ITEM INFORMATION
ITEM NO.
4 . D .
STAFF SPONSOR: HENRY HASH
ORIGINAL AGENDA DATE: 05/06/19
AGENDA I1INI TITLE Andover Park East - Water & Sewer Replacement Project
Project Completion and Acceptance
CATEGORY • Discussion
Motion
05/06/19
[1] Resolution
Mtg Date
El Ordinance
illtg Dale
111 Bid Award
Mtg Date
El Public Hearing
Ails Date
Other
Mtg Date
Mt_gDate
AltsDate
SPONSOR Council flMayor •HR EDCD EFinance Fire NITS
Pe-R Police ZP IF Court
SPONSOR'S The contract with Titan Earthwork, LLC of Pacific WA is complete for the Andover Park East
SummARy Water and Sewer Replacement Project. This project provided new and upgraded water and
sewer lines on Andover Park East between Strander Boulevard and Tukwila Parkway.
Construction began September 26, 2016 and was physically completed on March 15, 2018.
Council is being asked to accept and finalize the contract with Titan Earthworks for
$3,887,443.57.
REVIEWED BY
El C.O.W.
Mtg. J CDN Comm [1] Finance Comm.
Arts Comm. 111 Parks Comm.
COMMITTEE CHAIR: ZAK
0 Public Safety Comm.
I Trans &Infrastructure
U Planning Comm.
DATE: 04/16/19
IDAN
RECOMMENDATIONS:
SPoNsoR/ADmIN.
CommITIEE
Public Works Department
Unanimous Approval; Forward to Consent Agenda
COST IMPACT / FUND SOURCE
EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED
$3,887,443.57 $4,556,089.38 $0.00
Fund Source: 401 & 402 WATER & SEWER (PAGES 66 & 84, 2017 CIP)
Comments:
MTG. DATE
RECORD OF COUNCIL ACTION
05/06/19
MTG. DATE
ATTACHMENTS
05/06/19
Informational Memorandum dated 04/12/19
Notice of Completion Contract No. 16-111
Minutes from the Transportation and Infrastructure Committee 04/16/19
13
14
ity of Tu
Public Works Department - Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation & Infrastructure Committee
FROM: Henry Hash, Public Works Director -
BY: Michael Ronda, PW Project Manager
CC: Mayor Ekberg
DATE: April 12, 2019
SUBJECT: Andover Park East - Water and Sewer Replacement
Project No. 99940103 & 91440204, Contract No. 16-111
Project Completion and Acceptance
Allan Ekberg, Mayor
ISSUE
Accept contract as complete and authorize release of retainage and performance bonds.
BACKGROUND
The Notice to Proceed for Contract No. 16-111 with Titan Earthwork LLC, of Pacific Washington,
was issued on September 26, 2016 for the Andover Park East (APE) Water and Sewer
Replacement Project. This project provided new and upgraded water and sewer lines on APE
between Strander Boulevard and Tukwila Parkway, in support of future development in the CBD.
The project also provided new pavement and select roadway improvements.
DISCUSSION
Construction was physically completed on March 15, 2018. Thirteen change orders were executed.
The major changes consisted of impacts to the new sewer line due to unforeseen subsurface
conditions in Strander Blvd and along the frontage of Hotel Interurban, as well as increased curb,
gutter and sidewalk revisions throughout the project boundary. After extended negotiations, a final
settlement change order was processed for $200,000, which was significantly less than what the
contractor had initially submitted.
FINANCIAL IMPACT
The construction budget for the APE Water and Sewer Replacement Project was $4,556,089.38
which included a 30% contingency of $1,051,405.24, mainly due to the high -risk nature of the
work (mostly deep utilities). Underruns were due to savings in unit price items that were included in
change orders and the elimination of the use of concrete sleds that were envisioned for extremely
unsuitable foundation conditions. The contractor obtained a retainage bond.
Expenses
Construction Contract $3,504,684.14
Change Order Total 662,031.88
Net Under -runs (279,272.45)
Total Contract Amount $3,887,443.57
RECOMMENDATION
Council is being asked to formally accept the Andover Park East Water and Sewer
Replacement Project with Titan Earthwork LLC, in the amount of $3,887,443.56 as complete
and authorize the release of the retainage and performance bond, subject to standard claim and
lien release procedures, and consider this item on the Consent Agenda at the May 6, 2019
Regular Council Meeting.
ATTACHMENT
Notice of Completion, Contract #16-111
W:1PW Eng1PROJECTSIA- WT Projects'APE Water Main Replacement (99940103)1Construction14.400 - ProjectTracking1005 - Milestone Docs1(025) - Notices of Completionllnfo Memo APE Final Acceptance - 04-
16-2019.dac
15
16
❑ Original
❑ Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Date: 3/19/19 Contractor's UBI Number: 602605763
Name & Mailing Address of Public Agency
City of Tukwila
6200 Southcenter Boulevard,
Tukwila, WA 98188
UBI Number: 179 000 208
Department Use Only
Assigned to:
Date Assigned:
Notice is hereby riven relative to the corn pie! on of contract or project described below
Project Name
Andover Park East Water & Sewer Replacement 99940103
Contract Number
16-111
Job Order Contracting
❑ Yes VNo
Description of Work Done/Include Jobsite Address(es)
Water and sewer line replacement and upgrade along Andover Park East between Strander Blvd and
Tukwila Parkway.
Federally funded transportation project? ❑ Yes Qf No (if yes, provide Contract Bond Statement below)
Contractor's Name
TITAN Earthworks LLC
E-mail Address
info@Titanearth.com
Affidavit ID*
809250
Contractor Address
1585 Valentine Ave SE
Te
206-325-3004
ephone #
If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number.
VRetainage Bond E .f Contract/Payment bond (valid for federally funded transportation projects)
Name: Berkley Insurance Company Bond Number: 0203356/0203354
Date Contract Awarded
August 1, 2016
Date Work Commenced
September26, 2016
Date Work Completed
March 15, 2018
Date Work Accepted
Were Subcontracters used on this project? If so, please complete Addendum A. [Yes ❑ No
Affidavit ID* - No L&I release will be granted until all affidavits are listed.
Contract Amount
Additions (+ )
Reductions (- )
Sub -Total
Amount of Sales Tax
(If various rates apply, please send a breakdown)
TOTAL
$ 3,504,684.14
$ 602,701.52
$ 464,782.86
$ 3,642,602,80
244840.77
$ 3,887,443.57
Liquidated Damages $ 0.00
Amount Disbursed $ 3,887,443.57
Amount Retained $ 0.00
NOTE: These two totals must be e
9
ual
TOTAL $ 3,887,443.57
Comments:
The tax rate changed in the middle of the project so 9.5% tax was applied to payments made before the
tax change on 4/1/17 and 10% was used for all payments after the change. The tax was applied only to
the schedules that were not for Roadway.
Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Diane Jaber
Email Address: diane.jaber@tukwilawa.gov
rfa
Department of Revenue
Public Works Section
(360) 704-5650
PWC@dor.wa.gov
Washington State Department of
Labor & Industries
Contract Release
(855) 545-8163, option # 4
ContractRelease@LNI. WA. GOV
Title: Fiscal Specialist
Phone Number: (206) 433-1871 x1871
Employment Security
Department
Registration, Inquiry,
Standards & Coordination
Unit
(360) 902-9450
publicworks@esdwa.gov
REV 31 0020e (4/28/14) F215-038-000 04-2014
17
Addendum A: Please List all Subcontractors and Sub -tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name:
UBI Nwnber: (Required)
Affidavid ID*
Glacier Drilling and Dewatering
603372976
804806
Penhall Company
601258537
805490
Everson's Econo-Vac Inc
601443326
702208
3D Construction Tech Consultants
601927083
810310
T. Barger Dirtworks, LLC
602812806
804692
C-More Pipe Services (Subtier to Columbia)
601854873
838746
Krazan & Associates
601498409
809678
Thiele Construction
603343720
804797
Icon Materials
601006854
728944
Columbia Pumping
601247586
723682
Olson Brothers Pro Vac (Also Subtier to Columbia)
602170975
752082/726989
Stripe Rite
601048084
805007
Ground Up Road Construction, Inc.
602790246
744229
Highmark Concrete Contractors
603004408
729006
Lakeside Concrete Pumping
601936653
706654
Cascade Utility Adjusting LLC
603407046
812881
Ben's Dozer Services
601432463
804874
Julie's Construction & Striping LLC
603495676
778367
Tony Lind Paving
602813830
728241
Miles Sand & Gravel (Supplier to Highmark)
171004760
729762
For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the
Washington Relay Service by calling 711.
REV 31 0020e Addendum (04/28/14) F215-038-000 04-2014
18
City of Tukwila
City Council Transportation & Infrastructure Committee
TRANSPORTATION & INFRASTRUCTURE COMMITTEE
Meeting Minutes
April 16, 2019 - 5:30 p.m. - Hazelnut Conference Room, City Hall
Councilmembers: Zak Idan, Chair; Thomas McLeod, Kate Kruller (by phone)
Staff: David Cline, Henry Hash, Hari Ponnekanti, Mike Ronda, Laurel Humphrey
CALL TO ORDER: Committee Chair Idan called the meeting to order at 5:30 p.m.
I. PRESENTATIONS
II. BUSINESS AGENDA
A.
Project Completion: Andover Park East - Water and Sewer Replacement
Staff is seeking Council approval of contract completion and release of retainage to Titan
Earthwork LLC in the amount of $3,887,443,56 for the Andover Park East Water and Sewer
Replacement Project. This project provided new and upgraded water and sewer lines on APE
between Strander Boulevard and Tukwila Parkway. Thirteen change orders were executed,
primarily due to unforeseen subsurface conditions. Afinal settlement change order was negotiated
for significantly less than what the contractor had initially submitted. The original contract was
$3,504,684.14. UNANIMOUS APPROVAL. FORWARD TO MAY 6, 2019 REGULAR CONSENT
AGENDA.
B. Project Completion: 2018 Central Business District Sanitary Sewer Rehabilitation
Staff is seeking Council approval of contract completion and release of retainage to the Michels
Corporation in the amount of $411,460.27 for the 2018 Central Business District Sanitary Sewer
Rehabilitation Project. This project installed approximately 3,660 lineal feet of pipe within the
right-of-way and private easements. The original contract was $449,633.25. Underruns were
mainly due to work deleted due to various conflicts that would not allow the relining at this
time. UNANIMOUS APPROVAL. FORWARD TO MAY 6, 2019 REGULAR CONSENT AGENDA.
C. Tukwila Infrastructure Design and Construction Standards Update
Staff updated the Committee on the effort to update the Tukwila Infrastructure Design and
Construction Standards, which have not been revised since 2009 and are intended to ensure
consistent design and construction requirements and adherence to the Comprehensive Plan.
They establish minimum criteria and specifications for both public and private construction
projects and utility and street improvements. The 2019 revisions integrate WSDOT standards,
low impact development principles, and were thoroughly reviewed by a staff committee and
the City Engineer. Chair Idan asked if the revised standards would address the issue of inconsist
connections with adjacent city streets as well as utility patching. Staff noted that utility work
is performed by third parties outside of the city's inspection process. Councilmember Kruller
asked if the standards include a street moratorium and staff replied that they do. All agreed
that Council and staff collaboration on messaging and enforcing the City's standards will be
helpful. Staff intends to review every two years and the Council will be kept informed.
DISCUSSION ONLY.
19