HomeMy WebLinkAboutReg 2019-05-20 Item 4C - Change Order #4 - 42nd Avenue South Phase III with Active Construction for $1,050,000COUNCIL AGENDA Siwosis Initials Meeting Date Prepared by Mayor's review Council review k9k4 05/20/19 HH JI, ITEM INFORMATION ITEM No. 4.C. STAIT SPONSOR: HENRY HASH ORIGIN , AGENDA DATE: 05/20/19 AGENDA ITEM TITLE 42nd Ave S Phase III Project (S 160th St - Southcenter Blvd) Construction Change Order No. 4 with with Active Construction, Inc. CATEGORY DiSeusston migDate 0 Motion 05/20/19 EI Resolution ;Wig Date 111 Ordinance MtgDate 0 Bic 1_,42pard Mtg Date LI Public Hearing Mtg Date Ell Other Mtg Date A tgDate SPONSOR Councii Major 0 HR EIDCD DFinance Fire ZITS OP R OCourt P .ce PW SPONSOR'S Change Order No. 4 to Contract No. 17-090 is for additional construction costs for the 42nd SUMMARY Ave S Phase III Project. 42nd Ave S has had major issues with the Gilliam Creek Culvert and utility conflicts which have caused delays and cost overruns. After extensive negotiations, Active Construction's Change Order No. 4 will resolve all disputes. Council is being asked to approve Change Order No. 4 with Active Construction for $1,050,000. REVIEWED BY •C.O.W. Mtg. lij CDN Comm Arts Comm. Finance Comm. E]Pubhc Safety Comm. Comm. [1:1 Planning Comm. CHAIR: ZAK IDAN 1 Trans &Infrastructure [1] Parks COMMITTEE DATE: 05/07/19 RECOMMENDATIONS: SPoNsoR/ADmiN, COMMITTEE Public Works Department Majority Approval; Forward to Regular Consent Agenda COST IMPACT / FUND SOURCE EXPENDITURE REQUIRED AMOUNT BUDGETED APPROPRIATION REQUIRED $1,050,000.00 $15,166,000.00 $ Fund Source: 103 RESIDENTIAL STREETS (PAGE 2, 2019 CIP) Comments: MTG. DATE RECORD OF COUNCIL ACTION 05/20/19 IVITG. DATE ATTACHMENTS 05/20/19 Informational Memorandum dated 0 /0 9 Page 2, 2019 CIP Active Construction's Change Order No. 4 Minutes from the Transportation and Infrastructure Committee meeting of 05/07/19 43 44 Public Works Department Henry Hash, Director INFOR ATIONAL E ORANDU TO: FROM: Henry Hash, Public Works Director BY: Peter Lau, Senior Program Manager CC: Mayor Allan Ekberg DATE: May 3, 2019 SUBJECT: 42nd Avenue South Phase III & Gilliam Creek Culvert Replacement Projects Project Nos. 99410303 & 99341208, Contract No. 17-090 Change Order No. 4 Transportation and Infrastructure Committee Allan Ekberg, Mayor ISSUE Approve Change Order (CO) No. 4 with Active Construction, Inc. (ACI) to resolve all new claims and disputes for the 42nd Avenue South Phase III Project. BACKGROUND Due to continuous issues with excessive ground water interference during excavation, changes and conflicts for Seattle City Light (SCL) facilities, design issues, some inefficiencies by the contractor, and other unanticipated utility conflicts, the 42nd Avenue South Phase III Project encountered schedule delays and cost overruns. DISCUSSION Change Order No. 3 was a compromise between the City and ACI to resolve outstanding construction disputes through May, 2018, which was approved by Council in July, 2018. The execution of CO No. 3 avoided potential claims and a .possible legal battle with substantial legal fees by both parties and produced cost savings for the City. After the execution of CO No. 3, PW staff and ACI worked cooperatively together to move the project forward. However, for the reasons stated above and more unanticipated issues, the project cost overruns continued. After extensive discussions and negotiations between PW staff and ACI, a mutual agreement was reached and both parties agreed that it is in their best interest to complete the project in the most efficient way possible. The new compromise is documented in Change Order No. 4. In summary, CO No. 4 will: • reduces the 14% mark-up rate (established in CO No. 3) to 12.5%, which still covers ACI's bond, insurance, other general and administrative overhead costs, and profit. This change will result in a savings of $164,000 for the City; • enables City project staff to continue to work cooperatively with ACI's construction crew, in order to efficiently complete the construction project with the least amount of cost; • requires ACI to physically complete the project within six weeks after the utility conversion work is completed; • resolves all outstanding claims and disputes between the City and ACI and agrees not to pursue legal action against each other when this CO is strictly followed. W:\PW EngIPROJECTS1A- RW & RS Projects142nd Ave S Phase III (99410303 94-RS03)1Consfructiont#,500 - Project Payments1030 - Change Proposals & COs1C0 #4 - Cost Plus 211nfo Memo for CO #4 91050319, pl,gl 042519.docx 45 46 Infmmational Memo 42nd Ave S CO 4 Page 2 FISCAL IMPACT The table below shows the project budget and expenditures, with the inclusion of CO No. 4: Design CM Construction Budget CH2M Hill Design & Staff $1,563,995 $1,564,000 AECOM Original CM & Sups No. 1 & 2 $1,768,424 1,897,000 CH2M Hill Supplemental No. 7 & 8 79,272 AKANA Consultant Contracts 79,450 Widener & WSDOT JA 9753 18,000 Active Construction Contract 17-090 $6,599,266 1 ,705,000 Active Change Orders No. 1 & 2 916,864 Active Change Order No. 3 w/ sales tax 2,741,136 Active Change Order No. 4 w/o sales tax 1,050,000 Construction Contingency 349,593 Total $1,563,995 $1,945,146 $11,656,859 Grand Total $15,166,000 $15,166,000 The current 2019 CIP project budget is sufficient to cover the cost of Change Order No. 4 and will leave a $349,593 construction contingency. CO No. 4 would require an increase of 33 working days for ACI to physically complete 42nd Ave S Phase III construction project. RECOMMENDATION Council is being asked to approve Change Order No. 4 to Contract No. 17-090 with Active Construction, Inc. in the amount of $1,050,000 for the 42nd Avenue South Phase III and Gilliam Creek Culvert Replacement Projects and consider this item on the Consent Agenda at the May 20, 2019 Regular Meeting. Attachments: 2019 CIP, page 2 Change Order No,4 W:IPW Eng1PROJECTSIA- RW & RS ProjectsI42nd Ave S Phase III (99410303 94-RS03)1ConstructionIt500 - Project Payments1030 - Change Proposals & COsICO #4 - Cost Plus 21Info Memo for CO tt4 91050319, MI 042519.docx 47 CITY OF TUKWILA CAPITAL PROJECT SUMMARY 2019 to 2024 PROJECT: 42nd Ave South Phase III Project No. 99410303 DESCRIPTION: Design and construct street improvements, drainage, sidewalks, bike facilities, and driveway adjustments. JUSTIFICATION: Provide pedestrian and vehicle safety, drainage, and neighborhood revitalization. STATUS: Phase III (S/C Blvd (154th) - S 160 St), Design began in 2012, construction in 2017. Project No. 99410303 Phase IV (S 139 St - S 131 PI) in beyond. Project No. 99410301 Phase I 90-RW15 (SIC Blvd (154) - 144 St) $3,796 & Phase II 94-RS02 (144-139) $1,850, both completed. MAINT. IMPACT: Reduce pavement, shoulder, and drainage work. COMMENT: Only Phase III is shown in active years. Project includes Surface Water's Gilliam Creek 42nd Ave S Culvert project for $1.3m and is part of the Walk & Roll Plan. Seattle City Light's funding is a 60/40 underground split. FINANCIAL Through Estimated in $000s) 2017 2018 2019 2020 2021 2022 2023 2024 BEYOND TOTAL EXPENSES Design 1,564 1,564 Land (RAN) 0 Const. Mgmt. 809 688 400 1,897 Construction 2,232 5,231 2,100 9,563 Under -grounding 508 1,634 2,142 TOTAL EXPENSES 5,113 7,553 2,500 0 0 0 0 0 0 15,166 FUND SOURCES Seattle City Light 1,285 1,285 Surface Water 1,415 2,881 4,296 Other Utilities 1 575 576 Bond 6,487 6,487 City Oper. Revenue (2,790) 2,812 2,500 0 0 0 0 0 0 2,522 TOTAL SOURCES 5,113 7,553 2,500 0 0 0 0 0 0 15,166 2019 - 2024 Capital Improvement Program 48 2 DATE: CITY OF TUKWILA CONTRACT CHANGE ORDER NO. 4 April 15, 2019 BUDGET NOs.: 103.98.595.300.65.00 412.98.594.382.65.00 PROJECT NO.: 99410303 CONTRACT NO.: 17-090 PROJECT NAME: 40th — 42nd Avenue South Phase III Project TO: Active Construction, Inc. You are hereby directed to make the herein described changes to the plans and specifications or do the following described work not included in the plans and specifications on this contract: NOTE: This change order is not effective until approved by the "Owner" and a notice to proceed is issued. Conditions: A. The following change, and work affected thereby, are subject to all contract stipulations and covenants; B. The rights of the 'Owner" are not prejudiced; C. All claims against the "Owner" which are incidental to or as a consequence of this change are waived; and D. The Contractor must submit all Field Overhead and Home Office Overhead Rates for approval in advance of all change orders. CHANGE: See Attached Exhibit "A," incorporated herein by this reference. We the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept the prices shown above and below as full payment for . ACCEPTED: Date By or Contractor: Active Construction, Inc. Title Original on ct (without tax) $ 99,266.04 APPROVED BY THE CITY OF TUKWILA Prevp‘Change Order $ 3,345,367.97 Date This Change Order (without $ 1,050,000.00 By Mayor REV. CONTRACT AMOUNT Previous Contract Time: 321 Working Days City Engineer )/C Additional Contract Time for this Change Order: 33 Working Days Updated Contract Time: 354 Working Days $10,994,634.01 ORIGINAL: City Clerk (1 of 2) Contractor (2 of 2) PW Project Finance File cc: Finance Department (w/encumbrance) Project Management File 49 40th -- 42nd Avenue South Phase III Project Contract Change Order No. 4 EXHIBIT A DESCRIPTION OF WORK Change Order (CO) #3 for the 401h — 42nd Avenue South Phase 3 Project, which was a compromise between the City and the construction contractor (ACI) on resolving all the outstanding construction disputes through May 20, 2018, was executed on July 17, 2018, However, three months after the execution of CO #3, ACI started to alert the City that the cost increase from CO #3 would be insufficient to pay for all the remaining contract works. As a result, the City requested ACI to provide justifications for the cost increase beyond the new contract amount from CO #3. After reviewing ACT's provided cost increase justifications, the City contended that ACI was partially responsible for causing the additional cost increase. ACI disagreed with the City's contention. After months of further monitoring of the actual project cost increase, and negotiations between City project staff and ACI, another compromise has been reached between the parties. This new compromise is herein documented in this CO #4. In this CO #4, the City and ACI have mutually agreed to work collaboratively to physically complete the project within 6 weeks after the utility conversion works were completed by all utility companies. The City also agrees to a reduction of the 14% markup rate (previously generated from CO #3) to 12.5%, of the actual overall cost of construction. The 12.5% markup is to compensate ACT's general and administrative overhead cost, and profit. The actual overall cost of this 40th — 42nd Avenue South Phase 3 Project refers to all the direct expenditures spent by ACI on this particular construction project, includes the mobilization/field overhead cost, but excludes the indirect overhead cost. However, for costs incurred after the date of this CO #4, if the expenditure was caused by ACI's own negligence, such expenditure will not be counted as part of the actual project costs to be paid by the City, and ACI will remain fully responsible for such expenditures. As for all the subcontracts among ACI and it's subcontractors, this CO #4 will not apply to any subcontracts executed prior to the execution of CO #3, and all the corresponding Bid Items paying for these subcontracts. The City will just continue to pay for these subcontract costs and with the new 12.5% markup. As a result, the existing payment mechanism among ACI and it's current subcontractors will continue to be preserved. After the execution of CO #4, all new subcontracts among ACI and it's future subcontractors will be subjected to the new 12.5% mark-up as the subcontractors' direct costs. ACI's actual cost for this 401h 42nd Avenue South Phase 3 Project will continue to be subject to a detailed review monthly before the issuance of the monthly pay estimate for such work, and before the issuance of the final payment by the City. At the option of the City, the actual cost reviews and verifications may continue to be conducted by a Certified Public Accountant or other City of Tukwila designated representatives: The current projected total cost for ACI to complete this 401h — 42nd Avenue South Phase 3 Project is $9,773,008.01, per the enclosed projected cost breakdown provided by ACI. Adding 12.5% to the projected cost of $9,773,008.01, it would result in $10,994,634.01 as the cost. Both the City and ACI agree that after the execution of this CO #4, the City's construction management team will continue to have the option of determining the means and methods of ACI in constructing this project. The execution of this CO #4 supercedes the previous COs #1 and #2 on the payment and bid item parts, but the scope issues and Contract time increase will remain in effect. This CO #4 also supercedes CO #3 on all applicable and conflicting Contract terms and conditions. Both the City and ACI agree that mutual execution of this CO #4 continues to resolve any and all outstanding disputes between the parties relating to the Project, including any claims for prior delays, and ACI and the City hereby release each other from any such claims. Both the City and ACI agree not to pursue legal action against each others if both parties strictly abide by the terms of this CO #4. The parties agree to continue to discuss and negotiate when necessary, in order to resolve any additional Contract disputes that arise after the execution of this CO #4. Page 2 of 3 50 The City looks forward to continuing to work with ACI to complete this important project. CONTRACT TIME Per CO #3, the Contract time was to expire on November 13, 2018. CO #4 will add 33 working days to this Contract, since • ACI vacated the project site on November 16, 2018, allowing the utility companies to continue the utility conversion works. Therefore, between November 13 and 16 of 2018, 3 working days of Contract time extension is needed. • The construction project will be retroactively suspended starting from November 17, 2018, until the utility conversion works are completed. • ACI will have 30 working days to complete all remaining works for the construction project, including all the punch list items. Therefore, the Contract time will need to be increased by 33 working days total. As part of this CO #4, the parties agree that the Contract time will not be extended further, with the exception of: • weather related delays; • delays encountered that are out of the control of the Contractor or the City; • and unanticipated changes to the work where extension of Contract time would otherwise be determined in accordance with Section 1-08 of the WSDOT Standard Specifications, 2016 version. Page 3 of 3 51 52 Transportation & Infrastructure Committee Minutes May 7, 2019 D. Staff noted that this could be a policy issue and/or on the Council's legislative agenda. Staff also noted that Tukwila has one staff and one business representative on Seattle City Light's Review Panel. Chair Idan asked if staff could quantify the cost incurred by Seattle City Light related delays and staff will provide that information. Councilmember Kruller said she appreciated staff's response to the resident who was unhappy with work occurring on the weekend without notification. MAJORITY APPROVAL. FORWARD TO MAY 20, 2019 REGULAR CONSENT AGENDA. Change Order: 42" Avenue South Phase III & Gilliam Creek Culvert Staff is seeking Council approval of Change Order No. 4 with Active Construction, Inc. in the amount of $1,050,000 to resolve all claims and disputes for the 42nd Avenue South Phase III Project. This project encountered schedule delays and cost overruns due to issues with excessive ground water interference during excavation, changes and conflicts for Seattle City Light facilities, design issues, contract inefficiencies, and other utility onflicts. Change Order No. 3 was negotiated to resolve outstanding disputes through May 2018 and avoided potential clams and legal fees, but unanticipated issues resulted in more costly delays. Change Order No. 4 was extensively negotiated and agreed to by both parties. It will reduce the 14% mark- up rate established in CO No. 3 to 12.5%, enable City staff to continue cooperative work with ACI, requires physical completion of the project within six weeks after utility conversion work is done, and resolves all outstanding claims and disputes with agreement for no future legal action. The current project budget is sufficient to cover the cost of Change Order No. 4 and leaves a $349,593.00 contingency. Chair !clan mentioned the importance of the construction schedule. MAJORITY APPROVAL. FORWARD TO MAY 20, 2019REGULAR CONSENT AGENDA. E. Waste Management Contract Status Update Staff updated the Committee on the ongoin negotiations with Waste Management. The current contract will expire on October 31, 2019 but has a provision for up to two 2-year extensions, whichstaff recommends pursuingdue to the favorable rates. The contract extension proposal wilt be brought to the next Committee meeting. Terms will include a 5% rate increase and 10%utility tax increase forcommercial customers and trash collection at the bus stops along Tukwila International Boulevard. The rates will still be comparatively favorable with thesencreases, which are due to the changes to the international recycling market and the impacts to roads by the heavy trucks. Councilmember Kruller expressed concerns about impacts to the business community. Councilmember Hougardy said that it will be important to consider the history of the issue when the contract is next bid, and that messaging to the business community should include the information about the rate compared with other Cities. Councilmember Kruller suggested reaching out to the Chamber. Waste Management will also be messaging the community about the increase. Chair Idan suggested that the Council would benefit from education on pavement conditions citywide. DISCUSSION ONLY. III. SCATBd/RTC There was no report. 53