HomeMy WebLinkAboutReg 2019-03-04 Item 4C - Final Acceptance - 2018 Overlay and Repair Program by ICON Materials for $896,833.41COUNCIL AGENDA SYNOPSIS
Initials
Meeting Date
Prepared by
I Mayor's review I
Council review
03/04/19
I
HH
/4/f-. f'
I
i'ti
ITEM INFORMATION
ITEM No.
STAFF SPONSOR: HENRY HASH ORIGINAL AGENDA DATE: 03/04/19
AGENDA ITEM TITLE 2018
Project
Overlay & Repair Program
Completion and Acceptance
' CATEGORY ❑ Discussion
Mtg Date
Motion
Date 03/04/19
❑ Resolution
Mtg Date
❑ Ordinance
Mtg Date
❑ Bid Award
Mtg Date
❑ Public Hearing
Mtg Date
❑ Other
Mtg Date
/1
Mtg
SPONSOR ❑Council ❑Mayor HR ❑DCD Finance Fire TS P&R Police ►1 PIV ❑Court
SPONSORS The contract with ICON Materials is complete for the 2018 Overlay and Repair Program.
SUMMARY This project included asphalt paving at three locations throughout the City, including
Southcenter Blvd and a portion of the parking lot at Fort Dent Park. Construction began
May 18, 2018 and was physically completed on July 20, 2018. Underruns show a credit of
($59,112.09). Council is being asked to accept and finalize the contract with ICON
Materials for $896,833.41.
REVIEWED BY
❑ C.O.W.
Mtg. ❑ CDN Comm ❑ Finance Comm. ❑ Public Safety Comm.
❑ Arts Comm. ❑ Parks Comm. ❑ Planning Comm.
20/ 19 COMMI FI EE CHAIR: ZAK IDAN
►1 Trans &Infrastructure
DATE: 02/
RECOMMENDATIONS:
SPONSOR/ADMIN.
COMMITTEE
Public Works Department
Approval; Forward to Consent Agenda
Unanimous
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$896,833.41 $1,003,742.78 $
Fund Source: 104 ARTERIAL STREETS (PAGE 16, 2019 CIP)
Comments:
MTG. DATE 1
RECORD OF COUNCIL ACTION
03/04/19
MTG. DATE
ATTACHMENTS
03/04/19
Informational Memorandum dated 02/15/19
Notice of Completion Contract No. 18-071
Minutes from the Transportation and Infrastructure Committee 02/20/19
1
2
City of Tukwila
Allan Ekberg, Mayor
Public Works Deportment Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Henry Hash, Public Works Director
BY: Scott Bates, Traffic Engineering Coordinator
CC: Mayor Ekberg
DATE: February 15, 2019
SUBJECT: 2018 Overlay and Repair Program
Project No. 91810401, Contract No. 18-071
Project Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of performance bond.
BACKGROUND
The Notice to Proceed for Contract No. 18-071 with ICON Materials, Inc. of Pacific, Washington was
issued on May 18, 2018 for the 2018 Overlay and Repair Project. This overlay project provided hot mix
asphalt (HMA) paving at three locations throughout the City and a portion of the parking lot at Fort Dent
Park. The street improvements included: pavement grinding; asphalt paving; removing and replacing
concrete curbs, gutters, sidewalks and ADA ramps; adjusting surface utilities to grade; and installing
roadway channelization.
ANALYSIS
Construction was physically completed on July 20, 2018. No change orders were executed. The
performance bond is held by the City. The budget for the 2018 Overlay & Repair construction was
$1,003,742.78 and included a 5% contingency, which was not utilized. Under -runs were primarily due
to fewer quantities needed during the unsuitable roadway excavation, haul and repair phase of the
project.
Construction Contract Amount
Under -runs
Total Amount Paid
$ 955,945.50
(59,112.09)
$ 896,833.41
RECOMMENDATION
Council is being asked to formally accept and authorize the release of the performance bond, subject to
standard claim and lien release procedures, for the 2018 Overlay and Repair Project with ICON Materials,
in the final amount of $896,833.41 and consider this item on the Consent Agenda at the March 4, 2019
Regular Meeting.
ATTACHMENT
Notice of Completion Contract No. 18-071
W:IPW EngIPROJECTS A- RW & RS ProjectslAnnual Overlay & Repair Programsl2018 Overlay & Repair Program (91810401 )\ConstructionlConlractor\Close Out to TICIInfo memo 2018 Overlay Closeout 120718 gl docx
3
4
Date: 10-9-2018
g Original
❑ Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Contractor's UBI Number: 601 006 854
Name & Mailing Address of Public Agency
City of Tukwila
6200 Southcenter Blvd Tukwila, WA 98188
UBI Number: 91-6001519
Department Use Only
Assigned to:
Date Assigned:
hereby given relative to the complet'on of contract or project described below
Project Name a
2018 Annual Overlay Program 91810401 118-071
Contract Number
Job Order Contracting
❑ Yes 'No
Description of Work Done/Include Jobsite Address(es)
Hot Mix Asphalt (HMA) Overlay at the following locations: Southcenter Blvd, 58th Ave S, S.133rd St and
Ft dent park.
Federally funded transportation project? ❑ Yes g No (if yes, provide Contract Bond Statement below) _
Contractor's Name
ICON Materials
E-mail Address
(mark.eichelberger@iconmate j1833761
Affidavit ID*
Contractor Address
1508 Valentine Ave SE Pacific, WA 98047
Te ephone #
I206-575-3200
If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number.
gRetainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects)
Name: Fidelity and deposit Company of MarylandBond Number: 9283910
Date Contract Awarded
5-11-2018
Date Work Commenced
5-18-2018
Date Work Completed
I7-20-2018
Date Work Accepted
Were Subcontracters used on this project? If so, please complete Addendum A. (1Yes ❑ No
Affidavit ID* - No L&I release will be granted until all affidavits are listed.
Contract Amount
Additions (+ )
Reductions (- )
$ 955,945.50
$ 59,112.09
Sub -Total $ 896,833.41
Sales Tax Rate n/a rule 171 %
(If various rates apply, please send a breakdown)
Sales Tax Amount $
TOTAL $ RAF 833.41
NOTE: These two totals must be equal
Liquidated Damages $ 0.00
Amount Disbursed $ 896,833.41
Amount Retained $ 0.00
TOTAL $ 896,833.41
Comments:
Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber
Email Address: Diane.jaber@tukwilawa.gov
(f4
Department of Revenue
Public Works Section
(360) 704-5650
PWC@dor.wa.gov
0 W:uhington State Department of
Labor & Industries
Contract Release
(855) 545-8163, option # 4
ContractRelease@LNI.WA GOV
Title: Fiscal Specialist
Phone Number: 206-433-1871
Employment Security
Department
Registration, Inquiry,
Standards & Coordination
Unit
(360) 902-9450
publicworks@esd.wa.gov
REV 31 0020e (10/26/15) F215-038-000 10-2014
5
Addendum A: Please List all Subcontractors and Sub -tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name: _
UBI Number: (Required)
Affidavit ID*
Able Industries
603542604
832343
Northwest traffic
602140049
815657
Cascade
603407046
821822
Bilbrey Construction
603002155
818138
O'Bunco
602045762
821890
SeaTac sweeping
601735583
819687
Northwest concrete cutting
603572428
811339
G&G Electrical
601381635
823096
Ground up Road Construction
602790246
830219
Acme Construction
602170211
830917
0-Co Concrete
603560682
818171
Construction Testing Laboratories
601580376
,r, /c
For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the
Washington Relay Service by calling 711.
REV 31 0020e Addendum (10/26/15) F215-038-000 10-2014
6
City of Tukwila
City Council Transportation & Infrastructure Committee
TRANSPORTATION & INFRASTRUCTURE COMMITTEE
Meeting Minutes
February 20, 2019 - 5:30 p.m. - Hazelnut Conference Room, City Hall
Councilmembers: Zak Idan, Chair; Kate Kruller, Thomas McLeod
Staff: David Cline, Henry Hash, Hari Ponnekanti, Ryan Larson, Susan Murrietta, Lynn
Miranda, Steve Carstens, Scott Bates, Laurel Humphrey
CALL TO ORDER: Committee Chair Idan called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. CONSENT AGENDA
Committee members discussed the new Consent Agenda format, intended to improve meeting
efficiency. Councilmember McLeod had questions about both items listed and requested they be
pulled from Consent and handled individually.
A. Project Completion - 2018 Overlay and Repair Program
Staff is seeking Council approval of contract completion and release of retainage to ICON Materials,
Inc. in the amount of $896,833.41 for the 2018 Overlay and Repair Project. This project provided hot
mix asphalt paving at three locations in the City and a portion of the Fort Dent Park parking lot. Under -
runs were primarily due to fewer quantities needed during the excavation, haul and repair phase of
the project. UNANIMOUS APPROVAL. FORWARD TO MARCH 4, 2019 REGULAR CONSENT AGENDA.
B. Grant Application: 42' Avenue South/Allentown Bridge Replacement
Staff is seeking Committee approval to submit an application for Federal Highway Bridge Grant
Program funding to replace the 42nd Avenue South Bridge over the Duwamish River. The bridge is
structurally deficient and replacement is preliminarily estimated at $15-20 million. The Committee
asked if staff will approach BNSF as a funding partner, as their heavy truck traffic contributes to
wear on the bridge. Staff said BNSF is aware the bridge is at the end of its life but that they do not
have a mechanism for funding of a public project. Councilmember Kruller suggested a bridge toll.
Committee members again discussed the need for an update on the BNSF preferred alternative
study, which is on the 2019 Committee work plan. UNANIMOUS APPROVAL.
III. BUSINESS AGENDA
A. 2019 Small Drainage Program Proposed Project List
Staff presented the proposed 2019 Small Drainage Project list to the Committee. These projects
are too large for City staff but smaller than a typical capital improvement projects, and typically
originate from resident complaints and maintenance staff recommendations. Staff prioritizes
projects based on need, expense, permitting requirements, and length of time on the list. Staff
intends to construct Priority 1 or 2 projects in 2019, but if design or permitting issues arise then
lower priority projects will be considered with the available budget. Committee members
discussed the importance of neighborhood equity within the list. Residents may perceive their
neighborhood does not receive capital investments which may not be the case. The Committee
7