HomeMy WebLinkAboutPermit M14-0154 - SAHALE SNACKS - FANSSAHALE SNACKS
3411 S 120 PL
M14-0154
Parcel No:
Address:
City of Tukwila
Department of Community Development
6300 Southcenter Boulevard, Suite #100
Tukwila, Washington 98188
Phone: 206-431-3670
Inspection Request Line: 206-438-9350
Web site: http://www.TukwilaWA.eov
1023049069
3411 S 120TH PL 100
Project Name: SAHALE SNACKS
MECHANICAL PERMIT
Permit Number: M14-0154
Issue Date: 8/29/2014
Permit Expires On: 2/25/2015
Owner:
Name:
Address:
Contact Person:
Name:
Address:
Contractor:
Name:
Address:
License No:
Lender:
Name:
Address:
SABEY CORPORATION
12201 TUKWILA INTL BLVD 4THFL ,
SEATTLE, WA, 98168
RUSTIN GILBERT
12646 INTERURBAN AVE S , TUKWILA,
WA, 98168
TCMS OF SEATTLE LLC
12856 INTERURBAN AVE S , TUKWILA,
WA, 98168
TCMSSSL905CB Expiration Date:
Phone: (206) 588-8787
Phone: (206) 588-8998
DESCRIPTION OF WORK:
INSTALL A SUPPLY FAN AND A RETURN FAN, CONNECT TO EXISTING DUCT FOR SPACE
Valuation of Work: $30,000.00
Type of Work: NEW
Fuel type: ELECT
Fees Collected: $585.58
Electrical Service Provided by: SEATTLE CITY LIGHT
Water District: 125
Sewer District: VALLEY VIEW SEWER SERVICE
Current Codes adopted by the City of Tukwila:
International Building Code Edition:
International Residential Code Edition:
International Mechanical Code Edition:
Uniform Plumbing Code Edition:
2012
2012
2012
2012
International Fuel Gas Code:
WA Cities Electrical Code:
WA State Energy Code:
2012
2012
2012
Permit Center Authorized Signature:
LOA `--J2 Date: :9 4H it
I hearby certify that I have read and examined this permit and know the same to be true and correct. All
provisions of law and ordinances governing this work will be complied with, whether specified herein or not.
The granting of this permit doers not presume to give authority to violate or cancel the provisions of any other
state or local laws regulating/construction or the performance of work. I am authorized to sign and obtain this
development permit andfagree% the conditions attached to this permit.
Signature:
Print Name:
,/herrt
Date: O/2 V/(71
This permit shall become null and void if the work is not commenced within 180 days for the date of issuance, or if
the work is suspended or abandoned for a period of 180 days from the last inspection.
PERMIT CONDITIONS:
1: Readily accessible access to roof mounted equipment is required.
2: All construction shall be done in conformance with the Washington State Building Code and the
Washington State Energy Code.
3: Remove all demolition rubble and loose miscellaneous material from lot or parcel of ground, properly cap
the sanitary sewer connections, and properly fill or otherwise protect all basements, cellars, septic tanks,
wells, and other excavations. Final inspection approval will be determined by the building inspector based
on satisfactory completion of this requirement.
4: All electrical work shall be inspected and approved under a separate permit issued by the City of Tukwila
Permit Center.
5: VALIDITY OF PERMIT: The issuance or granting of a permit shall not be construed to be a permit for, or an
approval of, any violation of any of the provisions of the building code or of any other ordinances of the City
of Tukwila. Permits presuming to give authority to violate or cancel the provisions of the code or other
ordinances of the City of Tukwila shall not be valid. The issuance of a permit based on construction
documents and other data shall not prevent the Building Official from requiring the correction of errors in
the construction documents and other data.
6: ***MECHANICAL PERMIT CONDITIONS***
7: All mechanical work shall be inspected and approved under a separate permit issued by the City of Tukwila
Permit Center (206/431-3670).
8: All permits, inspection record card and approved construction documents shall be kept at the site of work
and shall be open to inspection by the Building Inspector until final inspection approval is granted.
9: Manufacturers installation instructions shall be available on the job site at the time of inspection.
PERMIT INSPECTIONS REQUIRED
Permit Inspection Line: (206) 438-9350
1800 MECHANICAL FINAL
0701 ROUGH -IN MECHANICAL
CITY OF TUKK' 1
Community Development Department
Permit Center
6300 Southcenter Blvd., Suite 100
Tukwila, WA 98188
http://www.TukwilaWA.gov
Mechanical Permit No. M ILA — 0131
Project No. �l
Date Application Accepted: %11,\ 41
Date Application Expires: `-- %
(For of/ice use only)
MECHANICAL PERMIT APPLICATION
Applications and plans must be complete in order to be accepted for plan review.
Applications will not be accepted through the mail or by fax.
**please print**
SITE LOCATION
King Co Assessor's Tax No.: l UZ 3Ot/g O6°j
Site Address: 39 ((1enS(gt. *1 bu Qtt�t,e_ P Suite Number: 100 Floor:
Tenant Name: $atAtt-x_ New Tenant: Pr —Yes ❑.. No
PROPERTY OWNER
Name:
S0. b >° y
CO IT cc, (o1
�
r`: ,1
Address:
City:
State:
Zip:
CONTACT PERSON — person receiving all project
communication
Name: k S 1,. 6.1 (�J ic.„.t_
(�
Address: 114'-u 1N_I �ow
j'+ a-cr�.f �C Ca
City: ,,/ State: , fix Zip:12 6,
Phone: 2.0b i s-? '??7 Fax:
Email: C "h 4. C-N 1 1 orkr a tt.tvts c v re3
MECHANICAL CONTRACTOR INFORMATION
Company Name . t
5.t
—CC „4^ A
k
V 4� ``� '^L '^
Address:
City. State: J' 6� Zip:�17,
✓�1
Phone: Z 06 5?2VY7Fax:
Contr Reg No.m pc_ yosciPp Date:
Tukwila Business License No.: c'� _0 ?Is 0 o 9
/
cc.) I'Vl
Valuation of project (contractor's bid price): $ �t con /
Describe the scope of work in detail: .1r.$Ie,Q,L 0. S I e�d4W-A ram,
C T r G k stf .
Use: Residential: New
Commercial: New
Fuel Type: Electric ❑
❑
Replacement
Replacement
Gas ❑ Other: f k�S
H:\Applications\Forms-Applications On Line\2011 Applications\Mechanical Permit Application Revised 8-9-11.docx
Revised: August 2011
bh
Page 1 of 2
Indicate type of mechanical work being installed and the quantity below:
Unit Type
Qty
Furnace <100k btu
Furnace >100k btu
Floor furnace
Suspended/wall/floor
mounted heater
Appliance vent
Repair or addition to
heat/refrig/cooling
system
Air handling unit
<10,000 cfm
Unit Type
Qty
Air handling unit
>10,000 cfm
Evaporator cooler
Ventilation fan
connected to single duct
Ventilation system
•
Hood and duct
Incinerator — domestic
Incinerator —
comm/industrial
Unit Type
Qty
Fire damper
Diffuser
Thermostat
Wood/gas stove
9
Emergency generator
Other mechanical
equipment
Boiler/Compressor
Qty
0-3 hp/100,000 btu
3-15 hp/500,000 btu
15-30 hp/1,000,000 btu
30-50 hp/1,750,000 btu
50+ hp/1,750,000 btu
PERMIT APPLICATION NOTES -
Value of construction — in all cases, a value of construction amount should be entered by the applicant. This figure will be reviewed and is subject
to possible revision by the permit center to comply with current fee schedules.
Expiration of plan review — applications for which no permit is issued within 180 days following the date of application shall expire by limitation.
The building official may grant one extension of time for additional periods not to exceed 90 days each. The extension shall be requested in writing
and justifiable cause demonstrated. Section 105.3.2 International Building Code (current edition).
I HEREBY CERTIF THAT I HAVE : AD AND EXAMINED THIS APPLICATION AND KNOW THE SAME TO BE TRUE UNDER
PENALTY OF PERI BY THE LA S OF THE STATE OF WASHINGTON, AND I AM AUTHORIZED TO APPLY FOR THIS PERMIT.
BUILDING OW R ; -.0 R ZED AGENT:
Signature: f rfi Date: %/z' < < 7
Print Name: f- IAS'1'«1 (p-°- tT Day Telephone: 2 06 ( if 9?° 7
Mailing Address: r Z G l ( Th -Ft-r+. r %o it /4-1, ,, so Jua'l; i..z- Lt/ A u% e'/ ( >
City State Zip
H:Wpplications\Forms-Applications On Line\2011 Applications\Mechanical Permit Application Revised 8-9-11.docx
Revised: August 2011
bh
Page 2 of 2
DESCRIPTIONS
PermitTRAI
Cash Register Receipt
City of Tukwila
ACCOUNT
QUANTITY
PAID
729
M14-0154 Address: 3411 S 120TH PL 100
023049069
2
MECHANICAL
$450.45
PERMIT ISSUANCE BASE FEE
R000.322.100.00.00
0.00
$32.50
PERMIT FEE
R000.322.100.00.00
0.00
$417.95
TECHNOLOGY FEE
$22.52
TECHNOLOGY FEE
TOTAL FEES PAID BY RECEIPT: R2972
R000.322.900.04.00
0.00
$22.52
$472.97
Date Paid: Friday, August 29, 2014
Paid By: TCMS OF SEATTLE LLC
Pay Method: CHECK 007965
Printed: Friday, August 29, 2014 2:12 PM 1 of 1
CRWSYSTEMS
Cash Register Receipt
City of Tukwila
DESCRIPTIONS
ACCOUNT QUANTITY
PAID
PermitTRAK
112
M14-0154 ( Address: 3411 S 120TH PL 100 in-:11102304.906j
112.E
MECHANICAL
$11261
PLAN CHECK FEE
TOTAL FEES PAID BY RECEIPT: R2747
R000.322.102.00.00
0.00
$112.61
$112.61
Date Paid: Thursday, July 31, 2014
Paid By: RUSTIN GILBERT
Pay Method: CREDIT CARD 013413
Printed: Thursday, July 31, 2014 10:34 AM 1 of 1
CRWSYSTEMS
INSPECTION RECORD
Retain a copy with permit
,1'11.4
INSPECTION NO. PERMIT NO. �:. ,� /\
CITY OF TUKWILA BUILDING DIVISION ��
6300 Southcenter Blvd., #100, Tukwila. WA 98188 (206) 431 3670 .I
Permit Inspection Request Line (206) 431-2451
Project,
Type of Inspection: _
Address:
t2,
Date Called:
Special Instructions:
1
Date Wanted:
r� La.m=
( p.m.
Requester:
Phone No:
Approved per applicable codes. D Corrections required prior to approval.
COMMENTS:
r vv
,, tryNAo tJP
_/
,/
l
'
64 )
InspectO'r:
Date: I { I 1 — 14
REINSPECTION FEE REQUIRED. Prior to next inspection. fee must be
paid at 6300 Southcenter Blvd.. Suite 100. Call to schedule reinspection.
2012 Washin.ton State Ener• Code Compliance Forms for Commercial Grou. R1 and > 3 sto R2 and R3
Mechanical Summary
MECH-SUM
2012 Washington State Energy Code Compliance Forms for Commercial, Group R1, and > 3 story R2 & R3
Revised June 2013
Ivroj ect Info
Project Address 3ci ( ��Cr ( d4i I cfr ��
1
Date
, , CIA VI 61,
�In�_
For Building Dept. Use
/4.
�l"te'�ttci
Applicant Name: Q fin (1 RCA- Cr--
�"i/
Z�( Applicant Address: / vt+tAAr A.f) C
/�� J!
Applicant Phone: Ze6 pica ()Iwo?
Project Description
Briefly describe mechanical
system type and features.
Includes Plans
--� (A,, _ 'e---�
��„ r.QJL a-- S'�� ( ck -�l -r-t--x
_ VI4 L' ( L _eL C
Se C/1....e._ 64-Uatekr/1. )&r...ek
Include cumentation requiring compliance with commissioning provisions per Section C408. �D/ ✓
Compliance Option
imple System Complex System Oystems Analysis
Equipment Schedules
The following information is required to be incorporated with the mechanical equipment schedules on the
plans. For projects without plans, fill in the required information below.
Cooling Equipment Schedule
Equip.
ID
Equip
Type
Brand Name'
Model No.'
Capacity'
Btu/h
OSA CFM
or Econo?
SEER
or EER
IPLV3
Econmizer
Option or
Exceptions
Heat
Recovery
Y/N
OBE
CWED FOR
COMPLIANCE
Heating Equipment Schedule
-APPROVED
Equip.
ID
Equip
Type
Brand Name'
Model No.'
Capacity'
Btu/h
OSAcfm
or Econo?
Input Btuh
Output BOG
//{{��JJ
FF��ffiijenc
l
rr� 14Recove
Heat
Y/N
"1
City otTukwila
BUILDING
DIVISION
Fan Equipment
Schedule
Equip.
ID
Equip
Type
Brand Name'
Model No.'
CFM
SP'
HP/BHP
Flow Controls
Location of Service .
Service Water Heating Equipment Schedule
Equip.
ID
Equip
Type
Brand Name'
Model No.'
Input
Capacity
Sub -
Category
Er
Location of Service
1 If available. 2 As tested according to Table C403.2.3(1)A thru C403.2.3(8). 3 If required. 4 COP, HSPF, Combustion Effi ' y s
applicable. 5 Flow control types: variable air volume (VAV), constant volume (CV), or variable speed (VS). 6 Economizer exa�c to Simple
Systems C403.3.1 or Complex Systems C403.4.1. 7 Efficiency Factor per Table C404.2. CITY OF TUKWILA
M Ligan 0 Sy
JUL. 31 2014
PERMIT CENTER
Mechanical
Permit Plans Checklist - Page 1 of 3
State Energy Code Compliance Forms for Commercial, Group R1, and > 3 story R2 & R3
MECH-CHK
2012 Washington
Revised June 2013
Project Address
Date
The following information is necessary to check a mechanical permit application for commercial provision compliance with the 2012 WSEC.
NOTE: Define print area in Excel prior to printing MECH-CHK pages.
Applicability
(yes,no,na)
Code Section
Code Provision
Information Required
Location on'
Plans
Byjlding Department
'Notes
GENERAL PROVISIONS
Equipment Sizing & Performance
C403.2.1
Load calculations
Load calculations performed perASHRAE Std 183 or equivalent per Chapter 3
C403.2.2
Equipment and system sizing
Output capacity of heating and cooling equipment and systems do not exceed
calculated loads, note exceptions taken
C403.2.5
Minimum ventilation
Ventilation (natural or mechanical) provided per IMC; indicate mechanical
ventilation is capable of being reduced to minimum requirement per IMC
C403.2.3 &
C403.2.3.2 &
C403.2.12.1
Equipment minimum efficiency
Provide equipment schedules or complete MECH-SUM tables with type,
capacity, efficiency, test standard (or other efficiency source) for all mechanical
equipment
C403.2.13
Electric motor efficiency
Provide equipment schedule with hp, rpm, efficiency for all motors; note except.
C403.2.10
Fan power limitation
Fan system motor hp or bhp does not exceed limits per Table C403.2.10.1(1)
C403.2.10.3
& C403.2.13
Fractional hp fan motors
Indicate fan motors 1/12 to 1 hp are ECM type or meet minimum efficiency req.
C403.2.3
Maximum air cooled chiller
capacity
Indicate air-cooled chiller capacity does not exceed air-cooled chiller limit
C403.2.1
Non-standard water-cooled
chillers
Full -load and NPLV values for water-cooled centrifugal chiller adjusted for non -
standard operational conditions
C403.2.12.1.2
Centrifugal fan cooling towers
Large capacity cooling towers with centrifugal fan(s) meet efficiency
requirements for axial fan open circuit cooling towers
C403.2.3
Forced air furnace and unit
heaters
Indicate intermittent ignition or IID, flue/draft damper & jacket loss
C403.2.3.3
Packaged electric
heating/cooling equipment
List equipment required to be heat pumps on schedule
ti � i
• C403.2.3.4'•
Nuniidification
Indicate method of humidification (note requirements for systems with
economizer)
r
HVAO System Controls & Criteria '
i —
C403.2.4.1
Thermostatic controls
Indicate locations of thermostatic control zones on plans, including perimeter
systems
,
C403.2.4.1'1
Heat pump supplementary
heat
Indicate staged heating (compression/supplemental) & outdoor lock -out temp
C403.2.4.2
Setpoint overlap (deadband)
Indicate 5°F deadband minimum for systems controlling both heating & cooling
C403.2.4.3
Automatic setback and
shutdown
Indicate zone t-stat controls with required automatic setback & manual override
I'll t
C403.2,4.3.3
Automatic optimum) start
Indicate system controls that adjust equip start time to match load conditions
' - ''
C402.4.5.2 &
C403.2.4.4
Dampers
Indicate location of OSA, exhaust, relief and return air dampers; include AMCA
rated leakage and control type (motorized or gravity; note exceptions taken)
C403.2.11
Heating outside a building
Indicate radiant heat system and occupancy controls
C403.2.4.5
Snow melt systems
Indicate shut-off controls based on outdoor conditions
C403.2.4.6
Combustion heating
equipment
Indicate modulating or staged control
C403.2.4.7
Group R1 hotel/motel systems
Indicate method for guest room automatic setback & set-up of 5°F minimum
C403.2.4.8 / 9
Group R2/R3 dwelling unit
systems
Indicate 5-2 programmable thermostats in primary spaces with minimum of two
setback periods; note exceptions taken
C403.2.5.1
Demand controlled ventilation
Indicate high -occupancy spaces and systems requiring DCV
C403.2.5.2
Occupancy sensors
Indicate spaces requiring occupancy -based system control and method; or
alternate means provided to automatically reduce OSA when partially occupied
C403.2.5.3
Enclosed loading
dock/parking garage
ventilation
Indicate enclosed loading dock and enclosed parking garage ventilation system
activation and control method
C403.2.5.4.1
Kitchen exhaust hoods
Indicate kitchen hoods requiring make-up air; indicate make-up air source and
conditioning method
C403.2.5.4.2
Laboratory exhaust systems
Indicate lab exhaust systems requiring heat recovery, method & efficiency; or
alternative method taken (VAV, semi -conditioned makeup, or CERM calculation)
•
C403.2.6.1
Energy recovery - ventilation
systems
Indicate ventilation systems requiring ER, method & efficiency; note exceptions
C403.2.6.2
Energy recovery - condensate
systems
Indicate on -site steam heating systems requiring energy recovery
C403.2.6.3
Energy
gy recovery - condens
In ate''rem refrig and requiring ER d of c urr Sergi
it ��44
Mechanical Permit Plans Checklist - Page 2 of 3
MECH-CHK
Revised June 2013
IL
2012 Washington State Energy Code Compliance Forms for Commercial, Group R1, and > 3 story R2 & R3
Project Address 3Lj t ( J0lAkg- 12dt' St, O 'b J /u
Date 7 gn y
The following information is necessary to check a mechanical permit application for commercial provision compliance with the 2012 WSEC.
NOTE: Define print area in Excel prior to printing MECH-CHK pages.
Applicability
(yes,no,na)
Code Section
Code Provision
Information Required
Location on
Plans
Building Department
Notes
GENERAL PROVISIONS, CONTINUED
HVAC System Controls & Criteria, Continued
C403.2.12
Variable flow control -
fans/pumps
Indicate fan & pump motors requiring VF control & method (VSD or equiv
controls)
C403.2.12.1
Variable flow control - cooling
towers
Indicate cooling tower fans requiring variable flow control and method
��S
T
C403.2.12.2
Large volume fan systems
Indicate fan systems requiring airflow reduction based on heating and cooling
demand; or exception taken
C403.2.12.2
Single zone AC systems
Indicate method of cooling demand -based fan control for sys. > 110,000 btuh
C403.2.4.10
DDC system capabilities
Identify all DDC system input/output control points and indicate capability for
trending and demand response setpoint adjustment
Ducting Systems
C403.2.7.1 &
C403.2.7.3
Duct construction
Indicate all ductwork constructed and sealed per IMC, C402 leakage
requirements and IBC vapor retarder requirements
C403.2.7.3.1-3
Duct pressure classifications
Identify location of low, medium and high pressure ductwork on plans
C403.2.7.3.3
High pressure duct leakage
test
Indicate high pressure duct leakage testing requirements on plans; provide test
results to jurisdiction when completed
C403.2.7.1 / 2
Duct insulation
Indicate R-value of insulation on ductwork
Piping Systems
C403.2.8
Piping insulation
Indicate R-value of insulation on piping
C403.2.8.1
Piping insulation exposed to
weather
Indicate method of protection from damage/degredation
SIMPLE SYSTEMS
Qualifying Systems
C403.3
Qualifying single zone
systems
Verify unitary or packaged equipment does not exceed capacity limits, does not
have active humidifcation or simultaneous heating/cooling
C403.3
Qualifying 2-pipe heating
systems
Verify 2-pipe heating -only system does not exceed capacity limits
C403.3.2
Hydronic system controls
Refer to Complex Systems Section C403.4.3
Simple System Economizers
C403.3.1
Air economizer required
Indicate cooling systems requiring economizer controls; note in equip sched.
C403.3.1.1.1
Air economizer capacity
Indicate modulating OSA control capability up to 100% OSA, or exception
C403.3.1.1.3
Air economizer high limit
controls
Indicate high limit shut-off control method per Table C403.3.1.1.3(2)
C403.1.1.2
Integrated air economizer
operation
Indicate capability for partial air economizer operation for systems with capacity
> 65,000 btuh
C403.3.1
Air economizer exceptions
Indicate eligible exception(s) taken and provisions to comply with exception(s)
COMPLEX SYSTEMS
Complex System Economizers
C403.4.1
Air economizer required
Indicate cooling systems requiring economizer controls; note in equip sched.
C403.4.1.4
Economizer heating system
impact
Verify control method of HVAC systems with economizers does not increase
building heating energy usage during normal operation
C403.4.1.3
Integrated economizer
operation
Indicate capability for partial economizer operation for air or water econo
systems
Moved
Water economizer capacity
Indicate water econo capable of 100% cooling capacity at 50°F db/45°F wb
OSA
C403.4.1.2
Water economizer maximum
pressure drop
Indicate precooling coils and heat exchangers do not exceed pressure drop limit
C403.3.1
Air economizer exceptions
Indicate eligible exception(s) taken and provisions to comply with exception(s)
Mechanical Permit Plans Checklist
2012 Washington State Energy Code Compliance Forms for Commercial,
- Page 3 of 3
MECH-CHK
Revised June 2013
Group R1, and > 3 story R2 & R3
Project Address
Date
The following information is necessary to check a mechanical permit application for commercial provision compliance with the 2012 WSEC.
NOTE: Define print area in Excel prior to printing MECH-CHK pages.
Applicability
(yes,no,na)
Code Section
Code Provision
Information Required
Location on
Plans
Building Department
Notes
COMPLEX SYSTEMS, CONTINUED
Specific System Requirements
C403.4.2 &
C403.2,12
Variable flow control - fans
Indicate fans requiring variable flow control and method
C403.4.2.1
VAV fan static pressure
sensors
Indicate sensor locations on plans; include at least one sensor per major duct
branch
C403.4.2.2
VAV fan static pressure
setpoint
Indicate fan system static pressure setpoint based on zone requiring most
pressure
C403.4.5
VAV systems serving multi-
zones
Indicate supply air systems serving multiple zones that are required to be VAV,
method of primary air control, and zones served; note exceptions taken
C403.4.5.4
VAV system supply air reset
Indicate controls that automatically reset supply air temp in response to loads
C403.4
Large capacity cooling
systems
Indicate method of multi -stage or variable control for building cooling system
capacity > 300 tons
C403.4.7
Hot gas bypass limitation
Indicate cooling equipment unloading or capacity modulation method
C403.4.3
Large capacity boiler systems
Indicate multi -stage or modulating burner for single boilers > 500,000 btuh
C403.4.3
Boiler sequencing
Indicate automatic controls that sequence operation of multiple boilers
C403.4.3.5
Chiller / boiler plant pump
isolation
Indicate capability to automatically reduce overall plant flow and shut-off flow
through chillers & boilers when not in use
C403.4.2 &
C403.4.3.6
Variable flow control - pumps
Indicate pumps requiring variable flow control & method
C403.2.12.1
& C403.4.4
Variable flow control -cooling
towers
Indicate cooling tower fans requiring variable flow control and method
C403.4.3.4
Hydronic system part load
controls
Indicate heating & chilled water systems have the capability to automatically
reset supply water temp AND reduce flow by 2 50% for systems > 300,000 btuh
C403.4.3.2
Two -pipe changeover
systems
Indicate deadband, heating/cooling mode scheduling and changeover
temperature range
C403.4.3.3.1
Water loop heat pump -
deadband
Indicate capability of central equipment to provide min. 20°F water supply temp
deadband between heat rejection and heat addition modes
C403.4.3.3
Water loop heat pump - heat
rejection
Provide heat exchanger that separates cooling tower and heat pump loop in
Climate Zone 5
C403.4.3.3.3
Water loop heat pump -
isolation
Indicate 2-way isolation valve on each heat pump and variable flow control for
systems with total pump power > 10 hp
C403.4.6
Condenser water heat
recovery
Indicate system provided to pre -heat service water and efficiency
C403.5
Cooler / freezer - anti -sweat
heaters
Indicate w/sf & control method for walk-in cooler/freezer door anti -sweat heaters
C403.5 / 6
Cooler / freezer - evaporator
and condenser fans
Indicate motor type for evaporator and condenser fans < 1 hp
SERVICE WATER HEATING
Service Water Systems
C404.2
Water -heating equip min.
efficiency
Provide equipment schedule or complete MECH-SUM table with type, capacity,
efficiency, test standard (or other efficiency source)
C404.3
Temperature controls
Indicate temperature controls have required setpoint capability
C404.4
Heat traps
Indicate piping connected to equipment have heat traps on supply & discharge
C404.5
Insulation under water heater
Indicate R-10 insulation under tank
C404.6
Service water piping
insulation
Indicate R-value of insulation on piping; note exceptions taken
C404.7 / 8
Circulation systems and heat
trace shut-off
Indicate shut-off capability based on occupancy and periods of limited demand
C404.9
Group R-2 service hot water
meters
Indicate method of usage metering for dwell. units served by central HW system
Pools & In -Ground Permanently Installed Spas
C404.10.1
Pool heating equip min.
efficiency
Provide equipment schedule or complete MECH-SUM table with type, capacity,
efficiency, test standard (or other eff. source); heat pump heaters 2 4 COP
C404.10.1 / 2
Pool heater on /off controls
Indicate automatic on/off control based on scheduling & accessible on/off switch
on heater that operates independent of thermostat setting; or exception taken
C404.10.3
Pool covers
Indicate vapor retardant cover and insulation rating as required
C404.10.3
Pool assembly insulation
Indicate rating of insulation on sides and bottom of pools heated to > 90°F
C404.10.4
Heat recovery
Indicate method, exhaust air temperature reduction and recovered energy use
VILE
(c.S1 Coimufthz
9
J4
STRUCTURAL CALCULATIONS
SAHALE SNACKS HVAC FAN REPLACEMENT
Seattle, WA
TCMS, Temp Control Mechanical Service Corp.
July 21, 2014
Project No. 140178
6 Pages
REVIEWED FOR
CODE
COMPLIANCE
APPROVED
AUG 21 2014
BUILDING Tukwila
(VISION
* * *LIMITATIONS* * *
ENGINEER WAS RETAINED IN A LIMITED CAPACITY FOR THIS PROJECT.
DESIGN IS BASED UPON INFORMATION PROVIDED BY THE CLIENT,
WHO IS SOLELY RESPONSIBLE FOR THE ACCURACY OF THE SAME.
NO RESPONSIBILITY AND / OR LIABILITY IS ASSUMED BY,
OR IS TO BE ASSIGNED TO THE ENGINEER FOR ITEMS
BEYOND THAT SHOWN ON THESE SHEETS.
116057'1S 16d Se.
`j/aoreouuaa, ZU,¢ 98684
503, 737. 4344
�7LS-caodu to y@comecut, get
M i--0 5)4
RECEIVED
CITY OF TUKWILA
JUL, 31 2014
PERMIT CENTER
NEW HVAC FAN INSTALLATION
Existing loads: Roof dead load, wdl = 10 psf
Roof live load (snow), wil = 25 psf
Area tributary to beam, Atdb = 24 ft
Total existing load on beam, w = (wdl + WO* Atrlb = 840.000pIf
New fan load: P = 500 lb
Beam length: L = 57 ft
Fan location: 19 ft from support
EXISTING ROOF BEAM ANALYSIS & DESIGN (NDS)
STRUCTURAL GLUED LAMINATED TIMBER (GLULAM) BEAM ANALYSIS & DESIGN (NDS)
In accordance with the ANSUAF&PA NDS-2012 using the ASD method
0.899
TEDDS calculation version 1.6.00
Load Envelope - Combination 1
0.0— 0
ft
A
klp_tt
0.0
365.132
hI
A
57
Bending Moment Envelope
365.1
57
1
dQcJt� cft>r9 PJ12
RNS Consulting LLC
11605 NE 16th St.
Vancouver, WA 98684 (503) 737-4344
Project Sahale Snack Project Job # 140178
Address Seattle, WA
Client TCMS
By R.P. Date 7/18/2014
Page 1 of 6
bps 25.6
25.623-
0.0-
-25.623-
Applied loading
Beam loads
Span 1 loads
Load combinations
Load combination 1
Analysis results
Design moment
Total load on member
Reaction at support A
Shear Force Envelope
fll
A
M = 365131.8 Ib ft
Wtot = 51246.6 Ib
RA max = 25623 lb
Unfactored dead load reaction at support A
Unfactored snow load reaction at support A
Reaction at support B R8_max = 25623 Ib
Unfactored dead load reaction at support B
Unfactored snow load reaction at support B
-25.6
57
1 B
Dead self weight of beam x 1
Dead UDL 240 lb/ft from 0.00
Snow UDL 600 Ib/ft from 0.00
Support A
Span 1
Support B
Design shear
RA min = 25623 lb
RA Dead = 8523 lb
RA_Snow = 17100 Ib
RBmin = 25623 Ib
RB_Dead = 8523 lb
RB_snow = 17100 Ib
in to 684.00 in
in to 684.00 in
Dead x 1,00
Live x 1.00
Snow x 1.00
Dead x 1.00
Live x 1.00
Snow x 1.00
Dead x 1.00
Live x 1.00
Snow x 1.00
F = 25623.3 Ib
cR Af , Mkt ling
RNS Consulting LLC
11605 NE 16th St.
Vancouver, WA 98684 (503) 737-4344
Project Sahale Snack Project
Address Seattle, WA
Client
Job # 140178
TCMS
By R.P. Date 7/18/2014
Page 2 of 6
Glulam section details
Net finished section breadth
Number of sections
Stress class
Member details
Service condition
Length of bearing
Load duration
b = 6.75 in
N=1
24F-V4 DF/DF
Lb=8in
Ten years
Bearing perpendicular to grain - c
Adjusted compression Fb_pe
1.3.10.2
,P = 650 Ib)n2 Applied compression fc_pem = 475 lb/in2
PASS - Design compressive stress exceeds applied compressive stress at bearing
Net finished section depth d = 36 in
Alignment of laminations Horizontal
Strength in bending - c1.3.3.1
Design bending stress Fe = 2175 Ib/in2
Strength in shear parallel to grain - c1.3.4.1
Design shear stress F, = 265 Ib/in2
Deflection - c1.3.5.1
Allowable deflection
Sadm = 2.873 in
Actual bending stress fb = 3005 Ib/in2
FAIL - Design bending stress is less than actual bending stress
Actual shear stress f„ = 158 lb/in2
PASS - Design shear stress exceeds actual shear stress
Total deflection S. = 4.713 in
FAIL - Design deflection exceeds total deflection
EXISTING ROOF BEAM W/NEW FAN LOAD ANALYSIS & DESIGN (NDS)
STRUCTURAL GLUED LAMINATED TIMBER (GLULAM) BEAM ANALYSIS & DESIGN (NDS)
In accordance with the ANSI/AF&PA NDS-2012 using the ASD method
0.899
TEDDS calculation version 1.6.00
Load Envelope -Combination 1
0.0—e
tt
A
57
B
4Ln PP
RNS Consulting LLC
11605 NE 16th St.
Vancouver, WA 98684 (503) 737-4344
Project Sahale Snack Project
Address Seattle, WA
Job # 140178
Client TCMS
By R.P.
Date 7/18/2014
Page 3 of 6
klp_ft
0.0—
Bending Moment Envelope
369.897— 33079
ftl
A
kips 26.0
25.957— _,.,
0.0
-25.790—
Applied loading
Beam Toads
Span 1 loads
Load combinations
Load combination 1
1
ftl
A
369.9
57
Shear Force Envelope
8.4
57
-25.8
Analysis results
Design moment M = 369897.2 Ib ft
Total load on member Wlol = 51746.6 Ib
Reaction at support A RA max = 25957 Ib
Unfactored dead load reaction at support A
Unfactored snow load reaction at support A
Reaction at support B RB_max = 25790 Ib
Dead self weight of beam x 1
8
Dead UDL 240 lb/ft from 0.00 in to 684.00 in
Snow UDL 600 lb/ft from 0.00 in to 684.00 in
Dead point load 500 Ib at 228.00 in
Support A
Span 1
Support B
Dead x 1.00
Live x 1.00
Snow x 1.00
Dead x 1.00
Live x 1.00
Snow x 1.00
Dead x 1.00
Live x 1.00
Snow x 1.00
Design shear F = 25956.6 Ib
RA min = 25957 Ib
RA Dead = 8857 Ib
RA_snow = 17100 Ib
RB_min = 25790 Ib
,R,ALs' „.e c'tig /Ye
RNS Consulting LLC
11605 NE 16th St.
Vancouver, WA 98684 (503) 737-4344
Project Sahale Snack Project Job # 140178
Address Seattle, WA
Client TCMS
By R.P. Date 7/18/2014
Page 4 of 6
•
Unfactored dead load reaction at support B
Unfactored snow load reaction at support B
Glulam section details
Net finished section breadth
Number of sections
Stress class
Member details
Service condition
Length of bearing
Load duration
b = 6.75 in
N=1
24F-V4 DF/DF
Lb=8in
Ten years
Bearing perpendicular to grain - c1.3.10.2
Adjusted compression
Re Dead = 8690 Ib
Re snow = 17100 Ib
-PI 8" ,w
Net finished section depth d = 36 in
Alignment of laminations Horizontal
Fc_perp' = 650 Ib/in2 Applied compression fc_pe,p = 481 Ib/in2
PASS -
Design compressive stress exceeds applied compressive stress at bearing
Strength in bending - c1.3.3.1
Design bending stress Fti = 2175 Ib/in2
Strength in shear parallel to grain - c1.3.4.1
Design shear stress F,' = 265 Ibfin2
Deflection - c1.3.5.1
Allowable deflection
Sadm = 2.873 in
Actual bending stress fb = 3044 Ib/in2
FAIL - Design bending stress is less than actual bending stress
Actual shear stress f„ = 160 Ib/in2
PASS - Design shear stress exceeds actual shear stress
Total deflection Sa = 4.775 in
FAIL - Design deflection exceeds total deflection
cR&AL5' (' ualng Pie
RNS Consulting LLC
11605 NE 16th St.
Vancouver, WA 98684 (503) 737-4344
Project Sahale Snack Project Job # 140178
Address Seattle, WA
Client
TCMS
By R.P.
Date 7/18/2014
Page 5 of 6
Comparison by chapter 34, section 3404.3
Existing bending stress in beam: fbl = 3005 psi
Bending stress with new fan load: fb2 = 3044 psi % difference: ((fb2 - fbl) / fb1)*100 =1.298
Existing deflection in beam: = 4.713 in
Deflection with new fan load: A2 = 4.775 in % difference: ((A2 - A1) / Ai)*100 = 1.316
Differences are Tess than 5%, therefore existing beam is adequate
s?sVSnhuriln9
RNS Consulting LLC
11605 NE 16th St.
Vancouver, WA 98684 (503) 737-4344
Project Sahale Snack Project Job # 140178
Address Seattle, WA
Client TCMS
By R.P. Date 7/18/2014
Page 6 of 6
No.:
W
C
Date: 09-MAY-2014
' r
L. DATA SHEET
Three-phase induction motor - Squirrel cage rotor
Customer .•
Product line : W22 NEMA Premium - Ball Bearings
Frame : 182/4T
Output : 5 HP
Frequency : 60 Hz
Poles : 4
Full load speed : 1755
Slipo: 2.50083 CODE F
Voltage 208-230/460 V OR
Rated current : 14.3 12.9/6.45 A COMPLrA
Locked rotor current : 96.8/48.4 A NCE
Locked rotor current (II/In) : 7.5 APPROVED
No-load current : 6.40/3.20 A AU�
Full load torque : 14.8 ib.ft A 1 2014
Locked rotor torque : 230 %
Breakdown torque : 320 %
Design : B
TemperatureInsulat'on lass : F City rise : 80 K BUILD IGr�kw�la
Locked rotor time : 15 s (hot) DIVISION
Service factor : 1.25
Duty cycle : S1
Ambient temperature : -20°C - +40°C
Altitude : 1000
Degree of Protection : IP55
Approximate weight : 95 lb
Moment of inertia : 0.40033 sq.ft.lb
Noise level : 56 dB(A)
D.E. N.D.E.
Bearings 6207 ZZ 6206 ZZ
Regreasing interval — —
Grease amount — —
Load Power factor Efficiency (%)
100% 0.80 89.5
75% 0.74 89.5
50% 0.62 88.5
Notes:
Performed by
Checked
RECFRvPn
VLL1O5L1
CITY OF TUKWILA
JUL 3 1 2014
PERMIT CENTER
■w
_
No.:
Date: 09-MAY-2014
PERFORMANCE CURVES RELATED TO RATED OUTPUT
Three-phase induction motor - Squirrel cage rotor
100 _ 1.0 0.0
_'�
11111i-mos
•
0'
0
01
iioiohuohl
c
I1IDU%ri■■■■I
_
AiiBIRIilI
iu,•uuu••mui
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Percent of rated output (%)
Customer .•
Product line : W22 NEMA Premium - Ball Bearings
Frame : 182/4T Locked rotor current (II/In) : 7.5
Output : 5 HP Duty cycle : S1
Frequency : 60 Hz Service factor : 1.25
Full load speed : 1755 Design : B
Voltage : 208-230/460 V Locked rotor torque : 230 %
Rated current : 14.3-12.9/6.45 A Breakdown torque : 320 %
Insulation class : F
Notes:
Performed by
Checked
1
■w
_
No.:
Date: 09-MAY-2014
CHARACTERISTIC CURVES RELATED TO SPEED
Three-phase induction motor - Squirrel cage rotor
5.0 10 n
A - Torque related to rated torque (C/Cn)
O O 7' N N G) W A ?
O CT O CT o GT o U1 O CJ7
B - Current related to rated current (I/In)
'. 0 0 Co 0 0 0 0 0 0 C
CO tl) 4 C) c C
-
B
0 10 20 30 40 50 60 70 80 90 100
Speed related to rated speed (%)
Customer .•
Product line : W22 NEMA Premium - Ball Bearings
Frame : 182/4T Locked rotor current (II/In) : 7.5
Output : 5 HP Duty cycle : S1
Frequency : 60 Hz Service factor : 1.25
Full load speed : 1755 Design : B
Voltage : 208-230/460 V Locked rotor torque : 230 %
Rated current : 14.3-12.9/6.45 A Breakdown torque : 320 %
Insulation class : F
Notes:
Performed by
Checked
Notes:
Performed by:
Checked:
Customer:
W22 NEMA Premium - Ball Bearings
Three-phase induction motor
09-MAY-2014
Frame 182/4T - IP55
PERMIT CCORD COPY
PLAN REVIEW/ROUTING SLIP
PERMIT NUMBER: M14-0154
PROJECT NAME: SAHALE SNACKS
SITE ADDRESS: 3411 S 120 PL - STE 100
X Original Plan Submittal
Response to Correction Letter #
DATE: 07/31/14
Revision #
Revision #
before Permit Issued
after Permit Issued
DEPARTMENTS:
Building Division
Public Works
n
2 bWI'111
Fire Prevention
Structural
Planning Division
Permit Coordinator
n
PRELIMINARY REVIEW:
Not Applicable n
(no approval/review required)
REVIEWER'S INITIALS:
DATE: 08/05/14
Structural Review Required
DATE:
APPROVALS OR CORRECTIONS:
Approved
Corrections Required
n
n
(corrections entered in Reviews)
Approved with Conditions
Denied
(ie: Zoning Issues)
DUE DATE: 09/02/14
Notation:
REVIEWER'S INITIALS:
DATE:
Permit Center Use Only
CORRECTION LETTER MAILED:
Departments issued corrections: Bldg ❑ Fire 0 Ping ❑ PW 0 Staff Initials:
12/18/2013
TCMS OF SEATTLE LLC
Page 1 of 2
0 Washington State Department of
Labor & Industries
TCMS OF SEATTLE LLC
Owner or tradesperson
MOORE, WILLIAM J
Principals
MOORE, WILLIAM J, PARTNER/MEMBER
Doing business as
TCMS OF SEATTLE LLC
WA UBI No.
602 845 504
Parent company
MOORE HOLDING CORP
12646 INTERURBAN AVE S
SEATTLE, WA98168
206-588-8787
KING County
Business type
Limited Liability Company
License
Verify the contractor's active registration / license / certification (depending on trade) and any past violations.
Construction Contractor
License specialties
GENERAL
License no.
TCMSSSL905CB
Effective — expiration
02/01/2010— 02/10/2016
Bond
DEVELOPERS SURETY & INDEM CO
Bond account no.
269810C
Received by L&I
02/01/2010
Insurance
Phoenix Insurance Company, The
Policy no.
C09640N520
Received by L&I
10/09/2013
Active.
Meets current requirements.
$12,000.00
Effective date
01/27/2010
Expiration date
Until Canceled
$1,000, 000.00
Effective date
10/01/2013
Expiration date
10/01/2014
Insurance history