HomeMy WebLinkAboutPS 2018-08-20 Item 2B - Public Safety Plan - Fire Station #51 Design Development and EstimateCity of Tukwila
111LA
TO:
FROM:
CC:
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
Public Safety Committee
Rachel Bianchi, Communications and Government Relations Manager
Mayor Ekberg
DATE: August 20, 2018
SUBJECT: Fire Stations #51 Design Development and Estimate
ISSUE
The Project Team for Fire Station 51 has completed the Design Development Phase of the
project. The GCCM and the architect's estimator's numbers have been checked against each
other and the reconciled estimate is $8,611,345, which is $205,890 (2.45%) over the currently
approved construction budget of $8,405,455 - within the approved construction budget of
$9,396M, when the tax and preconstruction costs are added.
BACKGROUND
Over the past seven months, the design team completed the Design Development phase of
Station 51. The current estimate amount of $8,405,455 includes the following contingency
amounts, in accordance with the industry standard practices:
• 4 % design contingency of $272,519
• 3% escalation contingency of $212,565
• 3% Construction Manager Contingency of $ 218,942
Since these contingencies total to $704,026 at approximately 10% of the subcontractor's total
scope of work, the design team agree, and Steve Goldblatt, the Council's Program Management
Quality Assurance (PMQA) consultant concurs, that it will be possible to find appropriate project
adjustments and alternates strategies to stay within the approved budget in the Construction
Documents Phase. Some of these deductive alternates would be scopes of work that would not
compromise on functionality of the station, although it would result in lesser quality exterior
materials and surfaces.
RECOMMENDATION
The Public Safety Committee is asked to approve this item and move it to the August 27, 2018
Committee of the Whole for discussion and consensus to approve the project team to proceed
into the next design phase, Construction Documents, which includes the building permit
submittal to the City of Tukwila.
ATTACHMENTS
-Lydig's DD Estimate Summary dated 8/2/2018
-Fire Stations Budgets
3
4
YD
Tukwila Fire Station #51
Selected VE 100% DD Estimate Update
8/2/2018
UNIFORMAT BREAKDOWN
FOUNDATIONS
SUBSTRUCTURE
SUPERSTRUCTURE
EXTERIOR ENCLOSURES
ROOFING
INTERIOR CONSTRUCTION
STAIRS
INTERIOR FINISHES
PLUMBING
HVAC
FIRE PROTECTION
ELECTRICAL
EQUIPMENT
FURNISHINGS
SITE PREPARATION
SITE IMPROVEMENTS
CIVIL & MECHANICAL UTILITIES
ELECTRICAL UTILITIES
GENERAL REQUIREMENTS
TOTALS
12,540 SF
TFS51 Bldg
SITE DEVELOPMENT
DD BUDGET
PROJECT TOTAL
$/SF
Sub Bonds 1.25%
SUBTOTAL
Design Contingency 4.00%
SUBTOTAL
Escalation - Labor & Materials - January 2019 3.00%
SUBTOTAL
Construction Manager Contingency
Negotiated Support Services
MACC SUBTOTAL
Lydig Specified General Conditions -Fixed
Lydig Fee On MACC
100% SCHEMATIC DESIGN ESTIMATE TOTAL
Project Budget
Current Budget Overrun
Current Budget Overrun - Percentage
Ul TFS51 Summary
3.00%
4,50%
$147,937 $147,937
$0
$427,905 $427,905
$950,027 $950,027
$270,403 $270,403
$359,360 $359,360
$31,616 $31,616
$174,762 $174,762
$639,720 $639,720
$649,643 $649,643
$89,676 $89,676
$624,931 $624,931
$70,263 $70,263
$163,789 $163,789
$148,073 $148,073
$860,421 $860,421
$241,209 $241,209
$308,679 $308,679
$570,456 $570,456
$5,170,488 $1,558,383 S6,728,871 $536.59
11.80
0.00
34.12
75.76
21.56
28.66
2.52
13.94
51.01
51.81
7.15
49.84
5.60
13.06
11.81
68.61
19.24
24.62
$64,631 $19,480 $84,111
$5,235,119 $1,577,862 36,812,982 $543.30
$209,405 $ 63,114 $272, 519
$5,444,524 $1,640,977 $7,085,501 $565.03
$163,336 549,229 $212,565
$5,607,860 $1,690,206 $7,298,066 $581.98
$168,236 $50,706 3218, 942
$183,228 $183,228
$5,959,323 51,740,912 $7,700,236 $614.05
3433, 840 $130,759 3564, 599
$268,170 578, 341 3346, 511
$6,661,333 $1,950,013 $8,611,345 $686.71
Page 1 of 1
$
8,405,455
205,890
2.45%
8/2/201 B 1:03 PM
6
PROJECT COSTS
CITY OF TNKWU0A
Public Safety Plan
Fire Stations -51 52 and expended cost for 54
Schematic Design Budget Summary
YOE $ (in thousands)
7/23/2O1Q
Project Category
FS51
17,950sf
FSS2
6,567sf
FS 54
8,228sf
TOTAL
32,745 sf
A/EServices (both design &CA)
731
356
464
1,551
Land Acquisition
-
653
862
1,515
Permits/Fees
255
89
lIG
460
Construction (pre'con,uonst,tax)
7,808
3,278
4,273
15,360
Construction Related Costs (indbond)
1,047
438
651
2,036
PW1Services (inc|other prof avcs)
460
297
397
1,154
Contingency (indConstruction &Proj)
1,I45
546
665
2,356
TOTAL
$ 11,446
$ 5,657
$ 7,3I9
$ 24,432
Project Category
FS51 �
11'933 sf
FS52 �
15,068sf
R5G4
11933 sf
TOTAL
38,934sf
A/EServices (both design &CA)
899
1,244
1,003
3,146
Land Acquisition
854
854
Permits/Fees
234
353
262
849
Construction (pm-con,onnsttax)
8,956
12,677
9'935
31,568
Construction Related Costs (indbond)
931
1,398
1,039
3,367
PW1Services (indother prof sms)
426
687
476
1,589
Contingency (indConstruction &Pnoj)
1,062
1'294
1,185
3,541
1 The main fire station was originally identified as FS51, but has been changed to FS52 in the revised estimate.
2 FS 54 budget includes costs spent to date plus estimated costs to assess the scope of rehabilitation
Project Category
�� �
zz'933�
��� �
z�O68�
FSS4
�sm�
existing
TOTAL
32,399sf
A/EServices (both design QCA)
I,070
1,415
150
2,635
Land Acquisition
-
902
902
Permits/Fees
234
353
20
608
Construction (pre'con,consttax)
9,396
13,298
230
22,925
Construction Related Costs (indbond)
931
1,398
50
2,379
PK8Services (indother prof svod
526
787
100
1,413
Contingency (indConstruction &Pro])
1,115
1,358
50
2,523
TOTAL
g 13,279
$ 18,610
$ 1,502
$ 33,384
FUNDING
GAP
Z:\cvunu|xmenuo 082018 Attachment 2.x1sx, 1.22.18-HIGH
�
,