HomeMy WebLinkAboutTIC 2019-05-07 Item 2C - Contract Amendment #6 - 53rd Avenue South Construction Management with KPG IncCity of Tukwila Public Works Department - Henry Hash, Director INFORMATIONAL MEMORANDUM TO: Transportation and Infrastructure Committee FROM: Henry Hash, Public Works Director r' r/- BY: Peter Lau, Senior Program Manager CC: Mayor Allan Ekberg DATE: May 3, 2019 SUBJECT: 53rd Avenue South Project (South 137th Street to South 144th Street) Project No. 99110301, Contract No. 15-159 Construction Management Amendment No. 6 with KPG, Inc. ISSUE Approve Amendment No. 6 to Consultant Contract No. 15-159 with KPG, Inc. Allan Ekberg, Mayor BACKGROUND Contract No. 15-159 with KPG provided design and construction management (CM) services for the 53rd Ave S Project. DISCUSSION KPG's Amendment No. 6 will allow the continuation of construction engineering, inspection, and documentation compliance support for the full completion of the 53rd Ave S Project. The construction project is currently anticipated to be completed by June 2019. However, the progress of the utility conversion work will dictate when construction will actually be physically completed. If the slow progress of the utility conversion prohibits the contractor from efficiently completing the construction project, construction will be suspended until the utility conversion work is completed. FISCAL IMPACT The table below shows the project budget and expenditures, with the inclusion of KPG's Amendment No. 6: KPG's fee of $259,770.00 is reasonable for the scope of work provided to complete this challenging project. Design CM Construction Budget Design & ROW (up to Am No. 3) $809,382 $832,000 KPG CM Amendment Nos. 4 & 5 $858,842 870,000 KPG CM Amendment No. 6 259,770 City CM Staff (estimated total) 100,000 SCI Construction Contract w/ sales tax 5,953,250 7,548,000 SCI Change Orders No. 1 to 5 w sales tax 632,017 Construction Contingency 350,000 Total $809,382 $1,218,612 $6,935 267 Grand Total $8.963,261 $9.250.000 The current 2019 CIP project budget is sufficient to cover the cost of KPG's Amendment No. 6 and will leave a construction contingency of $300,000 to cover all future change orders and other additional costs needed to physically complete the 53rd Ave S Project. RECOMMENDATION Council is being asked to approve Amendment No. 6 to Contract No. 15-159 with KPG, Inc. in the amount of $259,770 for a new contract total of $1,774,201.69 for the 53rd Ave S Project and to consider this item on the Consent Agenda at the May 20, 2019 Regular Meeting. Attachments: 2019 CIP, page 3, KPG Amendment No. 6 W:1PW Eng1PROJECTSIA- RW & RS Projects153rd Ave S (99110301)1CN Managementllnfo Memo for KPG Supp #6, gl HH 050319.docx 21 PROJECT: DESCRIPTION: JUSTIFICATION: STATUS: MAINT. IMPACT: COMMENT: CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2019 to 2024 53rd Ave S (S 137th St - S 144th St) Project No. 99110301 Design and construct urban residential street improvements that include curb, gutter, sidewalk, undergrounding, and illumination. Street will coordinate with Water $1.1 m, Sewer $185k, and Surface Water $920k CIP projects. Provide pedestrian and vehicle safety, drainage, and neighborhood revitalization. Undergrounding is included at this time. Reduce pavement, shoulder, and drainage work. State TIB grant for $2.14M for roadway and drainage. See additional pages in Enterprise funds under 53rd Ave S Projects. Seattle City Light is now negotiating a 60/40 underground split and undergrounding costs have been added to project. Bond for $2 million. FINANCIAL (in $000's) Through Estimated 2017 2018 2019 2020 2021 2022 2023 2024 BEYOND TOTAL EXPENSES Design 607 21 628 Land (R/W) 157 47 204 Const. Mgmt. 435 435 870 Construction 3,239 2,050 5,289 Undergrounding 1,379 880 2,259 TOTAL EXPENSES 764 5,121 3,365 0 0 0 0 0 0 9,250 FUND SOURCES Utilities W/S/SWM 259 1,161 1,254 2,674 Awarded TIB Grant 65 1,912 364 2,341 Seattle City Light 729 428 1,157 Bond 2,049 2,049 CityOper. Revenue (1,609) 1,319 1,319 0 0 0 0 0 0 1,029 TOTAL SOURCES 764 5,121 3,365 0 0 0 0 0 0 9,250 Project Location • a, S;2a� w S 30 St \1 v ``` +, ,� ., C o 7. a _ 6 °e �itt; 913D. t 7/7 �/ %/4 0O 31 6 St m I- w oo u S 3 14 39t� 5 � e 47 S , i 1 .4.S S 11 St I 9 . 2019 - 2024 Capital Improvement Program 3 22 City of Tukwila Agreement Number: 6200 Southcenter oulevard, Tukwila WA 98188 CONTRACT FOR SERVICES Amendment #6 Between the City of Tukwila and KPG Inc. That portion of Contract No. 15-159 between the City of Tukwila and KPG Inc. is amended as follows: Article 2, Scope of Services, shall be supplemented with the following: The Consultant agrees to provide construction services in accordance with the scope of work included as Exhibit A-6. Article 4, Payment, shall be modified as follows: Payment for work provided by Consultant shall be made as provided on Exhibit B-6, attached hereto, provided that the total amount of payment to the Consultant for this work not exceed $259, 770.00 without express written modification of the Agreement signed by the City. The new total contract shall not exceed $1,774,201.69 without express written modification of the Agreement signed by the City. All other provisions of the contract shall remain in full force and effect. Dated this CITY OF TUKWILA Allan Ekberg, Mayor day of ATTEST/AUTHENTICATED Christy O'Flaherty, MMC, City Clerk CONTRACTOR 20 Printed Name: Nelson Davis, KPG APPROVED AS TO FORM City Attorney Page 1 of 1 23 EXHIBIT A-6 Supplement 6 Additional Construction Management Services Scope of Work March ���"o2019 City of Tuk,w^U@y Project No. 99110301 TIB Project No.: 8-1-116K012&_1 KPG Project #: 15085 BACKGROUND This work willl provide additional construction management services for the construction contract to complete 53m Avenue S Roadway Improvements /S 144'h' Street to S 137" Street). These additional services are the result of: Additional working days added through approved change orders (43 working days . Anticipated additional working days for force account work and to allow SCL to complete wiring, energization, of underground systemi, and wreckout of aerial system (27 working days estimated). a Weather days (3O.Sapproved todate, estimate 351o1a through physical completion) The original contract duration was Z1Sworking days, beginning onApril 9,J0I8and ending mnFebruary 15,2019. An additional 105 working days are anticipated based on, the change orders and weather days described above, resulting inacompletion date of1u|yI7,3019. This supplement is provided to continue construction management and inspection services in accordance with the original authorization and as detailed below: N. INTRODUCTION The following scope of services and associated costs are based upon the assumptions outlined below. General Assumptions: The proposed project team for additional working days vviU| include one part-time project manager, one part-time resident engineer, mnepart'tirnedocummentathonoontrolspedaUst,ome full-time inspector, additional part-time inspector for certain work elements, design team, management, and administrative support as required, sub -consultants to provide services for materials testing, and other supporting tasks ssdeemed necessary. |1isanticipated that fuN-tinne site observation will berequired for the entire duration ofconstruction. City 4/Tukwila S3mAve 5 Additional Construction Management 5emice 5copeoƒWork —Jupp6ymeot6 Page I of 4 KPG Project #15085 March 2019 24 EXHIBIT A-6 The level of service is based on additional project duration of up to 105 working days per the assumptions in the Background section of this scope of work. KPG field staff will continue to perform day to day public outreach to ensure affected residents are notified in advance of impending contractor activities. The design engineers from KPG will be available during construction to answer questions during construction and review RAMs, shop drawings, and answer RFIs. The engineer of record will be available to provide background information on the design should it be necessary. Services will be performed in accordance with the Contract plans & special provisions, WSDOT Local Agency Guidelines ("LAG"), the WSDOT Construction Manual, and the client engineering standards. The franchise utilities will provide field inspection for all work surrounding the construction or relocation of their utility systems not constructed by the Client's Contractor, if necessary. Client/Field Office: The Contractor will provide a field office as required by the contract documents. The Consultant's field staff shall have access to the field office. HI. SCOPE OF WORK The objective and purpose of this Construction Management Services Agreement is for the Consultant to successfully deliver the construction of the Project to the client by ensuring that the improvements are constructed in accordance with the approved Plans and Specifications, as may be amended or revised, that all of the required Project documentation is accounted for, and ultimately that the client receives a successful review by TIB at the end of the Project. TASK 1— MANAGEMENT/COORDINATION/ADMINISTRATION No additional funds are requested for this task. We have been able to mitigate the longer contract duration and can continue to provide the services described in the original scope of work within the previously authorized budget. TASK 2 DESIGN SUPPORT No additional funds are requested for this task. We have been able to mitigate the longer contract duration and can continue to provide the services described in the original scope of work within the previously authorized budget. TASK 3 — PRECONSTRUCTION SERVICES Work is complete, no additional funds are requested for this task. City of Tukwila 53rd Ave S Additional Construction Management Services Scope of Work — Supplement 6 Page 2 of 4 KPG Project #15085 March 2019 25 TASK 4 — CONSTRUCTION OBSERVATION Construction Observation services will continue in accordance with the originalscopemfmnork. Additkonal| observation time is required to achiieve physical com,pletion due to longer contract duration: 4.5The Consultant shall provide the services of one full-time inspector with necessary engineering, and administrative support for on additional 105 xvnddng days as described in the Background section of this scope ofwork,Part-time inspection is anticipated for certain, remaining work elements, The budget is based on 40 hours/week full-time inspection and 20 hours/week part- timeinspecdonforupto105vvorking days associated with change order and weather days, Deliverables wDaily Construction Reports with project photos—subnmittedomavveeWybasis * Punch List, Certificate mf Substantial Completion m Review test reports for cornp|iamce TASK 5—CONSTRUCTION SERVICES —OFFICE Construction Office services will continue in accorda!mce with the original scope of work. Additional time is required to achiieve physical completion due to longer contract durat�ion: 5.27The Consultant shall provide the services of one part-time resident engineer and one part-time documentation specialist with necessary oversight, engineering, and administrative support for an additional lOS working days as described in the Background section ofthis scope of work. The budget is based on 16 hours/week part-time resident engineer and JU hours/week part-time documentation specialist. Defiuerobles * Submittal log • RF|Log * Completed Record ofMaterial for Material Certification • Change {}rder(s) • Change Management Log *RFILog wMinor ChangeOrder(s) m Force Account Records m Recorddravvings in electronic and hard copy format TASK 6—SURVEY @&MATERIAL TESTNIG No additional funds are requested for this task. We have been able to mitigate the longer contract duration a:nd can continue to provide the services described in the od 'ma�| scope of work within the previously authorized budget. City ofTukwila S311 Ave Additional Construction Management Services Scope qfWork — Supplement 6 Page 3 of 4 KPG Project #15085 26 EXHIBIT A-6 TASK 7-ADDITIONAL SERVICES Additional services requested by the client, will be performed only when authorized by the client. Authorization, toperform additional services will beinwriting, specifying the work to beperformed, and basis of payment. Items such as Community Outreach (except as com:pleted on a day to day basis by the inspector and resident engineer as described herein), Public Meetings, Ribbon Cutting Ceremony, claims analysis, additional surveying, services during shutdown periods of non -working days, and services for extended working days are examples of possible additional services, This fee is based on 340 working days (two weeks prior toconstruction, 21Sworking day contract, 1O5additional d'aymper this supplement, and two weeks for closeout, 8 hour days), additional extension of days will be approximately $3,000 per day., City ofTukwila f3mAve f Additional Construction Management Services Scope 4fWork — Supplement 6 Page 4 of 4 KPG Project #15085 March 2019 27 HOU AND FEE ESTIMATE Project: City of Tukwila 53rd Ave S Supplement No. 6 EXHIBIT B-6 TIB No. 8.1-116(012)-1 Tukwila # 99110301 KPG No. 15085 Additional Construction Management Services interdisciplinary Design Task PAIIIMPAPPAPP. Description Project Manager $ 166.00 Project Engineer 140,00 Resident Engineer 125 00 Senior nspector 128.00 Con inspector 92 00 Cons Technician 77.00 Doc Control Admin 77.00 enior Admin 115.00 Budget Task 1 - Management/Coordination/Administration No Additional Budget Required Reimbursable expenses - no additionalre Task Totals 41111111111111111111111111114 Task 2 - Design Support duringConstruction No Additional Budget Required Reimbursable expenses - no additional required 0ired Task Total 0 0 0 0 0 -Preconstructton Servtces No Additional Budget Required 0 0 0 0 0 0 Reimbursable expenses - no additional re Task Total 0 uired 0 0 0 Task 4 - Construction Observation 4,5 Construction observation (addl 90 days) Reimbursable expenses - no additional rec Task Total Task 5 - Construction Services - Office 5.27 Construction office services (addi 90 days) Reimbursable expenses - no additional re Task Total Task 6 - Survey & Material Testing No Additional Budget Required 2 uired uired Reimbursable ex enses - no additional re uired Task Total Total Hours 21 105 42 42 42 42 42 42 336 336 0 0 378 840 840 0 0 0 840 420 420 0 0 420 0 0 0 0 0 0 420 42 $ 160 776 $ 160,776 Total Budget: $ 259,770 City of Tukwila 53rd Ave 5 Additional Construction Management Services Budget Estimate - Supplement 6 Page 1 of 1 KPG Project 15085 March 2019 28