HomeMy WebLinkAboutTIC 2019-04-16 Item 2B - Final Acceptance - CBD Sanitary Sewer Rehabilitation - 2018 Construction with Michels CorporationAllan Ekberg, Mayor Public Works Deportment - Henry Hash, Director INFOR ATIONAL EMORANDU TO: Transportation & Infrastructure Committee FROM: Henry Hash, Public Works Director /14/- BY: Michael Ronda, PW Project Manager CC: Mayor Ekberg DATE: April 12, 2019 SUBJECT: CBD Sanitary Sewer Rehabilitation — 2018 Construction Project No. 91140203, Contract No. 18-040 Project Completion and Acceptance ISSUE Accept the construction contract as complete and authorize release of retainage. BACKGROUND The Notice to Proceed for Contract No. 18-040 with Michels Corporation of Salem, Oregon was issued on April 30, 2018, for the 2018 CBD Sanitary Sewer Rehabilitation Project. This construction project installed approximately 3,660 lineal feet of cured -in -place pipe within the right-of-way of Andover Park West, Tukwila Parkway, Baker Boulevard and private easements in order to rehabilitate existing sewer pipes. DISCUSSION Construction was physically completed on January 15, 2019. The extended time for the contract was due to a short section of failed liner that had to be removed and replaced. Two change orders were executed during the project and several sections of sewer pipe lining were deleted from the contract. FINANCIAL IMPACT The construction budget for the 2018 CBD Sewer Rehabilitation Project was $539,559.90, with a 20% contingency of $89,926.65, which was not used. Underruns were mainly due to work deleted from the contract due to various conflicts that would not allow the relining to be performed at this time. Retainage of $18,702.74 is currently being held. Construction Contract Amount (w/tax) Change Order Nos. 1 & 2 Contract Under -runs Total Contract Amount Expenses $449,633.25 7,393.09 ($45,566.07) $411,460.27 RECOMMENDATION Council is being asked to formally accept the 2018 CBD Sanitary Sewer Rehabilitation Project with Michels Corporation in the amount of $411,460.27 as complete, and authorize the release of the retainage, subject to standard claim and lien release procedures, and consider this item on the Consent Agenda at the May 6, 2019 Regular Council Meeting. ATTACHMENT Notice of Completion, Contract #18-040 W:\PW Eng PROJECTS \A- SW Projects CBD Sewer Rehab (91140203)12018 CBD Sewer -Relining Construction 1#.700 - Post Construction & CloseoutlInfo Memo - 2018 CBD Sewer Rehab Final Acceptance - 05-06-2019.doc 5 i Original —1 Revised # NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT Date: 4/3/19 Contractor's UBI Number: 601061071 Name & Mailing Address of Public Agency City of Tukwila 6200 Southcenter Boulevard. Tukwila. WA 98188 UBI Number: 179 000 208 Department Use Only Assigned to: Date Assigned: Notice is hereby given relative to the completion of contract or project described below Project Name CBD Sewer Rehab - 2018 Construction 91140203 Contract Number 18-040 Job Order Contracting H Yes d No Description of Work Done/Include Jobsite Address(es) Install CIPP liners in several sections of sewer main within the Tukwila Urban Core. Federally funded transportation project? I— Yes No (if yes, provide Contract Bond Statement below) Contractor's Name Michels Corporation E-mail Address dphelps@michels.us Affidavit ID* 840882 Contractor Address 1715 16th Street SE, Salem OR, 97302 Te 920-583-3132 ephone # If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number. n Retainage Bond Contract/Payment bond (valid for federally funded transportation projects) Name: Continental Casualty Company & Liberty Mutual Insurance Bond Number: 30035085/190039223 Date Contract Awarded 3/5/2018 Date Work Commenced 4/30/2018 Date Work Completed 1/15/2019 Date Work Accepted Were Subcontracters used on this project? If so, please complete Addendum A. EYes n No Affidavit ID* - No L&I release will be granted until all affidavits are listed. Contract Amount Additions (+ ) Reductions (- ) Sub -Total Amount of Sales Tax 10.0 (If various rates apply, please send a breakdown) TOTAL $ 449,633.25 $ 7,107.32 $ 82,685.78 $ 374,054.79 37405.48 $ 411,460.27 Liquidated Damages $ 0.00 Amount Disbursed $ 392,757.53 Amount Retained $ 18,702.74 NOTE: These two totals must be equal TOTAL $ 411,460.27 Comments: Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract. NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates. Submitting Form: Please submit the completed form by email to all three agencies below. Contact Name: Diane Jaber Email Address: Diane.Jaber@tukwilawa.gov ,./PaDepartment of Revenue Public Works Section (360) 704-5650 PWC@dor.wa.gov 0 Washington State Department of Labor & Industries Contract Release (855) 545-8163, option # 4 ContractRelease@ LN I. WA.GOV Title: Fiscal Specialist Phone Number: (206) 433-1871 x 1871 Employment Security Department Registration, Inquiry, Standards & Coordination Unit (360) 902-9450 publicworks@esd.wa.gov REV 31 0020e (4/28/14) F215-038-000 04-2014, Reset This Form Print This Form 6 Addendum A: Please List all Subcontractors and Sub -tiers Below This addendum can be submitted in other formats. Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed. Subcontractor's Name: UBI Number: (Required) Affidavid ID* Traffic Control Services 601477384 842513 For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the Washington Relay Service by calling 711. REV 31 0020e Addendum (04/28/14) F215-038-000 04-2014 7