HomeMy WebLinkAboutPS 2019-03-18 Item 2A / 2B - Powerpoint Presentation - Justice Center and Fire Station 51 Mini-MACC and MACC Council ConsiderationJustice Center and
Fire Station 51
Mini-MACC and MACC Council Consideration
Bottom Line
• Both projects are on schedule
• Market conditions continue to be an issue; Sound Transit and WSDOT
alone currently working on $5.6+ Billion on current projects
• Justice Center mini-MACC under budget; many large bid packages
remain
• Fire Station 51 over budget
• The City has opportunities to address the overage at Fire Station 51
• The Administration recommends achieving the Fire Station 51 budget
delta with Justice Center savings, as well as funding key alternates
GCCM Process
• City had an RFP process for GCCM services for Fire Stations and
Justice Center
• GCCM joins the process early to inform team on cost impacts
associated with design
• Once design is complete, GCCM creates specific bid packages for
competitive bidding, per state law
• GCCM promotes bid packages to encourage a high number of bidders
• Bid packages opened at a specific time; lowest responsive bidder
must be chosen
Justice Center Mini-MACC
• Presenting the "mini-MACC" today, which includes:
• Demolition and abatement
• Foundations, structure and waterproofing
• Earthwork and utilities
• Allowance for shoring
• Allowance for contaminated groundwater
• Allowance for shop drawings and engineering for elevator, fire protection,
mechanical and electrical
• Formula -driven fees associated with the GCCM contract for negotiated
support services, MACC contingency, GCCM fee and Specified General
Conditions
City of Tukwila
Justice Center Mini-MACC PUBLIC SAFETY PLAN
Demolition & Abatement
Foundation/Structure/Waterproofing
Earthwork and Utilities
Allowance — shoring
Allowance — contaminated groundwater
Allowance - Shop drawings and engineering
Negotiated Support Services
MACC Contingency (2.5%)
GCCM Fee (5%)
Specified General Conditions
w Total Mini-MACC Contract
$910,582
$4,301,047
$5,057,079
$192,995
$4,288,300
$4,874,410
$50,000
$20,000
$250,000
$221,283
$241,893
$506,944
$248,633
$10,984,458
($717,587)
($12,747)
($182,669)
($843,003)
oUPDATED
City of Tuk
Justice Center M I n I - M A C C P Bpi
J sice Center
Contract total
Washington State Sales Tax
Total mini-MACC
Mini-MACC under budget by:
Soft cost savings due to savings above:
Land acquisition under budget by:
Total under budget to date:
$10,894,458
$1,089,446
$11,983,903
$843,003
$147,525
$341,809
$1,332,337
Remaining Services
to be Bid
City of Tuk is
Architectural casework
Exterior siding
Mechanical
Electrical
Insulation/GWB Assemblies
Miscellaneous specialties and equipment
Irrigation and landscaping
TOTAL Bid packages remaining (does not include formula -driven fees)
$18,940,632
Justice Center Budget
City of Tuk
LI
A/E Services
Permits/Fees
Construction, including sales tax
Construction related costs
PM Services, including other professional services
Contingency, including construction and project
Contingency for potential contamination
Land Acquisition
Contingency for land acquisition
TOTAL
$3,500,000
S700.000
$38,727,363
$2,282,639
$2,112,596
$4,861,492
$750,000
$14,052,253
$1,550,000
$68,536,343
$3,141,729
S111.317
$563,671
$562,398
$1,967,303
$13,679,370
$898,962
$20,953,976
$358,271
S588.683
$38,163,692
$1,720,241
$145,293
$4,861,492
$750,000
$343,657
$651,038
$47,582,367
Fire Station 51 MACC
• MACC includes all of the construction costs
• MACC includes $312,015 in priority alternates
• As discussed previously, the project requires an additional $200,000
outside of the contract to address an unforeseen issue with electricity
due to PSE's inadequate as-builts
• With tax, electrical allowance, MACC and priority alternates, Fire
Station 51 is over budget by $1,541,632
• Market conditions exacerbated by relatively small budget
UPDATED
Fire Station MACC
Earthwork/Utilities/Asphalt
Site Concrete
Concrete and Steel Structure, and Enclosure
City of Tukwila
LI
$661,444 $753,900 $92,456
$287,922 $391,500 $103,578
$1,799,575 $1,798,890 ($685)
Masonry
Glazing Package
GWB, Metal Framing and Insulation/Acoustical Ceiling
$253,878 $310,097 $56,219
$276,415 $298,628 $22,213
$467,883 $523,500 $55,617
Miscellaneous Package
Tile, Resilient Flooring and Traffic Coatings
$706,056 $704,500 ($1,556)
$35,436 $38,500 $3,064
Fencing and Gate Enclosures
$172,553
$299,000 $126,447
Landscaping and Irrigation
Electrical Contractor
Mechanical
Formula -driven costs
$237,778 $262,451 $24,673
$1,026,413 $1,235,963 $200,106
$1,398,430 $1,455,361 $56,931
$1,382,509
Value Engineering List
($179,500)
Alternates
$312,015
Total
$9,587,314 $1,116,514
Fire Station 51 Budget
City of Tuk
LI
A/E Services
Permits/Fees
Construction, including sales tax
Construction related costs
PM Services, including other professional services
Contingency, including construction and project
Land Acquisition
TOTAL
$1,292,781
S234.000
$9,396,000
$931,000
$526,000
$893,219
$1,236,572
S44.557
$165,000
$163,241
$344,681
$13,273,000 $1,954,050
$56,209
S189.443
$9,231,000
$767,759
$181,319
$893,219
$1
1,318,950
UPDATED
Fire Station 51 Alternates City of Tuk
P B I I
Fire hydrant in NE corner of rear apron
Additional paving for trailer parking
Four -fold doors
Fume hood for the shop
Rough in for new SCBA gear washer
Underground utilities for fueling station
Remainder of fueling station
Total alternates:
$190,000
$60,642
$84,228
$8,434
$25,128
$180,648
$621,970 (this cost
includes the $180,648 above)
$990,402
$83,200
$51,350
$81,565
$18,121
$4,438
$142,812
$333,209
$714,695
NEW
Fire Station 51 Alternates
Administration and
City of Tuk
LI
Fire Department Recommendations
Fire hydrant in NE corner of rear apron $83,200
Four -fold doors $81,565
Rough in for new SCBA gear washer $4,438
Underground utilities for fueling $142,812
station
$83,200
$164,765
$169,203
$312,015
In addition, there is consensus among the project team that if there are an additional
contingency funds available toward the end of the project, the first priority should be to add
back the additional paving for trailer parking alternate at $51,350.
Fire Station 51
Funding Options
• Use contingency funds from Fire Station 51
• Use savings from Justice Center mini-MACC and a transfer from the
project's contaminated soils budget
• Use the Council's contingency fund generated from 10% set aside of
one-time funds
• Use General Fund ending fund balance
Other Considerations
• Fire Station 52 includes $750,000 alternate to build out the
Administration space
• Fire Station 52 likely to experience a premium similar to Fire Station
51
• Justice Center full MACC will be done this spring; remaining bids not
likely to see much savings
• Public Works master plan will be done in May
• Currently $3M in construction budget (including tax) to retrofit Heiser
building; unknown at this time what budget will be needed
Recommendation
• Proceed with the mini-MACC for the Justice Center, which is under budget.
• The Administration recommends utilizing the $1,332,337 savings from the
Justice Center and a $200,000 from the Justice Center's contaminated soils
budget to achieve Fire Station 51's budget delta.
• The project team does not believe that there are any additional value
engineering targets on Fire Station 51 that would not affect the
functionality of the building or the firefighters who work there.
• The four alternates previously discussed totaling $312,015 are important
and should be moved into the base budget.
• The Council's Project Management Quality Assurance consultant agrees
with these recommendations.
Justice Center
Council Consideration:
• The Council is being asked to provide the mayor the authority to:
• Sign a contract with BNBuilders for $10,894,458 for initial
construction of the Justice Center.
• Spend $1,089,446 in sales tax associated with the contract above.
• If needed, approve the use of the proportional amount of the
project's contingency fee, budgeted at 10% of the total
construction cost, or up to $1,089,446.
Fire Station 51
Council Consideration:
• The Council is being asked to provide the mayor the authority to:
• Move $1,541,632 from the Justice Center budget to cover the
additional costs due to market conditions and the four priority
alternates.
• Sign a contract with Lydig Construction for $9,587,314 for the Fire
Station MACC.
• Spend $968,318 in sales tax associated with the contract above.
• If needed, approve the use of the contingency budget of $893,219.
Council Review and Actior City ofTUk
ARCH APRIL 1 MAY
Fire Station #52
us ice Center
Public Works
Facility
UNE DULY
AUGUST
SEPTEMBER OCTOBER NOVEMBER
Taraet dates