HomeMy WebLinkAboutReg 2019-01-07 Item 8 - Reports - City Administrator / Public Safety Plan Monthly UpdateA an Ekberg, Mayor
TO:
Mayor's Office - David Cline, City Administrator
The City of opportunity, the community of choice
Mayor Ekberg
Councilmembers
FROM: David Cline, City Administrator
DATE: January 2, 2019
SUBJECT: City Administrator's Report
The City Administrator Report is meant to provide the Council, staff and community an update on
the activities of the City and on issues that concern Tukwila. Please let me know if you have any
questions or need additional information about any of the following items.
Intergovernmental Update
• Young Southeast Asian Leaders Initiative (YSEALI) Summit: Mayor Ekberg attended the
Young Southeast Asian Leaders Initiative (YSEALI) Summit in Singapore December 3 - 5. The
Summit gathers 150 participants around the theme The United States and ASEAN: Partners in
Growth and Innovation and showcases innovative approaches to economic cooperation and
growth between U.S. companies, organizations and institutions present in the Association of
Southeast Asian Nations.
• King County City Managers/Administrators Monthly Meeting: On December 5 City
Administrator David Cline hosted the monthly King County City Managers/Administrators
meeting at the Tukwila Community Center. At the meeting they had a roundtable discussion
about Local Election Ballot Successes and Lessons learned.
• Soundside Alliance Annual Economic Outlook Breakfast: Councilmembers Hougardy and
McLeod and Economic Development staff attended the Soundside Alliance Annual Economic
Outlook Breakfast on December 6. Councilmember Hougardy serves as Chair of the
Soundside Alliance and she emceed the event. Speakers included James Henderson from
Greater Seattle Partners and Matthew Behrens from CBRE Hotels.
• District 11 Legislative Luncheon: On December 12 Mayor Ekberg, Council President Quinn,
City Administrator David Cline and Deputy City Administrator Rachel Bianchi hosted the 2018
Legislative Luncheon with our District 11 legislative representatives: Senator Hasegawa,
Representative Bergquist and Representative Hudgins and local business representatives.
• Advancing Racial Equity Conference: Mayor Ekberg, Councilmembers Idan and Quinn, City
Administrator David Cline, Deputy City Administrator Rachel Bianchi and Council Analyst
Laurel Humphrey attended the Advancing Racial Equity Conference on December 14. Mia
Navarro, formerly the City's Community Engagement Manager, was instrumental in helping
plan this conference over the past several months and attended in her new role with City of
Tacoma.
Tukwila City Hall 6200 Southc nter Boulevard • Tukwila, WA 981 • 206-433-1800 • ebsite: Tukwil WA.gov
81
City Administrator's Report
January 2,2019
Page 2
South King County Joint Planners and Developers Workgroup: Community Development
staff attended a meeting of the SKC Joint Planners and Developers Workgroup to hear an
update about the proposed housing focused interlocal agreement.
2020 Urban Growth Capacity Study: Community Development staff participated in the
Technical Committee meeting for the 2020 Urban Growth Capacity Study on December 18.
King County GIS will be conducting analyses on development that has happened around the
County since the last report was completed. Staff will be working with King County over the
next two years to provide data and input on the study methodology.
SCATBrd Meeting: Community Development staff attended the monthly SCATBrd meeting
on December 18. The group reviewed the proposed legislative agenda for 2019, which is
expected to be finalized at the beginning of 2019. Representative Adam Smith attended the
meeting to provide input on the proposed legislative agenda and to answer questions.
SCA Caucus Workshop: Staff attended an SCA Caucus Workshop for members of the
Regional Transit Committee on December 19. The group reviewed two recent motions passed
by the King County Council as part of the budget process: (1) a motion expressing support for
regional planning, coordination and funding efforts to address implementation of the Metro
Connects plan and ongoing maintenance needs of King County's transportation
infrastructure and transportation improvements; and (2) a motion outlining a process to
develop a regional mobility framework for evaluating mobility innovations. The group also
discussed possible 2019 vvorkplan items,
11. Community Events
• Spirit of Giving: Nearly $20,000 in donations and gifts were collected to help support over 300
children and families in Tukwila for this year's Spirit of Giving program. The following have
contributed hundreds of dollars in monetary and gift donations: Strong -Bridge Envision, Zee
Medical, Teamsters Local 763, King County Metro: Tukwila Base, Vault insurance, BECU,
Inspirus Credit Union, Macy's Logistics, Twin Peak Restaurant, Olive Garden, Tukwila Arts
Commission, Tukwila Library Advisory Board, Tukwila Parks Commission, as well as individual
donors. We've received several boxes of gifts from local residents who had collected items
throughout the year to help the program.
• 8th Annual Teen Leadership Summit: The 8th Annual Teen Leadership Summit was held in
Shoreline at the Richmond Highlands Recreation Center on December 15. Approximately 60
young people from 8 different communities (Tukwila, Shoreline, Seattle, Olympia, Lacey,
Auburn, Renton, and Burien) attended the event which included small group discussions on
the education gap, teacher diversity, school safety, racial equity vs equality, and immigration.
Nate Robinson and 9 Teens for Tukwila members participated in the event.
Phone: 206-433- 00 • Email: Mayor@TukwitaWA.gov • Website: TukwilaWA.gov
82
City Administrator's Report
January 2, 2019
Page 3
III. Staff Updates
Public Safety
• Train -the -Trainer: Community Policing and Engagement: Sergeant Zack Anderson and
Officer Matt Valdez attended Train -the -Trainer for Community Policing and Engagement
training.
• Shop With A Cop: Officer Lisa Harrison organized the Shop With A Cop event held on Saturday,
December 8. The Tukwila Children's Foundation, Target, the Tukwila Family Fun Center &
Bullwinkle's Restaurant, Azteca Mexican Restaurants, Acura of Seattle and Jimmy John's for
contributed to the event.
Project Updates
• 42"d Ave Phase III: Estimated Completion: December 2018
All private service connections for this project was completed on December 19. City staff are
coordinating with various utilities to complete their overhead to underground utility
conversions.
• 53rd Ave S: Estimated Completion: March 2019
Contractor has completed the main line stormwater installation and continues to install the
lateral connections. The electrical subcontractor continues to install services to residences.
The contractor will begin installation of the curb and gutters after the holidays. It is
anticipated that the base lift of paving will be installed in the first quarter of 2019.
• BAR Bridge Rehabilitation: Estimated Completion: February 2019
• Contractor continues to work on the sidewalk over the railroad and is anticipating
completion by the second week of January. The contractor will look at shifting the traffic
lanes in late January to complete incidental expansion joint work. Construction is on
schedule for completion in February.
• Tukwila Pond: Parks maintenance staff have been clearing site lines on the west side of the
Tukwila Pond Park. Staff is taking great care to not remove any trees, removing only invasive
plants and dead foliage. The goal will be to increase visibility and safety within the park to
reduce illicit activities and increase foot traffic within the park.
• Surface Water Billing Handled by King County Beginning 2019: On December 14 postcards
were mailed out to all Tukwila property owners advising that surface water billing for the City
of Tukwila will now be included on property tax statements mailed out by King County.
Boards and Commissions
• Arts Commission: No vacancies.
• Civil Service Commission: No vacancies.
• COPCAB: Vacant Position: School District Representative and Student Representative.
• Equity & Social Justice Commission: Vacant Position: Student Representative.
• Human Services Advisory Board: Upcoming Vacancy: Position #3 Resident, Recommended
appointment scheduled for January 7, 2019.
• Landmark Commission: No vacancies.
Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • ebsite: Tukwi A.gov
83
City Administrator's Report
January 2, 2019
Page 4
Library Advisory Board: Vacant Positions: Position #7 Resident & Student Representative.
Lodging Tax Advisory Committee: No vacancies.
Park Commission: Vacant Positions: Position #4 Resident & Student Representative.
Planning Commission: Upcoming Vacancy: Position #5 Resident. Recommended
appointment scheduled for January 7, 2019.
Phone; 206-433-1800 • Emai : Mayor@TukwilaVVA.gov • Website; TukwilaVVA.gov
84
TUKW|bAPU0UC SAFETY PLAN
Monthly Update
December 3l,ZO1D
Overall Plan
Outreach
w The second open house in 2018 took place on Saturday, November 17 from 10:00 a.m.
to 12:00 p.m. at Valley View Sewer District.
Financial Oversight Committee
0 The Committee reported to council on September 4, 2018.
Siting Advisory Committee
w The Siting Advisory Committee voted todefer regular meetings asthe major dedsions
have been made. They will meet onanas-needed basis.
Acquisition Lease Updates
w Staff secured leases with nine businesses and expects to have the remaining leases
completed by the end of November.
Disadvantaged Business Enterprise (DBE)Outreach
r See attached report.
Near -term Council Decisions and Key Dates
~ January — DLR contract amendment no. 3 for forestry and environmental services
w January — Contract for commissioning agent
• ]anuary—Contractforspeoia|inspectionsduringconstruotion
Fire Stations
Siting
0 The single-family home on the new Station 54/Star Nursery site has been demolished.
Architecture and Programming
• Architectural program has been reviewed and approved bythe team.
• Concurrent review and pricing ofthe Schematic Design byGCCM Contractor, Lvdig, and
estimating consultant has been completed and was shared with Council inFebruary
2018. Council gave approval to begin Design Development for Station 51.
85
Design and Permitting
• Design Development for Station 51 began mid -February; the team met meeting weekly.
Design Development effort wrapped up in June, 2018 with Design Development pricing
effort hnJuly and August.
• Construction Documents phase for Station 51 were completed and distributed to the
team December 3[lZOlO.
• Schematic Design phase underway for Station 52.
• Building permit for Station 5lwas submitted inOctober. Anticipate receiving approved
permit approval in December in all areas except wetlands report.
~ Permitting coordination meetings with City Staff are ongoing for Station 51 and Station
52. Station 52 anticipated to he phased permitting. Pre -application for Station 52
permit was submitted inNovember, ZQ2D.
Bidding and Construction
• Pre -construction services starting for Station 5Iand 52are underway.
• Lyclig completed the selection of mechanical and electrical subcontractors through the
E)ec±ricContractor/ConstrUct|on Management (ECCK8)and Mechanical Cpntractor
Construction Management (K4CCK4) selection process, Valley Electric and Johansen
Mechanical Inc. were selected. With Council decision to not move forward with F354/
vVecannot move forward with ECCK4. K4CCK4method for mechanical subcontractor will
provide for a consistent mechanical subcontractor for all three stations and will be able
tO.provide critical expertise during the Design Development phase. This contract i5
managed bythe GCCK4under the pre -construction phase.
• Bidding is scheduled to begin for 51 in January, 2019 with construction for 51 to begin
late March, 20l9.
• Bidding and construction phases scheduled tobegin for 5Z|nJune, 2Ol9. Early site work
is anticipated to begin in July.
Justice Center
Siting
• The City has agreements with all affected businesses nnthe Justice Center site.
• The City has agreements with all property owners and will take ownership of all
remaining properties onthe Justice Center site hythe end ofthe year. The long -vacant
building between Church bythe Side ofthe Road and the Tr8ve|odgehas now been
demolished. The Tnave|odgeis now empty, and the project team is accelerating the
demolition ofthis building.
• The City received Public Use and Necessity from Superior Court on September 14; no
party contested it due to the agreements made with all of the business owners.
86
Architecture and Programming
~ OLRGroup'sBuilding Program Report was submitted OeccnnberD. 3017. Program and
Estimate was presented to Public Safety Committee in December and Council in
]anuary,Z01O.
Design and Permitting
w DLR architects have completed the Design Development phase ofthe
project, BNBuilders and Roen (the architect's estimating consultant) compared their
estimates and the project |swithin the revised budget. The Design Development and
budget was presented to the Council in October and remains within the adjusted
budget.
• The project team has initiated the permitting and land use entitlements process and
submitted applications for 5EPA, Design Review, Conditional Use Permit and Parking
Determination in October. The SEPA determination is expected in November and the
Conditional Use Permit and Design Review approvals are expected in December.
• The project teannvvi||suhnl|tanapplicationforconstruCtionperrnit(sitevvDrk/Utilities)
inNovember of2O1D,with issuance .expected inJanuary of3Ol9.
Bidding and Construction
• BNBui|ders,the selected GC/CM, started pre -construction services following Council
approval oftheir contract oOMarch l9,ZOI8.
• BNBuilders will continue to work with the team on design phases, constructability, cost
estimating and scheduling throughout design and preconstruction.
• Construction scheduled tobegin inApril, 3Ol9.
Public Works Facility
Siting
• Due diligence items related tosite acquisition are complete. The assessment ofexisting
structures iscomplete.
• The City has agreements with all of the businesses on the Public Works site with the
exception ofone,
~ The Public Use and Necessity trial was held Friday, May 25 and the City was granted its
request.
Architecture and Programming
� Team solicited for Architectural services, Council approved acontract for programming
and master planning services with 5HKS in November 2018. Master planning and
programming phase began in late 2018, scheduled to be completed in May of 2019.
Design and Permitting
87
Bidding and Construction
0 Phases scheduled to begin in Q4 2019.
Based on Council direction to move forward with Station 51, Station 52, Justice Center
and Public Works Facility ($30M), team has updated the budgets.
Schedule
January2019
• Fire Station 5lbuilding permit issued
• Fire Station S1subcontractor bidding
• Justice Center subcontractor bidding
• Justice Center Construction Permit (sitevvork/utiUties)issuance
• Justice Center Construction Permit (main building) submittal
• Commissioning Consultant Contract toPublic Safety Committee and Council
• Construction Inspections Consultant Contract to Public Safety Committee and Council
• Commissioning Contract tQPublic Safety Committee and Council
• Construction Inspection Contract toPublic Safety Committee and Council
FebruarV2O1g
• Fire Station51 Construction Contract Approval to Public Safety Committee
• Fire Station 5Zschematic design estimate toCommittee
• Fire Station 5Zdesign development begins
• Public Works master plan present to Public Safety Committee
March2019
w Fire Station 51Construction Contract Approval toPublic Safety Council
• Fire Station 53schematic design estimate toCouncil
• Fire Station 51cVnstrurdon begins
Aph|2Ol9
• Justice Center Construction Permit (main building) issuance
• Justice Center construction begins (building demolition and hazardous materials
abatement)
• Fire Station 52 design development cost estimating complete with GCCIVI involvement
• Public Works programming complete
• Public Works Phase | design begins
88
May 2019
• Fire Station 52 design development cost estimating to Public Safety Committee
• Fire Station 53construction documents begin
• Public Works programming and estimates to Committee and Council
Juna20I9
w Fire Station 52design development estimate toCommittee and Council
• Public Works phase Idesign begins
• Fire Station 52phase Ipermit submitted
• Fire Station S2phase Ibidd1ng
July 2019
• Fire Station 52phase l permit received
• Fire Station 52phase Zpermit submitted
• Fire Station 52 phase I Lyclig contract amendment to Committee and Council
August30lg
m Public Works Phase I design complete and presented to Public Safety Committee and
[OUncU
• Fire Station 52construction documents begin
• Fire Station 52 phase 2 bidding
September 201
~ Fire Station 52 phase Z permit received
• Fire Station 53Lvd` contract amendment toCommittee and Council
• Fire Station S2phase Zconstruction begins
89
TK U����UU �& PUBLIC���F��'�' U����p�
— '-- _—_—_'''---`
Monthly DBE OUTREACH EFFORTS
12.31.18
Outreach Consultant updates for December 2018
0 The month of December has been quiet since all outreach events for public agencies and other
minority organizations are done for the year 2Ul8. [ will besending out tothe team various
Outreach opportunities for the upcoming months bvmid January 20l9`
0 | have reached out to Lyclig & BNB informing both to prepare and start reaching out to NAMC &
Tabor starting February 2019 and be visible to both organizations by attending monthly
meetings.
0 | have also followed this with anemail toKiel Lunxfnrd/Lydig & Geri Urbas/8NBtostart
strategizinga plan and put presentation to both organization. | will keep the team posted of
the efforts from Lydig & BNB Vfhow this isgoing tounfold.
* |amalso continuing to reach out to all the Pre -Apprenticeship Program on their upcoming
events, such asSeattle Vocational Tech;ANEVV/PACE,YouthQui|d,PACT, Cement Masons &
|rnnw/erkersfor upcoming graduation schedules. | have scheduled next week toreach out w/City
of Seattle John Besche, who has been communicating w/Paige McGehee at SOJ, to make sure
that the line ofcommunication is open regarding Pre -Apprenticeship Program updates.
* Continuing to have the relationship w/Bui|dinQTrades nn their events.
90
City of Tukwila - Facilities Plan
TOTAL PROJECT
MONTHLY Budget Report
(REVISED Budgets; D-20 Plan Adopted by Council)
Life to Date Costs
as o(December 31, 2018 (reconciled wfacc[g /hot Dec 07, 2018 GL,
COUNCIL REPORTING Si',II:I L-t R f"- Original llnngo
CENTER
Bodge, Trnu!r,
(men, Honker Committed Budget
Life to Dore Cnnr
mfn 0 Con mined
Remaining Bode
Ca at CompletionJl'STICE
A/E Services (both Design & CA)
$ 3,278,125
$ 221,875
$ 3,560,000
5 3,141,729
$ 1,372,809
$ 1,768,929
5 358,271
S -
Permits/Fees
$ 700,000
$ -
$ 700,000
5 20,445
5 20,445
$ -
$ 679,555
$
Construction (Pre -Con, Const & Tax)
5 38,738,678
5 (11,315)
$ 38,727,363
$ 398,571
3 262,878
$ 135,693
$ 38,328,792
$ -
Construction Related Costs (incl Bond)
$ 2,112,639
$ 170,000
5 2,282,639
$ 471,466
$ 396,951
$ 74,516
5 1,811,173
$
PM Services (incl Other Professional Svcs)
$ 1,815,875
5 296,721
5 2,112,596
$ 1,967,303
3 841,409
$ 1,125,894
$ 145,293
$
Contingency (incl Construction & Project)
$ 6,507,731
$ (1,646,239)
3 4,861,492
5 -
$ -
$ -
5 4,861,492
$ -
Contingency for Site Contamination (soils,hazmat)
Land Acquisition
S -
S 14,133,295
$ 750,000
$ (81,042)
$ 750,000
$ 14,052,253
$ -
$ 13,707,038
$ -
S 13,663,451
$ -
5 43,587
S 750,000
S 345,215
$
$
Contingency for Land Acquisition
S 1,250,000
5 300,000
5 1,550,000
$ 616,962
5 616,962
5 -
$ 933,038
$
-
S 68,536,343
$ -
$ 68,536,343
$ 20,323,515
5 17,174,896
S 3,148,619
S 48,212,828
8 -
C(7('NCII. REPORT! :M1't,'SC41JIdRL' D Dal Midget
FIRE STATION 51 dgiBudget
R I et Tnon r
/ -�
Goren !Judger Committed Bridget
A x
Life Dore Corn
J
Rennin Committed
R
Roman Bodge
ling ,ng
Cova, corn lerion
p
A/E Services (both Design & CA)
5 1,070,000
5 222,781
$ 1,292,781
5 1,235,072
$ 701,262
$ 533,810
$ 57,709
$
Land Acquisition
5 -
5 -
$ -
S -
$ -
$ -
$ -
$
Permits/Fees
$ 234,000
S -
$ 234,000
5 34,557
$ 34,557
5 -
S 199,443
$ -
Construction (Pre -Con, Const & Tax)
5 9,396,000
5 -
$ 9,396,000
$ 150,000
5 -
$ 150,000
$ 9,246,000
5 -
Construction Related Costs (incl Bond)
$ 931,000
$ -
$ 931,000
$ 83,987
3 78,628
$ 5,359
$ 847,013
5 -
PM Services (incl Other Professional Svcs)
$ 526,000
$ -
$ 526,000
$ 343,949
$ 113,739
$ 230,210
$ 182,051
$ -
Contingency (incl Construction & Project)
$ 1,116,000
5 (222,781)
$ 893,219
$ -
5 -
$ -
$ 893,219
$ -
,.
S 13,273,000
$ -
5 13,273,000
8 1,847,565
5 928,186
5 919,379
S 11,425,435
5 -
COUNCIL RTI\GSLLR1-
ST-ITION 52
0dgi,,,lBudget
Midget otfr`
Current !Dolga Committed Bodge
'I hrDalt D
RomneyCommitted
Rmmu, ring lodger
OW to CompletionFIRE
A/E Services (both Design & CA)
Land Acquisition
$ 1,415,000
$ 16,000
$ 234,222
5 -
$ 1,649,222
$ 16,000
$ 1,548,449
$ 15,800
$ 208,653
5 15,993
$ 1,339,796
$ (193)
5 100,773
$ 200
5
$ -
PerrnitslFees
$ 353,000
$ -
5 353,000
$ -
$ -
$ -
$ 353,600
$
Construction (Pre -Con, Const & Tax)
$ 13,298,000
$ 456,500
$ 13,754,500
5 125,000
$ -
$ 125,000
$ 13,629,500
$ -
Construction Related Costs (incl Bond)
$ 1,398,000
$ -
5 1,398,000
5 29,963
5 16,178
S 13,785
$ 1,368,037
$
PM Services (incl Other Professional Svcs)
5 787,000
$ -
3 787,000
$ 531,557
3 177,351
$ 354,206
5 255,443
$ -
Contingency (incl Construction & Project)
$ 1,343,000
5 (40,722)
5 1,302,278
$ -
$ -
$ -
$ 1,302,278
$
;,,
$ 18,610,000
5 650,000
S 19,260,000
$ 2,250,769
5 418,174
$ 1,832,595
$ 17,009,231
$ -
COUNCIL REPORTING MAY
-1 Original Budget
S
FIRE STATION 54
!hedger Tramiel,
Ciorenr Budget Committed Budget
Life to Done Cuss
11Rre tin 0 Committed
AAA
Remaining Budget
('tot at Comp ion
A/E Services (both Design & CA)
Land Acquisition
$ 150,000
5 902,668
$ (7,000)
S 25,596
$ 143,000
$ 928,264
3 132,995
$ 928,265
$ 131,495
$ 928,165
$ 1,500
3 100
$ 10,005
$ (1)
$
5 -
Permits/Fees
5 20,000
$ -
$ 20,000
3 1,517
5 1,517
$ -
5 18,483
$ -
Construction (Pre -Con, Const & Tax)
$ 230,000
5 -
$ 230,000
$ 97,000
$ -
5 97,000
$ 133,000
5 -
Construction Related Costs (incl Bond)
$ 50,000
5 9,875
$ 59,875
$ 44,752
5 22,798
$ 21,954
$ 15,123
$
PM Services (incl Other Professional Svcs)
5 107,500
$ 630
$ 108,130
$ 108,130
$ 85,279
5 22,851
$ -
$ -
Contingency (incl Construction & Project)
$ 41,832
S (29,101)
$ 12,731
$ -
5 -
$ -
$ 12,731
$
..
1,502,000
$ -
$ 1,502,000
$ 1,312,659
$ 1,169,254
$ 143,405
$ 189,341
S
C(IfA'C/L REPORTING Sf%a1.t7.•IRI'- Original Dinka
WORKS
Bodged Tm,n/er,
Current nudger Committed Budget
Life n: note Com
Remnid'GnrnirrRemaining 1o.Ig
n
C, at GnPkrioPUBLIC
A/E Services (both Design & CA)
5 767,385
$ 15,000
5 782,385
$ 318,882
5 17,385
5 301,497
$ 463,503
$ -
Land Acquisition
$ 22,000,046
5 3,333,913
$ 25,333,959
5 25,294,683
$ 25,292,483
$ 2,200
5 39,276
$
Permits/Fees
S 110,000
$ (20,000)
$ 90,000
$ -
$ -
$ -
5 90,000
$ -
Construction (Pre -Con, Const & Tax)
$ 4,950,000
$ (1,842,500)
$ 3,107,500
$ -
$ -
$ -
$ 3,107,500
$ -
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
$ 529,036
$ 668,426
$ (416,350)
$ (348,426)
$ 112,686
$ 320,000
3 64,864
$ 279,832
$ 49,030
S 125,082
$ 15,833
$ 154,750
$ 47,822
$ 40,168
5
$
Contingency (incl Construction & Project)
$ 975,107
$ (721,637)
$ 253,470
S -
$ -
$ -
5 253,470
$ -
.:. TOTAL - -
$ 30,000,000
$ -
S 30,000,000
S 25,958,261
$ 25,483,980
S 474,280
$ 4,041,739
S -
co
N
TUKWILA PUBLIC SAFETY PLAN
FIRE STATION .51.
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
FIRE STATION 52- ;,;
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
JUSTICE CENTER
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
PUBLIC WORKS;;
A/E PROCUREMENT
MASTER SITE PLAN
DESIGN PHASE 1
BIDDING/CONSTRUCTION PHASE 1
MOVE-IN/OCCUPANCY PHASE 1
CD
W
2016
2017
2018
2019
2020
2021
PROJECT
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY