HomeMy WebLinkAboutReg 2019-05-20 Item 6E - Report - Public Safety Plan: Program Management Quality Assurance Monthly ReportMay 13, 2019
TO: Tukwila City Council
FROM: Steve Goldblatt
PMQA Consultant
RE: Public Safety Plan
May update
Fire Station 51 construction preparation has begun. Station 52's design development phase
is underway. Justice Center sitework is underway. Programming and master planning of
the consolidated shops facilities continues. Boldfaced entries below are updated from
last month's report.
FIRE STATIONS
Site acquisition
The City owns the property planned for deferred Fire Station 54, and its use or disposi-
tion will be a future Council decision. Lydig demolished the property's structures. De-
ferred Station 54 lot consolidation is underway.
Station 51 construction
Lydig's MACC (Maximum Allowable Construction Cost) amendment was approved by
Council 25 March. The new Council -approved budget is $14.8 million. Lydig is mobi-
lized onsite and beginning construction preparation activities. Starting early in
June, Council will receive monthly construction reports with progress photos.
Station 52 design development and pre -construction services
Weinstein AU's design development for Station 52 is underway. Drive -through Station
52's Council -approved budget is $19.26 million. Lydig's schematic design estimate —
including the administrative tenant improvements as an alternate —will be presented
to Public Safety 20 May and COW 28 May. Council can expect budget growth for Sta
tion 52. Council can anticipate a mini-MACC contract amendment request by early July
to begin earthwork and site utilities timely this summer. The full MACC amendment
will follow in the fall to approve the start of Station 52 general construction. The City
has agreed to a timely permitting schedule.
Station 54 assessment
Last June, Council asked for an estimate to make life safety improvements to existing
Station 54. Staff presented four potential options —with very rough order of magnitude
cost estimates —to Public Safety 5 November; see Rachel Bianchi's 30 October memo
for details. Committee consensus was to revisit the options after Station 51 and Justice
Center construction costs firm up. The Committee agreed that the existing station
needs modest maintenance and repairs for the health of firefighters there. City staff is
compiling costs for presentation to Public Safety late spring/early summer.
225
FIRE STATIONS continued
Stations' budget
Including Station 51's budget growth and Station 54's substantially reduced scope, the
stations' overall Council -approved budget is 535.6 million. Station 52's budget will fur-
ther increase that amount.
• Disadvantaged Business Enterprise and local hiring policies
The Council unanimously passed Resolution 1929 last April, adopting DBE and local
hiring policies for the Plan's projects. The DBE goal is 17% and the local hiring goal is
20%, complementing the City's 10% apprenticeship requirement of Resolution 1814.
The first metrics that the Council sees can be expected midyear. Lydig—and BNBuild-
ers for the Justice Center —have been doing extensive outreach efforts with the DBE
community in this very competitive market. No DBE firms bid on Fire Station 51 trade
packages. Lydig intends to award some DBE firms work under its negotiated support
services. Council is receiving monthly updates.
JUSTICE CENTER
• Property acquisition
Lot consolidation is completed, and the property is recorded with King County.
Permitting
The building permit was issued in April.
• Full MACC and construction
BNB's mini-MACC amendment was approved by Council 25 March. The new Council -
approved budget is $66.9 million. The full MACC amendment to authorize the overall
scope of work will be presented to Public Safety 20 May and COW 28 May for possi-
ble Council approval 3 June. Having completed abatement and demolition, BNB is
performing underground utility work. Starting early in June, Council will receive
monthly construction reports with progress photos.
CONSOLIDATED SHOPS
• Property acquisition
The City has agreements with all three property owners. Lot consolidation on two
properties is underway. Ownership of the third property will transfer in 4+ years.
• Programming and master planning services
Having worked closely with Public Works staff, SHKS is incorporating their feed-
back to two test -fit master plan options. Council can expect a master plan and phas-
ing proposal to be ready for Public Safety and COW in June.
PMQA update May 13, 2019 page 2
226
CONSOLIDATED SHOPS continued
Renovation contracting
The project team is reviewing contracting options for an initial scope of renova-
tion work on existing facilities.
OTHER RESOURCES
Professional services
The project teams have been working through procurement of additional consultant
resources for the Fire Stations and Justice Center. Most recently, Council approved
Steve Amento's project neutral services contract for the Fire Stations and Justice
Center at a special meeting 22 April.
PROG
11 A
M SCHEDULE
Tight schedule
The overall schedule remains very ambitious. With so many activities under way, there
is little room for any missteps to meet the Plan's revised milestones. Fire Station 51
and Justice Center construction are beginning. Fire Station 52 is on a tight schedule to
begin its extensive earthwork this summer.
PROG' M BUDGET
Market conditions
All program element budgets are sensitive to tight construction market conditions.
These external budget pressures will manifest themselves as Fire Station 52 and future
consolidated shops project estimates are refined.
LEGEND
Meeting target
Proceeding as planned.
Caution advised
Steps needed to meet target.
Correction needed
Steps needed to attempt recovery,
Not meeting target
No recovery plan in place.