HomeMy WebLinkAboutCOW 2018-09-10 Item 3C - Public Safety Plan - Fire Station #52 Pre-Design Options and EstimateCOUNCIL AGENDA SYNOPSIS
Initiais
Meeting Date
Prepared by
Mayor's review
Council review
09/10/18
CO
ITEM INFORMATION
ITEM No.
3.C.
STAFF SPONSOR: DAVID CLINE
ORIGINAL, AGENDA DATE: 09/10/18
AGENDA I'I'I?;\r TITLE Fire Station #52 Pre -Design Options and Estimates
C.vTEGORY 11 Discussion
9/10/18
❑ Motion
Altg Date
❑ Resolution
Altg Date
❑ Ordinance
Altg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Altg Date
Mtg Date
SPONSOR ❑Council ►1Mayor HR DCD Finance ❑.Fire TS P&R ❑Police ❑PW Court
Si) ONSOR'S Council consensus is being requested on 2 options:
SLMMARY 1) Retain the current back -in station design, with the alternate bidding of the interior
finishes as described above. This option will keep the City in budget moving forward.
2) Design the drive -through site plan preferred by the Fire Department, with the
understanding of the additional $650,000 of funding required to complete the project.
RI?\'1IAviM I31' ❑ C.O.W. Mtg. ❑ CDN Comm
❑ Trans &Infrastructure ❑ Arts Comm.
DATE: 09/04/18
❑ Finance
❑ Parks
Comm.
Comm.
CHAIR: HOUGARDY
/1 Public Safety Comm.
❑ Planning Comm.
COMMI 1"1 EE
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITrEl;
Mayor's Office
Majority Approval on Option 2-drive through design; forward to C.O.W.
COST IMPACT / FUND SOURCE
EXPINDI'I'URI? RIQU1RI.1ID AMOUNT BUDGETED APPROPRIATION REQUIRED
$0.00 $0.00 $0.00
Fund Source: N/A
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
9/10/18
MTG. DATE
ATTACHMENTS
09/10/18
Informational Memorandum dated 9/4/18, with 4 attachments
Minutes from the Public Safety Committee Meeting of 9/4/18
34
City of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDUM
TO: Public Safety Committee
FROM: David Cline, City Administrator
CC: Mayor Ekberg
DATE: September 4, 2018
SUBJECT: Fire Stations #52 Pre -Design Options and Estimates
ISSUE
The Project Team has updated the Pre -Design estimate for Fire Station #52 project, using the
latest square footage costs recently generated for the Fire Station #51 Design Development
estimate. Due to the high site development cost, storm detention cost and the current
construction market, the project would only be within the currently approved construction budget
of $13,298,000 (including tax and preconstruction cost), if we can delay the interior finishes of
the Fire Department's administrative offices, and the Training Room / back up EOC space.
In addition, the Project Team was requested by the Fire Department to explore an alternate site
plan of being able to drive through the apparatus bays, in lieu of the currently designed back -in
configuration. For long-term operational efficiency, this site plan is preferred by the Fire
Department.
BACKGROUND
In November of 2016, the voters in Tukwila approved the City's Public Safety Bond as a part of
the overall Public Safety Plan. Included in the bond is funding for building fire stations to reduce
the risk of earthquake damage and provide equitable and improved response times.
In the past 2 months, the Project Team updated the Pre -Design phase estimate for FS #52
(from the 2017 estimate). Utilizing the current square foot cost derived from FS#51 DD
estimate, and fine-tuning the site development cost with better geotechnical and storm
infiltration test results, the GCCM was able to stay within budget with a strategy to bid the
interior finishes for the administrative area including the Training Room / back-up EOC as an
alternate. If we can bid this scope as an alternate (shown in Teal in attachments A2 & B2, with
approximately $800,000 in project value), the construction cost estimate of $12,005,384 is
$5,384 over the budget, which is within an acceptable range of the target value to start the
Schematic Design phase.
The project Team including the Fire Department agreed that the proximity of this station to the
existing 6300 building (with the assumption of utilizing the vacancy after the Police
Department's move into the new Justice Center), is a reasonable strategy to be able to keep
moving forward with the project within the current schedule and budget. See Attachments Al &
A2 for details.
The Project Team also evaluated the drive -through station design. The additional paved area
for the rear apron, combined with the expected higher cost of excavation and import of structural
fill material resulted in $650,000 above the current budget (this also assumes bidding the Teal
areas as an alternate). See Attachments B1, B2 for details.
35
INFORMATIONAL MEMO
Page 2
RECOMMENDATION
The Public Safety Committee is asked to make a recommendation to the full Council on whether
to proceed into the Schematic Design phase between the following options:
1) Retain the current back -in station design, with the alternate bidding of the interior
finishes as described above. This option will keep the City in budget moving forward.
2) Design the drive -through site plan preferred by the Fire Department, with the
understanding of the additional $650,000 of funding required to complete the project.
The time -sensitive decision to be made is to choose one of the two site plans. While there is
still time for the Council to decide on whether or not to include finishing of the interior spaces,
the decision to change the site plan to the drive -through option has to be made now. The
design team can not proceed into the Schematic Design phase unless one option is selected by
the Council.
The additional project funding required by these decisions would have to be identified to provide
direction to City staff on moving forward. Some of the possible options for additional funding
could come from one of the following sources; through additional debt financing, utilizing future
apparatus and equipment funds, decreasing costs in other projects or repurposing of general
funds.
ATTACHMENTS
Al - Weinstein AU's site plan for back -in station
A2 — Weinstein AU's pre -design floor plan for back -in station
B1 - Weinstein AU's site plan for drive -through station
B2 - Weinstein AU's pre -design floor plan for drive -through station
36 \\citystore\City Common\Council Agenda Items\Communications\PublicSafetySep4\Fire Station 52 PreDesign Estimate Memo to Council - dc_Ih.docx
Attachment Al
40'-0"
SECTION A
(I r%iZii
eth
EXISTING RETAINING WALL
FILL
126.5
ADMIN /
LINE OF EXISTING GRADE
_ _ _ _ _ LIVING
112.5FF ---- ___
NEW +/-15'H RETAINING WALL
I1Y
<STQIR &'LIF F
43 CITY HALL PARING
W
PRELIMINARY SITE STUDY
ENTRY PLAZA
111.0---------108.0
NEW RETAINING
VISITIN C APPA
ii_i_ i_i__
■■_� _■_ ■■■ar•
99 6a6
WALL
T�U,S/FARKIN
AIMr'
■te•
r
::.IIIIIE3ii . .
AiffiEtiiM
A Now -
Am CIF
ASMW
.Mar
.■ter
W LL W At-•
Ela
r so '
- 6
ii~-
im Li'
All.
TFS52 BACK -IN
TOTAL BUILDING = APPROX 15,800 GSF
ADMIN = APPROX 3,000 SF
1■■■■lPll ■1•\
MEN
98
NEW CONCRETE CURB AND SIDEWALK
ess°
98.39
se gS�A x
s 9q�9 :95.77
SITE AREA: 110,469 SF
SCALE: 1" = 40'
Weinstein A+U
TUKWILA FIRE STATIONS 8/22/18
x 92.1
Attachment A2
NECH
LAUND
BUNKS
BU KS
ELEC
TFS52 BACK -IN CONCEPTUAL LAYOUT
TOTAL BUILDING = APPROX 15,800 GSF
ADMIN = APPROX 3,000 SF
MECH
PHYS TRAINING
WC
GREAT ROOM
BACKUP EOCI TRAINING
UPPOR1
DECK
HAM17 XPL
ADMIN
ED
CONCEPTUAL PROGRAM STUDY SCALE: 1/32" = 1'-0"
w
Weinstein A+U
TUKWILA FIRE STATIONS 8/22/18
O
irrAls
11
VA, 1144,-
40'-0"
EXISTING RETAINING WALL
FILL
122.0
THE
NG WALL'',
131.5
123.0
SECTION A
122.68
120.95
112.0
LINE OF EXISTING GRADE
NEW +/-10'H RETAINING WALL
I1Y
<STQIR &'LIF F
43 CITY HALL PARING
ADMIN
111.0 FF
LIVING
------------
NEW RETAINING
EMS & APP BAY STORAGE
(1-STORY)
TAR
'1031
10,8.46�'
APP BAY
+111.0 FF
LIVING & ADMIN
(2-STORIES)
2ND FLR
DECK
N\� TRAF
GEN '
108.58
MOI J
996ao
ENTRY PLAZA
105.0
WALL
ISITING APPARATU,
%
% MAX S e " ON APRO
10966
+111.O FF I
%D
Priuuiu®uiUl
iraa11=r1i1111ir
SCREE
ro
906 A3 ' 1
ARK
108 99
100 08
Attachment B 1
TFS52 DRIVE TH RU
TOTAL BUILDING = APPROX 15,800 GSF
ADMIN = APPROX 3,000 SF
NEW ONCR
ammommgm ., •uINNEN&'------ ..M5...M.,
rigraWN
(BELOW-GROUN
DETENTIO ' VA 13-)3
o s�
IDEN
98
NEW CONCRETE CURB AND SIDEWALK
959
98.39
9 94�9 :6.77
SITE AREA: 110,469 SF
92.
PRELIMINARY SITE STUDY
SCALE: 1" = 40'
Weinstein A+U
TUKWILA FIRE STATIONS 8/22/18
N
Attachment B2
SUPPORT
EMS
RECEW
AIR
_OCK
FIRST FLOOR
APP BAY
WASH
TFS52 DRIVE-THRU CONCEPTUAL LAYOUT
CONCEPTUAL PROGRAM STUDY
Weinstein A+U
TOTAL BUILDING = APPROX 15,800 GSF
ADMIN (TEAL) = APPROX 3,000 SF
PHYS TRAINING
WC
BACKUP EOCI TRAININ
GREAT ROOM
HAMIEXPL
SUPPORT
WC
L
11111111111111
il
DECK
SECOND FLOOR
ED
SCALE: 1/32" = 1'-0"
TUKWILA FIRE STATIONS 8/22/18
44
City of Tukwila
City Council Public Safety Committee
PUBLIC SAFETY COMMITTEE
Meeting Minutes
September 4, 2018 - 5:30 p.m. - Hazelnut Conference Room, City Hall
Councilmembers: Kathy Hougardy, Chair; Dennis Robertson, Thomas McLeod
Staff: David Cline, Peggy McCarthy, Kim Walden, Eric Dreyer, Aaron Williams, Jay
Wittwer, Vicky Carlsen, Rachel Bianchi, Laurel Humphrey
Guests: Justine Kim, Shiels Obletz Johnsen; Steve Goldblatt, Public Safety Plan Program
Management Quality Assurance Consultant
CALL TO ORDER: Chair Hougardy called the meeting to order at 5:30 p.m.
I. ANNOUNCEMENT
II. BUSINESS AGENDA
Chair Hougardy announced that the Workforce Telestaff System agreement would be postponed to
a future date, and that Shiels Obletz Johnsen (SOJ) would provide a status update on the current
and purchased sites for Station 54.
A. Agreement: Workforce Telestaff System for Police Department
Postponed.
B. Fire Station 52 Pre -Design Options and Estimate
Staff is seeking Council direction on a site plan option to take into the Schematic Design phase
*for Station 51. The pre -design estimate has been completed and the project team has
determined that the project would only be within the currently approved budget if the interior
finishes of the administrative offices and training room/EOC space will be delayed and bid as
an alternate. Since this building is close to the 6300 building, vacancies in the latter can be used
as interim administrative space. In addition, the Fire Department requested the evaluation of
an alternate site plan including the ability to drive through the apparatus bays rather than the
current design of back -in only. It has been determined that a drive through site plan would
result in an additional cost estimated to be $650,000 above the current budget. Choosing either
drive -through or back -in is a time sensitive decision for the Council as the design team cannot
proceed until the choice is made. The additional project funding could come from additional
debt financing, use of future apparatus and equipment funds, decreasing other project costs or
repurposing general funds. Councilmembers discussed the pros and cons of the options.
Councilmember Hougardy asked if there would be a list of other design alternates requested by
the Fire Department. Alternates will be developed during the Schematic Design and Design
Development phases. Councilmember Robertson asked how firefighters would prioritize the
drive -through option on Station 54 with other preferred alternates, and Chief Wittwer stated
this would be top priority. Councilmembers Hougardy and McLeod expressed support for
45
Public Safety Committee Minutes September4, 2018
proceeding with the drive -through design as this is a permanent decision on a 50-year building,
and funding can be worked out. Councilmember Robertson expressed reservation on
committing to additional costs, particularly when addressing City Hall and 6300 Building
deficiencies remains unplanned and unfunded. MAJORITY APPROVAL. FORWARD TO
SEPTEMBER 10, 2018 COMMITTEE OF THE WHOLE.
C. Fire Station 54 Status Update
SOJ and staff provided a status update on activities associated with the current Fire Station 54
site as well as the new site that was purchased prior to the Council's decision to remove a new
station from the Public Safety Plan. Per the Council's direction, a building assessment is
underway and the Committee will receive cost estimates for varying tiers of retrofit within the
next month. Councilmember Robertson requested a table comparing cost estimates for
Station 54 both before the Council's "D-20" decision and after, including retrofit costs and the
soft costs absorbed by the other two stations. The Star Nursery site purchased for the proposed
new Station 54 has a derelict house on it that should be demolished as soon as possible due to
its liability to the City. SOJ is collecting estimates on the demolition cost, which is funded by
the approved Lydig contract amendment for preconstruction services. The Committee
expressed support for moving ahead with demolition as soon as possible.
D. 2019-2020 Biennial Budget: Public Safety Plan and City Facilities
Staff returned with the additional information requested on the proposed budgets for Public
Safety Plan (305 Fund) and City Facilities (306 Fund). The Public Safety Plan fund is used to
account for construction costs associated with the new Justice Center and fire stations,
including voter -approved debt, LTGO debt and dedicated revenue sources. The City Facilities
fund includes LTGO bond proceeds in 2019 to purchase land and remodel facilities for the
Public Works Shops facility. In response to information requests made at the last meeting, staff
added details explaining capitalization of supplies and equipment, clarified Capital
Improvement Program "revenues," added a summary of costs spent to date and proposed
budget for Station 54, and provided further explanation on the proposal to change the debt
issuance to $25 million to true up the budget for these funds. $297,000 is the proposed
estimate for the cost to retrofit Station 54. If the Council agrees with the $25 million debt
issuance, the drive -through design on Station 52 will be funded. Committee members
expressed support for $25 million with the understanding that not all we used if not needed.
They requested the 305 and 306 budgets return prior to moving on to Committee of the Whole.
RETURN TO COMMITTEE.
III. MISCELLANEOUS
Adjourned 6:33 p.m.
Committee Chair Approval
Summary by LH
46