HomeMy WebLinkAboutReg 2018-07-16 Item 4G - Change Order #3 - 42nd Avenue South Phase III / Gilliam Creek Culvert Replacement with Active Construction for $2,741,136 (Plus Tax)COUNCIL AGENDA SYNOPSIS Initials Meeting Date Prepared by 1 Mayor's review Council review 07/09/18 HH ❑ Ordinance Mtg Date ,1 ❑ Public Hearing Mtg Date -,-;n 07/16/18 1 HH1 iI Motion Mtg Date .4 1 i 14- ►1 PW SPONSOR'S Change Order No. 3 to Contract #17-090 is for additional construction costs for the 42nd SUMMARY Ave S Phase III Project. 42"d Ave S has had major issues with the Gilliam Creek Culvert and utility conflicts which have caused delays and cost overruns. After extensive negotiations, Active Construction's Change Order No. 3 will resolve all disputes and require that the project be substantially complete by November 2018. Council is being asked to approve Change Order No. 3 with Active Construction for $2,741,136 (with sales tax). REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte ❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. DATE: 07/09/18 COMMITTEE CHAIR: THOMAS i1 Transportation Cmte ❑ Planning Comm. MCLEOD RECOMMENDATIONS: SPONSOR/ADMIN. COMMITTEE Public Works Presented to TIC on same night, 7/9/18 ITEM INFORMATION ITEM No. 4G CAS NUMBER: !STAFF SPONSOR: HENRY HASH ORIGINAL AGENDA DATE: 07/09/18 AGENDA ITEM TITLE 42nd Construction Ave S Phase Change III Project (S 160th St - Southcenter Blvd) Order No. 3 with with Active Construction, Inc. 07/09/18 ❑ Resolution Mtg Date ❑ Ordinance Mtg Date ❑ Bid Award Mtg Date ❑ Public Hearing Mtg Date ❑ Other Mtg Date CATEGORY ►1 Discussion iI Motion Mtg Date Mtg Date 07/16/18 SPONSOR ❑ Council ❑ Mayor ❑ HR ❑ DCD ❑ Finance ❑ Fire ❑ IT ❑ P&R ❑ Police ►1 PW SPONSOR'S Change Order No. 3 to Contract #17-090 is for additional construction costs for the 42nd SUMMARY Ave S Phase III Project. 42"d Ave S has had major issues with the Gilliam Creek Culvert and utility conflicts which have caused delays and cost overruns. After extensive negotiations, Active Construction's Change Order No. 3 will resolve all disputes and require that the project be substantially complete by November 2018. Council is being asked to approve Change Order No. 3 with Active Construction for $2,741,136 (with sales tax). REVIEWED BY ❑ COW Mtg. ❑ CA&P Cmte ❑ F&S Cmte ❑ Utilities Cmte ❑ Arts Comm. ❑ Parks Comm. DATE: 07/09/18 COMMITTEE CHAIR: THOMAS i1 Transportation Cmte ❑ Planning Comm. MCLEOD RECOMMENDATIONS: SPONSOR/ADMIN. COMMITTEE Public Works Presented to TIC on same night, 7/9/18 COST IMPACT / FUND SOURCE EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $2,741,136.00 $11,774,000.00 $1,992,407.00 Fund Source: 103 RESIDENTIAL STREETS & SURFACE WATER (PAGES 2 & 100, 2017 CIP) Comments: MTG. DATE RECORD OF COUNCIL ACTION 07/09/18 Forward to Regular Meeting Consent 07/16/18 MTG. DATE ATTACHMENTS 07/09/18 Informational Memorandum dated 07/06/18 Active Construction Change Order No. 3 TIC Chair McLeod will report on action from Transportation & Infrastructure 7/9/18 07/16/18 No attachments 51