of work.
PROPOSED FEES
JRS Engineering proposes to undertake the services described above for the following fees, subjectto the
terms and conditions from the Agreement:
Fire Station 52
Phase/Title
Quantity/
Description
AnticipatedAdditional
Units/Hours
'Fixed
Anticipated
Additional
Hourly��mw
Costs
Total
Additional
Fee
Window Testing
• First test per day
[$2�O�/ep]
' 'n/a
^ Additional test (completed
same day) [$8OD/eo]
• 1 mobilization
+ 1 �e,�
^ 1 test
$2,800
Submittal, RFI,
and Shop
Drawing Reviews
Additional consulting, as
needed, to review submittals,
RFIs, and/or shop drawings
Approx. 27 hrs
$4,000
n/a
SUBTOTAL
54,000
S2,800
END OF SUPPLEMENT TO SCHEDULE "A"
ADDITIONAL SERVICES AGREEMENT
THIS ADDITIONAL SERVICES AGREEMENT made as of the 30th day of March, 2020, shall supplement
the Consultant Agreement for Building Envelope Consulting Services ("the Agreement") made as of the
215t day of March, 2018.
BETWEEN:
AND
City of Tukwila, having an office at
6200 Southcenter Boulevard
Tukwila, WA 98188
(the "Client")
JRS ENGINEERING, a Washington State Corporation having an office at
12721 30th Ave NE, 2nd Floor
Seattle, WA 98125 USA
(the "Engineer")
Subject to the terms and conditions of the Agreement, the Client agrees to hire the Engineer to provide the
additional services described in the attached Supplement to Schedule "A".
CLIENT
Per:
Name:
Title:
Date:
JRS ENGINEERING
Per:
Name: Jeff Deert Date: April 29, 2020
Title: Principal
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Agreement Number: 18-038 (b)
CONTRACT FOR SERVICES
Amendment No. 2
Between the City of Tukwila and JRS Engineering
That portion of Contract No. 18-038 between the City of Tukwila and JRS Engineering is
hereby amended as follows:
Section 1 Project Designation: The Consultant is retained by the City to perform building
envelope consulting services in connection with the project titled Tukwila Public Safety Plan,
Fire Stations 51, 52 and Justice Center.
Section 2 Scope of Services: The Consultant agrees to perform the services, identified on
Exhibit "A" attached hereto, including the provision of all labor, materials, equipment and
supplies.
Section 4 Payment: The Consultant shall be paid by the City for completed work and for
services rendered under this Agreement as follows:
Payment for the work provided by the Consultant shall be made as provided on Exhibit "A"
attached hereto, provided that the total amount of payment to the Consultant shall not exceed
$169,885 (including estimated expenses) without express written modification of the
Agreement signed by the City. The total amount for this amendment is $33,420.
All other provisions of the contract shall remain in full force and effect.
Dated this
CITY CZIJKWILA
ct
Allan Ekberg, Mayor
day of , 2019
CONTRACTOR
Pri d Nam Jeff & peert, Principal
ATTEST/AUTHENTICATED
'Christy O'Flaherty, MMC, City Clerk
CA Revised December 2016
/ 751
:/-k16 /N4CS
Page 1 of 1
NB
BUILDING EXCELLENCE
EXHIBIT A
PAGE 9 OF 10
Fire Station 51
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development
2 meetings
1 review
24
$3,240
$50
Construction Documents
2 meetings
2 reviews
51
$6,750
$100
Bidding Assistance
Assist in answering
Bidder questions
6
$810
$0
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related documents
30
$4,050
$0
Pre -installation
meetings
2 meetings on site
14
$1,890
$100
Mock-up observations
1 mock-up
8
$1,080
$50
Field review
15 visits (assumes 3jrnonth)
115
$15,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$3,800
$0
SUBTOTAL
248
$39,945*
$700
*Assumes 2 window tests completed in the same day.
Fire Station 52
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development
2 meetings
1 review
30
$4,050
$50
Construction Documents
2 meetings
2 reviews
65
$8,775
$100
Bidding Assistance
Assist in answering
Bidder questions
6
$810
$0
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related
documents
35
$4,725
$0
Pre -installation
meetings
2 meetings on site
14
$1,890
$100
Mock-up observations
1 mock-up
8
$1,080
$50
Field eview
21 Visits (assumes 3/month)
134
$18,000
475
Window Testing-
First test per day
Additional test (completed same
day)
$2,000
$800
$(.)
Air barrier testing
1 test
-
$4,300
SUBTOTAL
292
$46,430*
$775
*Assumes 2 window tests completed in the same day.
Highlighted totals;
$32,795 + $625 = $33,420
WWW.JRSENGINEERING.COM
rill
BUILDING EXCELLENCE
EXHIBIT A
PAGE 1 0 OF 1 0
tation 54
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
' bursables
Design Development
2 meetings
1 review
2,4
$32 , •.
$50
Construction Documents
2 meetings
views
51
$6,750
$11
100
Bidding Assistance
ring
Bidder questio
6
$810
$0
Submittal and RFI
reviews
Review of submittals,30
, ASIs and related• • u en s
50
$4,050
$0
Pre -installation
meetings
2 meetin. • site
21
$1,890
$100
Mock-up observations
1 mock-up
.: visits (assumes 3/month)
8
1 5
$ 080
25
$50
$400
Field review
Window Testing
First test per day
Additional test (completed same
day)
-
$800
Window Testing
Air b • r testing
1 test
$2,000
$800
$0
Air barrier testing
F117 OTAL
-
248
$39,945*
$700
*Assumes 2 window tests completed in the same day.
Justice Center
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development
2 meetings
1 review
35
$4,725
$50
Construction Documents
3 meetings
2 reviews
60
$8,100
$150
Bidding Assistance
Assist in answering
Bidder questions
6
$810
$0
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related documents
50
$6,750
$0
Pre -installation
meetings
3 meetings on site
21
$2,835
$100
Mock-up observations
2 mock-ups
16
$2,160
$50
Field review
18 visits (assumes 3/month)
115
$15,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$7,100
$0
SUBTOTAL
303
$50,805*
$750
*Assumes 2 window tests completed in the same day.
- Composite Hourly Rate is $1 35/hour
- Contracts will be awarded on a time -and -material basis by hourly rates.
$100,835
TOTAL
1,091
$177,125
$2,925
(Including exterior walls and roof systems)
WWW.JRSENGINEERING.COM
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Agreement Number: 18-038
CONTRACT FOR SERVICES
Amendment No. 1
Between the City of Tukwila and JRS Engineering
That portion of Contract No. 18-038 between the City of Tukwila and JRS Engineering is
hereby amended as follows:
Section 1 Pro'ect Desi • nation: The Consultant is retained by the City to perform building
envelope consulting services in connection with the project titled Tukwila Public Safety Plan,
Fire Stations 51, 52 and Justice Center.
Section 2 Scope of Services: The Consultant agrees to perform the services, identified on
Exhibit "A" attached hereto, including the provision of all labor, materials, equipment and
supplies.
Section 3 Duration of Agreement; Time for Performance: This Agreement shall be in full
force and effect for a period commencing upon execution and ending December 31, 2020,
unless sooner terminated under the provisions hereinafter specified. Work under this
Agreement shall commence upon written notice by the City to the Consultant to proceed. The
duration of the contract is now through December 31, 2020, unless modified by supplemental
agreement.
Section 4 Payment: The Consultant shall be paid by the City for completed work and for
services rendered under this Agreement as follows:
Payment for the work provided by the Consultant shall be made as provided on Exhibit "A"
attached hereto, provided that the total amount of payment to the Consultant shall not exceed
$136,465 (including estimated expenses) without express written modification of the
Agreement signed by the City. Total fee for services related to Amd. No. 1 is $56,465.
All other provisions of the contract shall remain in full force and effect.
Dated this 213 day of
CITY OF TUKWILA
Al an Ekberg, Mayor
ATTEST/AUTHENTICATED
1
fr
Christy O'Flaherty, C, City Clerk`"
CA Revised December 2016
, 2019
CONTRACTOR
hinted Na • eff Speert, Principal
APPROVED AS TO FORM
Office of the City . ttorney
Page 1 of 1
EXHIBIT A
BUILDING IEXCELLFNCE
PAGE 9 OF 1 0
I Fire Station 51
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development
2 meetings
1 review
24
53,240
550
Construction Documents
2 meetings
2 reviews
51
56,750
5100
Bidding Assistance
Assist in answering
Bidder questions
6
$810
$0
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related documents
30
$4,050
50
Pre -installation
meetings
2 meetings on site
14
51,890
5100
Mock-up observations
1 mock-up
8
51,080
550
Field review
15 visits (assumes 3/month)
1 1 5
515,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
52,000
$800
50
Air barrier testing
1 test
-
53,800
50
SUBTOTAL
248
$39,945*
$700
*Assumes 2 window tests completed in the same day.
Highlighted:
$29,145
$550 =1g
Fire Station 52
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development
2 meetings
1 review
30
54,050
550
Construction Documents
2 meetings
2 reviews
65
58,775
5100
Bidding Assistance
Assist in answering
Bidder questions
6
$81 0
$0
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIS cnd related
documents
35
$4,725
50
Pre -installation
meetings
2 meetings on site
14
51,890
$100
Mock-up observations
1 mock-up
8
$1,080
550
Field review
21 visits (assumes 3/month)
1 34
51 8,000
$475
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
5800
50
Air barrier testing
1 test
-
$4,300
50
SUBTOTAL
292
$46,430*
$775
*Assumes 2 window tests completed in the same day.
Highlighted: S32,795
5625 = N 11/ 41-0
V.VV .JR5ENGINEERING.COM
( BUILDING ECELLEI=CE
EXHI
PAGE 10 OF 10
Station 54
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
bursables
Design Development
_ 2 meetings
1 review
24
$3,2 s
$50
Construction Documents
",_ 2 meetings
views
51
$6,750
$100
Bidding Assistance
Assist in an ring
Bidder questio
•
$810
$0
Submittal and RFI
reviews
Review of submittals, =
RFIs, ASIs and related x = `uments'
30
$4,050
$0
Pre -installation
meetings
2 meetin... »h site
4
$1,890
$1 00
Mock-up observations
1 mock-up
8
$1,080
$50
Field review
visits (assumes 3/month)
1 1 5
525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,0'
$800
$0
Air b• '-r testing
1 test
-
$3,800
0
OTAL
248
$39,945*
$700
*Assumes 2 window tests completed in the same day.
Justice Center
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development
2 meetings
1 review
35
$4,725
$50
Construction Documents
3 meetings
2 reviews
60
$8,100
$150
Bidding Assistance Assist in answering
Bidder questions
6
$810
$0
Submittal and RFI i Review of submittals,
reviews RFIs, ASIs and related documents
50
$6,750
$0
Pre -installation
meetings
3 meetings on site
21
$2,835
$100
Mock-up observations
2 mock-ups
16
$2,160
$50
Field review ; 18 visits (assumes 3/month)
115
$15,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$7,100
$0
i
SUBTOTAL 1
303
$50,805*
$750
*Assumes 2 window tests completed in the same day.
Composite Hourly Rate is $135/hour
- Contracts will be awarded on a time -and -ma
ter
a
Highlighted:
basis by hourly rates.
$37,170
$100,835
$550
TOTAL
(Including exterior walls and roof systems
1,091
$177,125
$2,925
WVVW.JRSENGINEERING.00M
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Contract Numberl8-038
Council Approval 2/20/18
CONSULTANT AGREEMENT FOR
BUILDING ENVELOPE CONSULTING SERVICES
THIS AGREEMENT is entered into between the City of Tukwila, Washington, hereinafter
referred to as "the City", and JRS Engineering, hereinafter referred to as "the Consultant", in
consideration of the mutual benefits, terms, and conditions hereinafter specified.
1. Project Designation. The Consultant is retained by the City to perform building envelope
consulting services in connection with the project titled Public Safety Plan, Fire Stations 51,
52, 54 and Justice Center.
2. Scope of Services. The Consultant agrees to perform the services, identified on Exhibit "A"
attached hereto, including the provision of all labor, materials, equipment and supplies.
3. Duration of Agreement; Time for Performance. This Agreement shall be in full force and
effect for a period commencing upon execution and ending July 2019, unless sooner
terminated under the provisions hereinafter specified. Work under this Agreement shall
commence upon written notice by the City to the Consultant to proceed. The Consultant
shall perform all services and provide all work product required pursuant to this Agreement
no later than July 2019 unless an extension of such time is granted in writing by the City.
4. Payment. The Consultant shall be paid by the City for completed work and for services
rendered under this Agreement as follows:
A. Payment for the work provided by the Consultant shall be made as provided on Exhibit
"B" attached hereto, provided that the total amount of payment to the Consultant shall
not exceed $80,000 including reimbursable expenses without express written
modification of the Agreement signed by the City.
B. The Consultant may submit vouchers to the City once per month during the progress of
the work for partial payment for that portion of the project completed to date. Such
vouchers will be checked by the City and, upon approval thereof, payment shall be
made to the Consultant in the amount approved.
C. Final payment of any balance due the Consultant of the total contract price earned will
be made promptly upon its ascertainment and verification by the City after the
completion of the work under this Agreement and its acceptance by the City.
D. Payment as provided in this section shall be full compensation for work performed,
services rendered, and for all materials, supplies, equipment and incidentals necessary
to complete the work.
E. The Consultant's records and accounts pertaining to this Agreement are to be kept
available for inspection by representatives of the City and the state of Washington for a
period of three (3) years after final payments. Copies shall be made available upon
request.
/6t.,1on16//v1)LS
5. Ownership and Use of Documents. All documents, drawings, specifications and other
materials produced by the Consultant in connection with the services rendered under this
Agreement shall be the property of the City whether the project for which they are made is
executed or not. The Consultant shall be permitted to retain copies, including reproducible
copies, of drawings and specifications for information, reference and use in connection with
the Consultant's endeavors. The Consultant shall not be responsible for any use of the said
documents, drawings, specifications or other materials by the City on any project other than
the project specified in this Agreement.
6. Compliance with Laws. The Consultant shall, in performing the services contemplated by
this Agreement, faithfully observe and comply with all federal, state, and local laws,
ordinances and regulations, applicable to the services rendered under this Agreement.
7. Indemnification. The Consultant shall defend, indemnify and hold the City, its officers,
officials, employees and volunteers harmless from any and all claims, injuries, damages,
losses or suits including attorney fees, arising out of or resulting from the acts, errors or
omissions of the Consultant in performance of this Agreement, except for injuries and
damages caused by the sole negligence of the City.
Should a court of competent jurisdiction determine that this Agreement is subject to RCW
4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or
damages to property caused by or resulting from the concurrent negligence of the
Consultant and the City, its officers, officials, employees, and volunteers, the Consultant's
liability hereunder shall be only to the extent of the Consultant's negligence. It is further
specifically and expressly understood that the indemnification provided herein constitutes the
Consultant's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the
purposes of this indemnification. This waiver has been mutually negotiated by the parties.
The provisions of this section shall survive the expiration or termination of this Agreement.
8. Insurance. The Consultant shall procure and maintain for the duration of the Agreement,
insurance against claims for injuries to persons or damage to property which may arise from
or in connection with the performance of the work hereunder by the Consultant, its agents,
representatives, or employees. Consultant's maintenance of insurance as required by the
agreement shall not be construed to limit the liability of the Consultant to the coverage
provided by such insurance, or otherwise limit the City's recourse to any remedy available at
law or in equity.
A. Minimum Amounts and Scope of Insurance. Consultant shall obtain insurance of the
types and with the limits described below:
1. Automobile Liability insurance with a minimum combined single limit for bodily
injury and property damage of $1,000,000 per accident. Automobile Liability
insurance shall cover all owned, non -owned, hired and leased vehicles.
Coverage shall be written on Insurance Services Office (ISO) form CA 00 01 or a
substitute form providing equivalent liability coverage. If necessary, the policy
shall be endorsed to provide contractual liability coverage.
2. Commercial General Liability insurance with limits no Tess than $1,000,000 each
occurrence, $2,000,000 general aggregate. Commercial General Liability
insurance shall be written on ISO occurrence form CG 00 01 and shall cover
liability arising from premises, operations, independent contractors and personal
injury and advertising injury. The City shall be named as an insured under the
Consultant's Commercial General Liability insurance policy with respect to the
work performed for the City.
3. Workers' Compensation coverage as required by the Industrial Insurance laws of
the State of Washington.
CA revised : 1-2013.
Page 2
4. Professional Liability with limits no Tess than $1,000,000 per claim and
$1,000,000 policy aggregate limit. Professional Liability insurance shall be
appropriate to the Consultant's profession.
B. Other Insurance Provision. The Consultant's Automobile Liability and Commercial
General Liability insurance policies are to contain, or be endorsed to contain that they
shall be primary insurance with respect to the City. Any Insurance, self-insurance, or
insurance pool coverage maintained by the City shall be excess of the Consultant's
insurance and shall not be contributed or combined with it.
C. Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M.
Best rating of not less than A:VII.
D. Verification of Coverage. Consultant shall furnish the City with original certificates and
a copy of the amendatory endorsements, including but not necessarily limited to the
additional insured endorsement, evidencing the insurance requirements of the
Consultant before commencement of the work. Certificates of coverage and
endorsements as required by this section shall be delivered to the City within fifteen (15)
days of execution of this Agreement.
E. Notice of Cancellation. The Consultant shall provide the City with written notice of any
policy cancellation, within two business days of their receipt of such notice.
F. Failure to Maintain Insurance. Failure on the part of the Consultant to maintain the
insurance as required shall constitute a material breach of contract, upon which the City
may, after giving five business days notice to the Consultant to correct the breach,
immediately terminate the contract or, at its discretion, procure or renew such insurance
and pay any and all premiums in connection therewith, with any sums so expended to be
repaid to the City on demand, orr at the sole discretion of the City, offset against funds
due the Consultant from the City.
9. Independent Contractor. The Consultant and the City agree that the Consultant is an
independent contractor with respect to the services provided pursuant to this Agreement.
Nothing in this Agreement shall be considered to create the relationship of employer and
employee between the parties hereto. Neither the Consultant nor any employee of the
Consultant shall be entitled to any benefits accorded City employees by virtue of the services
provided under this Agreement. The City shall not be responsible for withholding or
otherwise deducting federal income tax or social security or for contributing to the state
industrial insurance program, otherwise assuming the duties of an, employer with respect to
the Consultant, or any employee of the Consultant.
10. Covenant Against Contingent Fees. The Consultant warrants that he has not employed or
retained any company or person, other than a bonafide employee working solely for the
Consultant, to solicit or secure this contract, and that he has not paid or agreed to pay any
company or person, other than a bonafide employee working solely for the Consultant, any
fee, commission, percentage, brokerage fee, gifts, or any other consideration contingent
upon or resulting from the award or making of this contract. For breach or violation of this
warrant, the City shall have the right to annul this contract without liability, or in its discretion
to deduct from the contract price or consideration, or otherwise recover, the full amount of
such fee, commission, percentage, brokerage fee, gift, or contingent fee.
11. Discrimination Prohibited. The Consultant, with regard to the work performed by it under
this Agreement, will not discriminate on the grounds of race, religion, creed, color, national
origin, age, veteran status, sex, sexual orientation, gender identity, marital status, political
affiliation or the presence of any disability in the selection and retention of employees or
procurement of materials or supplies.
-CA revised : V2013
Page 3
12. Assignment. The Consultant shall not sublet or assign any of the services covered by this
Agreement without the express written consent of the City.
13. Non -Waiver. Waiver by the City of any provision of this Agreement or any time limitation
provided for in this Agreement shall not constitute a waiver of any other provision.
14. Termination.
A. The City reserves the right to terminate this Agreement at any time by giving ten (10)
days written notice to the Consultant.
B. In the event of the death of a member, partner or officer of the Consultant, or any of its
supervisory personnel assigned to the project, the surviving members of the Consultant
hereby agree to complete the work under the terms of this Agreement, if requested to
do so by the City. This section shall not be a bar to renegotiations of this Agreement
between surviving members of the Consultant and the City, if the City so chooses.
15. Applicable Law; Venue; Attorney's Fees. This Agreement shall be subject to, and the
Consultant shall at all times comply with, all applicable federal, state and local laws,
regulations, and rules, including the provisions of the City of Tukwila Municipal Code and
ordinances of the City of Tukwila. In the event any suit, arbitration, or other proceeding is
instituted to enforce any term of this Agreement, the parties specifically understand and
agree that venue shall be properly laid in King County, Washington. The prevailing party in
any such action shall be entitled to its attorney's fees and costs of suit. Venue for any action
arising from or related to this Agreement shall be exclusively in King County Superior Court.
16. Severabilitv and Survival. If any term, condition or provision of this Agreement is declared
void or unenforceable or limited in its application or effect, such event shall not affect any
other provisions hereof and all other provisions shall remain fully enforceable. The
provisions of this Agreement, which by their sense and context are reasonably intended to
survive the completion, expiration or cancellation of this Agreement, shall survive termination
of this Agreement.
17. Notices. Notices to the City of Tukwila shall be sent to the following address:
City Clerk
City of Tukwila
6200 Southcenter Boulevard
Tukwila, WA 98188
Notices to Consultant shall be sent to the following address:
Jeff Speert
JRS Engineering
12721 30th Avenue NE, Suite 200
Seattle, WA 98125
18. Entire Agreement; Modification. This Agreement, together with attachments or addenda,
represents the entire and integrated Agreement between the City and the Consultant and
supersedes all prior negotiations, representations, or agreements written or oral. No
amendment or modification of this Agreement shall be of any force or effect unless it is in
writing and signed by the parties.
CA revised : 1-2013
Page 4
DATED this
CITY OF TUKWILA
day of
Allan Ekberg, Mayor
Attest/Authenticated:
ty6;14
FaCit Cler Chris O'heYOffice of the CityAttorney
CONSULTANT
By:
Printed Name: &re 4 JVe,Pr_
Title: rei g G 1413.064-.-
, 2o I
?4L.
,2oI
Approved as to Form:
CA revised : 1=2013
Page 5
ilk , BUILDING EXCELLENCE
EXHIBIT A I
PAGE 7 OF 10
6.0 AVAILABILITY AND CAPACITY
The JRS staff proposed for this project have the capacity to complete design reviews and construction
administration that follows as described in the schedule outlined in the RFP. All technical staff reside in the
greater Seattle area. JRS Seattle may draw on support from the Vancouver or Calgary offices to address any
specific technical issues or for administrative assistance.
7.0 PRICING
Pricing for services for each of the 4 projects included in the RFP are below. A general description of the tasks
undertaken within each phase are as follows:
Design Development: In this phase, JRS will develop the accepted conceptual design in sufficient detail to
allow the project team to start producing more detailed documents. We will complete the following
• Perform a technical review of Schematic Design drawings. Provide comments and mark-ups to the
Architect, identifying key areas requiring attention and highlighting issues and areas of discussion for
the project team. Update conceptual recommendations for enclosure assemblies and materials
• Attend design meetings, including one at the start of our work and one following a technical review.
• Review the overall durability of building envelope elements considering required maintenance,
renewals, and service life.
• Help determine the efficient layering of building envelope elements to help simplify future repairs and
replacements.
• Review project materials' compatibility and resistance to various mechanisms of deterioration given
their nature, function, and exposure.
• Review HVAC recommendations and energy modeling, identify relevant building envelope
coordination items, and recommend solutions.
• Produce an Enclosure Basis of Design report for use and consideration by the Owner and Architect.
Construction Documents: JRS will meet and coordinate with the project team, and attend design and
construction team meetings as needed. We will review the Architect's construction documents for consistency
with building envelope performance criteria established during earlier phases.
• Perform technical reviews of Design Development drawings, including comments and mark-ups.
Confirming Design Development phase recommendations and developing alternatives, if necessary due
to budget and constructability constraints.
• Revise the Enclosure Basis of Design report as needed.
• Review Construction Documents for building science good practice for consistency with the enclosure
basis for design. Produce marked up drawings and specifications with accompanying report for
consideration by owner and architect.
Bidding Assistance: JRS will perform the following services as -needed:
• Respond to bidder questions and substitution requests.
• Assist in leveling of bids.
• Review and respond to value engineering suggestions made by the General Contractor (GC) and
subcontractors.
Submittal and RFI Review: JRS will review building enclosure shop drawings and submittals for conformance
with established design concepts. We will assess design concepts for water resistance, air tightness and
thermal performance — both within each system and at integration points between different building systems.
RFIs will be reviewed and answered to resolve issues consistent with the enclosure design intent.
WWW.JRSENGINEERING.COM
BUILDING EXCELLENCE
PAGE 8 OF 10
Pre -Installation Meeting: JRS will attend pre -construction meetings for critical envelope components on
site with the Owner, Architect, GC, Installer, and Manufacturer's Representative to review site conditions,
site-specific detail concerns, and installation procedures. We will provide comments to the GC for inclusion
in meeting minutes.
Mock-up Observation: We typically recommend mock-ups for critical and common components on
projects. This commonly includes windows and other wall penetrations
• Attend building envelope related mock-ups to review installation of building envelope systems, and
evaluate their conformance with construction documents and industry good practice.
• Provide recommendations to help resolve unforeseen conditions that may arise at mock-ups.
• Document mock-ups in Field Review Reports.
Field Reviews: JRS will attend the site to review ongoing installation of envelope components
• At agreed-upon intervals, perform site visits to review in -progress installation of building envelope
components and assemblies.
• The intent of field reviews is to periodically compare observable in -progress building envelope
component installation with architectural drawings, pertinent specifications, shop drawings, and
mock-ups.
• Document field reviews in written reports. Review items requiring action with site staff prior to leaving
site.
• Track Action Items arising from field reviews using our customized searchable database. Provide Action
Item lists to the GC and construction team periodically during the course of construction, to address
open items.
• Reports are issued 24 hours after completion of review
Window Testing: Although not required by code, water penetration resistance testing on installed window
systems is considered good practice. JRS will review selected window/wall areas and perform testing in
accordance with ASTM E-1 105-00, using a calibrated rain rack and depressurizing the interior space to an
appropriate level, as outlined in the specifications or applicable codes and standards. Temporary enclosure
and a laborer, if required, are to be provided by others.
A report for each test will be prepared outlining test protocol, describing observations, and where
appropriate, presenting suggestions for possible modifications or improvements.
Air Barrier Testing: JRS will conduct a field test of the entire building, or a portion thereof, in compliance
with the 2015 Washington State Energy Code Section C402.4 — Air Leakage (Mandatory). JRS will provide
the personnel and equipment required to perform this testing, and will prepare and deliver a written report
of test results and findings. Building setup and preparation assistance from the Contractor will be necessary.
Prior to testing, JRS will meet with the Contractor on site to coordinate and develop a detailed list of setup
and preparation tasks.
WWW.JRSENGINEERING.COM
BUILDING EXCELLENCE
EXHIBIT B
PAGE 9 OF 10
Fire Station 51
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
(Design Development
2 meetings)
;1 review)
(24
240)
_$3, i
($50)
(Construction Documents)
(Construction Documents
.._ ..._
_ 2 meetings)
(2 reviews)
(51
$6,750
$100)
- -�
(Bidding Assistance ___J
___ _ Assist in answering)
(Bidder questions)
(..§_ _ _
_ _ $810
_�$)
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related documents
30
$4,050
$0
Pre -installation
meetings
2 meetings on site
14
$1,890
$100
Mock-up observations
1 mock-up
8
$1,080
$50
Field review
15 visits (assumes 3/month)
115
$15,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$3,800
$0
SUBTOTAL
SUBTOTAL
248
$39,945*
$700
*Assumes 2 window tests completed in the same clay.
Fire Station 52
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
Design Development)
(2 meetings)
(1 review)
O0
$4,050
` $59)
(Construction Documents)
(2 meetings)
(2 reviews)
(.4_:__.._5
_ ` $_8,775 -
�_
_ $i 00)
(Bidding Assistance)
(Assist in answering)
Bidder questions
_ $810
__ _ $0)
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related
documents
35
$4,725
$0
Pre -installation
meetings
2 meetings on site
14
$1,890
$100
Mock-up observations
1 mock-up
8
$1,080
$50
Field review
21 visits (assumes 3/month)
134
$18,000
$475
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$4,300
$0
SUBTOTAL
292
$46,430*
$775
*Assumes 2 window tests completed in the same day.
WWW.JRSENGINEERING.COM
font BUILDING EXCELLENCE
PAGE 10 OF 10
Fire Station 54
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
(Design Development
�-
_ _ 2 meetings;
(1 review;
(4 `
_ _ $3_,240 _
_ $50)
(Construction Documents
2 meetings;
(2 reviews
(51
$6,750
$100)
(2 reviews)
(Bidding Assistance
_ Assist in answering)
Bidder questions
(
$810 _
$_0)
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related documents
30
$4,050
$0
Pre -installation
meetings
2 meetings on site
14
$1,890
$100
Mock-up observations
1 mock-up
8
$1,080
$50
Field review
18 visits (assumes 3/month)
115
$15,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$3,800
$0
SUBTOTAL
$0
248
$39,945*
$700
*Assumes 2 window tests completed in the same day.
Justice Center
Phase/Title
Quantity/
Description
Anticipated
Hours
Anticipated
Hourly Rate
Costs
Reimbursables
(Design Development__
2 meetings)
(1 review)
(35 _ _ _
_ $4,725
V �_
$50)
(Construction Documents
3 meetings
(60 _
$8,100
��
$150)
__
(2 reviews)
(Bidding Assistance_
_ Assist in answering)
%Bidder questions)
(6
$810
$o.)
Submittal and RFI
reviews
Review of submittals,
RFIs, ASIs and related documents
50
$6,750
$0
Pre -installation
meetings
3 meetings on site
21
$2,835
$100
Mock-up observations
2 mock-ups
16
$2,160
$50
Field review
18 visits (assumes 3/month)
115
$15,525
$400
Window Testing
First test per day
Additional test (completed same
day)
-
$2,000
$800
$0
Air barrier testing
1 test
-
$7,100
$0
SUBTOTAL
303
$50,805*
$750
*Assumes 2 window tests completed in the same day.
- Composite Hourly Rate is $135/hour
- Contracts will be awarded on a time -and -material basis by hourly rates.
TOTAL
1,091
$177,125
$2,925
(Including exterior walls and roof systems)
WWW.JRSENGINEERING.COM
$49,530