HomeMy WebLinkAboutReg 2018-04-02 Item 4D - Agreement - Andover Park East Water and Sewer Replacement with AECOM for $90,000COUNCIL AGENDA SYNOPSIS
Initials
MeetingDate
Prepared by
Mayor's review
Council rep/en'
04/02/18
HH
Motion
Date 04/02/18
El Resolution
Mg Dote
Ordinance
ANDate
E] Bid /1 ward
Ally Date
['Public hearing
Ally Date
0 Other
Nits Date
Alto
SPONSOR Council Mayor El HR II] DC!) Finance Fire IT P&R Police [Z] Pilo
SPONSOR'S Original Contract No. 16-103 with AECOM Technical Services provided construction
SUMMARY management services for the Andover Park East Water and Sewer Replacement Project.
Due to several issues during construction and to complete the closeout of the project, a
new construction management contract is needed with AECOM. Council is being asked to
approve AECOM's additional CM contract in the amount of $90,000.00.
Ri,NIFAVI,;D BY COW Mtg. El CA&P Cmte El F&S Cmte
El Utilities Cmte []Arts Comm. []Parks Comm.
DATE: 03/26/18 COMMITTEE CHAIR: THOMAS
Fri Transportation
Cmte
El Planning Comm.
MCLEOD
RECOMMENDATIONS:
SPoNsoR/ADNIIN.
C()mmiTridi
ITEM INFORMATION
ITEM No.
4.D.
STAFF SPONSOR: HENRY HASH
ORIGINAL AGENDA DATE: 04/02/18
AGENDA ITEM TITLE Andover Park East Water and Sewer Replacement Project
Construction Management Agreement with AECOM Technical Services
C,v11:(;()RY Discussion
AN Date
1
Motion
Date 04/02/18
El Resolution
Mg Dote
Ordinance
ANDate
E] Bid /1 ward
Ally Date
['Public hearing
Ally Date
0 Other
Nits Date
Alto
SPONSOR Council Mayor El HR II] DC!) Finance Fire IT P&R Police [Z] Pilo
SPONSOR'S Original Contract No. 16-103 with AECOM Technical Services provided construction
SUMMARY management services for the Andover Park East Water and Sewer Replacement Project.
Due to several issues during construction and to complete the closeout of the project, a
new construction management contract is needed with AECOM. Council is being asked to
approve AECOM's additional CM contract in the amount of $90,000.00.
Ri,NIFAVI,;D BY COW Mtg. El CA&P Cmte El F&S Cmte
El Utilities Cmte []Arts Comm. []Parks Comm.
DATE: 03/26/18 COMMITTEE CHAIR: THOMAS
Fri Transportation
Cmte
El Planning Comm.
MCLEOD
RECOMMENDATIONS:
SPoNsoR/ADNIIN.
C()mmiTridi
Public Works Department
Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITt IRE RI QUIR1 D AMOUNT BUDGETED APPROPRIATION REQUIRED
$90,000.00 $640,000.00 $0.00
Fund Source: 401 WATER & 402 SEWER FUNDS (PAGES 60 & 77, 2017 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
04/02/18
MTG. DATE
ATTACHMENTS
04/02/18
Informational Memorandum dated 03/23/18
2017 CIP, pages 60 & 77
AECOM's Construction Management Agreement
Minutes from the Transportation & Infrastructure Committee meeting of 03/26/18
_ _
38
11111111111111111114111
11111111111111111111111111111111
City of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Transportation & Infrastructure Committee
FROM: Henry Hash, Public Works Director
BY: Michael Ronda, Project Manager - Construction
CC: Mayor Ekberg
DATE: March 23, 2018
SUBJECT: Andover Park East Water and Sewer Replacement
Project Numbers 99940103 & 91440204
Construction Management Contract with AECOM
ISSUE
Approve a new Construction Management (CM) contract with AECOM Technical Services for CM
support to close the Andover Park East (APE) Water and Sewer Replacement Project.
BACKGROUND
Council awarded the construction management contract for the APE Water and Sewer
Replacement Project to AECOM in August 2016 for $532,893.84. Several issues were discovered
during construction which were not included in the original CM scope of services. These issues
extended the completion date of the contract and required that additional CM resources be
dedicated to the management effort. In the closeout process the punchlist activity by the contractor
extended past the original CM contract completion date. Now that the construction activities appear
to be complete, a new CM contract is required to finalize the payments and close out the project.
DISCUSSION & FISCAL IMPACT
To complete the construction management effort, the AECOM CM team will require additional time
and resources to close out the remaining paperwork and resolve negotiated payment items. The
total additional fee for this contract is $90,000.00. With this contract, the CM budget will be
allocated as follows:
AECOM Original CM Contract
AECOM Closeout CM Contract
APE Water/Sewer Replacement CM Budget
Total
CM Expense
$532,893.84
90,000.00
$622,893.84
Budget
$640,000.00
$640,000.00
RECOMMENDATION
Council is being asked to approve the Construction Management Contract with AECOM in the
amount of $90,000.00 and consider this item on the Consent Agenda at the April 2, 2018 Regular
Council Meeting.
Attachments: Pages 60 & 77, 2017 CIP
CM Consultant Services Contract Scope and Fee with AECOM
W:\PW Eng \ PROJECTS A- WT Projects\APE Water Main Replacement (99940103)\Consultant Selection \(010) - CM Scope And Encumbrances\AECOM\New CM Contract \Info Memo AECOM CM Contract 030818.Docx
39
40
PROJECT:
DESCRIPTION:
JUSTIFICATION:
STATUS:
MAINT. IMPACT:
COMMENT:
FINANCIAL
(in 3000'sl
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
Andover Park E Water Main Replacement Project No. 99940103
Design and construct 2,700 LF of new 8" & 16" ductile iron pipe along Andover Park East from Tukwila Pkwy
to Strander Blvd.
Support future growth within this area of the CBD as aging cast iron system has suffered frequent failures.
Survey and design is complete. Construction is scheduled for 2016 from Strander Blvd to Tukwila Pkwy
with final paving in 2017.
A new pipe will significantly reduce impact on crews from the risk of cataclysmic events.
PWTF loans were rescinded in 2014 & 2015 by the State Legislature.
Through Estimated
2015 2016 2017
2018
2019
2020
2021
2022
BEYOND TOTAL
EXPENSES
1 Project Locati
,���I
S
I 4'�
Design
140
59
Ir
Ica
[
L!d
s 96fY
gg
M1 rw.rwMd
GIS
199
Land (RNV)
0
Const. Mgmt.
284
100
384
Construction
2,100
685
2,785
TOTAL EXPENSES
140
2,443
785
0
0
0
0
0
0
3,368
FUND SOURCES
Awarded Grant
0
Proposed Bond
0
Mitigation Actual
0
Mitigation Expected
0
Utility Revenue
140
2,443
785
0
0
0
0
0
0
3,368
I
TOTAL SOURCES
140
2,443
785
0
Q
0
0
0
0 'I
3,368
2017 - 2022 Capital Improvement Program
60
41
1 Project Locati
,���I
S
I 4'�
h
II
f "
V
Ir
Ica
[
L!d
s 96fY
gg
M1 rw.rwMd
GIS
2017 - 2022 Capital Improvement Program
60
41
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Andover Park East Sewer Replacement Project No. 91440204
DESCRIPTION: Design and construct 1,600 LF of 15" and 12" sanitary sewer from Strander Blvd. to 1-405 in Andover Park E.
JUSTIFICATION: Sewer improvement will provide additional capacity for future development along Andover Park East.
STATUS: Project will overlay Andover Park East from Strander Blvd to 1-405 in 2017.
MAINT. IMPACT:
COMMENT: Construction is scheduled for 2016 from Strander Blvd to Tukwila Parkway.
FINANCIAL Through Estimated
5 2016 2017
2018
2019
2020
2021
2022
BEYOND TOTAL
EXPENSES
Design
47
43
90
Land (RJ\P
0
Const. Mgmt.
206
50
256
Construction
1,626
! 500
2,126
TOTAL EXPENSES
47
1,875
550
0
0
0
0
0
0
2,472
FUND SOURCES
Awarded Grant
0
Proposed PWTF/Bond
0
Mitigation Actual
0
Mitigation Expected
290
290
Utility Revenue
47
1,585
550
0
0
0
0
0
0
2,182
TOTAL SOURCES
47
1,875
550
0
0
0
0
0
0
2,472
2017 - 2022 Capital Improvement Program
42
77
City of Tukwila
6200 Southcenter Boulevard, Tukwila WA 98188
Contract Number:16-103
CONSULTANT AGREEMENT FOR
CONSTRUCTION MANAGEMENT SERVICES
THIS AGREEMENT is entered into between the City of Tukwila, Washington, hereinafter
referred to as "the City", and AECOM Technical Services, hereinafter referred to as "the Consultant",
in consideration of the mutual benefits, terms, and conditions hereinafter specified.
1. Project Designation. The Consultant is retained by the City to perform construction
management services in connection with the project titled `Andover Park East Water Main
and Sewer Replacements'.
2. Sco • e of Services. The Consultant agrees to perform the services, identified on Exhibit "A-
1" attached hereto, including the provision of all labor, materials, equipment and supplies.
3. Duration of Agreement; Time for Performance. This Agreement shall be in full force and
effect for a period commencing upon execution and ending June 30, 2018, unless sooner
terminated under the provisions hereinafter specified. Work under this Agreement shall
commence upon written notice by the City to the Consultant to proceed. The Consultant
shall perform all services and provide all work product required pursuant to this Agreement
no later than June 30, 2018 unless an extension of such time is granted in writing by the City.
4. Payment. The Consultant shall be paid by the City for completed work and for services
rendered under this Agreement as follows:
A. Payment for the work provided by the Consultant shall be made as provided on Exhibit
"B" attached hereto, provided that the total amount of payment to the Consultant shall
not exceed $90,000.00 without express written modification of the Agreement signed by
the City.
B. The Consultant may submit vouchers to the City once per month during the progress of
the work for partial payment for that portion of the project completed to date. Such
vouchers will be checked by the City and, upon approval thereof, payment shall be
made to the Consultant in the amount approved.
C. Final payment of any balance due the Consultant of the total contract price earned will
be made promptly upon its ascertainment and verification by the City after the
completion of the work under this Agreement and its acceptance by the City.
D. Payment as provided in this section shall be full compensation for work performed,
services rendered, and for all materials, supplies, equipment and incidentals necessary
to complete the work.
E. The Consultant's records and accounts pertaining to this Agreement are to be kept
available for inspection by representatives of the City and the state of Washington for a
period of three (3) years after final payments. Copies shall be made available upon
request.
43
5. Ownership and Use of Documents. All documents, drawings, specifications and other
materials produced by the Consultant in connection with the services rendered under this
Agreement shall be the property of the City whether the project for which they are made is
executed or not. The Consultant shall be permitted to retain copies, including reproducible
copies, of drawings and specifications for information, reference and use in connection with
the Consultant's endeavors. The Consultant shall not be responsible for any use of the said
documents, drawings, specifications or other materials by the City on any project other than
the project specified in this Agreement.
6. Compliance with Laws. The Consultant shall, in performing the services contemplated by
this Agreement, faithfully observe and comply with all federal, state, and local laws,
ordinances and regulations, applicable to the services rendered under this Agreement.
7. Indemnification. The Consultant shall defend, indemnify and hold the City, its officers,
officials, employees and volunteers harmless from any and all claims, injuries, damages,
losses or suits including attorney fees, arising out of or resulting from the acts, errors or
omissions of the Consultant in performance of this Agreement, except for injuries and
damages caused by the sole negligence of the City.
Should a court of competent jurisdiction determine that this Agreement is subject to RCW
4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or
damages to property caused by or resulting from the concurrent negligence of the Consultant
and the City, its officers, officials, employees, and volunteers, the Consultant's liability
hereunder shall be only to the extent of the Consultant's negligence. It is further specifically
and expressly understood that the indemnification provided herein constitutes the
Consultant's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the
purposes of this indemnification. This waiver has been mutually negotiated by the parties.
The provisions of this section shall survive the expiration or termination of this Agreement.
8. Insurance. The Consultant shall procure and maintain for the duration of the Agreement,
insurance against claims for injuries to persons or damage to property which may arise from
or in connection with the performance of the work hereunder by the Consultant, its agents,
representatives, or employees. Consultant's maintenance of insurance as required by the
agreement shall not be construed to limit the liability of the Consultant to the coverage
provided by such insurance, or otherwise limit the City's recourse to any remedy available at
law or in equity.
A. Minimum Amounts and Scope of Insurance. Consultant shall obtain insurance of the
types and with the limits described below:
1. Automobile Liability insurance with a minimum combined single limit for bodily
injury and property damage of $1,000,000 per accident. Automobile Liability
insurance shall cover all owned, non -owned, hired and leased vehicles.
Coverage shall be written on Insurance Services Office (ISO) form CA 00 01 or a
substitute form providing equivalent liability coverage. If necessary, the policy
shall be endorsed to provide contractual liability coverage.
2. Commercial General Liability insurance with limits no less than $1,000,000 each
occurrence, $2,000,000 general aggregate. Commercial General Liability
insurance shall be written on ISO occurrence form CG 00 01 and shall cover
liability arising from premises, operations, independent contractors and personal
injury and advertising injury. The City shall be named as an insured under the
Consultant's Commercial General Liability insurance policy with respect to the
work performed for the City.
3. Workers' Compensation coverage as required by the Industrial Insurance laws of
the State of Washington.
CA revised : 1-2013
44
Page 2
4. Professional Liability with limits no less than $1,000,000 per claim and $1,000,000
policy aggregate limit. Professional Liability insurance shall be appropriate to the
Consultant's profession.
B. Other Insurance Provision. The Consultant's Automobile Liability and Commercial
General Liability insurance policies are to contain, or be endorsed to contain that they
shall be primary insurance with respect to the City. Any Insurance, self-insurance, or
insurance pool coverage maintained by the City shall be excess of the Consultant's
insurance and shall not be contributed or combined with it.
C. Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M.
Best rating of not less than A:VII.
D. Verification of Coverage. Consultant shall furnish the City with original certificates and
a copy of the amendatory endorsements, including but not necessarily limited to the
additional insured endorsement, evidencing the insurance requirements of the Consultant
before commencement of the work. Certificates of coverage and endorsements as
required by this section shall be delivered to the City within fifteen (15) days of execution
of this Agreement.
E. Notice of Cancellation. The Consultant shall provide the City with written notice of any
policy cancellation, within two business days of their receipt of such notice.
F. Failure to Maintain Insurance. Failure on the part of the Consultant to maintain the
insurance as required shall constitute a material breach of contract, upon which the City
may, after giving five business days notice to the Consultant to correct the breach,
immediately terminate the contract or, at its discretion, procure or renew such insurance
and pay any and all premiums in connection therewith, with any sums so expended to be
repaid to the City on demand, or at the sole discretion of the City, offset against funds
due the Consultant from the City.
9. Independent Contractor. The Consultant and the City agree that the Consultant is an
independent contractor with respect to the services provided pursuant to this Agreement.
Nothing in this Agreement shall be considered to create the relationship of employer and
employee between the parties hereto. Neither the Consultant nor any employee of the
Consultant shall be entitled to any benefits accorded City employees by virtue of the services
provided under this Agreement. The City shall not be responsible for withholding or
otherwise deducting federal income tax or social security or for contributing to the state
industrial insurance program, otherwise assuming the duties of an employer with respect to
the Consultant, or any employee of the Consultant.
10. Covenant A• ainst Contin • ent Fees. The Consultant warrants that he has not employed or
retained any company or person, other than a bonafide employee working solely for the
Consultant, to solicit or secure this contract, and that he has not paid or agreed to pay any
company or person, other than a bonafide employee working solely for the Consultant, any
fee, commission, percentage, brokerage fee, gifts, or any other consideration contingent
upon or resulting from the award or making of this contract. For breach or violation of this
warrant, the City shall have the right to annul this contract without liability, or in its discretion
to deduct from the contract price or consideration, or otherwise recover, the full amount of
such fee, commission, percentage, brokerage fee, gift, or contingent fee.
11. Discrimination Prohibited. The Consultant, with regard to the work performed by it under
this Agreement, will not discriminate on the grounds of race, religion, creed, color, national
origin, age, veteran status, sex, sexual orientation, gender identity, marital status, political
affiliation or the presence of any disability in the selection and retention of employees or
procurement of materials or supplies.
12. Assignment. The Consultant shall not sublet or assign any of the services covered by this
Agreement without the express written consent of the City.
CA revised : 1-2013
Page 3
45
13. Non -Waiver. Waiver by the City of any provision of this Agreement or any time limitation
provided for in this Agreement shall not constitute a waiver of any other provision.
14. Termination.
A. The City reserves the right to terminate this Agreement at any time by giving ten (10)
days written notice to the Consultant.
B. In the event of the death of a member, partner or officer of the Consultant, or any of its
supervisory personnel assigned to the project, the surviving members of the Consultant
hereby agree to complete the work under the terms of this Agreement, if requested to do
so by the City. This section shall not be a bar to renegotiations of this Agreement
between surviving members of the Consultant and the City, if the City so chooses.
15. Applicable Law; Venue; Attorney's Fees. This Agreement shall be subject to, and the
Consultant shall at all times comply with, all applicable federal, state and local laws,
regulations, and rules, including the provisions of the City of Tukwila Municipal Code and
ordinances of the City of Tukwila. In the event any suit, arbitration, or other proceeding is
instituted to enforce any term of this Agreement, the parties specifically understand and
agree that venue shall be properly laid in King County, Washington. The prevailing party in
any such action shall be entitled to its attorney's fees and costs of suit. Venue for any action
arising from or related to this Agreement shall be exclusively in King County Superior Court.
16. Severability and Survival. If any term, condition or provision of this Agreement is declared
void or unenforceable or limited in its application or effect, such event shall not affect any
other provisions hereof and all other provisions shall remain fully enforceable. The
provisions of this Agreement, which by their sense and context are reasonably intended to
survive the completion, expiration or cancellation of this Agreement, shall survive termination
of this Agreement.
17. Notices. Notices to the City of Tukwila shall be sent to the following address:
City Clerk
City of Tukwila
6200 Southcenter Boulevard
Tukwila, WA 98188
Notices to Consultant shall be sent to the following address:
AECOM Technical Services
710 5th Avenue, Suite 1000
Seattle, WA 98004
18. Entire Agreement; Modification. This Agreement, together with attachments or addenda,
represents the entire and integrated Agreement between the City and the Consultant and
supersedes all prior negotiations, representations, or agreements written or oral. No
amendment or modification of this Agreement shall be of any force or effect unless it is in
writing and signed by the parties.
CA revised : 1-2013
46
Page 4
DATED this day of , 20
CITY OF TUKWILA CONSULTANT
Allan Ekberg, Mayor
By:
(:)
, f
Printe&Name: 1/1(1
Title: '0.1 V VW fid 4'4) r
Attest/Authenticated: Approved as to Form:
City Clerk, Christy O'Flaherty
CA revised : 1-2013
Office of the City Attorney
Page 5
47
48
Andover Park East
City of Tukwila
Exhibit A-1
SCOPE OF SERVICES
Construction Management and Contract Administration Services for the
Andover Park East Water Main and Sewer Replacements
City of Tukwila
AECOM Technical Services, Inc. ("Consultant") proposes to provide to the City of Tukwila, Washington
("Client") construction management services for the Andover Park East (APE) Water Main and Sewer
Replacement Project (hereinafter called "Project"). These services will include inspection, construction
management, and contract administration assistance for the project as detailed in the following:
I. INTRODUCTION
The following scope of services is based upon the assumptions outlined herein. Associated costs are
detailed in EXHIBIT B- Rev 1.
Assumptions:
• Services will be performed in accordance with the Local Agency Guidelines (LAG) and the WSDOT
Construction Manual.
• Design by Others: It is understood and agreed that the Consultant did not prepare the Contract
Documents for the project, and the Client will provide the Consultant the support of the Engineer -of -
Record during the course of the Consultant's work.
I. DETAILED SCOPE OF WORK
Subtask 1 — Administration/Quality Control
Consistent with the hours shown in EXHIBIT B — Rev 1, the Consultant shall provide overall project
management and contract administration associated with the service agreement between the Consultant
and the Client. This effort will include the following elements:
1.1 Prepare of Consultant invoicing and progress reporting to the Client.
1.2 Perform internal administration of the Consultant's Task Order.
1.3 Prepare any supplements to the Consultant's Task Order.
1.4 Make periodic field visits and conduct project reviews for the quality of services provided by
AECOM and consistency with AECOM's project quality plan.
Subtask 2 — Document Control
Consistent with the hours shown in EXHIBIT B - Rev 1, the Consultant shall provide document control
services including the following elements:
2.1 Process; track and archive construction records including: Inspectors Daily Reports (IDR's);
Requests for Information (RFI's); Submittals; Requests for Approval of Materials (RAM's);
Statements of Working Days. Consultant shall maintain submittal and RFI logs to track when
documents are received and returned to the contractor.
2.2 Compile and review inspector pay quantity and force account records, and prepare monthly
contractor progress pay estimates.
2.3 Review and archive project record documentation associated with prevailing wage reporting,
including Requests to Sublet, Intents to Pay Prevailing Wage, Certified Payroll, Affidavits of
Wages Paid, and Contractor employee wage interviews.
Page 1 of 5
Updated: 3/5/2018
49
Andover Park East
City of Tukwila
2.4 Review and archive Certificates of Materials Origin tracking and reconcile against the Projects
Record of Materials prepared by others.
2.5 Attend and provide minutes for up to 26 weekly contractor construction progress meetings.
2.6 Maintain a material testing log that tracks the test date, type of material test, test result,
specification requirement and action taken if a failed result is received from the material testing
consultant.
2.7 Maintain a list of approved change orders and potential change orders. Potential change orders
will have a force account estimate of the extra work related to that item(s), until an approved
change order is executed.
Subtask 3 — Field Inspection
The Consultant shall provide construction inspection services consistent with the hours shown in
EXHIBIT B - Rev 1. This effort will include the following elements:
3.1 Prepare daily construction reports recording the contractor's operations performed for each day
the Consultant is on site; measure the quantities of materials installed, log equipment and staff
present, weather conditions, and any observed problems or construction issues.
3.2 Prepare Daily Payment Notes, Statements of Working Days, and Force Account Records (if
necessary).
3.3 Respond to contractor questions which may arise as to the quality and acceptability of
furnished materials or work performed per the requirements of the construction contract
documents.
3.4 Respond to general questions raised by adjacent property owners, businesses, or general
public. Complaints or detailed questions shall be referred to the Client.
3.5 Prepare field records and documents in accordance with Projects Record of Materials.
3.6 Coordinate with Resident Engineer and Client for changes and updates to the ROM.
3.7 For each day the Consultant is on site, provide photographs of traffic control set-up and work
activities during the course of construction. Photographs will be in digital format and cataloged
by date.
3.8 Facilitate the Contractor's coordination with existing utilities within the project boundaries.
3.9 Review the Record of Materials (ROM) against the material testing results provided by the
Project's material testing consultant, and advise the Contractor accordingly.
3.10 Monitor the Contractor's compliance with water quality permits and the requirements of the
TESC and SPCC Plans.
3.11 Attend added weekly construction meetings due to extended contract time. (WORK
COMPLETE BUT UNPAID ADDED COSTS ARE INCLUDED)
3.12 The Construction Inspector shall review monthly pay estimates with the Contractor and provide
recommendations to the Resident Engineer and Client. (WORK COMPLETE BUT UNPAID
ADDITIONAL COSTS EXPENDED FOR THIS DUE TO ADDITIONAL PAY ESTIMATES ON
THE PROJECT IS INCLUDED)
3.13 Verify Contractor provided markups accuracy and forward to the Client. The Consultant
Inspector will track and record field changes on drawings and use this information to verify the
Contractor's construction record drawings.
3.14 Participate in the Project's final inspection and assist in developing a list of any remaining
deficiencies. (WORK COMPLETE BUT UNPAID COSTS ARE INCLUDED)
3.15 For the days present on site, the construction inspector shall observe day-to-day construction
activities. By providing inspection oversight, the Consultant shall assume no responsibility for
proper construction techniques or job site safety but will report to the Contractor and Client any
known public safety concerns immediately. The presence of the Consultant's personnel at the
Page 2 of 5
50
Updated: 3/5/2018
Andover Park East
City of Tukwila
construction site is for the purpose of providing to the Client a greater degree of confidence that
the completed work will generally conform to the Contract Documents and that the integrity of
the design concept as reflected in the Contract Documents has been implemented and
preserved by the Construction Contractor.
3.16 The Consultant will endeavor to protect all parties against defects and deficiencies in the work
of the Contractor, but cannot guarantee the Contractor's performance and shall not be
responsible for construction means, methods, measurements, techniques, sequences of
procedures, or for safety precautions and programs in connection with the work performed by
the Construction Contractor and any subcontractors.
Subtask 4 — Construction Management
Provide construction management services, consistent with the hours shown in EXHIBIT B — Rev 1. This
effort will include the following elements:
4.2 Supervise the Consultant's field personnel assigned to the project.
4.3 Liaison between the Contractor's management and the Client's management personnel, acting
as the direct point of contract for both parties.
4.4 Review and approve daily construction reports prepared by the construction inspector.
4.5 Respond to contractor questions which may arise as to the quality and acceptability of
furnished materials, work performed, and to general questions raised by adjacent property
owners or general public.
4.6 Facilitate coordination between the Contractor, Client and project stakeholders regarding status
and issues of construction activities.
4.7 Chair additional weekly construction meetings. (WORK COMPLETE BUT UNPAID ADDED
COSTS ARE INCLUDED)
4.8 Prepare official correspondence to the Contractor and issue upon the Client's approval.
4.9 Review monthly pay estimates with the Contractor and provide recommendation to the Client
for release of payment.
4.10 Supervise contract close-out activities including as -built drawings, final payment, and
completion notices. Consultant shall provide the Client, at contract close-out, construction
records to the all applicable funding agencies.
4.11 The Consultant shall assume no responsibility for proper construction techniques or job site
safety but will report to the Contractor and Client any observed public safety concerns
immediately. The presence of the Consultant's personnel at the construction site is for the
purpose of providing to the Client a greater degree of confidence that the completed work will
generally conform to the Contract Documents and that the integrity of the design concept as
reflected in the Contract Documents has been implemented and preserved by the construction
Contractor.
4.12 The Consultant will endeavor to protect all parties against defects and deficiencies in the work
of the Contractor, but cannot guarantee the Contractors' performance and shall not be
responsible for construction means, methods, measurements, techniques, sequences of
procedures, or for safety precautions and programs in connection with the work performed by
the construction contractor and any subcontractors.
Subtask 6 — Materials Testing
The Consultant will retain a materials testing subconsultant to perform soil and concrete testing which
includes: gradations, in-place density, Proctor compaction tests, concrete air entrainment, concrete test
cylinders, and asphalt composition. These services are budgeted as an allowance and the actual costs of
Page 3 of 5
Updated: 3/5/2018
51
Andover Park East
City of Tukwila
the testing effort may vary. The Consultant shall advise the Client regarding the status of the materials
testing budget to allow funds to be added or removed as necessary.
In addition to traditional materials testing, Contaminated Materials from the project site were discovered.
The Consultant retained a firm to perform testing on potentially contaminated materials. The Consultant
performed additional services for sampling, analysis, and disposal permitting.
THIS TASK'S WORK IS COMPLETE BUT UNPAID COSTS ARE INCLUDED.
Subtask 7 — Archaeological Monitoring and Inadvertent Discovery Plan and Field
Monitoring.
The Consultant shall prepare Archaeological Monitoring and Inadvertent Discovery Plan to the
Washington State Historic Preservation Officer (SHPO), Department of Archaeology and Historic
Preservation (DAHP) and the Tribes. The Plan shall address the required response by the contractor and
project team for a potential intersection of the construction work with pre -contact archaeology or human
remains. The plan shall be based upon previous archeological surveys by others. The draft plan shall be
submitted to DAHP and the Tribes for comment and subsequently finalized. At the conclusion of open cut
excavation activities, the Consultant shall prepare a final report summarizing the findings of the
monitoring effort. The Consultant shall provide a qualified archaeological monitor during open cut
excavation activities by the Contractor. This person shall be responsible for monitoring the Contractor's
compliance with the Archaeological Monitoring and Inadvertent Discovery Plan, and to be available to
respond to related Contractor questions. The monitor shall not enter the excavation without the specific
direction by the Consultant's Resident Engineer.
THIS TASK'S WORK IS COMPLETE BUT UNPAID COSTS ARE INCLUDED.
Subtask 8 — Change Order Resolution
The Consultant shall provide services for preparing change order packages consistent with the hours
shown in Exhibit B — Rev 1, this includes independent cost estimates (ICE), change order forms; and,
force account records.
Subtask 9 — Claims/Disputes Support
Consultant will use existing records from construction to summarize remaining dispute items for
reconciliation between Contractor and the City of Tukwila and coordinate/attend one meeting to try to
resolve these issues equitably.
Ill. Consultant Deliverables; including but not limited to:
Inspector Daily Reports
ii. Construction Photographs
iii. Weekly Meeting Minutes and Agendas
iv. Submittal, RFI, and Material Testing Logs
v. Change Order Log
vi. Monthly Contractor Pay Requests with field note record and quantity documentation
vii. Punch -lists and tracking documentation
viii. All Project Records received from the Contractor described under Subtask 2
ix. Other records generated as a result of this Contract, when requested by the Client, or as
deemed necessary by a public record request.
Page 4 of 5
52
Updated: 3/5/2018
Andover Park East
City of Tukwila
IV. Responsibilities of the Client
Provide CM oversight and approval authority for all construction activities.
ii. Manage the Designer -on -Record team as part of the Project Designer's on-call design
support and architectural submittal review.
iii. Process all contract documents through the City's approval process (e.g. CM services
invoices, construction contract, monthly pay estimates, change order execution, cost
reduction proposals, time extensions, etc.).
iv. Provide preferred forms and formats, and filing structure to the Consultant.
v. Oversee the Consultant on conducting schedule evaluation, monitoring, and evaluate Time
Impact Analysis for changes.
vi. Provide and assist the Consultant in utility coordination with third -party utilities under project
specific or franchise agreements.
vii. Provide operations & maintenance interface with other City Staff for ongoing project issues.
Page 5 of 5
Updated: 3/5/2018
53
54
APE Water Sewer Replacement
Exhibit B - Rev 1 Estimate 2 months remaining for closeout.
Estimated Hours to Complete Project
1-Admin/QC
Hours to complete
2 hours
9 hours
10.25 hours
5 hours
5 hours
4 hours
Raw Rate (Payroll Rate) Raw Total Billing Rate
$ 100.51 $ 201.02 $ 270.51 bill rate
86.20 $ 775.80 $ 232.00 bill rate
29.64 $ 303.81 $ 79.77 bill rate
34.06 $ 170.30 $ 91.67 bill rate
30.52 $ 152.59 $ 82.14 bill rate
88.79 $ 355.14 $ 238.96 bill rate
.Loaded Total
Employee
35.25Total Hour
2 - Doc Control
Hours to complete
99.5 hours
151
40 hours
Payroll Bra
1,958.67 "total Loaded (revenue) !,
Raw Total Billing Rate
33.66 $
31.96 $
36.00
3,349.17 $
4,825.96 $
1,440.00
82.37 bill rate
86.02 bill rate
96.89 bill rate
290.5; Total Hours
3 - Inspection
Hours to complete
189 hours
12.5 hours
16 hours
217.51Total Hours
4 - Construction Management
Hours to complete
30.51hours i......._
161hour .........
s
305 Total Hours
7 - Arch Monitoring
Hours to complete
6 hours
9.5 hours $
2.5 hours $
7 hours 1
$
1 hours I $
8 hours $
COI Labor Costs
34 Total Hours
$ 9,615.13 Total Loaded (reenu)
Raw Rate (Payroll Rate) Raw Total
Billing Rate
5
S
541.03 Fillis - Expended
2,087.99 Bardwell - Expended
817.67 Coughlin - Expended
458.35 Epperson - Expended
410.69 Coughlin
955.83 Bardwell
5,271.56
:Loaded Total
Employee
8,195.42
$ 12,988.59
$ 3,875.62
$ 25,059.62
Juan - Expended
Shinsato - Expended
Shinsato
58.09 $ 10,979.01
33.66
58.67 $ 938.72
142.15 bill rate
82.37
143.57 bill rate
$ 11,917.73 ! Total Loaded (revenue)
Raw Rate (Payroll Rate) Raw Total Billing Rate
86.20 ,; $ 2,629.10 $ 232.00 bill rate 1
88.79 j $ 1,420 58 j $ 238.96 bill rate
$ 2,629.10 Total Loaded ..�
(revenue)
Raw Rate (Payroll Rate)
Raw Total Billing Rate
Loaded Total
$ 26,865.64
$ 1,029.58
2,297.05
I 30,192.26
Employee
Vaughn - Expended
Juan - Expended
Vaughn
Loaded Total Employee
44.34 I $ 266.05 $ 119.34 bill rate
58.67 ; $ 557.37 $ 143.57 bill rate
28.70 $ 71.74 $ 77.23 'bill rate
33.66 $
235.62 $ 82.37 bill rate..
63.40 1 $ 63.40 $ 170.63 !bill rate
28.70 j $ 229.57 $ 77.23 bill rate
$ 1,423.74 Total Loaded (revenue)
$ 7,075.96 Bardwell - Expended
$ 3,823.34 Bardwell
$ 7,075.96
Loaded Total Employee
716.04 Butler - Expended
1,363.87 Becker - Expended
193.08 Bergeson Expended
576.56 Kline - Expended
170.63 McDaniel - Expended
617.86 McLandrich - Expended
626.00 Expended Monitoring Laboi
4,264.05
8 - Change Order Resolution
Hours to complete Raw Rate (Payroll Rate) Raw Total Billing Rate Loaded Total
[ 36.00 ..... $ 7 646.6..,
8
hours $
40 $ 1,440.00 $ 96.89 bill rate$ 3,875.62
72 Total Hours $ 4,281.15 Total Loaded (revenue) hours32 billrate
$ 11,522.29
mmm Employee
Bardwell
Shinsato
55
9 - Contaminated Materials
Hours to complete
Raw Rate (Payroll Rate)
Raw Total Billing Rate
:Loaded Total
5.5 hours
1.5 hours
8 hours
1.5 hours
6.75 hours
2.5 hours
51hors
urs
ANALYTICAL TESTING
37.77 $ 207.74
30.04 r $ 45.06 $
38.27 $ 306.16 $ 103.00
29 .68,
4 $ 4 44 52 . 79.88
27.17 $ 183.40 $ 73.13
31.78 $ 79.45
$ 101.65 bill rate
80.85 bill rate {
bill rate
bill rate
bill rate
bill rate
bill rate
85.53
63.40 $ 317.00 $ 170.63
559.10
121.27
824.00
119.82
493.60
$
213.83
._,._ 853.17
Employee
Cabanillas - Expended
Ellenberger - Expended
Garner Expended
Gebel - Expended
Holmes- Expended
Panteleeff Expended
Raubvogel - Expended
720.00
30.75'Total Hours
56
1,183.32
Total Loaded (revenue
ETC - Materials Testing
ETC OOC
Total Additional Costs
- Remaining Budget = $
04.79
$ 2,425.00
$ 94,715.54
4,775.65 recent invoice
Vehicles and supplies
Amount remaining after most
Added Budget Required = $ 89,939.89
Use $90,000
City of Tukwila
City Council Transportation & Infrastructure Committee
TRANSPORTATION & INFRASTRUCTURE COMMITTEE
Meeting Minutes
March 26, 2018 - 5:30 p.m. - Foster Conference Room, 6300 Building
Councilmembers: Thomas McLeod, Chair; De'Sean Quinn, Zak Idan
Staff: David Cline, Henry Hash, Mike Ronda, Ryan Larsen, Mike Cusick, Greg Villanueva,
Gail Labanara, Peter Lau, Steve Carstens, Laurel Humphrey
CALL TO ORDER: Committee Chair McLeod called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. BUSINESS AGENDA
A. NPDES Program 2017 Annual Report and 2018 Stormwater Management Program Plan
Staff provided an overview of the National Pollutant Discharge Elimination System (NPDES)
2017 Annual Report and 2018 Stormwater Management Program (SWMP) Plan. The Annual
Report reflects activities completed in 2017. The SWMP Plan is required by the NPDES Program
to show that the City complies with requirements outlined in the NPDES Phase II permit, and
contains elements such as public education and outreach, public involvement and
participation, illicit discharge detection and elimination, runoff control, municipal operations
and maintenance, compliance with maximum daily load requirements, and monitoring and
assessment. Committee members discussed the importance of public education and
awareness of stormwater fees and how they benefit the community. Staff will work with Chair
Mcleod on an editorial for the local press. DISCUSSION ONLY.
B. Contract Amendments: GIS Services for Water, Sanitary Sewer & Surface Water
Staff is seeking Council approval to amend two contracts with David Evans and Associates for GIS
services for the Water, Sanitary Sewer, and Surface Water Systems. These amendments, in the
amount of $124,581.00 for the 2018 Sanitary Sewer and Surface Water, and $99,825.40 for the Water
GIS Survey, will update existing GIS databases to address new construction and discrepancies.
David Evans and Associates was selected from three firms rated on the strength of its previous work
for the City. UNANIMOUS APPROVAL. FORWARD TO APRIL 2, 2018 REGULAR CONSENT
AGENDA.
Contract: Andover Park East Water & Sewer Replacement Construction Management
Staff is seeking Council approval of a contract with AECOM Technical Services in the amount
of $90,000.00 for construction management services for the Andover Park East Water and
Sewer Replacement Project. Several issues were discovered during construction that were not
included in the original scope of services, and this proposed contract will allow finalization of
payments and project closeout. The final total amount for construction management services
is $622,893.84 and under the $640,000 budget. UNANIMOUS APPROVAL. FORWARD TO APRIL
2, 2018 REGULAR CONSENT AGENDA.
57