HomeMy WebLinkAboutReg 2019-02-04 Item 7C - Reports - City Administrator / Public Safety Plan Monthly UpdateAllan Ekberg, Mayor
TO:
Mayor's Office - David Cline, City Administrator
The City of opportunity, the community of choice
Mayor Ekberg
Councilmembers
FROM: David Cline City Administrator
DATE: January 30, 2019
SUBJECT: City Administrator's Report
The City Administrator Report is meant to provide the Council, staff and community an update on
the activities of the City and on issues that concern Tukwila. Please let me know if you have any
questions or need additional information about any of the following items.
I. Intergovernmental Update
• House Appropriations Committee: On January 14 Mayor Ekberg, along with a panel of other
Mayors, testified before the House Appropriations Committee in Olympia regarding
Streamlined Sales Tax Mitigation payments.
• Annual United Conference of Mayors: Mayor Ekberg attended the 87th Annual United
Conference of Mayors Winter Meeting in Washington DC January 23 - 25.
9 Board of Architectural Review Meeting: On January 24 the Tukwila Board of Architectural
Review approved with conditions the Variance, Design Review Major Modification, and
Subdivision Preliminary Plat applications for Phase 2 of the Osterly Park Townhomes. The
Board also approved the Conditional Use Permit and Design Review application for
Vietnamese Martyrs Church located at 6841 and 6847 S 180th St.
II. Community Events
• Tip -a -Cop: On January 24 the Tip -a -Cop event was held at the Old Spaghetti Factory and
$1,500 was raised for the Special Olympics of Washington. The funds will be used for
equipment, attire, venues and medical checks for athletes at each of the Special Olympics
games.
• Youth Basketball Program: On January 26 King County Councilmember Dave Upthegrove
presented a $5,000 check to the Parks and Recreation Department for the Youth Basketball
Program. These funds will be used for scholarships to over 90 players (1/3 of the league
participants).
• Tukwila Library Advisory Board: The Tukwila Library Advisory Board will be hosting the new
King County Library System Director, Lisa Rosenblum, on February 5 at 5:30 PM at the Tukwila
Community Center.
Tukwila City Hall • 6200 Southcenter Boulevard • Tukwila, WA 98188 • 206-433-1800 • Website: TukwilaWA.gov
211
City Administrator's Report
January 30, 2019
Page 2
III. Staff Updates
Public Safety
• Homeless Camps: The Community Police Team is working with other city departments to
clean up homeless camps and provide resources to those experiencing homelessness along
Interurban Ave S.
Project Updates
• 42nd Ave Phase III: Estimated Completion: March 2019
Waiting to hear from Seattle City Light (SCL) about cutover work and removal of overhead
power lines. Comcast is working on their overhead wire removal. After all other utilities have
completed their overhead to underground utility conversions, CenturyLink will remove their
remaining overhead wires and the utility poles.
• 53rd Ave S: Estimated Completion: May 2019
The contractor is focusing on finalizing electrical services to residences as well as utility work
related to installing the PSE gas line. It is anticipated that the base lift of paving will be
installed in the first quarter of 2019.
• BAR Bridge Rehabilitation: Estimated Completion: March 2019
Contractor continues to work on the sidewalk over the railroad and is anticipating sidewalk
completion by the end of January. The contractor will look at shifting the traffic lanes in late
January to complete incidental expansion joint work. Construction is on schedule for
completion in March.
• S 140th St/TIB Intersection Improvements: Bid set plans and specs are now complete for
the two new crosswalks. Bid opening is scheduled for Feb 11 with the tentative bid award
requested at the Feb 19 regular meeting.
• Tukwila Village: The Food Innovation Network (FIN), which is a program of Global -to -Local, is
working on a plan to open a mini -food hall that would be operated by a cluster of very small
businesses. The mini -food hall would be located inside Building A, which is the building
currently under construction. FIN is seeking funding for the food hall from the State
legislature.
• King County Metro Transit: King County Metro has applied for a building permit which will
include a new bus base and maintenance facility with a project value of $3.6 million.
• Holden at Southcenter: Holden at Southcenter has applied for a building permit for a 7
story, 134 unit assisted living community with a project value of $21.3 million.
• Change in Business License Process: Staff from the Finance department, Economic
Development and Communications are developing an outreach plan to notify businesses that
effective March 15 business license applications and renewals will be processed through the
State's portal.
• Teen Program: Nate Robinson and 14 Teens for Tukwila members will be in Olympia January
27-28 attending Youth Action Day. They plan to meet with Senator Bob Hasegawa,
Representative Steve Bergquist, and Representative Zak Hudgins
Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov
212
City Administrator's Report
January 30, 2019
Page 3
Boards and Commissions
• Arts Commission: Vacant Positions: Positions #3 and #7 Residents.
• Civil Service Commission: No vacancies.
• COPCAB: Vacant Position: School District Representative and Student Representative.
• Equity & Social Justice Commission: Vacant Position: Student Representative.
• Human Services Advisory Board: Vacant Position: Position #3 Resident.
• Landmark Commission: No vacancies.
• Library Advisory Board: Vacant Positions: Position #7 Resident & Student Representative.
• Lodging Tax Advisory Committee: No vacancies.
• Park Commission: Vacant Positions: Position #4 Resident & Student Representative.
• Planning Commission: No vacancies.
Phone: 206-433-1800 • Email: Mayor@TukwilaWA.gov • Website: TukwilaWA.gov
213
214
TUKW|LAPUBUC SAFETY PLAN
Monthly Update
Overall Plan
Outreach
w Team anticipates 2 events for the public in 2019, starting with a ground breaking
ceremony for FS51 on Saturday, March 30, 2019.
Financial Oversight Committee
0 The Committee reported to council on September 4, 2018.
Siting Advisory Committee
w The Siting Advisory Committee voted todefer regular meetings asthe major decisions
have been made, They will meet onanas-needed basis.
Acquisition Lease Updates
� Staff secured leases with nine businesses and expects tohave the remaining leases
completed bythe end ofNovember.
Disadvantaged Business Enterprise (DBE)Outreach
0 A formal update will be provided to the Council at the February 25, 2019 COW meeting.
Near -term Council Decisions and Key Dates
• Commissioning Consultant Contract toPublic Safety Committee and Council
• Construction Inspections Consultant Contract to Public Safety Committee and Council
• JC Architect Contract Amendment to Public Safety Committee and Council
Fire Stations
Siting
~ With Council approval received, the team completed demolition of the single-family
home onthe Station 54site.
• Team will be working on lot consolidation for Station 54 to consolidate the main parcel
with the smaller parcel.
Architecture and Programming
0 Architectural program has been reviewed and approved by the team.
�1� �
~_.~ �
Design and Permitting
• Concurrent review and pricing of the Schematic Design by GCCM Contractor, Lydig, and
estimating consultant has been completed and was shared with Council in February
2018. Council gave approval to begin Design Development for Station 51.
• Design Development for Station 51 began mid -February; the team met meeting weekly.
Design Development effort wrapped up in June, 2018 with Design Development pricing
effort in July and August.
• Construction Documents phase for Station 51 were completed and distributed to the
team December 20, 2018.
• Schematic Design phase underway for Station 52, planning to be complete by end of
January. Estimating for Station 52 to begin when final Schematic Design plans are
issued.
• Building permit for Station 51 was submitted in October. Anticipate receiving approved
permit approval in December in all areas except wetlands report.
Permitting coordination meetings with City Staff are ongoing for Station 51 and Station
52. Station 52 anticipated to be phased permitting. Pre -application for Station 52
permit was submitted in November, 2018 and the pre -application meeting for Station
52 was held in December, 2018.
Bidding and Construction
• Pre -construction services starting for Station 51 and 52 are underway.
• Lydig completed the selection of mechanical and electrical subcontractors through the
Electric Contractor/Construction Management (ECCM) and Mechanical Contractor
Construction Management (MCCM) selection process. Valley Electric and Johansen
Mechanical Inc. were selected. With Council decision to not move forward with FS54,
we cannot move forward with ECCM. MCCM method for mechanical subcontractor will
provide for a consistent mechanical subcontractor for all three stations and will be able
to provide critical expertise during the Design Development phase. This contract is
managed by the GCCM under the pre -construction phase.
• Bidding began for 51 in January, 2019 with construction for 51 to begin late March,
2019.
Bidding and construction phases scheduled to begin for 52 in June, 2019. Early site work
is anticipated to begin in July.
Justice Center
Siting
• The City has agreements with all affected businesses on the Justice Center site.
• The City has ownership of all properties on the Justice Center site with the exception of
the Travelodge. The long -vacant building between Church by the Side of the Road and
the Travelodge has now been demolished. The Travelodge is now empty, and the
216
project team is waiting on Seattle City Light to disconnect electrical service before they
proceed with the demolition ofthis building.
Architecture and Programming
w DLR Grouu's Building Program Report was submitted December Oi 2017' Program and
Estimate was presented to Public Safety Committee in December and Council in
]anuary,3DlG.
Design and Permitting
• DLRarchitects completed the Design Development phase ofthe project. The Design
Development and budget was presented tothe Council inOctober.
° The project t2annhas completed the SEPA,Design Review, Conditional Use Permit and
Parking Determination processes. TheSEpA determination was issued in November and
the Conditional Use Permit and Design Review approvals were received in December.
w DLR architects began the Construction Documents phase in October and issued the 95%
Construction Documents in January, The 100% Construction Documents will be issued
following receipt ofconstruction permits.
• The project team submitted application for Public Works Permit (sitework/utilities) in
November of3O1X,and application for Building Permit |nJanuary of3O19.
Bidding and Construction
• BNBuilders, the selected GC/CM, started pre -construction services following Council
approval oftheir contract on March 19, 2018.
• BNBuilders will continue to work with the team on design phases, constructability, cost
estimating and scheduling throughout design and preconstruction.
• BNBuj}derswill release the first subcontract bid packages inlate January.
• Construction scheduled to begin in April, 2019 with hazardous materials abatement and
demolition ofremaining buildings Onthe site, followed bygrading and underground
utilities work.
Public Works Pac|itV
Siting
• Due diligence items related tosite acquisition are complete. The assessment ofexisting
structures iscomplete.
^
m The City has agreements with all of the businesses on the Public Works site.
• The Public Use and Necessity trial was held Friday, May 25 and the City was granted its
request.
Architecture and Programming
� Team solicited for Architectural services. Council approved a contract for programming
and master planning services with 5HK5 in November 20I8.
217
w Master planning and programming phase began in late 2018, with regular meetings with
Public Works staff. Master planning and programming bscheduled tobecompleted 1n
May Df2O19.
Design and Permitting
0 Phase I design scheduled to begin Q2 in 2019, after council approval.
Bidding and Construction
0 Phases scheduled to begin in Q4 2019.
� Based on Council direction to move forward with Station 51, Station 52, Justice Center
and Public Works Facility ($30M), team has updated the budgets.
Schedule
February 2019
~ Fire Station 52 schematic design estimate to Committee
• Fire Station S2design development begins
~ Fire Station 53 parking determination application submitted
• Survey Contract Approval toPublic Safety Committee and Council
° Trave|odge building demolition
• Justice Center Public Works Permit (siteVvork/uti|ities)issuance
March2DI9
• Fire Station 51 Construction Contract Approval to Public Safety Committee and Council
• Justice Center Construction Contract (mini-MACC) Approval to Public Safety Committee
and Council
• Fire Station 51con6truct|0n begins
• Fire Station 5lgroundbreaking event
• Fire Station 52 parking determination received
• Fire Station 52 SEPA application submitted
• Fire Station S2conditional use/BAR applications submitted
• Miscellaneous Consultant Construction Observation Contract Approvals to Public Safety
Committee and Council
Apri|2Dl9
• Justice Center Construction Permit (main building) issuance
• Justice Center construction begins (bUUdingderncHitkon and hazardous materials
abatement)
218
~ Fire Station 53SEPAdetermination
• Public Works programming complete
May 2019
• Fire Station 52 design development cost estimating to Public Safety Committee
• Fire Station 53 construction documents begin
• Fire Station 52conditional use/BAR public hearing
w Public Works programming and estimates toCommittee and Council
June 2019
~ Fire 5tation5l construction complete
• Fire Station 52design development estimate toCommittee and Council
• Fire Station SZ phase I (grading/wall) permit submitted
• Fire Station 52 phase 1 bidding
~ Public Works phase Idesign begins
July 2019
w Fire Station SI move -in
• Fire Station 52phase l /gradins/vva|Upernnit received
• Fire Station 52 phase (building) permit submitted
• Fire Station 52 phase I Lyclig contract amendment to Committee and Council
August]019
w Public Works Phase ldesign complete
* Fire Station 5Icon5tructon documents begin
w Fire Station 52 phase bidding
Septernber2019
0 Fire Station 52 Lyclig contract amendment to Public Safety Committee and Council
October 2039
• Fire Station 5Zphase 2(huj|ding) permit issued
~ Fire Station 52phase 2construction begins
• Public Works Phase I construction contract approval to Public Safety Committee and
Council
NoVecnber2019
m Public Works Phase Iconstruction begins
Qecenmber2O1g
JanuarV2020
219
February 2020
• Public Works Phase 1 construction complete
March 2020
• Public Works Phase 1 move -in
September 2020
• Justice Center construction complete, start move -in
220
City of Tukwila - Facilities Plan
TOTAL PROJECT
MONTHLY Budget Report
(REVISED Budgets; D-20 Plan Adopted by Council)
Life to Date Costs
as of Jan rare 25, 2019 (reconciled irlacctg that De • 31, 2018 Gld
COUNCIL REPORTING SUlIMARY -
JUS17CE CENTER
A/EServices(bothDesign&'CA)
Permits/Fees
Construction (Pre -Con, Coast & Tax)
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
Contingency for Site Contamination (soils,hasnat)
Land Acquisition
Contingency for Land Acquisition
Original Midget
3,278,125
S 700,000
38,738,678
2,112,639
1,815,875
S 6,507,731
S -
S 14,133,295
5 I 250,000
Budge( Tramiel,
221,575
$ -
$ (11,315)
$ 170,000
$ 296,721
$ (1,646,239)
$ 750,000
S (81,042)
$ 300,000
Current Badger
5 3,500,0003,141,729
709,000
$ 38,727,363
$ 2,282,639
$ 2,112,596
$ 4,861,492
5 750,000
S 14,052,253
$ 1,550,000
Conintifteil Midget
5 99,868
$ 563,671
$ 407,828
$ 1,967,303
S -
$ -
S 13,705,681
S 918,462
Lifr to Rafe COM
Re11111111k Committed
Remaining Midget
Coit at Completion
1,705,300
99,868
282,108
242,726
S 870,929
S -
S -
13,679,255
5 918,462
$ 1,436,429
$ -
$ 281,563
$ 165,102
S 1,096,374
S -
-
$ 26,427
S -
$ 358,271
$ 600,132
$ 38,163,692
$ 1,874,811
$ 145,293
S 4,861,492
$ 750,000
$ 346,572
$ 631,538
-
$ -
$ -
$-
S -
$ -
S -
$ -
$
-
S 68,516,343
5 20,804,542
,S 17,798,648
S 3,005,894
$ 47,731,801
S -
COUNCIL REPORUNGSUILIVIRY -
FIRE S7:4 770N 51
A/E Services (both Design 8c CA)
Land Acquisition
Permits/Fees
Construction (Pre -Con, Const & Tax)
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
Original Budge
$ 1,070,000
S -
S 234,000
$ 9,396,000
$ 931,000
5 526,000
5 1,116,000
Ihillgel Trarrifert
$ 222,781
S -
S -
$ -
$ -
S -
$ (222,781)
Carrent nudger
$ 1,292,781
S -
$ 234,000
$ 9,396,000
$ 931,000
S 526,060
$ 893,219
Committed Rodger
$ 1,236,572
$ -
S 34,557
$ 165,000
5 133,546
5 344,681
S -
ofr to MO Coo,
&Wining Committed
Remaining Budget
Coil of Completion
S 747,820
S -
$ 34,557
t S 99,273
$ 80,187
S 120,475
; S -
$ 488,751
S -
5 -
5 65,727
S 53,358
$ 224,206
, $
$ 56,209
S -
5 199,443
S 9,231,000
$ 797,454
5 181,319
5 893,219
5 -
$ -
S _
$ -
S -
5 -
$
-
5 13,273,000
5 1,914,355
S 1,082,313
5 832,043
S 11,358,645
S -
COIM7L REPOR77NGSW WA RI' -
FIRE ST4 770N 52 Original Rodger
Bodge, Mintier,
Owen( Illidgin
Committed Bodge]
Life. Date Conic
Rimming Committed
Remaining Urntgri
(rotat Compterime
A/E Services (both Design & CA)
Land Acquisition
Permits/Fees
Construction(Pre-Con, Const & Tax)
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
S 1,415,000
S 16,000
$ 353,000
$ 13,298,00(1
$ 1,398,000
5 787,000
5 1,343,000
5 234,222
$
5 -
$ 456,500
S -
S -
$ (40,722)
$ 1,649,222
16,000
S 353,000
5 13,754,500
5 1,398,000
5 787,000
5 1,302,278
$ 1,548,449
5 17,157
5 -
$ 137,500
5 393,815
5 532,289
$ -
i 5 252,910
5 17,157
S -
5 -
' $ 16,258
5 187,089
s $ -
$ 1,295,539
S 0
$ -
S 137,500
S 377,557
S 345,200
$ -
$ 100,773
5 (1,157)
S 353,000
S 13,617,000
5 1,004,185
S 254,711
1,302,278
$ _
$ -
$ -
S _
S _
$ .
5 -
5 18,610,000
S 650,000
5 19,260,000
S 2,629,210
S 473,413
S 2,155,797
5 16,630,790
COUNCIL REPORTING SIM:11AR Y -
FIRE ST-1770N ,1
5
Se ''c th D i CA
Land Acquisition
Permits/Fees
Construction (Pre -Con, Const & Tax)
Construction Related Costs Oriel Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
Original Midget
,0
5 902,668
5 20,000
$ 230,000
$ 50,000
$ 107,500
5 41,832
Budget rranifer.
7, )
5 25,596
5 -
5 -
5 9,875
5 -
5 (28,471)
Current Bodge
5 143,000
S 928,264
5 20,000
5 230,000
$ 59,875
S 107,500
$ 13,361
Committed Midget
$ 832,995;5
5 928,265
S 1,517
$ 106,700
$ 44,752
S 106,665
$ .
1 OB r fa are Coin
Reaming Coniniittml
& weaning Midget
o Con
Coat ipktion
131,495
S 928,165
1,517
67,856
22,798
84,815
, -
S 1,500
' 5 100
J S -
$ 38,844
S 21,954
5 21,850
$ -
10,005
$
S 18,483
$ 123,300
5 15,123
S 835
$ 13,361
5 -
-
5 ..
S -
-
S _
$ _
1,502,000
5 -
S 1,502,000
S 1,320,894
1 5 1,236,646'
84,248
5 181,106
S
COUNC71. REPORTING SI MIL-IR r -
PLYILIC ll'ORIO.'J A/E Services (both Design & CA)
Land Acquisition
Permits/Fees
Construction (Pre -Con, Coast & Tax)
Construction Related Costs (incl Bond)
PM Services (incl Other Professional Svcs)
Contingency (incl Construction & Project)
Original Reidget
5 767,385
5 22,000,046
5 110,000
5 4,950,000
5 529,036
5 668,426
5 975,107
Bioko Traffifert
$ 15,000
S 3,333,913
$ (20,000)
S (1,842,500)
5 (4 [6,293)
S (348,426)
S (721,694)
Owen, Iliolgo
S 782,385
5 25,333,959
5 90,000
S 3,107,500
S 112,743
5 320,000
5 253,413
Committed linilgo
S 318,882
$ 25,294,683
S
S -
$ 65,643
$ 279,832
5 -
Life ell Dare Cinti
Retuning Committed
Remaining Inidget
OM at Compktion
S 33,393
5 25,292,483
-
S -
5 50,471
t S 129,585
S
5 285,489
$ 2,200
-
$ 15,172
S 150,247
S 463,503
$ 39,276
90,000
5 3,107,500
S 47,100
$ 40,168
253,413
$ .
$
$ _
S
$ _
S -
5
-
5 30,000,000
5 25,959,040
S 25,505,932
S 453,108
4,040,960
-
N
N
N
TUKWILA PUBLIC SAFETY PLAN
FIRE STATION 5
NE PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
ARE STATION 52
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
JUSTICE CENTER
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY
PUBLIC WORKS
A/E PROCUREMENT
MASTER SITE PLAN
DESIGN PHASE 1
BIDDING/CONSTRUCTION PHASE 1
MOVE-IN/OCCUPANCY PHASE 1
Ni
cA)
2016
2017
2018
2019
2020
.111111111.1111111•1111111111=111111111=1.
UliD
2021
PROJECT
A/E PROCUREMENT
PROGRAMMING
DESIGN/PERMITTING
BIDDING/CONSTRUCTION
MOVE-IN/OCCUPANCY