Allan Ekberg, Mayor
`°0\,,,,,,_ __A?
29os° INFORMATIONAL MEMORANDUM
TO: Public Safety Committee
FROM: Rachel Bianchi, Deputy City Administrator
CC: Mayor Ekberg
DATE: November 28, 2018
SUBJECT: Architect's Amendment# 2 to Contract#17-068 for Fire Stations #51 & #52
ISSUE
The City issued the architect's and engineering (A&E) contract with Weinstein Architects
and Urban Designers (WAU) for the design of three fire stations in April of 2017. At that time,
the contract was based on the City's original 2016 estimates for the three fire stations. The
contract was amended July 2018 to reflect the updated construction costs, as well as the
deletion of the new Fire Station 54. However, at that time the additional costs to stations 51 and
52 resulting from removing Fire Station 54 (approximately 5% per station) were inadvertently left
out, resulting in the need to update WAU's contract to reflect the firm's actual fees, which are
tied to the construction costs. In addition, there are some additional fees previously discussed
with Council for making Fire Station 52 a drive-through station and retaining various alternates
associated with each station.
The Council is being asked to approve a contract amendment with WAU for the increase in the
amount of$383,462 in order to compensate the A&E team according to the Washington's
State's A&E Fee Guidelines for their services, as well as some additional services required to
carry out the project designs. This increase is within the existing budget for Fire Stations 51 and
52.
BACKGROUND
In November of 2016, the voters in Tukwila approved the City's Public Safety Bond as a part of
the overall Public Safety Plan. Included in the bond is funding for building three fire stations to
reduce the risk of earthquake damage and provide equitable and improved response times.
By early summer of 2018, the design team completed the programming, site analysis and
estimating for the three stations. Last July, the Council directed the team to remove Fire Station
54 from the Public Safety Plan. The Schematic Design, Design Development and most of
Construction Documents phases of station 51 has been completed. The Schematic Design
phase of station 52 is well underway.
For station 51, the GCCM is planning to bid the subcontractor packages starting in January, and
the start of construction is scheduled to begin in late March. For station 52, the early site work
is scheduled to start in summer of 2019, and the building construction will follow in the late
fall/early winter.
The total original contract amount was proportionally based on the construction costs (including
tax and pre-construction costs) which was approximately $15.36M for three stations. The
updated construction cost estimate for station 51 & 52 is approximately $ 20.1M. This estimate
includes the additional costs to accommodate the drive-through design for station 52, as well as
all the alternates approved by the council. The previous contract amendment did not include the
necessary fee increase to reflect the higher construction budget and must be amended to align
with the Washington State's A&E Fee Guidelines. 13
INFORMATIONAL MEMO
Page 2
This increase is included within the Council approved overall project budget of $13.273M for
station 51 and $19.260M for station 52. No additional project budget increase is requested for
this amendment.
RECOMMENDATION
The Public Safety Committee is asked to approve the contract amendment no. 2 for services
with Weinstein AU. The staff asks that the contract be moved to the December 10, 2018
Committee of the Whole meeting and subsequent Special meeting that same evening
ATTACHMENTS
Proposed Amendment No. 2 to Contract 17-068
14 W:12018 Info Memos\Weinstein Amendment 2 Memo to Council.doc
SECOND AMENDMENT TO
CONSULTANT AGREEMENT FOR ARCHITECTURAL DESIGN AND PLANNING
SERVICES
FOR
TUKWILA FIRE STATIONS 51, 52, AND 54 PROJECT
This Second Amendment (the "Second Amendment"), effective as of _, 2018 (the
"Effective Date"), is entered into by and between CITY OF TUKWILA, WASHINGTON
("City"), and WEINSTEIN AU, LLC ("Architect"). This Second Amendment is an addition to
and modifies the Consultant Agreement for Architectural Design and Planning Services between
the parties dated April 19, 2017 (the "Agreement"). This Second Amendment incorporates the
contractual obligations outlined in the Agreement, and modifies the Agreement as stated below.
Unless defined differently herein, all capitalized terms in this Second Amendment have the same
meaning as in the Agreement. Now for and in consideration of the mutual promises contained
herein and other good and valuable consideration, the receipt of which is hereby acknowledged,
the parties agree as follows:
1. Basis for Amendment. The original compensation for the Architect in the Agreement
was based on the construction costs for three fire stations and calculated with Washington State's
A/E Fee guidelines. The First Amendment deleted one fire station (Fire Station 54) from the
Agreement, but increased the compensation amount due to increased project costs on the
remaining two fire stations (Fire Station 51 and Fire Station 52) and additional services requested
by the City. This Second Amendment increases the compensation for the Architect according to
Washington State's A/E Fee guidelines because of increased project construction costs and
identifies the fees the City had incurred for Fire Station 54. This Second Amendment also
increases the compensation for the following additional services approved by the City:
AS13a FS51: Southcenter Pkwy Redesign Scope Adjustment $6,079
AS16 FS54: Rehab Concept Scope Development $1,563
AS17 FS52: Drive-Through Added Drilling $10,120
AS18a FS51: Additional Civil Scope $12,760
AS18b FS52: Additional Civil Scope $16,500
AS20 FS51: Site Alternates Documentation Fees $37,360
Second Amendment Additional Services $84,382
2. Compensation. Architect's compensation for the Project shall be increased by a net total
of Three Hundred Eighty-Three Thousand Four Hundred Sixty-Two Dollars ($383,462).
Accordingly, Architect's total compensation for the Project will not exceed Two Million Eight
Hundred Sixty-Eight Seven Hundred Sixteen Dollars ($2,868,716), as further described in the
A/E Fee Reconciliation Summary dated November 26, 2018, which is attached as Exhibit A and
incorporated by this reference. All provisions of the Agreement referring to Architect's
compensation, including Exhibit B Article 11, shall be revised accordingly.
(AET1822272.DOC;2/05720.00000I/) 1
15
The Table of Fees on Page 5 of the Agreement shall be revised to read:
FS 51 Design and Construction $1,027,750
FS 52 Design and Construction $1,370,308
Subtotal $2,398,058
First Amendment Additional Services $148,051
Second Amendment Additional Services $84,382
Subtotal $232,433
Programming Phase (completed) $155,116
Site Selection (completed) $83,109
Subtotal $238,225
Total Fee $2,868,716
3. All other terms and conditions of the Agreement remain unchanged and are hereby
ratified and confirmed.
IN WITNESS WHEREOF, the Parties have executed this Second Amendment as shown
below.
CITY OF TUKWILA WEINSTEIN AU, LLC
By:
Allan Ekberg, Mayor (Signature)
Printed Name:
Title:
Attest/Authenticated: Approved as to Form:
City Clerk, Christy O'Flaherty Office of the City Attorney
{AET1822272.DOC;2/05720.000001/} 2
16
Exhibit A
Please see the attached A/E Reconciliation Summary, dated November 26, 2018
{AET1822272.DOC;2/05720.000001/} 3
17
18
TUKWILA FIRE STATIONS
Weinstein A+U
FS51 Additional Services Summary,Amendment#2
11/26/18
Basic Fee Change Fee Increase per MACC $105,318
Reduced CA Fee -$10,000
$95,318
AS13a FS51:Southcenter Pkwy Redesign WHPacific $5,526
Scope Adjustment WAU Mark-up $553
TOTAL $6,079
AS16 FS54 Rehab Concept Scope Development K. Wild, 12.5hrs $1,563
TOTAL $1,563
AS18a FS51 Additional Civil Scope LPD $11,600
WAU Mark-up $1,160
TOTAL $12,760
AS20 FS51 Site Alternates Documentation Fees LPD $19,800
Swift $14,164
WAU Mark-up $3,396
TOTAL $37,360
TOTAL $153,080
19
TUKWILA FIRE STATIONS
Weinstein A+U
FS52 Additional Services Summary, Amendment #2
11/26/18
FS52 MACC Calculation (per Lydig conceptual estimate of 8/23/18)
Total cost of work $8,996,885
Admin Build-out $450,000
-27% for CA phase -$121,500
TOTAL $9,325,385
Sub bonds 1.50% $139,881
SUBTOTAL $9,465,266
Design Contingency 10.00% $946,527
SUBTOTAL $10,411,792
L&M Escalation - January 2020 $460,310
L&M Escalation - Early Start July 2019 $154,971
SUBTOTAL $11,027,073
CM Contingency 3.00% $330,812
Neg. Support Services $300,000
MACC TOTAL $11,657,886
Basic Fee Change Fee Increase per MACC $213,762
Reduced CA Fee -$10,000
$203,762
AS17 FS52 Drive-Through Added Drilling Hart Crowser $9,200
WAU Mark-up $920
TOTAL $10,120
AS18b FS52 Additional Civil Scope LPD $15,000
WAU Mark-up $1,500
TOTAL $16,500
TOTAL $230,382
20
Weinstein A+U Tukwila Fire Stations
Fee Proposal
FS51 Fee Calculation
Amendment#2 November26,2018
BASIC FEE CALCULATION
Baseline Building Area 11,933 SF Total Fee Summary $1,027,751
Site Area +/_85,000 SF
Project(MACC)per 8/15/18 Estimate $8,457,576
A/E Base Service Per WA State Fee Schedule 2015-Type"B" 8.23% Total Basic Fee= $650,496
Total Extra Services= $355,131
Assumes a 15 Month Construction Period Total Reimbursable Allowar $22,124
COMPLETE COMPLETE
Percent Fee 18% 25% 26% 2% 27% 2% 100%07,,I�z='
Total Base Fee b Phase $125,291 $174,015 $180,975 $13,921 $187,936 $13,921 $696,059
De n Construction Bidding+ Contract
BASIC SERVICES(Scope per State Fee Schedule Guidelines) ° i i Close Out TOTAL
DFs=g, �_ �:�pr?�.,, Documents Negotiaton Administraton
Description Firm
Architectural Weinstein AIU 58.241 80,890 107,745 8,256 122,500 8,673 $386,305
Consultant Budgets
Structural Swenson Say Faget 12.996 18,050 16,718 1,286 17,361 1,286 $67,697
Specifications Axt 4,500 6,250 15,834 1,250 5,833 833 $34,500
Mechanical,Plumbing&Fire Protection Greenbusch 18,057 25,079 22,732 1,749 23,606 1,749 $92,972
Electrical,Fire Alarm and Lighting Travis Filzmaurice 1 1,340 15,750 16,380 1,260 17,010 1,260 $63,000
Civil(Basic Scope) LPD 1,084 1.506 1,566 120 1,626 120 $6,022- iays
BASIC PHASE SUBTOTALS ;-_" _ 106,318 147,526,'= 180,975 ' '_13 921 -' 167,936 ,. 13 921' $650,496
EXTRA SERVICES SUBTOTAL(See following page for detail) $355,131
REIMBURSABLES ALLOWANCE
Reimbursable allowance -Fixed Fee(2%of Total Fee) WAU $20,113
SUBTOTAL W/WAL Mul(iplier 109b _ $22,124
TOTAL FEE PROPOSAL $1,027,751
Previous Basic Fee Total $932,433
Delta
$95,318
N
TFS_MainContractFeeRevision November18 FINAL Printed:11/26/2018
Weinstein A+U Tukwila Fire Stations
N Fee Proposal
N
FS52 Fee Calculation
Amendment#2
November 26,2018
BASIC FEE CALCULATION
Baseline Building Area 15,500 SF Total Fee Summary -$1,370,308
Site Area +/-60,000 SF
Project(MACC)per 8/23/18 Estimate $11,657,886
A/E Base Service Per WA State Fee Schedule 2015-Type"B" 7.87% Total Basic Fee= $917,476
Total Extra Services= $423,334
Assumes a 15 Month Construction Period Total Reimbursable Allowar $29,498
Percent Fee 18% 25% 26% 2% 27% 2% 100%
Total Base Fee b Phase $165,146 $229,369 $238,544 $18,350 $247,718 $18,350 $917,476
Schematic Design Construction Bidding+ Contract
BASIC SERVICES(Scope per State Fee Schedule Guidelines) Close Out TOTAL
Design Development Documents Negotiation Administration
Description Firm
Architectural Weinstein AEU 113,633 157,824 164,137 12,626 170,450 12,626 $631,296
Consultant Budgets
Structural Swenson Say Faget 15,385 21,370 22,225 1,710 23,080 1,710 $85,480
Specifications Axt 1,406 1,953 2,969 234 1,094 156 $7,812
Mechanical,Plumbing&Fire Protection Greenbusch 21,501 29,862 31,056 2,389 32,251 2,389 $119,448
Electrical,Fire Alarm and Lighting Travis Fitzmaur ce 11,700 16,250 16,900 1,300 17,550 1,300 $65,000
Civil(Basic Scope) LPD 1.519 2,110 2,194 169 2,279 169 $8,440
BASIC PHASE SUBTOTALS
' _ 165;144 229,369 - ;, 239,481; 18,428 �.., ' 2246,703 18,350 ` $917,476
EXTRA SERVICES SUBTOTAL(See following page for detail) $423,334
REIMBURSABLES ALLOWANCE
Reimbursable allowance -Fixed Fee(2%of Total Fee) WAU i $26.816
SUBTOTAL WIWAUMultiplier10% ` S29,498
TOTAL FEE PROPOSAL° $1,370,308
Previous Basic Fee Total $1,166,546
Delta $203,762