HomeMy WebLinkAboutTIC 2018-10-08 Item 2E - Discussion - 2019 Annual Overlay and Repair ProjectAllan Ekberg, Mayor
Public Works Department - Henry Hash, Director
INFOR ATIONAL E ORANDU
TO: Transportation and Infrastructure Committee
FROM: Henry Hash, Public Works Director
BY: Cyndy Knighton, Senior Program Manager and Scott Bates, Traffic Operations
Coordinator
CC: Mayor Ekberg
DATE: October 5, 2018
SUBJECT: 2019 Annual Overlay and Repair Project
Project No. 91910401
ISSUE
Brief the Transportation Committee on the selection process used to develop the 2019 Annual Overlay
and Repair project list.
BACKGROUND
Every year road segments are identified for possible inclusion in the City's annual Overlay Program.
Tukwila uses a pavement management system (PMS) to rate the condition of the pavement which is
the first step in identifying street segments for overlay. The PMS includes a visual and physical
inspection of all paved roads in the City, which is conducted every few years to keep the pavement
conditions current. The last inspection was done in 2014. A planning -level cost estimate is developed
based on the condition of the pavement.
Using the pavement scores created in the PMS, staff considers the pavement condition and preliminary
cost to overlay, along with other factors such as frequency of ongoing maintenance needs to develop
a "long list" of potential projects for the next overlay cycle. The selected consultant for the design work
is then authorized to begin the design on the "long list," and develop more refined cost estimates. When
the design work is at 50%, staff meets with the design team to select the final list of street segments
that will be fully designed and constructed. At that point, selection of the final list is generally made
based on funding availability for the highest priority segments. The locations not selected for final design
are generally brought forward the following year for completion.
DISCUSSION
The "long list" for the 2019 Overlay and Repair Program was identified by staff and negotiations are
underway with KPG for the design work. Staff will brief the Committee members on the process and
discuss the selected locations for 2019.
FINANCIAL IMPACT
No financial impact is associated with this item, but the 2019 list will be tailored to the available budget.
RECOMMENDATION
Information only.
Attachments: Map of Proposed 2019 Locations ("Long List")
Overlay Program Street List (2017-2022)
Map of 2017-2022 Overlay Needs
Map of City-wide Pavement Condition Rating
\\pwstore\pw common$\pw eng \projects \a- rw & rs projects \ annual overlay & repair programs 12019 overlay & repair program\info memo - briefing to tic on selection process 10-8-
1eidocx
39
RAINIER
GOLF &
COUNTRY
CLUB
W(
40
Tukwila Overlay Program Street List - (2017-2022)
Commercial and Residential in order of priority starting with highest (most severe rating)
Updated 8/3/16
r i
Class Street Limits Notes
PMS Pavement
Condition Rating
ROM Construction
Cost (July 2018)
Notes (July 2018)
1
West Marginal Place from 102nd to city limit. M&O List
35
$ 1,000,000.00
KC concern with proximity to 96" interceptor
2
West Marginal Way Cecile Moses Park to 102nd St. & the north City Limits line
46
$ -
This segment is in good shape
3
_ Interurban Ave. South 42nd Ave. north the East Marginal Way
50
$ 616,000.00
4
Interurban Ave. South 42nd Ave. southerly to1-5 off -ramp.
50
$ 504,000.00
5
Interurban from Macadam (42nd Ave) north to new asphalt. Approx. 200 Ft. M&O List
50
incl. above
Included in segment above
6
Orilla Rd. North city limit to south city limit. M&O List
50
$ 1,216,000.00
7
East Marginal Way Norfolk North to new pavement (North 800 LF) - Committed to FHWA
63
$ 219,000.00
8
200th St. S. Orilla Rd. to S.C. Pkwy. M&O List
65
$ 455,000.00
9
Boeing Access Rd. East bound to 15 overpass, west bound from 15 to new. M&O List
65
$ -
Need to review
10
Southcenter Parkway Minkler Boulevard to McDonald's south of Strander Priority #2 Major Segment
67
$ 759,000.00
11
. Andover Park West Strander Boulevard to S. 180th Street
74
$ 1,074,000.00
12
Minkler Blvd. APE to city shops. M&O List
74
$ 203,000.00
Overlaps Minkler below
13
- - - - Southcentcr Boulevard McAdam to 66th Ave Bridge (T Line)
7-6
$ -
Completed
Minkler Blvd. Andover Park East to Industry Drive
14
77
$ 132,000.00
15
Andover Park East 180th to Costco Dr
80
$ 195,000.00
Completed with sewer?
16
Interurban Ave. South 58th Avenue northerly to 1-5 along golf course
82
$ 875,000.00
17
Interurban Ave. South 58th Avenue South and southerly to the reconstructed portion
84
$ 146,000.00
18
Andover Park West 180th to Minkler
86
$ 506,000.00
19
5. 180th Street Southcenter Pkwy to Zepp Bridge over the Green R. Priority #3 Major Segment
96
$ 632,000.00
20
S. 180th Street West Valley Highway to the east City Limits
96
$ 207,000.00
Total Arterial Estimate $ 8,739,000.00
2019 Target Budget
21
45th Ave S. At 1,9th Leg Gravel
l.0 UD ,C, N CO 00 CO GT
$ -
Completed
(West area)
S. 128th Street Military » 650 feet East. Priority / M&O List
22
$ 170,000.00
Remote from others, no concrete work
23
1, 5, 133rc Street 5, 134th P1. East Marginal Way
$ -
Completed
12t t
1 11 �_° 51st Ave. S. S. 137th Street to S. 138th Street behind Foster Upper Field
24
$ 94,000.00
Cleanup following 53rd project
25
I '. 58th Avenue S Interurban S. 142nd Street
$ -
Completed
uth to
• S.128th St. East Marginal Way to M&O Li,t
26
$
Completed
• west new.
S.130th St. 34th Avc 32nd Ave. M&O Li,t
27tl
$ -
Completed
to
14�rd Place Interurban Ave. to end
28
$
Completed
29
�1�
5. 128th Street Ea.Marginal Way 37th Ave.
$
Completed
,t we,terlq to
) S. 144th St. 42nd to 46th Ave S. east bound lane. M&O List
30
incl. below
Good candidate in combo with project below
31
' . S. 144th Street 42nd to Showalter (48th approx.)
$ 425,000.00
Significant tree issues with curb and sidewalk
32
S. 137th Street West of Macadam Road to 43rd
$ 300,000.00
Some ramp work required
33
13 52nd Ave. S. West of Interurban up to 51st Street
$ 303,000.00
Cleanup following 53rd project
34
t a 143rd Interurban Ave. to end
$ 248,000.00
Industrial dead end off IU
35
' 55th Avenue S. North of 144th Street to 140th
$ 338,000.00
Cleanup following 53rd project
36
) _ S. 126th Street East Marginal Way westerly to 37th Ave.
$ 138,000.00
Some ramp work required
37
East Marginal Way Near Light Rail from Interurban to the bridge over SR599
$ -
Good condition
1�- Total Residential Estimate
$ 2,016,000.00
-' 2019 Target Budget
RAINIER
GOLF &
COUNTRY
CLUB
W(
42
Pavement Condition Rating
PCR Values
masterMap.PE_PCR
< 20
20-39
40 - 59
60 - 79
80 - 100
Figure 11. Pavement Engineers,pc.