HomeMy WebLinkAboutPS 2018-10-01 Item 2B - Public Safety Plan - Justice Center Design DevelopmentCity of Tukwila
Allan Ekberg, Mayor
INFORMATIONAL MEMORANDU
TO: Public Safety Committee
FROM: Rachel Bianchi, Deputy City Administrator
CC: Mayor Ekberg
DATE: September 24, 2018
SUBJECT: Justice Center Design Development
ISSUE
The City has completed Design Development of the Justice Center. The end of Design
Development provides the owner with a more refined budget number for the project based on a
more detailed design. After significant Council review and deliberation, the budget for the
Justice Center was increased to $68.5 million, largely due to cost escalation and market
conditions. The Schematic Design estimate confirmed this budget. The Design Development
estimate further confirms this budget.
BACKGROUND
The Justice Center will hold the City's Police Department, Municipal Court and Emergency
Operations Center. It will provide a seismically safe, efficient facility for City staff and better
access to key City services for the public. Stakeholders from the Police Department, Court and
EOC have been directly involved in the planning and design of the facility, which features the
following:
• Conference center area allows for flexible use by City staff and the community that morphs
into the Emergency Operations Center during an activation; this maximizes the use of
key space.
• Modern Court facilities, including necessary private meeting rooms, holding area, and
probation spaces.
• Critical police functions addressed, including records area, evidence, training facilities and
team areas to facilitate teamwork.
• HUB area that creates a joint staff room area for co-worker collaboration.
• Planned areas for future expansion (second court room when needed, additional office
space for the Police Department).
The building as currently designed totals approximately 47,200 square feet. Similar to the
process with the fire stations, once Design Development was finished, DLR Group's cost
estimator, Roen, and the General Contractor/Construction Manager (GC/CM) firm, BNBuilders
(BNB), developed cost estimates for the Justice Center independently of each other. Both initial
cost estimates came within less of one percent of each other and the two organizations have
reconciled to the same estimated construction costs as the Schematic Design number, that
stays within the approved $68.5 million total project budget. The ability to have a GC/CM on
board early and throughout the Schematic Design and Design Development phases directly led
to this successful cost estimate reconciliation.
Although the design advanced significantly from Schematic Design to Design Development, the
overall cost estimates and budget remained on target with minimal adjustments. These
included:
3
INFORMATIONAL MEMO
Page 2
* Construction costs decreased slightly, from $38.738,578to338727.363. Additional detail
can befound iOthe BNBui|dersEstimate Comparison attached.
* Project Management services increased from $1.5B4.00Oto$1.815,875due toan
increase in Construction Management fee allocation, as well as additional consultant
fees for legal and other professional services.
° Land Acquisition decreased from $14.133.2S5tO$14.D52.253aooresult ofclosed
transaction prices while Contingency for Land Acquisition increased from $1,250,000 to
$1.55O.00Odue tobusiness assistance.
° (]mara|| project contingencies decreased from $5.757.731 to $5.33O.213tOfund the
adjustments listed above.
RECOMMENDATION
Staff is seeking committee approval to forward this issue to the October 8, 2018 Committee of
the VVh[de meeting with a recommendation that the City continue into the Construction
Documents phase for the Justice Center.
Despite the budget challenges, the need for amodern, Justice Center remains very real, for the
broader community and for the staff that work inthese facilities. The Council will continue to
have decision points in the future that provide "off ramps" if so desired.
ATTACHMENT
-Justice Center Design Development PresentstiOn
-BNBui|deraEstimate Comparison
-Justice Center Budget
TUKWILA JUSTICE CENTER
U'i
TUKWILA JUSTICE CENTER I landsca
De site plan
0)
pOref A*, -
(71
SHRUB/GROUNDCOVER AREA
CONCRETE PAVEMENT
CONCRETE AND WOOD
FURNISHINGS
QUANTITY: PARKING:
LARGE TREES
MEDIUM TREES
SMALL TREES
MAIN LOT:
21 POLICE (LARGER STALLS)
52 STANDARD (34 STAFF, 18 VISITOR)
32 COMPACT
NORTH LOT:
6 ADA
59 STANDARD
SHRUB/GROUNDCOVER AREA 25 COMPACT
STORIVIWATER DETENTION AREA TOTALS:
10 ADA
21 POLICE
LAWN AREA 111 STANDARD
57 COMPACT
CONCRETE AREA
ASPHALT AREA
SITE FURNISHINGS
LAWN AREA
WOOD STAGE
ART POLES
GRAND TOTAL:
199 STALLS
BIOFILTRATION
AREA
ASPHALT PAVEMENT
"1-
SWIFT COM PAW Lic
JULY 27, 2018
LEVEL 1 AREA
Police
EOC
Courts
Shared Spaces
Building Support
13,532
2,047
9,685
5,866
1,015
Total 32,145 GSF
TOTAL FACILITY GROSS SF AREA
Police 28,798
EOC 2,047
Courts 9,685
Shared Spaces 5,866
Building Support 1,671
Total 48,067 GSF
00
LEVEL 2 AREA
Police
EOC
Courts
Shared Spaces
Building Support
15,266
656
Total 15,922 GSF
TOTAL FACILITY GROSS SF AREA
Police 28,798
EOC 2,047
Courts 9,685
Shared Spaces 5,866
Building Support 1,671
Total 48,067 GSF
CITY OF TUKWILA
Public Safety Plan
Justice Center
Conceptual Budget Summary
YOE $ (in thousands)
PROJECT COSTS
ce Cente
Project Category
SC E
ATICIDESIGISL
Estimate
A/E Services (both design & CA)
3,500,000
Permits/Fees
700,000
Construction: Building & Site Development (pre -con, const, tax)
38,738,678
Construction Related Costs (incl bond)
2,112, 639
PM Services (incl other prof svcs)
1,594,000
Contingency (incl Construction & Proj)
5,757,731
Contingency for Site Contamination (soils, hazmat)
750,000
SUBTOTAL
53,153,048
Land Acquisition
14,133, 295
Contingency for Land Acquisition
1,250,000
TOTAL
68,536,343
teiCenteDESIGNEDEVEL.
Project Category
BUD ES ATUropt
Estimate
ALE Services (both design & CA)
3,500,000
Permits/Fees
700,000
Construction: Building & Site Development (pre -con, const, tax)
38,727,363
Construction Related Costs (incl bond)
2,112, 639
PM Services (incl other prof svcs)
1,815,875
Contingency (incl Construction & Project)
5,328,213
Contingency for Site Contamination (soils, hazmat)
750,000
SUBTOTAL
52,934,090
Land Acquisition
14,052,253
Contingency for Land Acquisition
1,550,000
TOTAL
68,536,343
• COUNCIL CONSENSUS TO PROCEED
• CONSTRUCTION DOCUMENTS
• TARGET VALUE COORDINATION WITH GCCM
• CITY LAND USE AND PERMITTING PROCESS
• EARLY CONSTRUCTION PACKAGES FOR GCCM
• CONSTRUCTION START APRIL 1
B
NB
BNB SD vs DD ESTIMATE COMPARISON
CONFIDENTIAL
BN Builders
PROJECT: JUSTICE CENTER
OWNER: CITY OF TUKWILA
ARCHITECT: DLR GROUP
Building System Breakdown
A10 - Foundations
A20 - Basement Construction
B10 - Superstructure
B20 - Exterior Enclosure
B30 - Roofing
C10 - Interior Construction
C20 - Stairs
C30 - Interior Finishes
D10 - Conveying
D20 - Plumbing
D30 - HVAC
D40 - Fire Protection
D50 - Electrical
E10 - Equipment
E20 - Furnishings
F10 - Special Construction
F20 - Selective Building Demo
G10 - Site Preparation
G20 - Site Improvements
G30 - Site Mech Utilities
G40 - Site Elec Utilities
G90 - Other Site Construction
Direct Construction Costs (DCC)
Design / Estimating Contingency
Escalation
Negotiated Support Services
Trade Package Bonds (See Sub Plan)
MACC Contingency (%-DCC + Des + Esc TP)
Maximum Allowable Construction Cost (MACC)
Contractors Fee (% of MACC - Bid %)
Specified General Conditions
Specified General Conditions
Specified General Conditions
GC/CM Performance & Payment Bond
BNB Insurances
B&O Taxes
Preconstruction Services
Total Contract Costs (TCC)
Washington State Sales Tax
Guaranteed Maximum Price (GMP)
$ per GSF / Component GSF
SD ESTIMATE (RECONCILED 4/26/18)
Total Project Cost
RECONCILED - WITH BOL
ESTIMATE TYPE:
ISSUE DATE:
DD ESTIMATE (RECONCILED w/BOL 9/25/18)
Iota Project Cos
DD
9/25/2018
Total Cost
r-rrfrtWr'Pr5Zgfr4-)y-
Zi&iTfw yef-MDerimx r157 Tirfrirgif r;„
VO
31,7501 34.71 1 23.14 1 $ 1,102,069 1 32,1501 $ 36.50 1 24.64 1 $ 1,173,396 11 71,327 1 1 Geo Layer + Slight Bldg Footprint Increase.
01 -
Comments
4- 7,200 $ 38.08 37.74 1 1,797,562
25,148 $ 102.95 54.35 1 $ 2,588,884
31,750 $ 32.91 21.94 1 $ 1,044,898
47,200 $ 52.21 51.74 $ 2,464,197
47,200 $ 1.68 $ 1.67 1 $ 79,466
47,200 $ 24.42 $ 24.20 $ 1,152,633
4- 7,2001 $ 2.12 $ 2.10 1 $ 100,000
47,200, $ 15.33 $ 15.19 $ 723,470
47,200 $ 51.60 $ 51.13 1 $ 2,435,520
47,200 $ 5.52 $ 5.47 $ 260,362
47,2001 $ 49.42 $ 48.98 1 $ 2,332,689
47,200 $ 16.50 $ 16.35 $ 778,674
4- 7,200 $ 8.81 $ 8.73 1 $ 416,038
01 $ - $
54,821 $ 9.12 $ 10.50 $ 500,000
198,519 $ 10.38 $ 43.25 $ 2,059,902
- 1 $ 01 $ - - $ -
40.08 $ 1,908,951 11
$ 529.64 $24,999,217
% of DCC ---> SUB PLAN 1 $ 2,224,519
% of DCC ---> SUB PLAN 1 $ 1,931,898
EST DETAIL 1 $ 1,762,449
% of DCC ---> SUB PLAN 1 $ 437,335
2.50%1 $ 739,824
$ 679.98 $32,095,242
5.00%1 $ 1,604,762
(AS -BID) $ 580,891
(JC-9 Early)
Addll MACC Value $ 696,084
Included w/Fee
Included w/Fee
Included w/Fee
Owner (Bid) Value $
240,000
$ 746.12 $ 35,216,979
10.00%1 $ 3,521,698
47,630 $ 40.08
25,875
97.74
53.10
2,529,101
37,195 29.05 1$
47,630 $ 2.74 1 $
47,630 $ 20.21 1 $
47,6301 $ 2.31 1 $
47,630 $ 52.49
111,389 1 1 Slight Bldg Size Increase, Steel Unit Costs, More NLT
(59,783) Canopy at HUB Plaza, Panel/Screen Scope
22.69 $ 1,080,660 1 35,762
52.49 $ 2,500,067 1 35,870 Custom Woodwork, GWB Increases
2.74 $ 130,530 1 51,064 Added Stair to roof, Feature Stair Increase
20.21 $ 962,366 $ (190,267)
2.31 $ 110,000 1 $ 10,000
47,630 $ 15.88 $
47,630 $ 44.98 $
47,630 $ 6.38 $
47,6301 $ 57.13 $
47,630 $ 27.91 $
47,630 $ 12.19 $
15.88 $ 756,450 $ 32,980
44.98 $ 2,142,635 j (292,885)1
6.38 $ 304,007 $ 43' 645
57.13 $ • 2,721,086 1 $ 388,397 Added Low Voltage Scope
27.91 $ 1,329,342 $ 550,668 Security walls and ceilings, Lab Eq
12.19 $ 580,544 1 $ 164,506 Casework and Tops
,
- $ - 0 $ - , $ - $ - $ -
54,8211 $ 10.02 $ 11.53 ' $ • 549,164 1 $ 49,164 Rat eradication.
204,659 $ 8.92 $ 38.31 $ 1,824,765 $ (235,137)
204,6591 $ 11.69 $ 50.22 $ 2,391,816 1 $ 466,805 Landscape Density and Art Poles
204,6591 $ 12.74 1 $
204,6591 $ 2.78 1 $
01 $ - 1 $
54.74 $ • 2,607,198 $ (229,918)
11.95 $ 569,288 1 $ 168,562
$ 549.47 $26,171,366
$1,172,149
1,886,001 11 $
1,050,154 11$
1,780,660 11 $
$ 435,360
$ 738,572 $
$ 673.15 $32,062,113
(338,518)1 1 See Sub Plan for Development of This Value
(881,744) 1 See Sub Plan for Development of This Value
18,211 1 1 Reference Estimate Detail Information
(1,975) 1 See Sub Plan for Development of This Value
(1,252) 1 % Based Calculation
($33,129)
$ 1,603,106 $
580,891
25,818 $
$ 694,766
$ - $
(1,656) 1 % Based Calculation
- 1 As -Bid Specified General Conditions
25,818 1 JC-9 Early Demolition
(1,318) 1 % Based Calculation for Value Above Original MACC
- ' Included with Fee
- Included with Fee
Included with Fee
$ 240,000 $
$ 739.17 $ 35,206,693
3,520,669
(10,286)
Allowance
(1,029) % Based Calculation
$ 38,738,677
$ 38,727,363
(11,314)
$ 820.73 47,200
$ 813.09
47,630
430
Slight Increase in Building GSF
12
CITY OF TUKWILA
Public Safety Plan
Justice Center
Conceptual Budget Summary
YOE $ (in thousands)
PROJECT COSTS
Project Category
Estimate
ALE Services (both design & CA)
3,500,000
Permits/Fees
700,000
Construction: Building & Site Development (pre -con, const, tax)
38,738,678
Construction Related Costs (incl bond)
2,112,639
PM Services (incl other prof svcs)
1,594,000
Contingency (incl Construction & Proj)
5,757,731
Contingency for Site Contamination (soils, hazmat)
750,000
SUBTOTAL
53,153,048
Land Acquisition
14,133,295
Contingency for Land Acquisition
1,250,000
TOTAL
68,536,343
SIG. MEV
Project Category
T BUDGET ESTIMATE
01
Estimate
A/E Services (both design & CA)
3,500,000
Permits/Fees
700,000
Construction: Building & Site Development (pre -con, const, tax)
38,727,363
Construction Related Costs (incl bond)
2,112,639
PM Services (incl other prof Svcs)
1,815,875
Contingency (incl Construction & Project)
5,328,213
Contingency for Site Contamination (soils, hazmat)
750,000
SUBTOTAL
52,934,090
Land Acquisition
14,052,253
Contingency for Land Acquisition
1,550,000
TOTAL
68,536,343
13