HomeMy WebLinkAboutReg 2018-05-21 Item 7E - Report - Public Safety Plan: Program Management Quality Assurance Monthly ReportMay 15, 2018
TO: Tukwila City Council
FROM: Steve Goldblatt
PMQA Consultant
RE: Public Safety Plan
May update
The Council now has a better understanding of the Plan's significant budget stress. The Fi-
nance Committee and City staff are addressing the challenge by exploring phasing and rev-
enue options, while the Project Executive Team and City partners have had another pro-
ductive month on all fronts. Timely due diligence, access, and property acquisitions remain
key to maintaining the Plan's momentum.
FIRE STATIONS
Site acquisition
The City now owns the majority of the property for Fire Station 54 and is in the process
of purchasing a very small portion of the site. Geotechnical exploration will inform site
development costs for Fire Station 52.
Station 51 design development
Per Council consensus 12 February to move forward from schematic design, Weinstein
AU is well into Station 51's design development phase. Weekly meetings are ongoing
through May, with pricing expected in June/July.
Stations 52 and 54 schematic design
Weinstein AU will begin the schematic design phase for Stations 52 and 54 in July.
Stations' budget
With input from GC/CM Lydig Construction, Station 51's schematic design estimate of
$12.5 million was the first "real" number presented to Council 12 February. The pro-
ject team is working on understanding Station 51's schematic design estimate and its
implications on the other two station budgets, specifically adjusted to the final sites. At
this point, the overage is expected to total $20.5 million for all three stations.
GC/CM pre -construction services
Lydig has conducted the process to select an EC/CM electrical contractor and an
MC/CM mechanical contractor pursuant to RCW 39.10.385. A Request for Proposals
was advertised 9 April, a pre -proposal meeting was held 12 April, five proposals were
submitted 24 April, interviews of those firms were held 3 May, and final proposals
were submitted 8 May. Valley Electric was selected as EC/CM and Johansen Mechanical
as MC/CM.
175
Disadvantaged Business Enterprise and local hiring policies
The Council unanimously passed Resolution 1929 on 2 April, adopting DBE and local
hiring policies for the Plan's projects. The DBE goal is 17% and the local hiring goal is
20%, complementing the City's 10% apprenticeship requirement of Resolution 1814.
Lydig's first opportunity to implement the new policies is reflected in its E/MCCM
RFPs and selections. The first metrics that the Council sees can be expected mid -2019.
Lydig will be represented at the 23 June open house to talk about project job opportu-
nities.
JUSTICE CENTER
Property acquisition
Depending on due diligence and site access, the Council should expect final pricing and
closed transactions for some of the Justice Center's properties in June or July. If site ac-
quisition is extended, permitting, environmental, and construction starts may be de-
layed.
Schematic design estimate
DLR has completed schematic design. An updated cost estimate with GC/CM input and
results of site investigations was presented to Public Safety 7 May, confirming the pro-
gram estimate: roughly $38 million over the budget developed for the Plan's bond
measure. Due to the lack of access to three parcels in the middle of the site, there re-
main unknown risks that haven't been fully estimated.
Next phase: design development
On 7 May Public Safety recommended continuation into the next phase: design devel-
opment. At COW on 14 May, the Council concurred with the recommendation.
GC/CM pre -construction services
Of the seven firms submitting proposals in January, BNBuilders was selected as the
highest -scoring firm in early February. A pre -construction contract with BNBuilders
was unanimously approved by Council 19 March. BNB has been working with the pro-
ject team, providing regular input on the schematic design and estimate.
CONSOLIDATED SHOPS
Property acquisition
Depending on due diligence and site access, the Council should expect final pricing and
closed transactions for the Shop's properties later this year. Site investigations and ne-
gotiations are ongoing.
OTHER RESOURCES
Professional services
The Project Executive Team is working through procurement of additional consultant
resources for the Fire Stations and Justice Center; e.g., envelope consultant, archeolo-
gist, testing, and inspections. Following the envelope consultant 12 February, Council
can expect to see more contracts for these services.
PMQA update
176
May 15, 2018 page 2
PROPERTY ACQUISITIONS
Due diligence
On 20 November, Council approved contracts to conduct surveys, environmental re-
views, and geotechnical analyses to prepare for property acquisitions. That work has
been underway. As expected, soil contamination has been found on the first Justice
Center parcel. On 19 March, the Council unanimously approved amendments to all
three contracts to allow necessary work to continue and to provide contingencies.
These activities continue.
PROGRAM SCHEDULE
Tight schedule
The overall schedule remains very ambitious. With so many activities under way, there
is little room for any missteps to meet the Plan's revised milestones. The Project Exec-
utive Team, City staff, and Council are doing as well as can be expected given all the
new properties' access, due diligence, and acquisition challenges. Fire Station 51 bid-
ding and construction are now expected to begin in January 2019.
PROGRAM BUDGET
Financial gap
On 6 February, the Finance Committee began an intensive work plan to develop recom-
mendations for full Council discussion in June re the Plan's significant financial gap. On
21 February and 6 March, the Committee discussed staff's financial framework and
revenue options in conjunction with the development of the 2019-2020 biennial
budget. On 20 March, the Committee discussed potential cost implications of delaying
any program element(s). On 3 April, the Committee discussed several options pre-
sented by staff on funding and phasing of specific projects. On 17 April, the Committee
continued its review of phasing and revenue options; staff recommended option C1 for
consideration. On 8 May, staff presented and sought Committee consensus on a sched-
ule that will meet the timeline to host an open house on 23 June. On 22 May, staff will
present the updated six-year financial plan to the Committee.
Market conditions
Like the Fire Stations, the Justice Center and Consolidated Shops budgets will need to
be sensitive to tight construction market conditions and increasing property values.
These external budget pressures will manifest themselves as property is procured and
project estimates are refined.
LEGEND
Meeting target
Proceeding as planned.
Caution advised
Steps needed to meet target.
Correction needed
Steps needed to attempt recovery.
Not meeting target
No recovery plan in place.
PMQA update May 15, 2018 page 3