HomeMy WebLinkAboutReg 2018-11-19 Item 3F - Final Acceptance - 2017 Overlay and Repair Program with ICON Materials for $563,162.38COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
11/19/18
Prepared by
HH
Mayor's review
eX'
Council review
t•\
ITEM INFORMATION
ITEM No.
3.F.
STAFF SPONSOR: HENRY HASH
ORIGINAL AGENDA DATE: 11/19/18
AGENDA ITEM TIME 2017 Overlay and Repair Program
Project Completion and Acceptance
CATEGORY . Discussion
Z Motion
Mg Date 11/19/18
E] Resolution
Mtg Date
11 Ordinance
Mtg Date
U Bid Award
Al tg Date
['Public Hearing
Mtg Date
U Other
Mtg Date
Mg Date
SPONSOR Council UMayor 01-IR Li DCD U Finance UFire UTS UP&R UPolice Zmr7 UCourt
SP ONSOR' S The contract with ICON Materials is complete for the 2017 Overlay and Repair Program.
SUMMARY This project included asphalt paving at five locations and a portion of the parking lot at
Fort Dent Park. Construction began August 14, 2017 and was physically completed on
October 27, 2017. Additional warranty work kept the contract open. Underruns show a
credit of ($96,278.62). Council is being asked to accept and finalize the contract with ICON
Materials for $563,162.38.
REVIEWED BY
0 C.O.W.
Mtg. 0 CDN Comm El Finance Comm. III Public Safety Comm.
U Arts Comm. Ej Parks Comm. ill Planning Comm.
cOmmIllEE CHAIR: THOMAS MCLEOD
Trans &Infrastructure
DATE: 11/13/18
RECOMMENDATIONS:
SPONSOR/ADMIN.
CommiTrEE
Public Works Department
Unanimous Approval; Forward to Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$563,162.38 $692,413.05 $
Fund Source: 104 ARTERIAL STREETS
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
11/19/18
MTG. DATE
ATTACHMENTS
11/19/18
Informational Memorandum dated 11/09/18
Notice of Completion Contract #17-141
Minutes from the Transportation and Infrastructure Committee 11/13/18
101
102
Allan Ekberg, Mayor
Public Works Department - Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Henry Hash, Public Works Director # i/-
BY: Scott Bates, Traffic Engineering Coordinator
CC: Mayor Ekberg
DATE: November 9, 2018
SUBJECT: 2017 Overlay and Repair Program
Project No. 91710401, Contract No. 17-141
Project Completion and Acceptance
ISSUE
Accept the construction contract with ICON Materials as complete and authorize release of performance
bond.
BACKGROUND
The Notice to Proceed for Contract No. 17-141 with ICON Materials, Inc. of Pacific, Washington was
issued on August 14, 2017 for the 2017 Overlay and Repair Project. This overlay project provided hot
mix asphalt paving at five locations throughout the City and a portion of the parking lot at Fort Dent
Park. The street improvements included: pavement grinding; asphalt paving; removing and replacing
concrete curbs; gutters; sidewalks and ADA ramps; adjusting surface utilities to grade; and installing
roadway channelization.
ANALYSIS
Construction was physically completed on October 27, 2017. The budget for the 2017 Overlay &
Repair construction was $692,413.05 for Schedule "A" and "B" (Fort Dent). This included a 5%
contingency, which was not utilized. No change orders were executed. A performance bond is being
held for the retainage. In late 2017, after the paving weather window closed, it became apparent
cosmetic pavement warranty work was needed at Fort Dent and this work was recently completed in
2018.
Construction Contract Amount
Under -runs
Total Amount Paid
$659,441.00
(96,278.62)
$ 563,162.38
RECOMMENDATION
Council is being asked to formally accept and authorize the release of the performance bond, subject to
standard claim and lien release procedures, for the 2017 Overlay and Repair Project with ICON
Materials, in the final amount of $563,162.38 and consider this item on the Consent Agenda at the
November 19, 2018 Regular Meeting.
ATTACHMENTS
Notice of Completion Contract No. 17-141
W:IPW EngIPROJECTSIA- RW & RS Projects Annual Overlay & Repair Programs12017 Overlay & Repair Program(9170401)1Constructon\Contractor\Close Out to TCIOocs to TICtinfo memo 2017 Overlay Closeout gl.docz
103
104
(Y1 Original
❑ Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Date: 10-9-2018 Contractor's UBI Number: 601 006 854
Name & Mailing Address of Public Agency
City of Tukwila
6200 Southcenter Blvd Tukwila, WA 98188
UBI Number: 91-6001519
Department Use Only
Assigned to:
Date Assigned:
Notice is hereby given relative to the completion of contract or project described below
Project Name
2017 Annual Overlay Program 917104401
Contract Number
17-141
Job Order Contracting
❑ Yes VNo
Description of Work Done/Include Jobsite Address(es)
Hot Mix Asphalt (HMA) Overlay at the following locations: S.128th St, S.133rd St, S.130th St, S.143rd
St, 45th Ave s and Ft dent park.
Federally funded transportation project? ❑ Yes [1 No (if yes, provide Contract Bond Statement below)
Contractor's Name
ICON
E-mail Address
mark.eichelberger@iconmatef
Affidavit ID*
771616
Contractor Address
1508 Valentine Ave SE Pacific, WA 98047
Te
206-575-3200
ephone #
If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number.
Retainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects)
Name: Fidelity and deposit Company of Maryland Bond Number: 9262708
Date Contract Awarded
8-7-17
Date Work Commenced
8-14-2017
Date Work Completed
10-4-2018
Date Work Accepted
-
Were Subcontracters used on this project? If so, please complete Addendum A. LYjYes ❑ No'
[if
Affidavit ID* - No L&I release will be granted until all affidavits are listed.
Contract Amount
Additions (+ )
Reductions (- )
Sub -Total
Sales Tax Rate n/a rule 171 e%
(If various rates apply, please send a breakdown)
Sales Tax Amount
i
$ 659,441.00
$ 96,278.62
$ 563,162.38
$
Liquidated Damages $ 0.00
Amount Disbursed $ 563,162.38
Amount Retained $ 0.00
TOTAL $ 563.1 62.38
• - NOTE: These two totals must be equal
TOTAL $ 563,162.38
Comments:
Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber
Email Address: Diane.jaber@tukwilawa.gov
fta
Department of Revenue
Public Works Section
(360) 704-5650
PWC@dor.wa.gov
Washington State Department of
Labor & Industries
Contract Release
(655) 545-8163, option # 4
ContractRelease@LN I. WA.GOV
Title: Fiscal Specialist
Phone Number: 206-433-1871
Employment Security
Department
Registration, Inquiry,
Standards 8, Coordination
Unit
(360) 902-9450
publicworks@esd.wa.gov
105
REV 31 0020e (10/26/15) F215-038-000 10-2014
Addendum A: Please List all Subcontractors and Sub -tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name:
UBI Number: (Required)
Affidavit ID*
Northwest concrete cutting
603 572 428
751318
0-CO Concrete Construction
603 560 682
752635
Pacwest grinding
603 493 970
753276
Bilbrey Construction
603 002 155
752792
Apply -a -line
600 553 941
776714
Moby's 24hr street sweeping
603 358 194
752391
Cascade Utility adjusting
603 407 046
751324
For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the
Washington Relay Service by calling 711.
REV 110)&0e Addendum (10/26/15) F215-038-000 10-2014
City of Tukwila
City Council Transportation & Infrastructure Committee
TRANSPORTATION & INFRASTRUCTURE COMMITTEE
Meeting Minutes
November 13, 2018 - 5:30 p.m. - Hazelnut Conference Room, City Hall
Councilmembers: Thomas McLeod, Chair, De'Sean Quinn, Zak Idan
Staff: David Cline, Henry Hash, Hari Ponnekanti, Cyndy Knighton, Scott Bates, Steve
Carstens, Gail Labanara, Laurel Humphrey
CALL TO ORDER: Committee Chair McLeod called the meeting to order at 5:30 p.m.
MISCELLANEOUS
Staff stated that after reporting last week that the 53rd Avenue South project could be paved by
the end of December, the contractor communicated that the cost would be an additional $110k.
This is cost prohibitive, and paving conditions are generally better in February anyway. Chair
McLeod will report out at the Council meeting.
I. BUSINESS AGENDA
A. South 140th Street Pedestrian Improvements
Staff reported that the siting and design work is continuing along with communication with
the Director of the Abu Bakr Islamic Center. The Transportation Improvement Board meets
at the end of this week and the City should hear on the status of its grant application soon.
DISCUSSION ONLY.
B. Project Completion: 2017 Overlay and Repair Program
Staff is seeking Council approval of project completion and release of the retainage bond
to ICON Materials, Inc. for a project total of $563,162.38 for the 2017 Overlay and Repair
Project. This project provided hot mix asphalt paving at five locations and a portion of the
parking lot at Fort Dent Park. Construction was completed on October 27, 2017. Cosmetic
pavement warranty work was recently completed at Fort Dent Park. UNANIMOUS
APPROVAL. FORWARD TO NOVEMBER 19, 2018 REGULAR CONSENT AGENDA.
C. Project Completion: Baker Boulevard Non -Motorized Improvements Project
Staff is seeking Council approval of project completion and release of the retainage bond
to Road Construction Northwest, Inc. for a project total of $828,198.09 for the Baker
Boulevard Non -Motorized Improvements Project. This project included bike lanes and a
road diet on Baker Boulevard from Andover Park West to Christensen Road.
Reconstruction of the sidewalk access ramps at the intersection of Andover Park
East/Baker Boulevard was part of the Americans with Disabilities Act Program and
included with this project for cost savings. Work was physically completed on July 2.
UNANIMOUS APPROVAL. FORWARD TO NOVEMBER 19, 2018 REGULAR CONSENT
AGENDA.
107