SPONSOR'S KPG is currently the design consultant for the 2018 Overlay & Repair Project with Contract
SUMMARY No. 17-154. During construction, the City will need construction management support and
KPG was selected as the most qualified. The construction bid will be awarded to ICON
Materials on 5/7/18. Council is being asked to approve Supplemental Agreement No. 1 for
construction management with KPG in the amount of $167,200.00.
REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm.
DATE: 05/07/18 COMMITTEE CHAIR:
►1 Transportation
Cmte
❑ Planning Comm.
THOMAS MCLEOD
ITEM INFORMATION
ITEM No.
5.D.
STAFF SPONSOR: HENRY HASH
ORIGINAL AGENDA DATE: 05/07/18
AGENDA ITEM TITLE 2018 Annual Overlay & Repair Program
Construction Management Supplemental Agreement with KPG, Inc.
CATEGORY ❑ Discussion
Mtg Date
/1
Motion
Date 05/07/18
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
Mtg
SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police
// PTV
SPONSOR'S KPG is currently the design consultant for the 2018 Overlay & Repair Project with Contract
SUMMARY No. 17-154. During construction, the City will need construction management support and
KPG was selected as the most qualified. The construction bid will be awarded to ICON
Materials on 5/7/18. Council is being asked to approve Supplemental Agreement No. 1 for
construction management with KPG in the amount of $167,200.00.
REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte
❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm.
DATE: 05/07/18 COMMITTEE CHAIR:
►1 Transportation
Cmte
❑ Planning Comm.
THOMAS MCLEOD
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITI
Public Works Department
EE Unanimous Approval; Forward to Regular Consent Agenda
COST IMPACT / FUND SOURCE
EXPEND MIR' RI QUIRI?D AMOUNT BUDGETED APPROPRIATION REQUIRED
$167,200.00 $200,000.00 $0.00
Fund Source: 104 ARTERIAL STREET FUND (PAGE 18, 2017 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/07/18
MTG. DATE
ATTACHMENTS
05/07/18
Informational Memorandum dated 04/20/18
Page 18, 2017 CIP
KPG Supplement No. 1 to Contract 17-154, Scope of Work, and Fee
Minutes from the Transportation & Infrastructure Committee meeting of 04/23/18
30
City of Tukwila
Allan Ekberg, Mayor
Public Works Department - Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Henry Hash, Public Works Director
BY: Dave Sorensen, Project Manager
CC: Mayor Allan Ekberg
DATE: April 20, 2018
SUBJECT: 2018 Overlay and Repair Program
Project No. 91810401, Contract No. 17-154
Supplemental Agreement No. 1 for Construction Management Services
ISSUE
Execute Supplemental Agreement No. 1 with KPG, Inc. (KPG) to provide construction
management services for the 2018 Overlay and Repair Program.
BACKGROUND
On August 21, 2017 the Council approved the contract with KPG to provide engineering design
services for the project. KPG was selected to also provide construction management services
as a supplement to the design contract.
DISCUSSION
KPG has provided a supplement, scope of work, and fee estimate for construction
management services for the 2018 Overlay and Repair Program for $167,200.00. Construction
bid opening was April 5, 2018.
FISCAL IMPACT
Sup No. 1 CM Budget
Construction Management Sup No. 1 $ 167,200.00 $ 200,000.00
RECOMMENDATION
Council is being asked to approve Supplemental Agreement No. 1 to Contract No. 17-154 for
construction management services with KPG, Inc. for the 2018 Overlay and Repair Program in
the amount of $167,200.00 and consider this item on the Consent Agenda at the May 7, 2018
Regular Meeting.
attachments Page 18, 2017 CIP
Contract, Scope of Work and Fee Estimate
W:1PW Eng1PROJECTSIA- RW & RS Projects1Annual Overlay & Repair Programs12018 Overlay & Repair Program (91810401)ICN Management\Construction Management\Docs to TIC12018 Overlay CM.docx
31
32
CITY OF TUKWILA CAPITAL PROJECT SUMMARY
2017 to 2022
PROJECT: Annual Overlay and Repair Program Project No, 9xx10401
DESCRIPTION: Select, design and construct asphalt and concrete pavement overlays of arterial and residential streets,
JUSTIFICATION: Preserve and maintain the street structure in a safe and useable state by resurfacing before failure which also
minimizes costs. Some individual sites may be coordinated with water, sewer, and surface water projects.
STATUS: Each year various sections of roadway throughout the City are designed and constructed for asphalt overlay.
MAINT. IMPACT: Reduces annual maintenance.
COMMENT: Ongoing project. Only one year actuals shown in first column.
FINANCIAL Through Estimated
in $000's
2015 2016 2017
2018
2019
2020
2021
2022
BEYOND TOTAL
EXPENSES
Design
123
135
150
150
175
175
200
200
200
1,508
Land (R/W)
0
Const. Mgmt.
276
175
200
200
225
225
250
250
275
2,076
Construction
1,289
1,260
1,050
1,050
1,330
1,340
1,350
1,350
1.375
11,394
TOTAL EXPENSES
1,688
1,570
1,400
1,400
1,730
1,740
1,800
1,800
1,850
14,978
FUND SOURCES
Awarded Grant
0
Proposed Grant
0
Mitigation Actual
0
Mitigation Expected
0
City Opel-. Revenue
1,688
1,570
1,400
1,400
1,730
1,740
1,800
1,800
1,850
14,978
TOTAL SOURCES
1,688
1,570
1,400
1,400
1,730
1,740
1,800
1,800
1,850
14,978
2017 - 2022 Capital Improvement Program
18
33
34
SUPPLEMENTAL AGREEMENT NO. 1
AGREEMENT No. 17-154
PROJECT NO. 91810401
City of Tukwila
Public Works Department
6300 Southcenter Boulevard #100
Tukwila, WA 98188
KPG, Inc.
753 - 9th Avenue N.
Seattle, WA 98109
PROJECT: 2018 Overlay Program — Construction Services
This SUPPLEMENTAL AGREEMENT NO. 1 is to supplement the agreement entered into with KPG,
Inc. and the City of Tukwila, which was executed on the 5th day of September, 2017.
All provisions in the basic agreement remain in effect, except as expressly modified as follows:
Article 2, Scope of Services, shall be supplemented with the following:
The Consultant agrees to provide construction services in accordance with the scope of work included as
Exhibit A-1.
Article 3, Duration of Agreement; Time for Performance, shall be modified as follows:
The Consultant shall perform all services and provide all work product required pursuant to this Agreement
no later than December 31, 2018 unless an extension of such time is granted in writing by the City.
Article 4, Payment, shall be modified as follows:
Payment for work provided by Consultant shall be made as provided on Exhibit B-1, attached
hereto, provided that the total amount of payment to the Consultant for this work not exceed $167,200.00
without express written modification of the Agreement signed by the City. The new total contract shall
not exceed $280, 903.07 without express written modification of the Agreement signed by the City.
IN WITNESS WHEREOF, the parties hereto have set their hands and seals this day
of , 2018.
APPROVED: APPROVED:
CITY OF TUKWILA KPG, INC.
Allan Ekberg
Mayor
Attested:
Christy O'Flaherty, City Clerk
Nelson Davis, P.E.
Principal
35
36
EXHIBIT A-1
Construction Management Services
Scope of Work
April 10, 2018
City of Tukwila — 2018 Overlay Program
This work will provide construction management services for the construction contract to complete the
City of Tukwila — 2018 Overlay Program. These services will include design support, project
management, documentation control, inspection, materials testing, public involvement, and contract
administration during the construction of the project, as detailed below. KPG ("Consultant") will provide
to the City of Tukwila ("City") construction management services for the project.
A detailed scope for the Contract follows:
I. INTRODUCTION
The following scope of services and associated costs are based upon the assumptions outlined below.
General Assumptions:
• The proposed project team will include one part-time documentation control specialist, a
part-time resident engineer during construction activities, a full-time inspector, an additional
inspector if required, sub -consultants to provide services for materials testing, and other
supporting tasks as deemed necessary. It is anticipated that full- time site observation will be
required for the entirety of the project.
• The level of service is based on a construction project duration of approximately 40 working
days.
• KPG estimates a total project construction duration of 60 working days (12 weeks) including
preconstruction service, construction services, and project closeout. No suspensions or stop
work periods are anticipated during this duration.
• It is anticipated that the KPG will develop the Record of Materials (ROM). This scope of services
provides the management of the ROM and scheduling of required materials testing respectively.
• It is anticipated that the City will review and execute the insurance, bonds, and the Construction
Contract.
• KPG will do all public outreach, and ensure affected business and residents are notified of
impending contractor activities one week prior to work by door to door and or A -board signs
that include date, hours of work, and a KPG staff phone number to call for questions.
• The design engineers from KPG will be available during construction to answer questions during
construction and review RAM's, shop drawings, and answer RFI's that require a level of
City of Tukwila — 2018 Overlay Program
Construction Management Services
Scope of Work
Page 2 of 7
KPG
Project Number 17135
4/10/2018
37
EXHIBIT A-1
engineering expertise outside of the capabilities of the Consultant.
• Services will be performed in accordance with the Contract plans & special provisions, and City
engineering standards.
II. SCOPE OF WORK
The objective and purpose of this Construction Management Services Agreement is for the Consultant
to successfully deliver the construction of the Project to the City by ensuring that the improvements are
constructed in accordance with the approved Plans and Specifications, as may be amended or revised,
that all of the required Project documentation is accounted for.
TASK 1— MANAGEMENT/COORDINATION/ADMINISTRATION
Provide overall project management, coordination with the City, monthly progress reports, and
invoicing. This effort will include the following elements.
• Organize and layout work for project staff. Prepare project instructions on contract
administration procedures to be used during construction.
• Review monthly expenditures and CM team scope activities. Prepare and submit project
progress letters to the City along with invoices describing CM services provided each month.
Prepare and submit reporting required by funding source(s), if any.
Deliverables
• Monthly invoices and progress reports
TASK 2 — PRECONSTRUCTION SERVICES
2.1 Preconstruction Conference: The Consultant will prepare an agenda for, distribute notices of,
and conduct a preconstruction conference in the City's offices. The Consultant's project
manager, resident engineer, inspector, and document control specialist will attend the
preconstruction conference. The Consultant will prepare a written record of the meeting and
distribute copies of the minutes to all attendees and affected agencies, staff, etc.
At the Pre -construction conference, the Consultant shall facilitate discussions with the
Contractor concerning the plans, specifications, schedules, issues with utilities, unusual
conditions, Federal, State, and local requirements and any other items that will result in better
project understanding among the parties involved.
Deliverables
• Preconstruction conference agenda with meeting minutes
TASK 3 — CONSTRUCTION SERVICES - FIELD
3.1 On-site Observation: The Consultant shall provide the services of one full time inspector
during construction activities and other tasks necessary to monitor the progress of the work. An
additional inspector, may be incorporated as dictated by the Contractor's approach to the Work.
Construction staff shall oversee the following items of work, on the project site, and will observe
the technical progress of the construction, including providing day-to-day contact with the
City of Tukwila — 2018 Overlay Program
Construction Management Services
Scope of Work
38
Page 3 of 7
KPG
Project Number 17135
4/10/2018
EXHIBIT A-1
Contractor and the City:
o Preparation to include mobilization and clearing and grubbing
o Erosion Control
o HMA grinding and paving
o Driveways, curb, gutter and sidewalk
o And all incidental items necessary to complete the Work as described in the Plans
and/or Specifications.
Field inspection staff will perform the following duties as a matter of their daily activities:
i. Observe technical conduct of the construction, including providing day-to-day contact
with construction contractor, City, utilities, and other stakeholders, and monitor for
adherence to the Contract Documents. The Consultant's personnel will act in
accordance with Sections 1-05.1 and 1-05.2 of the Standard Specifications.
ii. Observe material, workmanship, and construction areas for compliance with the
Contract Documents and applicable codes, and notify construction contractor of
noncompliance. Advise the City of any non -conforming work observed during site visits.
iii. Document all material delivered to the job site in accordance with the contract
documents.
iv. Prepare daily inspection reports, recording the construction contractor's operations as
actually observed by the Consultant; includes quantities of work placed that day,
contractor's equipment and crews, and other pertinent information.
v. Interpret Contract Documents in coordination with the City and KPG.
vi. Resolve questions which may arise as to the quality and acceptability of material
furnished, work performed, and rate of progress of work performed by the construction
contractor.
vii. Establish communications with adjacent property owners. Respond to questions from
property owners and the general public.
viii. Coordinate with permit holders on the Project to monitor compliance with approved
permits, if applicable.
ix. Prepare field records and documents to help assure the Project is administered in
accordance with the funding requirements.
x. Collect and calculate delivery tickets and salesman's daily reports of aggregate. All
tickets will be initialed with correct bid item and stationing identified (Construction
Manual 10-2).
xi. Attend and actively participate in regular on-site weekly construction meetings.
xii. Take periodic digital photographs during the course of construction, and record
locations.
xiii. Coordinate with the City's maintenance personnel.
xiv. Punch list. Upon substantial completion of work, coordinate with the Client and
affected agencies, to prepare a 'punch list' of items to be completed or corrected.
Coordinate final inspection with those agencies.
City of Tukwila — 2018 Overlay Program
Construction Management Services
Scope of Work
Page 4 of 7
KPG
Project Number 17135
4/10/2018
39
EXHIBIT A-1
Assumptions:
• Consultant will provide observation services for the days/hours that the contractor's
personnel are on-site.
• Consultant will provide qualified personnel for inspection of all bid item work.
• The Consultant's monitoring of the construction contractor's activities is to ascertain
whether or not they are performing the work in accordance with the Contract Documents;
in case of noncompliance, Consultant will reject non -conforming work, and pursue the
other remedies in the interests of the City, as detailed in the Contract Documents. The
Consultant cannot guarantee the construction contractors' performance, and it is
understood that Consultant shall assume no responsibility for: proper construction means,
methods, techniques; project site safety, safety precautions or programs; or for the failure
of any other entity to perform its work in accordance with laws, contracts, regulations, or
City's expectations.
3.2 Substantial Completion: Upon substantial completion of work, coordinate with the City and
other affected agencies, to perform a project inspection and develop a comprehensive list of
deficiencies or `punchlist' of items to be completed. A punchlist and Certificate of Substantial
Completion will be prepared by the Consultant and issued by the City.
3.3 Materials Testing: Coordinate the work of the materials testing technicians and testing
laboratories in the observation and testing of materials used in the construction; document and
evaluate results of testing; and address deficiencies. Frequency of testing shall be determined
by the resident engineer.
Deliverables
• Daily Construction Reports with project photos — submitted on a weekly basis
• Punch List, Certificate of Substantial Completion
• Review test reports for compliance
TASK 3.4 — CONSTRUCTION SERVICES — OFFICE
A. Document Control. Original documentation will be housed at the Consultant's office, and
filed in accordance with standard filing protocol. A copy of working files will be maintained in
the field office.
B.
C.
Document Control consists of:
■ Final Estimate (Approving Authority File)
■ Comparison of Preliminary and Final Quantities (Approving Authority File)
■ Final Records (Approving Authority File)
■ Record of Material Samples and Tests
■ Affidavit of Wages Paid
■ Release for the Protection of Property Owners and General Contractor
Project Coordination: Liaison with City, construction contractor, engineer, utilities
property owners on a regular basis to discuss project issues and status.
Plan Interpretations: Provide technical interpretations of the drawings, specifications, and
contract documents, and evaluate requested deviations from the approved design or
specifications. Coordinate with City for resolution of issues involving scope, schedule, and/or
budget changes.
and
City of Tukwila — 2018 Overlay Program
Construction Management Services
Scope of Work
40
Page 5 of 7
KPG
Project Number 17135
4/10/2018
EXHIBIT A-1
D. Weekly Meetings: Lead weekly meetings, including preparation of agenda, meeting minutes,
and distribution of minutes to attendees. Outstanding issues to be tracked on a weekly basis.
E. Initial Schedule Review: Perform detailed schedule review of contractor provided CPM for
conformance with the contract documents.
F. Lump Sum Breakdown: Evaluate construction contractors' Schedule of Values for lump sum
items. Review the Contract Price allocations and verify that such allocations are made in
accordance with the requirements of the Contract Documents. Lump Sum Breakdowns for
payment each month will be calculated with detailed data.
G. Monthly Pay Requests: Prepare monthly requests for payment, review with the City,
contractor and approve as permitted. Utilize City provided format for pay estimates, or
Consultant format.
H. Monthly Schedule Review: At the monthly cutoff, review contractor's updated schedule and
compare with field -observed progress, as described in Section 1-08 of the Special Provisions.
In addition, perform schedule analysis on contractor provided CPM updates and review
schedule for delays and impacts. Coordinate with Contractor in the development of recovery
schedules, as needed, to address delays caused by either events or issues within the
Contractor's control or other events or issues beyond the Contractor's control.
I. Certified Payroll: Process and track all certified payroll per State Prevailing Wage
Requirements. This includes verifying the initial payroll for compliance and 10% of all payrolls
submitted thereafter. Tracking payroll each week.
J. Weekly Statement of Working Days: Prepare and issue weekly statement of working day
report each week.
K. Subcontractor Documentation: Process / Approve all required subcontractor documentation.
Request to Sublets will be verified and logged. This includes checking System Award
Management System (SAMS), verifying business licensing, reviewing insurance documentation,
verifying city business licensing, Intent to Pay Prevailing Wage and Affidavit of Wages Paid. All
subcontractor documentation will be logged into KPG's subcontractor logs.
L. Record Drawings: Review record drawings prepared by the Contractor, and prepare a
conformed set of project record drawings based on Contractor provided information and from
inspection notes. Record drawings to be verified on a monthly basis, as part of the progress
payment to the Contractor. Upon project completion, contractor provided markups will be
verified for completeness and supplemented with inspection information. The Consultant will
provide the marked up plan sheets with both the contractors and inspectors as -built
information. Revisions to the CAD drawings are not included
M. Physical Completion Letter: Following completion of all punchlist work, prepare physical
completion letter to the contractor, and recommend that City and/or Utilities accept the
project.
N. Project Closeout: Transfer all project documents to the City for permanent storage.
• Schedule review comments
• As -built schedule
• Meeting agendas and notes
• Monthly Pay Estimates
• Subcontractor Packets
• Cost Projection
• Physical Completion Letter
City of Tukwila — 2018 Overlay Program Page 6 of 7 KPG
Construction Management Services Project Number 17135
Scope of Work 4/10/2018
41
EXHIBIT A-1
• Final Project Documents
TASK 3.5 — SUBMITTAL/RFI PROCESSING
A. Submittals: Coordinate review process for shop drawings, samples, traffic control plans, test
reports, and other submittals from the Contractor for compliance with the contract documents.
Key submittals to be transmitted to the City for their review and approval. Submittals shall be
logged and tracked.
B. Request for Information (RFI): Review and respond to RFI's. RFI's shall be logged and tracked.
C. Record of Materials (ROM): Utilize ROM prepared by KPG and update based on Special
Provisions and Plans for use on the project, based on the contract specifications. The ROM will be
maintained by the Resident Engineer. The ROM will track all of the materials delivered to the site
including manufacturer/supplier, approved RAM's, QPL items, material compliance
documentation, and all other required documentation.
Deliverables
• Submittal log
• RFI Log
• Completed Record of Material for Material Certification
TASK 3.6 — CHANGE MANAGEMENT
A. Case Log: Develop and maintain a case log which includes change orders, RFP's, Field Work
Directives
B. Change Orders: Develop change orders and provide technical assistance to negotiate change orders,
and assist in resolution of disputes which may occur during the course of the project. Each change
order will be executed in accordance with WSDOT Standard Specifications and contain the
following:
• Change order
• Independent Cost Estimate
• Time Impact Analysis
• Contractor's Pricing
• Verbal Approval Memo
• Back up documentation
C. Field Work Directives: Prepare field work directives as necessary to keep the contractor on
schedule.
D. Minor Change Orders: Develop minor change orders per WSDOT Standard Specifications. Each
minor change order will be executed and contain the following:
• Independent Cost Estimate
• Verbal Approval Memo
• Back up documentation
E. Force Account: Track contractor force account labor, equipment and materials. All force account
calculations will be verified by the engineer and double checked by the documentation specialist.
Deliverables
City of Tukwila — 2018 Overlay Program
Construction Management Services
Scope of Work
42
Page 7 of 7
KPG
Project Number 17135
4/10/2018
• Change Order(s)
• Case Management Log
• RFI Log
• Minor Change Order(s)
• Force Account Records
City of Tukwila — 2018 Overlay Program
Construction Management Services
Scope of Work
EXHIBIT A-1
Page 8 of 7
KPG
Project Number 17135
4/10/2018
43
44
Project Name:
Consultant:
COST PLUS FIXED FEE
Exhibit B-1
Consultant Fee Determination
2018 Overlay Program
Supplement No. 1 - Construction Services
KPG
Classification Hours Rate Cost
Project Manager 24 $ 81.32 $ 1,952
Resident Engineer 240 $ 50.96 $ 12,230
Project Engineer 64 $ 50.96 $ 3,261
Design Engineer 16 $ 46.26 $ 740
Engineering Technician 16 $ 37.59 $ 601
Construction Inspector 480 $ 42.65 $ 20,470
Survey Crew I 0 $ 59.63 $ -
Document Specialist 190 $ 40.48 $ 7,691
Construction Admin 112 $ 33.25 $ 3,724
Total Direct Salary Cost (DSC)
Overhead (146.70% x DSC)
Fixed Fee (30% x DSC)
1,142
$50,669
$74,330.83
$15,200.58
Subtotal: $140,200.00
REIMBURSABLES
Construction Vehicle Mileage $1,0001
Miscellaneous - Repro, Field Supplies $1,000
Subtotal: $2,000
SUBCONSULTANT COSTS
Material Testing Allowance $25,000
Subtotal: $25,000
TOTAL $ 167,200.00
45
46
Transportation & Infrastructure Committee Minutes April 23, 2018
Construction Management Services: 2018 Overlay and Repair Program
Staff is seeking Council approval of Supplemental Agreement No. 1 with KPG, Inc. in the
amount of $167,200.00 for construction management services for the 2018 Overlay and Repair
Program. KPG is also designing the program and this supplement is under the construction
management budget of $200,000. UNANIMOUS APPROVAL. FORWARD TO MAY 7, 2018
REGULAR CONSENT AGENDA.
D. Grant Application: Green River Trail Improvements
Staff is seeking Committee approval to submit a grant application to the Puget Sound Regional
Council Congestion Mitigation & Air Quality (CMAQ) grant program to fund improvements on
the Green River Trail between the new Pedestrian/Bicycle Bridge landing and Christensen
Road. This is an approximately 700 -foot stretch of the trail that was designed and permitted as
part of the bridge project, but was removed due to insufficient construction funds. The
proposed project would widen the trail in this section to 14 feet with 1-2 foot shoulders, install
illumination, provide cameras and fiber connection, and construct a pedestrian plaza with
wayfinding. If successful, the grant will require a 13.5% match that would need to be
programmed for 2020 or 2021. UNANIMOUS APPROVAL.
E. Grant Application: Safe Routes to School
Staff is seeking Committee approval to submit a grant application to the Washington State
Department of Transportation for the 2018 Safe Routes to School funding program. Public
Works and Community Development staff jointly identified four potential projects that meet
the funding criteria: 46th Avenue South and South 144th Street sidewalk and crossing
improvements, Macadam Road South sidewalk and crossing improvements between South
144th St and South 150th St, sidewalks on the South 144th St bridge over 1-5, and South 152nd
Street sidewalks between Tukwila International Boulevard and 42nd Avenue South. Committee
members and staff discussed the projects and agreed that staff would submit applications for
both the Macadam Road S and the South 144th bridge over 1-5 projects. UNANIMOUS
APPROVAL.
F. Grant Application: Green the Green Project
Staff is seeking Committee approval to apply to WRIA 9 for its Small Grant Fund for Salmon
Habitat and Restoration Projects for the City's Green the Green Project. This project will
enhance shoreline riparian plant communities to benefit salmon and beautify the river
corridor. The maximum amount to be awarded is $50,000 and if successful, the grant
agreement would be with the King County Flood Control District. Staff is also seeking approval
to apply to other grant opportunities that become available. UNANIMOUS APPROVAL.