HomeMy WebLinkAboutREG 2018-05-07 Item 7A - Motion - $300,000 Payment for Increased Flagging and Railroad Costs for Boeing Access Road Over BNRR Rehabilitation with BNSFCOUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
.Mayor:r yii
Council review
05/07/18
HH ,/
Motion
Date 05/07/18
Resolution
AN Dale
Ordinance
A lis Date
OBid Award
Mtg Date
E1 Public I learins,
AN Dale
El Other
AN Date
Mtg
SPONSOR Council Mayor Ell [TR El DC!) J Finance Hre IT P &R Police PIV
SPONSOR'S Council is being asked to approve additional costs for Burlington Northern Santa Fe's
St 1MMARY (BNSF) flagging and inspection fees during construction of the Boeing Access Road over
BNRR Bridge Rehabilitation Project. The original contract with BNSF to work over the
railroad's right-of-way was $149,000 and the average charges in the last six months show
that additional fees of $300,000 are necessary to finish the project. Council is being asked
to approve additional costs for BNSF flagging in the amount of $300,000.
RINIEwl:,1) BY Ei COW Mtg. El] CA&P Cmte F&S Cmte E Transportation Cmte
fl Utilities Cmte Arts Comm. E Parks Comm. Ell Planning Comm.
DATE: 04/23/18 COMMUTE:Pi CI IAIR: THOMAS MCLEOD
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMNIITIEF:
Public Works
Unanimous Approval; Forward to Regular New Business
COST IMPACT / FUND SOURCE
ITEM INFORMATION
ITEM No.
7.A.
CAS NtiNitiFIR:
STAFF' SPONSOR: HENRY HASH
ORIGINAL AGENDA DATE: 05/07/18
AGENDA ITEm THLE Boeing Access Rd over BNRR Bridge Rehabilitation Project
Additional BNSF Flagging Expenses
cxi.EG()RY LIJ Discussion
Mtg Dale
Motion
Date 05/07/18
Resolution
AN Dale
Ordinance
A lis Date
OBid Award
Mtg Date
E1 Public I learins,
AN Dale
El Other
AN Date
Mtg
SPONSOR Council Mayor Ell [TR El DC!) J Finance Hre IT P &R Police PIV
SPONSOR'S Council is being asked to approve additional costs for Burlington Northern Santa Fe's
St 1MMARY (BNSF) flagging and inspection fees during construction of the Boeing Access Road over
BNRR Bridge Rehabilitation Project. The original contract with BNSF to work over the
railroad's right-of-way was $149,000 and the average charges in the last six months show
that additional fees of $300,000 are necessary to finish the project. Council is being asked
to approve additional costs for BNSF flagging in the amount of $300,000.
RINIEwl:,1) BY Ei COW Mtg. El] CA&P Cmte F&S Cmte E Transportation Cmte
fl Utilities Cmte Arts Comm. E Parks Comm. Ell Planning Comm.
DATE: 04/23/18 COMMUTE:Pi CI IAIR: THOMAS MCLEOD
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMNIITIEF:
Public Works
Unanimous Approval; Forward to Regular New Business
COST IMPACT / FUND SOURCE
EXPENDITURE RI,:QUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$300,000.00 $2,958,096.00 $0.00
Fund Source: 104 ARTERIAL STREETS (PAGE 10, 2017 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/07/18
MTG. DATE
ATTACHMENTS
05/07/18
Informational Memorandum dated 04/20/18
2017 CIP, page 10
Minutes from the Transportation & Infrastructure Committee meeting of 4/23/18
. __
154
City of Tukwila
Public Works Department - Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation Committee
FROM: Henry Hash, Public Works Director
BY: Steve Carstens, Senior Program Manager
CC: Mayor Ekberg
DATE: April 20, 201
SUBJECT: Boeing Access Road over BNRR Bridge Rehabilitation Pro'lect
Project No. 99410408
BNSF Flagging expenses
Allan Ekberg, Mayor
ISSUE
Approve Burlington Northern Santa Fe's (BNSF) flagging and inspection cost increases.
BACKGROUND
In October 2013, the City contracted with Jacobs Engineering, Inc. to provide the design for the
rehabilitation of the Boeing Access Road over BNRR Bridge. The BNSF Overpass Agreement
allows the City and its contractor to work in the BNSF right-of-way and pays for required railroad
flagging and inspection services performed by BNSF.
ANALYSIS
BNSF's Overpass Agreement is for required construction and maintenance costs related to the
work over the railroad's right-of-way and covers inspection services and flagging required by the
BNSF. Average charges from the previous six months were used to forecast the additional flagging
costs of $300,000.00.
FISCAL IMPACT
The Overpass Agreement is within the approved construction management budget which includes
a contingency for unanticipated work.
Jacobs CM Contracts
BNSF Original Flagging and Inspection
New BNSF Flagging and Inspection
Construction Contingency
Total
Contract CM Budget
$1,785,249.83 $1,224,000.00
149,428.00 149,428.00
300,000.00
$2,234,677.83
1,584,668.00
$2.958.096.00
RECOMMENDATION
Council is being asked to approve the increased flagging and railroad costs with BNSF for the
Boeing Access Rd over BNRR Rehabilitation Project in the amount of $300,000.00 and consider
this item on the Consent Agenda at the May 7, 2018 Regular Meeting.
attachments Page 10, 2017 CIP
W:1PW Eng1PROJECTSWA- RW & RS Projects\Boeing Access Rd Bridge Rehab (99410408)105 ROW Esmt Permits\BNSF CM AgreementlInfo Memo BNSF Flagging 042018.docx
155
156
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Boeing Access Rd over BNRR Bridge Rehabilitation Project No. 99410408
DESCRIPTION: Rehabilitate the existing bridge with a 340' long concrete or steel bridge structure. It will be 6 lanes
and have a sidewalk on one side.
The existing bridge is structurally and seismically deficient. Several pedestals are leaning, have concrete
JUSTIFICATION: spalls, exposed rusty anchor bolts and reinforcements and some cracks. The existing railings do not meet
current bridge standards.
Type, size, and location draft report (specifically required for bridges) was completed in 2005. Federal
STATUS: grant applications were submitted in 2008 and 2010 and the bridge rehabilitation was successful for
funding in 2012 for federal bridge funds. A Public Works Trust Fund (PWTF) loan was rescinded in 2013.
MAINT. IMPACT: Maintenance will be reduced.
COMMENT:
Bridge will be rehabilitated in phases to allow continued traffic use. Federal bridge grant of $9,745,600
requires a 20% local match. A bond issue for the City match was issued in 2015 with the Interurban Ave S.
FINANCIAL Through Estimated
in $000's
2015 2016 2017
2018 2019 2020 2021 2022 BEYOND TOTAL
EXPENSES
Design
1,249
104
1,353
Land (RNV)
100
100
Const. Mgmt.
1,124
1,124
Construction
9,745
9,745
TOTAL EXPENSES
1,249
204
10,869
0
0
0
0
0
0
12,322
FUND SOURCES
Awarded Grant
905
163
8,677
9,745
Proposed Grant
0
Fund Balance -Bond
344
41
2,192
2,577
Mitigation
0
City Oper. Revenue
0
0
0
0
0
0
0
0
0
0
TOTAL SOURCES
1,249
204
10,869
0
0
0
0
0
0
12,322
Project Location
2017 - 2022 Capital Improvement Program
10
157
158
City of Tukwila
City Council Transportation & Infrastructure Committee
TRANSPORTATION & INFRASTRUCTURE COMMITTEE
Meeting Minutes
April23, 2018 - 5:30 p.m. - Hazelnut Conference Room, City Hall
Councilmembers: Thomas McLeod, Chair; De'Sean Quinn, Zak Idan
Staff: David Cline, Henry Hash, Steve Carstens, Dave Sorensen, Jack Pace, Jaimie
Reavis, Cyndy Knighton, Gail Labanara, Laurel Humphrey
CALL TO ORDER: Committee Chair McLeod called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. BUSINESS AGENDA
BNSF Flagggingand Inspection Cost Increases
Staff is seeking Council approval of BNSF's increased flagging and inspection costs for the
remainder of the Boeing Access Road over BN RR Bridge Rehabilitation Project. An Overpass
Agreement currently in effect allows the City and its contractor to work in the BNSF right-of-
way and pays for the required railroad flagging and inspection services performed by BNSF.
The original flagging and inspection fees were estimated at $149,428, and the additional
$300,000 was calculated based upon average charges from the previous six months. The
project contingency is sufficient to cover this additional cost. Committee members expressed
concern about the change in cost and asked staff to communicate with BNSF to ensure there
are no further increases. The Committee decided to place this item under New Business at the
May 7, 2018 Council meeting rather than the Consent Agenda to give staff opportunity to
explain the change. UNANIMOUS APPROVAL. FORWARD TO MAY 7, 2018 REGULAR
MEETING.
B. Bid Award: 2018 Overlay and Repair Program
Staff is seeking Council approval to award a construction bid to ICON Materials in the amount of
$955,945.50 for the 2018 Overlay and Repair Program. Construction will include pavement repairs
and an asphalt overlay at four locations in the City as determined by the pavement condition index
rating on which all roads in the City are evaluated. ICON was the low bidder and constructed last
year's overlay program and staff was very happy with their work. Chair McLeod heard from a
resident with professional experience in road paving who shared personal opinions about the
responsive bidders. Chair McLeod asked what compels the City to go with the lowest responsive
bidder and staff replied this is state law. Unless the City has a specific negative experience with a
company, it cannot legally turn down the lowest responsive bid. Councilmember Quinn noted that
funding of this program should be evaluated with regard to the 2019-2020 budget. The Committee
decided to place this item under New Business rather than the Consent Agenda of the May 7, 2018
Regular Meeting. UNANIMOUS APPROVAL. FORWARD TO MAY 7, 2018 REGULAR MEETING.