Loading...
HomeMy WebLinkAboutTIC 2019-06-04 Item 2D - Resolution - 2020-2025 Transportation Improvement ProgramAllan Ekberg, Mayor PAIMMINIMAI Public ° „ Arks Department Henry Hash, Director INFORMATION MEMORANDUM TO: Transportation and Infrastructure Corromittee FROM: Henry Hash, Public Works Director BY: Cyndy Knighton, Senior Program Manager CC: Mayor Ekberg DATE: May 31, 2019 SUBJECT: Resolution for Six -Year Transportation Improvement Program (2020-2025 ISSUE Approve a Resolution adopting the annual update of the Six -Year Transportation Improvement Program for 2020-2025. BACKGROUND The Transportation Improvement Program (TIP) is updated annually as required by the Revised Code of Washington (RCW). The TIP is adopted by resolution after a public hearing at the local agency level and incorporated into regional and state TIPs. The TIP is primarily a financial planning document for projects competing for grants. Any project submitted for federal grant funding must be included in the local, regional, and state adopted TIPs. The TIP is a rolling plan showing various funding sources: grants, developer and local funds. Projects "roll" as funds or stages occur (design report, final design and construction). Tukwila's TIP and Capital Improvement Program (CIP) list many of the same transportation -related projects. The TIP generally lists only those transportation -related projects planned within the next six years that are deemed regionally significant or that have grant funding awarded or expected. The TIP is scheduled for adoption on June 17, 2019. ANALYSIS The attached spreadsheet is the "Draft" 2020 - 2025 TIP and was created by modifying the 2019 - 2024 TIP to add or remove projects and adjust project costs. No prioritization was assigned and the list of projects is presented in alphabetical order. Prioritization of projects is reflected in the current CIP. No new projects were added, and 5 projects were removed because they have either been completed or moved beyond the 6-year time frame of the TIP. One project was combined into a larger project: West Valley Highway/Longacres Way Shared Use Pathways has been merged into the larger West Valley Highway project. Deleted: Completed: 40-42nd Avenue S Phase III and 53rd Avenue S. Moved to Beyond: TUC/TOD Pedestrian Improvements; Tukwila Int'I Blvd Retrofit; and Multipurpose Trails. FINANCIAL IMPACT None. RECOMMENDATION Council is being asked to approve the Resolution for the 2020 - 2025 Six -Year Transportation Improvement Program and consider this item at the June 10, 2018 Committee of the Whole with a Public Hearing and subsequent June 17, 2019Regular Meeting. ATTACHMENTS • Draft Resolution • Draft 2020-2025 TIP Summary • 2020 — 2025 "Draft" Transportation Improvement Program • Current Adopted 2019 — 2024 TIP W:\PW Eng\PROJECTS \A- RW & RS Projects \TIP\Info Memo TIP 2020 docx 25 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, ADOPTING A SIX -YEAR TRANSPORTATION IMPROVEMENT PROGRAM (2020- 2025), AND DIRECTING THE SAME TO BE FILED WITH THE STATE SECRETARY OF TRANSPORTATION AND THE TRANSPORTATION IMPROVEMENT BOARD. WHEREAS, pursuant to the requirements of Chapters 35.77 and 47.26 of the Revised Code of Washington, the City Council of the City of Tukwila has previously adopted a Transportation Improvement Program and has thereafter periodically modified said Transportation Improvement Program by resolution, in compliance with state law; and WHEREAS, the City Council has reviewed the work accomplished under said program, determined current and future City street and arterial needs and, based upon these findings, has prepared a Six -Year Transportation Improvement Program for the ensuing six calendar years (2020-2025); and WHEREAS, on June 10, 2019, a public hearing was held regarding the City's Six - Year Transportation Improvement Program; NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, HEREBY RESOLVES AS FOLLOWS: Section 1. Program Adopted. A Six -Year Transportation Improvement Program for the calendar years 2020 to 2025, attached hereto as Exhibit A, is hereby adopted. Section 2. Filing of Program. The City Clerk is hereby authorized and directed to file a copy of this resolution, together with the exhibit attached hereto, with the Secretary of Transportation and the Transportation Improvement Board of the State of Washington. W:\Legislative Development\TIP 2020-2025 5-14-19 CK:bjs Review and analysis by Barbara Saxton Page 1 of 2 26 PASSED BY THE CITY COUNCIL OF THE CITY OF TUKWILA, WASHINGTON, at a Regular Meeting thereof this day of , 2019. ATTEST/AUTHENTICATED: Christy O'Flaherty, MMC, City Clerk Kathy Hougardy, Council President APPROVED AS TO FORM BY: Filed with the City Clerk: Passed by the City Council: Resolution Number: Rachel B. Turpin, City Attorney Exhibit A: City of Tukwila Six -Year Transportation Improvement Program for 2020 to 2025 W:\Legislative Development\TIP 2020-2025 5-14-19 CK:bjs Review and analysis by Barbara Saxton Page 2 of 2 27 2019-2024 CIP Sheet DRAFT 2020 - 2025 TIP SUMMARY PROJECT I"IILE May 22, 2019 Project Costs in Thousands of Dollars FUNDING SOURCES 2020 2021 2022 2023 2024 2025 TOTAL Federal State/TIB Developer Unsecured City 15 42nd Avenue S Bridge Replacement 1,600 1,250 6,500 6,400 0 0 15,750 12,000 4 46th Avenue Safe Routes to School 0 412 2,125 0 0 0 2,537 2,537 18 ADA Improvements 50 200 200 200 200 200 1,050 17 Annual Bridge Inspections and Repairs 335 405 405 450 450 450 2,495 16 Annual Overlay and Repair Program 1,400 1,400 1,400 1,400 1,400 1,400 8,400 26 APE/Minkler Blvd Intersection 144 1,570 0 0 0 0 1,714 13 BAR over Airport Wy Bridge Seismic Retrofit* 2,614 0 0 0 0 0 2,614 2,614 BNSF Regional Center Access 0 0 0 100 0 0 100 25 Green River Trail 0 74 962 0 0 0 1,036 5 Macadam Road S Complete Streets Project 0 0 497 2,733 0 0 3,230 20 S 140th St Intersection Improvements 0 125 625 0 0 0 750 14 S 144th St Bridge Sidewalks 0 0 216 227 0 0 443 6 S 152nd Street Safe Routes to School 0 0 243 2,584 0 0 2,827 10 Strander Blvd/SW 27th St St Phase III 3,720 38,389 37,889 0 0 0 79,998 13,217 12 West Valley Highway 3,545 0 0 0 0 0 3,545 441 2,326 3,750 0 1,050 2,495 8,400 1,714 0 100 896 140 2,770 460 675 75 443 0 2,827 0 66,278 503 778 TOTAL 13,408 43,825 51,062 14,094 2,050 2,050 126,489 28,272 4,863 PROJECTS REVISED FROM 2019-2024 TIP Modified Deleted/Completed: WVH/Longacres Way Shared Use Pathways 40-42nd Ave S Phase III 53rd Avenue S Deleted/Moved to Beyond: TUC/TOD Pedestrian Improvements Tukwila Int'I Blvd Retrofit Multipurpose Trails 73,889 19,465 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17 TUK-62 42nd Ave S Bridge Replacement 42nd Ave S over he Duwamish River at the intersection with Interurban Ave S Interurban Ave S to Northern end of bridge Replace the existing 42nd Ave S steel truss bridge. The replacement would require preliminary engineer design, right-of-way, and construction phases. The new structure would meet current road and bridge design standards. The replacement structure configuration would be two through lanes, possibly a turn pocket, and include sidewalks. 06/10/19 06/17/19 11 0.100 DCE Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2020 BR 1,280,000 0 320,000 1,600,000 P RW 2021 BR 800,000 0 450,000 1,250,000 P CN 2022 BR 9,920,000 0 2,980,000 12,900,000 Totals 12,000,000 0 3,750,000 15,750,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 1,600,000 250,000 250,000 250,000 0 RW 0 1,000,000 0 0 0 CN 0 0 6,250,000 6,150,000 0 Totals 1,600,000 1,250,000 6,500,000 6,400,000 0 Report Date: May 22, 2019 Page 1 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 19 WA-11113 46th Avenue Safe Routes to School 46th Avenue S S 150th Street to S 144th Street Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S, including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised crosswalk across S 144th Street with RRFB. 06/10/19 06/17/19 05 0.370 Yes Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2021 0 SRTS 180,000 0 180,000 P RW 2021 0 SRTS 232,000 0 232,000 P CN 2022 0 SRTS 2,125,000 0 2,125,000 Totals 0 2,637,000 0 2,537,000 Expenditure Schedule Phase 1st 2nd 3rd 4th ' 5th & 6th PE 0 180,000 0 0 0 RW 0 232,000 0 0 0 CN 0 0 2,125,000 0 0 Totals 0 412,000 2,125,000 0 0 Report Date: May 22, 2019 Page 2 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 WA-05405 Americans with Disabilities Act (ADA) Improvements Various locations to Design and construct ADA compliant upgrades to City infrastructure in conjunction with a City developed plan. 06/10/19 06/17/19 06 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2020 0 0 1,050,000 1,050,000 Totals 0 0 1,050,000 1,050,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 50,000 200,000 200,000 200,000 i 400,000 Totals 50,000 200,000 200,000 200,000 400,000 Report Date: May 22, 2019 Page 3 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m k 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16 WA-07746 Andover Park E/Minkler Blvd Intersection Andover Park E Minkler Blvd to Construct left turn lanes on Andover Park East and reconstruct traffic signal 06/10/19 06/17/19 03 C G O P S TW No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2022 0 0 134,000 134,000 P RW 2022 0 0 10,000 10,000 P CN 2023 0 0 1,570,000 1,570,000 Totals 0 0 1,714,000 1,714,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 134,000 0 0 0 0 RW 10,000 0 0 0 0' CN 0 1,570,000 0 0 0 Totals 144,000 1,570,000 0 0 0 Report Date: May 22, 2019 Page 4 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14 WA-03731 Annual Bridge Inspections and Repairs Various City Street to Perform load ratings and bi-annual inspections as well as construct necessary repairs and maintenance 06/10/19 06/17/19 06 No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2020 0 0 2,495,000 2,495,000 Totals 0 0 2,495,000 2,495,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 335,000 405,000 405,000 405,000 i 900,000 Totals 335,000 405,000 405,000 405,000 900,000 Report Date: May 22, 2019 Page 5 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16 WA-03733 Annual Overlay and Repair Program Various City Streets to Repair, rehabilitate, and overlay City streets as needed in an annual program 06/10/19 06/17/19 06 C G O P S TW No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S ALL 2020 0 0 8,400,000 8,400,000 Totals 0 0 8,400,000 8,400,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 1,400,000 1,400,000 1,400,000 1,400 000 i 2,800,000 Totals 1,400,000 1,400,000 1,400,000 1,400,000 2,800,000 Report Date: May 22, 2019 Page 6 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 WA05409 BNSF Regional Center Access New Facility to Construct a new access to the BNSF Regional Distribution Center, relocating the 900+ daily truck trips from residential streets in Allentown. 06/10/19 06/17/19 08 EIS No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P PE 2023 0 0 100,000 100,000 Totals 0 0 100,000 100,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th PE 0 0 0 100,000 i 0 Totals 0 0 0 100,000 0 Report Date: May 22, 2019 Page 7 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14 / 1380(004) TUK-61 Boeing Access Road over Airport Way Seismic Retrofit S Boeing Access Road over Airport Way S Airport Way S to Airport Way S Install seismic protection on the structure. 06/10/19 06/17/19 06 0.050 CE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds S CN 2020 STP(BR) 2,613,855 0 0 2,613,855 Totals 2,613,855 0 0 2,613,855 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th CN 2,614,000 0 0 0 i 0 Totals 2,614,000 0 0 0 0 Report Date: May 22, 2019 Page 8 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description G. Structure ID m 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 WA-11115 Green River Trail Green River Trail Christensen Road to Green River Replace the existing 8-foot wide Green River Trail with 12-foot wide concrete paved trail with 2-foot gravel shoulders, including illumination, CCTV, wayfinding, and pedestrian plaza. 06/10/19 06/17/19 28 0.140 DCE No Funding Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State Fund Code State Funds Local Funds Total Funds P ALL 2022 STP(E) 896,000 0 140,000 1,036,000 Totals 896,000 0 140,000 1,036,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 5th & 6th ALL 0 74,000 962,000 0 0 Totals 0 74,000 962,000 0 0 Report Date: May 22, 2019 Page 9 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number \ E. Begin &End Termini \ F. Project Description \ ture ID m to Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17 \\\ \ Macadam Rd S Complete Streets Project 0 Macadam Road \\\\\\ S 150th Street to S 144th Street . .. Design and construction of a complete street on Macadam Road. Road widening and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of the roadway. Includes illumination, curb, and storm drainage. s\\ 06/10/19 06/17/19 04 0.350 DCE No Funding\, o\\� \\\\\\\o• \ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal F( I '-- *\ote Fun \ de State Funds Local Funds Total Funds P PE 2022 0 ��,, o P e'l-gram �\\\\\\\\ 397,000 0 397,000 P RW 2022 0 Ped/ rogram 4 I 100,000 ��\\\ 0 100,000 P CN 2023 0 Ped/ rogram ' \\- 273,000 460,000 2,733,000 Totals 0 0,000 460,000 3,230,000 Expenditure Schedule \\\ Phase 1st 2nd 3rd 4th 5th & 6th \ PE 0 0 397,000 0 RW 0 0 100,000 0 \ \ 0 CN 0 0 0 2,733,000 \\- 0 Totals 0 0 497,000 2,733,000 0 Report Date: May 22, 2019 Page 10 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number \ E. Begin &End Termini \ F. Project Description \ ture ID m y ° o . Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14 \\\ \ S 140th St Intersection Improvements \ \; S 140th Street \ \' Tukwila International Blvd to \ \. Design and construct a new traffic signal at the S 140th Street/Tukwila International Blvd intersection 06/10/19 06/17/19 04 C G P S T W 0.100 DCE Yes Funding o \\ o , O\\\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fiala,. lI to Fun de State Funds Local Funds Total Funds P PE 2021 0� "*gram 67,000 8,000 75,000 P RW 2021 0 Ped/ ogram 40,000 10,000 50,000 P CN 2022 0 Ped/"\grogram 4\ 568,000 57,000 625,000 Totals 0 \\\\\\I 5,000 75,000 750,000 Expenditure Schedule \"\\\ I Phase 1st 2nd 3rd 4th 5th & 6th \\ PE 0 75,000 0 0 1 RW 0 50,000 0 0 0 CN 0 0 625,000 0 \ \ 0 Totals 0 125,000 625,000 0 \ 0 1 Report Date: May 22, 2019 Page 11 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. C. Project Title D. Road Name or Number F. Begin t End Termini F. Project Description \ \ B. STIP ID ture ID m ' Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17 S 144th St Bridge Sidewalks S 144th Street 51st Ave S to 53rd Ave S Widen existing sidewalks on bridge over \ . \ 5 between 51st Ave S and 53rd Ave S \ \ \ \\\ 06/10/19 06/17/19 28 0.250 No Funding o\\ \\\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal ds -und e State Funds Local Funds Total Funds P PE 2022 SRTS 4\ \\\ 0 0 443,000 Totals 4000 \ 0 0 443,000 Expenditure Schedule \„_, ��� Phase 1st 2nd 3rd 5th \.- o\ PE 0 0 216,000 ...\-N- IloV \\\\\\\\\\\\\\ Op 0 Totals 0 0 216,000 �17,000 \�� \\\O\\\\\\\\0 Report Date: May 22, 2019 Page 12 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number \ E. Begin &End Termini \ F. Project Description \ ture ID m Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 19 \\\\\... \ S 152nd Street Safe Routes to School 2 S 152nd Street \\\\\\ Tukwila International Blvd to 42nd Avenue S \ Design and construct curb, gutter and sidewalks on both sides including widening pavement width by 3 feet to construct on -street parking lane on north side of street. 06/10/19 — 06/17/19 05 0.300 No Funding \\oo... \: Status Phase Phase Start Year (YYYY) Federal Fund Code Federal‘ds to Fundje State Funds Local Funds Total Funds P PE 2022 \\1\ SR\ 243,000 0 243,000 P CN 2023 0 ,N�� 2,584,000 0 2,584,000 Totals 0 \ \ \\\\\\�\ 2,827,000 0 2,827,000 Expenditure Schedule \ \ \\I\ Phase 1st 2nd 3rd 4th , 5th & 6th $\ PE 0 0 243,000\ 0 CN 0 0 0 2,584,000 Totals 0 0 243,000 2,584,000 �� Report Date: May 22, 2019 Page 13 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. C. Project Title D. Road Name or Number \ E. Begin &End Termini \ F. Project Description \ B. STIP ID ture ID m to Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16 1276(007)�\\\\ " \\ Strander Blvd./SW 27th St Extension Strander Blvd./SW 27th St Extension \\\ West Valley Highway to Naches Ave This project is Phase 3 of a multi -phase improvement that will connect Strander Blvd./SW 27th St between West Valley Hwy in Tukwila and Oakesdale Ave in Renton. This project will complete the design, right-of-way and construction phases for the roadway segment between West Valley Hwy and Naches Ave. Project components include a railroad bridge for the Union Pacific RR to provide grade separation, a new 4/5 lane roadway segment east of West Valley Hwy, roadway lanes rportion nnewtailb dgfortheInterrurbanTraiil(includingnnewtrailproject segment, a separated wideningjoint-use tStrander Blvd.), a new flyover bridge connection to the Tukwila Station, a new traffic signal serving the Tukwila Station, and storm drainage facilities. Current funding will complete the preliminary engineering and right of way phases. Construction will be funded as part of a future phase. \ 59 \ \�� \` \\\t\ 06/10/19 \\\\ \\ 06/17/19 01 0.300 DCE Yes Funding \\ \ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State F $! de Mate Funds Local Funds Total Funds S PE 2020 STP 1,730,000 6.\\ 270,000 2,000,000 S RW 2020 STP(UL) 1,487,000 233,000 1,720,000 S CN 2021 FMSIB 5,000,000 \ \\� 0 5,000,000 S CN 2021 Discretionary 5,000,000 JP 0 0 5,000,000 P CN 2021 STP 4,760,000 TIB 4P00,000 0 16,760,000 P CN 2021 TIGER 25,000,000 WSDOT\�24,518,000 0 49,518,000 Totals 42,977,000 36,518,000 503,000 79,998,000 Report Date: May 22, 2019 Page 14 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Expenditure Schedule ��\ Phase 1st 2ndd 4th 5th & 6th PE 2,000,000 \ J� ' 0 0 0 0 RW 1,720,000 0 \ 0 0 0 CN 0389,000 37,00 0 0 Totals 3,720,000 000 0 0 0 Report Date: May 22, 2019 Page 15 tat Agency: Tukwila County: King MPOIRTPO: PSRC Y Inside Six Year Transportation Improvement Program From 2020 to 2025 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number \ E. Begin &End Termini F. Project Description \ ture ID m 2 y ° o o, Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14�\\\\ 6 \ \0 West Valley Highway/Longacres Way Shared Use Pathways SR 181 &Longacres Way \\\ W end of planned Green River Bridge to Longacres Way . ._ Improvements will be completed on SR 181 from the west end of the planned Green River non -motorized Bridge to Longacres Way, including a 12-14 ft. separated shared use path with a 5 ft. landscaped buffer strip on the west side of the highway. Design -only will be completed for future improvements on Longacres Way between\\\\\ SR 181 to the Tukwila Sound Transit Link Station. 06/10/19 \\ 06/17/19 28 0.170 DCE No Funding \\ \\ ,o Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds SW, Atode to Funds Local Funds Total Funds S PE 2020 0 50,000 50,000 100,000 S CN 2020 CMAQ 441,000 --,-,'S ,,,,, ' -_ \-- \ 276,000 728,000 3,445,000 Totals 441,000 N,--,-,- 778,000 3,545,000 Expenditure Schedule \ ,. \\ \\\ Phase 1st 2nd 3rd 4th 5th & 6th PE 100,000 0 0 0 CN 3,445,000 0 0 0 \ 0 Totals 3,545,000 0 0 0 \- 0 Federal Funds S ends Local Funds Total Funds Grand Totals for Tukwila 59,370,855 47,653,000 19,465,000 126,488,855 Report Date: May 22, 2019 Page 16 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin End Termini \ F. Project Description mat \ \ ure ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17\ 45 40-42 Ave S (S 160 St - S 131 PL) \\\\ \\\ S 160th Street to S 131 st Place Design and construct street improvements, underground aerial utilities, drainage, sidewalks, bike facilities, and driveway adjustments 06/25/18 \\\\ 07/02/18 1938 04 C G O P S TW DCE Yes Funding\ \ \ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds\ - St ono J d Code State Funds Local Funds Total Funds S CN 2019 0 U II \ \ 0 3,000,000 3,000,000 P CN 2024 0 \\\N" o \\`,,,, \\\\\\\\\ 0 4,360,000 4,360,000 Totals 0\ 0 7,360,000 7,360,000 Expenditure Schedule \\ \\\"\\\ 4t1% , th & 6th Phase 1st 2nd 3rd CN 3,000,000 0 0 \\\\Q\\\\\\\\ 0 Totals 3,000,000 0 0 \\\0 \Q* Report Date: May 21, 2019 Page 1 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title \ D. Road Name or Number E. Begin & End Termini \ \ F. Project Description \ mature ID = (D\\\ 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 08\�� 401 42nd Ave S Bridge Replacement \ 42nd Ave S \\\ Interurban Avenue S to North Bridge Design and construct a replacement structure for the existing S 42nd Ave bridge. \ 810970 06/25/18 07/02/18 1938 11 C G P S T W 0.060 DCE No Funding \I\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds ��a and Cod State Funds Local Funds Total Funds P PE 2020 BR 1 ,-Wt0\ \ O 0 546,000 2,100,000 P RW 2021 BR 740,000 \� �OO000' 0 260,000 1,000,000 P CN 2022 BR 10,206,000 \\\\\\1\ 0 2,444,000 12,650,000 Totals 12,500 000 O �p 0 3,250,000 15,750,000 Expenditure Schedule O \ -N' - Phase 1st 2nd 3rd 4t}a\N, th & 6th PE 0 1,600,000 0 000 mR RW 0 0 1,000,000 \\\\\\ \ I IP0 CN 0 0 250,000 6,250,04 46,1b0 Totals 0 1,600,000 1,250,000 6,500,000 6, l 00 Report Date: May 21, 2019 Page 2 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number F. BeginEnd Termini \\ F. Project Description \ mature ID = 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 19\ 113 46th Avenue Safe Routes to School 46th Avenue S \\\\\ S 150th Street to S 144th Street '\\ \ \\ Design and construct curb, gutter and sidewalk on the west side of 46th Avenue S, A\\\\\ including curb bulb -out at the SE corner of 46th Avenue S/S 144th Street with raised crosswalk across S 144th Street with RRFB. \\ 06/25/18 \\\\ 07/02/18 1938 05 0.370 Yes Funding \ \ -i '-\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund, - St ads oc State Funds Local Funds Total Funds P PE 2019 0 \' �� 180,057 \\\\\\\O 0 180,057 P RW 2019 0 TS v \� 232,000 0 232,000 P CN 2020 0 4 RTS \\�\124,668 0 2,124,668 Totals 0 \\ \\\\\\\ 6 725 0 2,536,725 Expenditure Schedule \\\ Phase 1st 2nd 3rd 4th � \ h & 6th \\N- PE 180,057 0 0 \\\\Q\\\\\0 \ 0 RW 232,000 0 0 \ 0 CN 0 2,124,668 0 0' Totals 412,057 2,124,668 0 0 \ 0 Report Date: May 21, 2019 Page 3 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID D. Project Title D. Road Name or Number E. Begin &End Termini F. Project Description \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17\ 601 3144th St :::::::: Design and construct urban residential street improvements that include curb, gutter, sidewalk , illumination and undergrounding. Street portion will coordinate with Water, Surface Water and Sewer capital improvement program projects. 06/25/18 07/02/18 1938 04 C G O P S TW 0.420 CE Yes Funding .--N��\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun' . Sta ,,���� _\tate Funds Local Funds Total Funds S CN 2019 0 2,274,365 2,714,849 4,989,214 Totals 0 \\.0 ���2,274,365 2,714,849 4,989,214 Expenditure Schedule N\ \�\ Phase 1st 2nd 3rd 4th\ 5th & 6th CN 4,101,249 250,000 0 \\\\\\\\O\\ 0\\ 0 \\\\\\ Totals 4,101,249 250,000 0 \\ 0 \\1 Report Date: May 21, 2019 Page 4 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title \ D. Road Name or Number F. BeginEnd Termini \ \ F. Project Description \ \ mature ID = (D\\\ 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00\\\ 405 Americans with Disabilities Act (ADA) Improvements Various locations \\\\\ \ to \\ \ \\ Design and construct ADA compliant upgrades to City infrastructure in conjunction with a Citydeveloped plan. 06/25/18 07/02/18 1938 06 No Funding 11 \\\\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds "' �und Cod State Funds Local Funds Total Funds S ALL 2019 \ 0 \\ 0 1,200,000 1,200,000 Totals 0 \ �OO000"\ 0 1,200,000 1,200,000 Expenditure Schedule \" -\\\ Phase 1st 2nd 3rd \\4th \ 5th ALL 200,000 200,000 200,000000 \\\\\\\\\\\\\\\\\ ''1400,000 Totals 200,000 200,000 200,000 J 00,000 \ 4 Report Date: May 21, 2019 Page 5 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title \ D. Road Name or Number E. Begin & End Termini \ \ F. Project Description mat \ \ ure ID = (D\\\ 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16\ 46 \\\\� \ Andover Park E/Minkler Blvd Intersection Andover Park E . \\\ Minkler Blvd to Construct left turn lanes on Andover Park East and reconstruct traffic signal 06/25/18 07/02/18 1938 03 C G O P S TW No Funding , \I\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds �-a and Cod State Funds Local Funds Total Funds P PE 2020 \ 0\ \ 0 134,000 134,000 P RW 2020 0 \\ 0 10,000 10,000 P CN 2021 0 \\\\\\1\ \\\\\\\\\\\\\\\\ 0 1,570,000 1,570,000 Totals 0 \ O 0 1,714,000 1,714,000 Expenditure Schedule O ,,,,,,,--N- \\\ Phase 1st 2nd 3rd 4t}a\\ \\th & 6th PE 0 134,000 0 0 RW 0 10,000 0 \ \ 0 CN 0 0 1,570,000 \ ' 0 Totals 0 144,000 1,570,000 0 \ 0 Report Date: May 21, 2019 Page 6 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title \ D. Road Name or Number F. BeginEnd Termini \ \ F. Project Description \ \ mature ID = (D\\\ 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14\\\ 731 Annual Bridge Inspections and Repairs Various City Street to \ \ Perform load ratings and bi-annual inspections as well as construct necessary repairs and maintenance 06/25/18 07/02/18 1938 06 No Funding 11 \ \\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds "' �und Cod State Funds Local Funds Total Funds S ALL 2019 \\\ 0 \\ 0 2,300,000 2,300,000 Totals 0 - �OO000" 0 2,300,000 2,300,000 Expenditure Schedule \" -\\\ Phase 1st 2nd 3rd \\4th \ 5th ALL 335,000 335,000 405,000000 ', 820,000 Totals 335,000 335,000 405,000 \- 05,000 \ 82-�\ Report Date: May 21, 2019 Page 7 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number \\\\ Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required A. PINIProject No. B. STIP ID D. Project Title D. Road Name or Number \ = F. Begin t End Termini \ F. Project Description \ \ mature ID 0 16\�� 733 06/25/18 07/02/18 1938 06 C G O P S No TW Annual Overlay and Repair Program Various City Streets \ \\ to Repair, rehabilitate, and overlay City streets as needed in an annual program Funding I\I,� Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds `1 "' o4\tiund Cod State Funds Local Funds Total Funds S ALL 2019 \\\ 0 \\ 0 10,870,000 10,870,000 Totals 0 \ �\\000"\ 0 10,870,000 10,870,000 0 Expenditure Schedule \" 11k Phase 1st 2nd 3rd \\4th \ 5th ALL 1,730,000 1,740,000 1,800,000 \000 \\\\\\\\\\\\p\\\\\ 3,850,000 Totals 1,730,000 1,740,000 1,800,000 850,000 \ \\\\\ � 3'8 *- Report Date: May 21, 2019 Page 8 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number \\\\ A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin End Termini \ F. Project Description \ \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00 \\ , 40 BNSF Regional Center Access New Facility to \ \ Construct a new access to the BNSF Regional Distribution Center, relocating the 900+ daily truck trips from residential streets in Allentown. 06/25/18 07/02/18 1938 08 EIS No Funding 11 \\\\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds ` �und Cod I State Funds Local Funds Total Funds P PE 2024 \\ 0 \\ 0 100,000 100,000 Totals 01/4 0 100,000 100,000 Expenditure Schedule \" \\ Phase 1st 2nd 3rd \\4th \ 5th PE 0 0 0 \ 0 -1 100,000 Totals 0 0 0 \\ 0 \\\\\\\\ 1 Report Date: May 21, 2019 Page 9 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number \\\ A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini \ F. Project Description \ \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17\ \,117 Boeing Access Road over Airport Way Bridge Seismic Retrofit Boeing Access Road to \ \ Provide seismic modifications to the Boeing Access Road over Airport Way Bridge to allow it to withstand earthquake forces. 06/25/18 07/02/18 1938 47 0.100 No Funding \ . \\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds "' o4,und Cod State Funds Local Funds Total Funds S PE 2019 BR bb0 .. \ 0 0 370,000 S CN 2019 BR 2,611,000 \\ 0 0 2,611,000 Totals 2,981,000 \\\\\\ 0 0 2,981,000 Expenditure Schedule \ \ \,\\\\ \\ Phase 1st 2nd 3rd 4th \� 5th & 6t1 PE 370,000 0 0\ 0 CN 0 2,611,000 0 \_ 0 , Totals 370,000 2,611,000 0 \\ \ 0 Report Date: May 21, 2019 Page 10 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini \ F. Project Description \ \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00\115 Green River Trail Green River Trail \\\\\ Christensen Road to Green River '' \ \\ Replace the existing 8-foot wide Green River Trail with 12-foot wide concrete paved \\\\\\ trail with 2-foot gravel shoulders, including illumination, CCTV, wayfinding, ands pedestrian plaza. 06/25/18 07/02/18 1938 28 0.140 DCE No Funding \ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund St ads oc State Funds Local Funds Total Funds P CN 2021 STP(E) 891140 \ 0 139,860 1,036,000 Totals 896,140 0 139,860 1,036,000 Expenditure Schedule \\ Phase 1st 2nd 3rd ''4th \ IP .7 \ 5th&6' CN 0 0 1,036,000 0 \\\\\\\\h.. Totals 0 0 1,036,000\ 0 Report Date: May 21, 2019 Page 11 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini F. Project Description \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17 N\ \ \4 10 Macadam Rd S Complete Streets Project Macadam Road \\\\\ S 150th Street to S 144th Street '' \ \\ Design and construction of a complete street on Macadam Road. Road widening A\\\\\ and rechannelization to add 5-foot bike lanes and 5-foot sidewalks on both sides of the roadway. Includes illumination, curb, and storm drainage. 06/25/18 07/02/18 1938 04 0.350 DCE No Funding \ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund\W St a oc State Funds Local Funds Total Funds P PE 2019 ' 0 Ped ��e��,N,�- --,..� � \�\\\\\\\O 397,369 0 397,369 P RW 2019 0 Ped, Program \\ 100,000 0 100,000 P CN 2020 0 PeWie Program j �' \\\272,947 460,000 2,732,947 Totals 0 \\ \\\\\\\ 0 316 460,000 3,230,316 Expenditure Schedule \\\ Phase 1st 2nd 3rd 4th \\\ h & 6th JJtN- PE 397,369 0 0 \0 \ 0 RW 100,000 0 0 \ 0 CN 0 2,732,947 0 0 \, Totals 497,369 2,732,947 0 0 \ 0 Report Date: May 21, 2019 Page 12 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number \\\\ A. PINIProject No. B. STIP ID C. Project Title \ D. Road Name or Number E. Begin End Termini \ F. Project Description \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 00\ 783 Multipurpose Trails to \ Wide array of necessary trail improvements to existing trail system infrastructure \ 06/25/18 \\ 07/02/18 1938 28 CE No Funding \ " \\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federn�nds ,, , We Fund Cod State Funds Local Funds Total Funds P ALL 2024 -13' 0 150,000 150,000 Totals \ 0 ' \ 0 150,000 150,000 Expenditure Schedule \ ,,,,,,,--N. ,, _ Phase 1st 2nd 3rdth 5tfi ALL 0 0 0 '\,. OL IP 50,000 Totals 0 0 0\\\ 0 \\\\\\� 150 WO Report Date: May 21, 2019 Page 13 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number F. BeginEnd Termini \ F. Project Description\ \ �� ure ID = 2 � Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14\ 73 S 140th St Intersection Improvements \\\\ S 140th Street . \\\ Tukwila International Blvd to Design and construct a new traffic signal at the S 140th Street/Tukwila International Blvd intersection 06/25/18 07/02/18 1938 04 C G P S T W 0.100 DCE Yes Funding \\\\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds\J St ono J I Code State Funds Local Funds Total Funds P PE 2021 0 Ped 1 a ,�"�. ��� �o \ \ppp�� 67,000 8,000 75,000 P RW 2021 0 Pe Program p\` \\\\,\\\\\\\\\\ 40,000 o �p 10,000 50,000 P CN 2022 0 Pe eProgram, �, \\\\\\\ �pppp�\\\\\\\\568,000 57,000 625,000 Totals 0 \\ ,, \ I5,000 75,000 750,000 Expenditure Schedule \\,. Phase 1st 2nd 3rd 4th\\\\ \h & 6th PE 0 0 75,000 \\\\\Q \I\\Io RW 0 0 50,000 �\\\\\O\`0 \� \ \ \\ 0 CN 0 0 0 625,00' \ f 0 Totals 0 0 125,000 625,000 \\���' \N 0 Report Date: May 21, 2019 Page 14 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number F. BeginEnd Termini \ F. Project Description \ �� mature ID = 2 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17 , 78 S 144th St Bridge Sidewalks S 144th Street 51 st Ave S to 53rd Ave S \ \ Widen existing sidewalks on bridge over 1-5 between 51st Ave S and 53rd Ave S \ 06/25/18 \\ 07/02/18 1938 28 0.250 No Funding \ " \\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federn�nds ,O , ' Cod -',-‘es State Funds Local Funds Total Funds P PE 2019 SRTS 1� ������Fund _ AVVV\� 0 27,000 200,000 P CN 2019 SRTS 1 ,000 \ 0 163,000 1,210,000 Totals 1,220 000 \ \ \��\\ 0 190,000 1,410,000 Expenditure Schedule Phase 1st 2nd 3rd 4th 0 p 5th &4. PE 200,000 0 0 \ 0 \\\\Q\\\\\\\\ O 0 CN 0 1,210,000 0\ 0 Totals 200 000 1,210,000 0 \\\\ 0\ \\,1 Report Date: May 21, 2019 Page 15 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number \\\\ Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required A. PINIProject No. B. STIP ID C. Project Title \ D. Road Name or Number \\ F. BeginEnd Termini \ \Ei = (D\\\ F. Project Description \ \ mature ID 17\\\ \ 414 06/25/18 07/02/18 1938 05 0.100 DCE No S 144th Street Bridge Sidewalks S 144th Street \\\\\ \ 51st Avenue S to 53rd Avenue S '\\ \\ Design of pedestrian improvements to the S 144th Street Bridge over 1-5 to include \\\\\\ widening the existing 3-foot sidewalks to 6-feet with a barrier to separate vehicles and pedestrians Funding \\ \�\ \\\\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund St a oc State Funds Local Funds Total Funds P PE 2019 0 PedW�- .� \�\\\\\\\O 416,000 27,000 443,000 Totals 0 \\\\\\\\ j \\� 416,000 27,000 443,000 Expenditure Schedule \\\ Phase 1st 2nd 3rd ''4th \ \\P "' \ 5th & 6 PE 443,000 0 0 0 \\\\\\\\\\\\\\\ Totals 443,000 0 0\ 0 Report Date: May 21, 2019 Page 16 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini \ F. Project Description \ \ mature ID = Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 19\112 S 152nd Street Safe Routes to School S 152nd Street \\\\\ Tukwila International Blvd to 42nd Avenue S '' \ \\ Design and construct curb, gutter and sidewalks on both sides including widening pavement width by 3 feet to construct on -street parkinglane on north side of street. 06/25/18 07/02/18 1938 05 0.300 No Funding \\ \\ Status Phase Phase Start Year (YYYY) Federal Fund Code FederaiPunds �` �-a and Cod State Funds Local Funds Total Funds P PE 2019 0 243,000 0 243,000 P CN 2020 0 ' '- \ \ 2,583,356 0 2,583,356 Totals 0 ����o \\\\\\`\ \\\ �� \\\\\\\ 2,826,356 0 2,826,356 Expenditure Schedule \ \\\\\ \\ Phase 1st 2nd 3rd 4th \ 5th & 6tt PE 243,000 0 0 b 0 �� I CN 0 2,583,356 0��� 0\ Totals 243,000 2,583,356 0 \\ J 0 Report Date: May 21, 2019 Page 17 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. C. Project Title D. Road Name or Number E. Begin &End Termini \ F. Project Description \ \ B. STIP ID mature ID = Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 16 1276(007)\ Strander Blvd./SW 27th St Extension Strander Blvd./SW 27th St Extension West Valley Highway to Naches Ave \\ This project is Phase 3 of a multi -phase improvement that will connect Strander Blvd./SW 27th St between West Valley Hwy in Tukwila and Oakesdale Ave in Renton. This project will complete the design, right-of-way and construction phases for the roadway segment between West Valley Hwy and Naches Ave. Project components include a railroad bridge for the Union Pacific RR to provide grade separation, a new 4/5 lane roadway segment east of West Valley Hwy, roadway widening of two lanes fora portion of the project segment, a separated joint -use trail, a new trail bridge for the Interurban Trail (including new trail connections to Strander Blvd.), a new flyover bridge connection to the Tukwila Station, a new traffic signal serving the Tukwila Station, and storm drainage facilities. Current funding will complete the preliminary engineering and right of way phases. Construction will be funded as part of a future phase. \ \ \\\ V� 59 -. \\ -� N 01 0.300 DCE Yes Funding \ \\\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds State F� ode 'ate Funds Local Funds Total Funds S RW 2019 STP(UL) 1,254,250 195,750 1,450,000 Totals 1,254,250 195,750 1,450,000 Expenditure Schedule Phase 1st 2nd 3rd 4th &6th \\ ALL Totals Report Date: May 21, 2019 1,450,000 1,450,000 0 0 0 0 0 0 \� 0 1 Page 18 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID C. Project Title D. Road Name or Number E. Begin & End Termini \ F. Project Description \ mature ID = (D\ 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 17\ 772 TUC/TOD Pedestrian Improvements Baker Blvd (if extended) \\\\\ Andover Park W to E City Limits Construct bike/pedestrian connection between the Tukwila Urban Center (TUC) and Tukwila Station, with service by Amtrak Sounder Commuter Rail/Transit Oriented Development (TOD) area. N, 06/25/18 \\ 07/02/18 1938 28 0.750 CE Yes Funding \ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fund St a oc State Funds Local Funds Total Funds P ALL 2023 STP(E) 3,41i7000 \ 0 850,000 4,250,000 Totals 3,400,000 j \ � 0 850,000 4,250,000 Expenditure Schedule Phase 1st 2nd 3rd ''4th \ IP N 5th&6 ALL 0 0 0 0 \\\\Q\\\\\\\\ 4,270$ Totals 0 0 0\ 0 4_\ Report Date: May 21, 2019 Page 19 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID D. Project Title D. Road Name or Number F. PEnd Termini \ F. Project Description \ mature ID = 2 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14\ 418 Tukwila International Boulevard Retrofit \ Tukwila International Blvd\\ \ Southcenter Blvd to S 116th Way Design and planning of retrofit to Tukwila International Blvd to implement complete streets, improve pedestrian and vehicular safety, and reduce regional pass -through traffic. 06/25/18 07/02/18 1938 15 C G O P S T W 2.400 No Funding -N \„�\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun' . Sta „��� rotate Funds Local Funds Total Funds P PE 2019 0 1 o���,,. 0 100,000 100,000 Totals 0 \\ Q\\\\\\\\ 0 100,000 100,000 Expenditure Schedule\ \\ \�\ Phase 1st 2nd 3rd 4th\ \\\\\\\\\\\\\ 5th & 6th PE 100,000 0 0 0 Totals 100,000 0 0 \\ 0\1 Report Date: May 21, 2019 Page 20 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. D. Project Title D. Road Name or Number E. Begin &End Termini F. Project Description \ \ B. STIP ID mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14\ West Valley Highway SR 181/West Valley Highway 1-405 to Strander Blvd Design and construct completion of 7 lane sections of West Valley Highway with sidewalks, curbs, gutters, storm drainage, lighting, and traffic control, including safety and capacity improvements at the S 156th St intersection. \ 779 \\ 06/25/18 07/02/18 1938 03 C G O P S TW 0.500 CE No Funding .--N��\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Fun' . Sta ,,�,�� �tate Funds Local Funds Total Funds S PE 2019 0 IB 280,820 37,180 318,000 S CN 2020 0 \tIB j\ \, 1,872,740 679,161 2,551,901 Totals 0\ \ - \\\\\\\\53,560 716,341 2,869,901 Expenditure Schedule \ \\ Phase 1st 2nd 3rd 4th\\th & 6th \ \I PE 318,000 0 0 \\ 0 \.. CN 0 2,551,901 0 �\ Totals 318,000 2,551,901 0 \��, 0 Report Date: May 21, 2019 Page 21 tat Agency: Tukwila County: King MPOIRTPO: PSRC Six Year Transportation Improvement Program From 2019 to 2024 N Outside Functional Class Priority Number A. PINIProject No. B. STIP ID D. Project Title D. Road Name or Number F. PEnd Termini F. Project Descnption \ mature ID = 0 Adopted Amendment Resolution No. Improvement Type Utility Codes Total Length Environmental Type RW Required 14\ 60 West Valley Highway/Longacres Way Shared Use Pathways SR 181 &Longacres Way W end of planned Green River Bridge to Longacres Way A Improvements will be completed on SR 181 from the west end of the planned Green River non -motorized Bridge to Longacres Way, including a 12-14 ft. separated shared use path with a 5 ft. landscaped buffer strip on the west side of the highway. \ Design -only will be completed for future improvements on Longacres Way between SR 181 to the Tukwila Sound Transit Link Station. \\ \\\\ . 28 0.170 DCE No Funding \\ . \\ Status Phase Phase Start Year (YYYY) Federal Fund Code Federal Funds Sta ie 4 to Funds Local Funds Total Funds S PE 2019 CMAQ 186,840��� \� 0 29,160 216,000 S CN 2019 CMAQ 441,063 \ \\\\\\Q\\ o \\\\\\ 0 68,836 509,899 Totals 627,903 \A 0 97,996 725,899 Expenditure Schedule \\ Phase 1st 2nd 3rd 4th nth & 6th \\1 ALL 725,899 0 0��X \ \A0 Totals 725,899 0 0 \ 0 Federal Funds Funds \\ a Fun Total Funds Grand Totals for Tukwila Report Date: May 21, 2019 22,879,293 13,65 2 3" 6 moo 69,042,411 Page 22