PS 2018-12-03 Item 2D - Public Safety Plan - Travelodge Demolition Contract Amendment with BNBuilders
City of Tukwila Allan Ekberg, Mayor INFORMATIONAL MEMORANDUM TO: Public Safety Committee FROM: Rachel Bianchi, Deputy City Administrator CC: Mayor Ekberg DATE: November 28, 2018 SUBJECT: GC/CM Contract Amendment No. 3 for the Justice Center ISSUE On November 1, 2018 the City acquired the Travelodge motel property located at 14845 Tukwila International Boulevard ("JC-8") for the Justice Center project. Amendment No. 3 to BNBuilderscontract would allow for demolition of the existing vacant buildings on this property, BACKGROUND JC-8 is a 38,290 square foot parcel, with two buildings totaling 21,424 square feet that previously housed a Travelodge motel franchise, The buildings are vacant at this time. The Police Department has already reported incidents related to the boarded -up property. Despite site fencing and signs saying "No Trespassing" there is significant risk that trespassing, vandalism and other criminal activity could occur at the property while the buildings sit vacant. Based on these risks, the City believes the building poses an immediate and continued threat to public safety and should be demolished as soon as possible. The necessary work includes hazardous building materials abatement and building demolition. BNBuilders, the City's General Contractor/Construction Manager (GC/CM), obtained competitive bids for the demolition and associated work. The total cost for demolition of these buildings is $165,100, which includes a $10,000 Owner's contingency should unexpected changes of scope arise in the process of demolition. The total amount will be allocated as follows: ContractAmount (Amendment No. 3) $165,100 Owner's Contingency 10,000 Total $175,100 The demolition and associated work is included in the Justice Center project budget. The contractor is hoping to begin demolition in December 2018, pending utility disconnects and permits. The contract amendment was prepared by the City's outside legal counsel and reviewed by the City's project management consultant (SOJ) and the Council's Project Management Quality Assurance consultant (Steve Goldblatt). RECOMMENDATION The Public Safety Committee is asked to approve the contract amendment. The staff asks that the contract amendment be moved to the consent agenda at the special meeting on December 10, 2018 in order to facilitate the quick demolition of these buildings. ATTACHMENTS BNBuilders Contract Amendment No. 3 23 24 Init. 74AIA Document AI33TM - 2009 Exhibit A Guaranteed Maximum Price Amendment for the following PROJECT: (Name and address or location) Tukwila Justice Center Tukwila WA JC-8 Early Abatement and Demolition Scope THE OWNER: (Name, legal status and address) City of Tukwila 6200 Southcenter Boulevard Tukwila WA 98188 THE CONSTRUCTION MANAGER: (Name, legal status and address) BNBuilders, Inc. 2601 Fourth Ave Suite 350 Seattle, WA 98121 ARTICLE A.1 § A.1.1 Total Contract Cost Pursuant to Section 2.2 of the Agreement, the Owner and Construction Manager hereby amend the Agreement to establish a Maximum Allowable Construction Cost (MACC), Total Contract Cost (TCC) and terms governing a specified scope of work related to early abatement and demolition of two buildings on the JC-8 parcel, which is one of several parcels for the future Justice Center ("JC-8 Early Abatement and Demolition Scope"). The Work required by the JC-8 Early Abatement and Demolition Scope is further described in the BNBuilders Building System Summary attached hereto as Exhibit A and the Site Plan attached hereto as Exhibit B, both of which are incorporated by this reference. As agreed by the Owner and Construction Manager, the Total Contract Cost is an amount that the Contract Sum shall not exceed. The Total Contract Cost consists of the MACC (including the Construction Cost, Negotiated Support Services, and MACC Contingency); the Fixed Fee; the Fixed Amount for Specified General Conditions work; and applicable Washington State sales tax. § A.1.1.1 The Total Contract Cost for the JC-8 Early Abatement and Demolition Scope, including Washington State Sales Tax is guaranteed by the Construction Manager not to exceed One Hundred Sixty -Five Thousand One Hundred Dollars ($ 165,100 ), subject to additions and deductions by Change Order as provided in the Contract Documents. § A.1.1.2 Itemized Statement of the Total Contract Cost. Provided below is an itemized statement of the Total Contract Cost for the JC-8 Early Abatement and Demolition Scope organized by its component parts: ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text. This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification. AIA Document A201 Tm-2007, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified. AIA Document A133TM — 2009 Exhibit A. Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 17:17:57 ET on 11/29/2018 under Order No.2264341377 which expires on 08/30/2019, and is not for resale. User Notes: (1868788844) 25 26 Specified General Conditions $26,999 Maximum Allowable Construction Contract (MACC) Construction Total $105,824 Negotiated Support Services (NSS) $8,761 MACC Contingency @ 2.5% $2,646 GC/CM Fixed Fee @ 5% (Fee is not allowed on the Specified General Conditions, or Preconstruction Allowance) $5,862 TOTAL CONTRACT COST (Excluding WSST) $150,091 Washington State Sales Tax $15,009 Sum $165,100 (Paragraphs deleted) § A.1.1.2.1 The Preconstruction Services NTE Limit, as previously agreed to by the parties, is: To be stated in the GMP Amendment for the full scope of the Work. § A.1.1.3 The Total Contract Cost for the JC-8 Early Abatement and Demolition Scope is based on the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner: (State the numbers or other identification of accepted alternates. If the Contract Documents permit the Owner to accept other alternates subsequent to the execution of this Amendment, attach a schedule of such other alternates showing the amount for each and the date when the amount expires.) Not applicable. § A.1.1.4 Allowances included in the Total Contract Cost, if any: (Identify allowance and state exclusions, if any, from the allowance price.) Item Price ($0.00) Not applicable. Not applicable. § A.1.1.5 Assumptions, if any, on which the Total Contract Cost is based: Not applicable. § A.1.1.6 The Total Contract Cost is based upon the following General Conditions: AIA Document A201 — 2007, General Conditions of the Contract for Construction, as modified (Table deleted) § A.1.1.7 The Total Contract Cost is based upon the following Specifications: (Either list the Specifications here, or refer to an exhibit attached to this Agreement.) Not applicable. Section Title Date Pages § A.1.1.8 The Total Contract Cost is based upon the following Drawings: (Either list the Drawings here, or refer to an exhibit attached to this Agreement.) Not applicable. Number Title Date § A.1.1.9 The Total Contract Cost is based upon the following other documents and information: (List any other documents or information here, or refer to an exhibit attached to this Agreement.) Init. AIA Document A133TM — 2009 Exhibit A. Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 17:17:57 ET on 11/29/2018 under Order No.2264341377 which expires on 08/30/2019, and is not for resale. User Notes: (1868788844) Exhibit A: BNBuilders Building System Summary Exhibit B: Site Plan ARTICLE A.2 § A.2.1 Substantial Completion Dates The required date for Substantial Completion of the JC-8 Early Abatement and Demolition Scope established by this Amendment: 60 calendar days from issuance by the Owner of the Notice to Proceed for the JC-8 Early Abatement and Demolition Scope § A.2.2 Physical Completion Dates The required date for Physical Completion of the JC-8 Early Abatement and Demolition Scope established by this Amendment: Not applicable. § A.2.3 Final Completion Dates The required date for Final Completion of the JC-8 Early Abatement and Demolition Scope established by this Amendment: Not applicable. § A.2.4 Construction Schedule Not applicable (See Section A.2.1 above). ARTICLE A.3 Key Personnel The following named key personnel shall remain assigned for the duration of the Project unless otherwise agreed to in writing by Owner: Project Manager: Geri Urbas Project Superintendent: David Cantrell Project Engineer: To be assigned. OWNER (Signature) CONSTRUCTION MANAGER (Signature) (Printed name and title) (Printed name and title) Init. AIA Document A133TM — 2009 Exhibit A. Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AlA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 17:17:57 ET on 11/29/2018 under Order No.2264341377 which expires on 08/30/2019, and is not for resale. User Notes: (1868788844) 27 EXHIBIT A 28 BNBuilders PROJECT: JUSTICE CENTER OWNER: CITY OF TUKWILA ARCHITECT: DLR GROUP Building System Breakdown A10 - Foundations A20 - Basement Construction B10 - Superstructure B20 - Exterior Enclosure B30 - Roofing C10 - Interior Construction C20 - Stairs C30 - Interior Finishes D10 - Conveying D20 - Plumbing D30 - HVAC D40 - Fire Protection D50 - Electrical E10 - Equipment E20 - Furnishings F10 - Special Construction F20 - Selective Building Demo (Abatement Only) G10 - Site Preparation (Includes Bldg Removal) G20 - Site Improvements G30 - Site Mech Utilities G40 - Site Elec Utilities G90 - Other Site Construction Direct Construction Costs (DCC) Design / Estimating Contingency Escalation Negotiated Support Services Trade Package Bonds (See Sub Plan) MACC Contingency (%-DCC + Des + Esc + TP) Maximum Allowable Construction Cost (MACC) Contractors Fee (% of MACC - Bid %) Specified General Conditions Specified General Conditions Specified General Conditions GC/CM Performance & Payment Bond BNB Insurances B&O Taxes Preconstruction Services Total Contract Costs (TCC) Washington State Sales Tax Guaranteed Maximum Price (GMP) $ per GSF / Component GSF Building System Summary ESTIMATE TYPE: EARLY WORK ISSUE DATE: 11/29/2018 JC-8 Early Bldg Demo (Dec '18/Jan '19) Location 00 0 o' $ - 0 $ $ - o $ $ - 0 $ $ - 0 $ $ 0 $ - $ - $ 0 $ - $ - $ 0 $ - $ - $ 0 $ - $ - $ 0 $ - $ - $ 0 $ - $ - $ 0 $ - $ - $ 0 $ - $ - $ 21,424 $ 0.50 $ 0.50 $ 10,804 21,424 $ 4.44 $ 4.44 $ 95,020 0 $ - $ - $ •1 $ - 0 $ - $ 0 $ - $ 0 $ - $ - 4.94 $105,824 NOT APPLICABLE NOT APPLICABLE SEE EST DETAIL $ NOT APPLICABLE $ 2.50% $ 8,761 2,646 5.47 $117,231 (AS -BID) 5.00% $ 5,862 (JC-8 Early) $ 26,999 Add'I MACC Value $ Included w/Fee $ Included w/Fee $ Included w/Fee $ Owner (Bid) Value 7.01 $ 150,091 10.000% $ 15,009 $ 165,100 $ 7.71 21,424 CONFIDENTIAL EXHIBIT B 30 LEGEND NOTES DEMOLITION GENERAL NOTES DEMOLMION NOTES APELa AO ALE JD., ACE NEES TAKES POSSESSION. APE', EOR OBTAIN ANNA. FAME, FOR DEMCOMON REAM, FROM TKIE C GE TOM, C AEA, =OR CBE. AEC MAKE PAYMENE EC ANO COORDINATE NA MAL GAS ANO POWER EXCESSME NOISE OR VORATION SHALL BE ERE APEROVED AND TAE EXCEPTION OF THE NCLUDING HE NOT LacIFEK NO ARCA BON c WASHINGTON AWE LABOR AND KKAMSKRIES FERMIUM GENERAL AA ELIA AND AS DEEMED NECESCARE Me THE OMNA MILLWORK E.,18,11e MKT., CEINGS SOFFITS. OEMOLIMONCOOKS tRECOON 'MOM DESCRIBED AV TA K MEW. EAOTECTIGN FOR AU EMS,. MEKONG MATERIALS AKA EQUIPMENT FROM DAMAGE DUE TO AV DEMOLITION OR CONTRACT DEMOLIMON OR CONSTRJCOON re 1,,,CH EMT,. FN. WHEW:. OR ACM.MaRORIZAD ARCHMEOTMENGNEER OE THEIR MICE acER AOMECENTPROPERMES MC OE DIVOR AREA OKAM.OTPT TO BE DEMOLISHED DEMO PERMIT SITE PLAN JC-8 BUILDING DEMO SITE PLAN JC-8 scaLE SITE INFORMATION MAN.. NET SQUARE FOOTAGE:2DM, MZE AEC PARCEL 00,00-0315