HomeMy WebLinkAbout2019-06-10 Committee of the Whole MinutesTukwila City Council Committee of the Whole Meeting
City Hall Council Chambers June 10, 2019 — 7:00 P.M.
MINUTES
COMMITTEE OF THE WHOLE
CALL TO ORDER/PLEDGE OF ALLEGIANCE
Council President Hougardy called the Tukwila City Council meeting to order at 7:00 p.m. and led the
audience in the Pledge of Allegiance.
OFFICIALS
Present were Council President Hougardy; Councilmembers Dennis Robertson, Verna Seal,
De'Sean Quinn, Kate Kruller, Thomas McLeod, Zak Idan.
CITY OFFICIALS
Allan Ekberg, Mayor; David Cline, City Administrator; Rachel Bianchi, Deputy City Administrator;
Bruce Linton, Police Chief; Jay Wittwer, Fire Chief; Vicky Carlsen, Finance Director; Jack Pace,
Community Development Director; Henry Hash, Public Works Director; Hari Ponnekanti, Deputy Public
Works Director/City Engineer; Cyndy Knighton, Senior Program Manager; Lynn Miranda, Senior Planner;
Jeff Friend, Fiscal Manager; Barbara Saxton, Administrative Support Coordinator, City Clerk's Office.
SPECIAL PRESENTATIONS
Update from David Foster, Lobbyist.
Rachel Bianchi, Deputy City Administrator, introduced David Foster, the City's contract lobbyist for state
lobbying.
Mr. Foster utilized a PowerPoint presentation to provide an update with highlights from the 2019
Washington State Legislative session. Mr. Foster noted he previously provided Councilmembers with
an end -of -session report. Democrats were in control of the House and Senate this year. The 105-day
session ended on time. This was a year of budgeting for the next biennium starting July 1, 2019, for the
capital budget and for transportation.
City priorities
• Sales tax mitigation (aka funding for manufacturing and warehousing cities): This was fully funded in
the two-year operating budget. Mr. Foster acknowledged efforts by Mayor Ekberg and Representative
Pat Sullivan, who represents the Kent -Auburn -Covington area, on this issue.
• SCORE (South Correction Entity): There will be a daily rate increase.
• The number of Basic Law Enforcement Academy classes will increase from 10 to 19.
Capital Budget projects
Housing Trust Fund $175,000,000 (this is a statewide number).
Potential funding opportunities in the 2020-2021 session.
Early Learning Facilities (School District) $196,000
Health Point $1,000,000
Starfire Sports STEM $250,000
Tukwila Village Food Hall $400,000
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 2 of 12
South 116th Street at $260,000
Green-Duwamish River in the WWRP
Chinook Wind Public Access in the $157,000
Aquatic Lands Enhancement Account
Transportation Budget
• No funding for either Strander Boulevard or the Allentown Bridge. No new funds going into the
operating budget for transportation funding.
• A pilot project has been put forth related to the use of automated vehicle noise enforcement cameras
in areas that have been designated by ordinance as "Stay Out of Areas of Racing."
• A bill authorizing tolling on 1-405 from Tukwila to Lynnwood, as well as SR167 and SR509, was signed
into law.
Policy Bills
• Cities and counties may use a credit against the state sales tax to help build affordable or supportive
housing. This will potentially increase the amount of money going into homelessness and housing
efforts.
• Seniors and veterans property tax exemption, with the income threshold raised to reflect county
median income.
• Sales tax mitigation: Bills that would have created a manufacturing and warehousing job centers
account to help mitigate losses through 2030 did not pass. Efforts will continue on this issue.
• Bill that would have allowed the property tax to be increased based on population change and inflation
did not pass.
A new Speaker of the House will be elected in July. The 2020 legislative session will run January 13
through March 12, and is a 60-day supplemental session.
Mr. Foster stated they expect to see many of the same issue areas in 2020 as in 2019, including
education funding, mental and behavioral health funding, and transportation. Funding in the
transportation budget is more likely to occur in 2021.
Councilmember Robertson asked if public disclosure was a hot issue for the legislature. Mr. Foster noted
it is a hot issue in the media. The legislature is trying to find balance to allow the legislature to do its job
without releasing all information in advance of a decision, while also letting the public know what is going
on.
Mr. Foster noted that since this will be a short session, there may be issues that would best be put forth
collectively in partnership with the Association of Washington Cities (AWC) and similar organizations.
PUBLIC COMMENTS
Joe Duffie, 5332 South 140th Street, expressed appreciation for the two speed bumps that were installed
on 53rd Avenue South. He asked about the spacing of the bumps on 53rd, as there were four speed
bumps installed on 160th. He also asked if the City was responsible for any accidents caused by a speed
bump. Mr. Duffie noted there was a bicycle training event at a Tukwila park over the weekend, and he
expressed concern about cars backing up in the same area. He also noted there was a large crowd at
the park on Saturday and the group had music playing very loudly.
PUBLIC HEARING
a. A resolution adopting the 2020-2025 Six -Year Transportation Improvement Program.
7:23 p.m. Council President Hougardy opened the public hearing.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 3 of 12
Cyndy Knighton, Senior Program Manager, provided an overview of this item. The State requires that
all cities adopt a Six -Year Transportation Improvement Program (TIP) every year by July 1. This year's
TIP is for 2020-2025. All projects in the TIP are transportation related and developed in concert with the
City's Capital Improvement Program (CIP). Ms. Knighton noted that once the TIP is adopted, it can be
modified.
Page 15 in the agenda packet lists several projects that have been removed from the current TIP:
• The West Valley Highway/Longacres Way Shared Use Pathways project has been merged into the
larger West Valley Highway project.
• The 40-42nd Avenue South Phase III and 53rd Avenue South projects have been completed.
• Three projects were deleted as they are projected to move beyond the current 6-year time frame:
TUC/TOD Pedestrian Improvements, Tukwila International Boulevard Retrofit, and Multipurpose Trails.
In response to questions from Councilmembers relating to the Strander Boulevard/SW 27th Street project
listed in the draft TIP, Ms. Knighton stated the total shown (approximately $80 million) is for the full project
as it currently exists in the CIP—before any decisions are made relating to proposed options for this
project. The costs are broken down as $3,720,000 in 2020, $38,389,000 in 2021, and $37,889,000 in
2022.
7:30 p.m. Council President Hougardy called for public comments.
There were no public comments.
7:31 p.m. Council President Hougardy closed the public hearing.
b. An ordinance to clarify the types of multi -family dwellings permitted in the Tukwila South
Overlay Zone.
7:31 p.m. Council President Hougardy opened the public hearing.
Lynn Miranda, Senior Planner, explained the ordinance would amend Table 18-6, "Land Uses Allowed by
District," in the City's zoning code to clarify the types of multi -family dwellings permitted in the Tukwila
South Overlay District.
The area affected covers approximately 400 acres: South180th Street on the north to 204th Street on the
south, and from the City limits at 1-5 on the west to the Green River on the east. The underlying zoning
includes Heavy Industrial, Mixed -Use Office, Low Density Residential, and Tukwila Valley South. The
Tukwila South Overlay (TSO) covers the entire area and supersedes the underlying zoning.
A Master Plan prepared by Segale Properties in 2009 was adopted along with a Development Agreement
between the City and Segale, which called for new development in a combination of campus style office
and research environments with a mix of other supporting uses. A wide variety of low- to high-rise multi-
family dwelling types were anticipated in the Plan, including a mix of townhouses and flats above retail
uses.
As shown in Table 18-6 (page 70 of the agenda packet), current zoning standards allow various types of
multi -family units, senior housing and assisted living facilities in the TSO zone after a Residential Design
Manual is adopted by ordinance. Segale Properties recently indicated an interest in developing
townhouses in the TSO zone. To ensure consistency between envisioned uses in the Master Plan, an
amendment to Table 18-6 will clarify that townhouses, duplexes, triplexes and fourplexes are allowed in
the TSO zone after a Residential Design Manual is adopted, which is consistent with current
requirements for other forms of multi -family housing in the TSO zone. The draft Residential Design
Manual will come before the Council at a later date.
Councilmember Idan asked whether this would affect any property owners other than Segale Properties.
Ms. Miranda stated that Clarion also owns some property in that area.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 4 of 12
Councilmember Kruller asked whether this amendment will change the infrastructure already put in place.
Ms. Miranda responded no.
7:37 p.m. Council President Hougardy called for public comments.
Mike Pruett of Segale Properties stated he was available to answer any questions. Councilmember
Quinn asked that he confirm the information presented by staff this evening is consistent with his
understanding, and he responded in the affirmative.
7:40 p.m. Council President Hougardy closed the public hearing.
SPECIAL ISSUES
a. A resolution adopting the 2020-2025 Six -Year Transportation Improvement Program.
Councilmember Idan stated that Councilmember Kruller sat in as Chair at the Transportation and
Infrastructure Committee meeting on June 4, 2019. Ms. Kruller indicated the committee members
forwarded this item with unanimous approval.
COUNCIL CONSENSUS EXISTED TO FORWARD THIS ITEM TO THE NEXT REGULAR MEETING.
b. An ordinance to clarify the types of multi -family dwellings permitted in the Tukwila South
Overlay Zone.
Councilmember Quinn indicated this item was discussed at the Community Development and
Neighborhoods Committee meeting on April 23, 2019, and May 14, 2019. The item was added to those
agendas under "Miscellaneous," at which time the Committee approved staff's request to forward the item
to the Planning Commission.
COUNCIL CONSENSUS EXISTED TO FORWARD THIS ITEM TO THE NEXT REGULAR MEETING.
c. An ordinance extending the non-exclusive Franchise Agreement with Astound Broadband,
LLC (dba Wave Broadband), for one year.
Councilmember Idan stated that Councilmember Kruller sat in as Chair at the Transportation and
Infrastructure Committee meeting on June 4, 2019. She indicated the committee members forwarded
this item with unanimous approval.
Cyndy Knighton, Senior Program Manager, stated the ordinance would extend the City's existing
franchise agreement with Astound Broadband, LLC (dba Wave), which has been in existence for almost
5 years and will expire in August. The agreement contains a clause that allows for a one time, one-year
extension to allow time for negotiation of a new agreement.
COUNCIL CONSENSUS EXISTED TO FORWARD THIS ITEM TO THE NEXT REGULAR MEETING.
d. Consensus on Strander Boulevard Extension Project.
Councilmember Idan stated that Councilmember Kruller sat in as Chair at the Transportation and
Infrastructure Committee meeting on June 4, 2019. She indicated two Committee members moved the
item forward with a recommendation, and one member had no recommendation at that time.
Henry Hash, Public Works Director, stated it has taken the City a great deal of effort to get to where we
are today. Conversation on the Strander Boulevard Extension started in the 1980s. The City of Renton
had the lead at that time and completed Phases 1 and 2 of the project. The City of Tukwila is the lead on
Phase 3. The purpose of the project is to meet growth management concurrency standards, and to move
22,500 vehicles per day off of South 180th Street, Grady Way and 1-405. The project would complete the
last 1,500 feet of an east -west connection by constructing a safe crossing of a key regional railroad line.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 5 of 12
Over the last year the City has started work on the design process as part of the preliminary engineering
phase for a four -lane configuration. Due to the increased complexity of the project and projected
increased estimates, WSDOT (Washington State Department of Transportation) and the Transportation
Improvement Board (TIB) recommended that a Value Engineering Study (VE) be performed for the
project to either find cost savings that could be incorporated into the design or validate the current design
as the most cost-efficient option. Design was stopped at 30% in order to conduct the VE Study.
BergerABAM (now part of WSP) was selected as the City's consultant. Project stakeholders —the State
legislature and funding authorities at the state, as well as the City of Renton —have expressed continued
support for the project. Staff is seeking consensus from the Council on the preferred option for moving
forward.
Bob Fernandez of WSP utilized a PowerPoint presentation to present the three project options identified
for consideration.
Project Purpose and Need — Quality of Life
• Improves freight mobility in the Green River Valley
• Reduces traffic congestion for commuters
• Improves connectivity to large employment centers
• Improves access to a regional urban center
• Reduces air and noise pollution
Project Purpose and Need — Accommodates Growth
• Facilitates the City's ability to meet growth management concurrency standards
• Moves 22,500 vehicles per day, including 1,800 trucks, off existing South 180th Street, Grady Way and
1-405
• Provides Level of Service (LOS) "E" on South 180th Street and Grady Way
• Provides $65M in travel time economic benefits (2022 to 2052)
Project Background
Mr. Fernandez showed a map of the current 4-lane layout (page 106 of the agenda packet) in which the
colors depict the three project phases:
Orange City of Renton, Phase 1
Red City of Renton, Phase 2
Blue City of Tukwila, Page 3
Challenges
• Utility conflicts: Pipelines, PSE utility, water, sanitary sewer, and telecommunications.
• Groundwater management: Proposal is to separate the groundwater from the storm water. If the
underpass was made watertight, there would be very little groundwater beyond a continual flow that
would be routed to the Green River along with any pond overflow. This would be a pipeline project and
require some pump station modifications. Sludge can occur when groundwater is exposed to oxygen;
making the underpass watertight will help alleviate future long-term maintenance issues.
In response to questions from Councilmember Robertson, Mr. Fernandez explained that stormwater is
run-off from the roadway, which is treated and discharged to the river. Groundwater is naturally occurring
and never touches the roadway surface. With a cut in the ground to build the underpass, groundwater
comes in through cuts and from below if walls are not built. The water needs to be collected in a separate
system so that it is not co -mingled with stormwater. As groundwater comes in, it is never exposed such
that it would be heated up; it is transferred through a pipe and would only mix with stormwater at the end
of the pipe where it empties into the river.
7:56 p.m. Councilmember Kruller left the Council Chambers
A cross-section from the proposed design is depicted on page 110 of the agenda packet.
The ground would be improved to create a watertight seal on the bottom and walls would be built on the
sides to limit the amount of groundwater coming in. The underpass on South 180th Street is an example
of a similar watertight structure.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019
Page 6 of 12
The underpass for the Strander Boulevard project is currently partially sealed (as part of Phase 2). There
is a naturally occurring condition whereby the layer of soil is fairly impermeable to the water coming up
from the bottom. There has been a little more water than anticipated from the ground and the side slope,
which is heavily lined with rock to prevent sliding. In this situation, the groundwater and stormwater mix in
the pond and overflow into the wetland.
8:00 p.m. Councilmember Kruller returned to the Council Chambers.
Current project funding status
The chart below (page 114 of the agenda packet) shows a considerable shortfall between the
$17,646,000 in potential funding and the $83,781,626 total estimated costs for Phase 3.
Current Project Funding Status
NNSI
PHASET;FUNDING PE ROW CONSTRUCTION TOTAL NOTES
City of Tukwila
PSRC (STPUL)
FASTLANE
State Funding
FMSIB
TIB
State Legislative Funding
City of Renton
Additional City of Tukwila
Additional PSRC (STP)
Sound Transit
Port of Seattle
UPRR
BNSF
Other Federal Grants (BUILD)
Subtotal
Phase 3 Costs
Stronder Boulevard Extension
$607,500
53,892,500
$4,500,000
$4,500,000
5195,750
$1,254,250
5270,166
$1,720,166
$1,720,166
$1,196,750
S-
55,000,000
5229,834
$5,000,000
5-
5-
5-
5-
5-
5-
5-
5-
5-
5-
$10,229,834
$77,561,460
S2,000,000
S5,146,750
S5,000,000
5500,000
S5,000,000
5-
$-
5-
5-
5-
5-
5-
5-
5-
5-
$17,646,000
$83,781,626
Secured
Secured (obligate ROW by 11/19)
Secured (Award Const. by 11/19)
Secured
Secured
Current Estimate for Phase 3
In response to a question from Councilmember Robertson, Mr. Fernandez stated that WSP is very
confident in the estimated project cost. Contractors were consulted to review the project and estimates.
Cost escalation and contingencies have been built in. He explained that because this is a complicated
project, the number of qualified contractors is limited and bids would depend on what other projects are
happening at the same time.
The most expensive components of the project are the walls and seal (pie chart on page 116 of the
agenda packet). There would also be costs associated with a considerable amount of temporary
construction that is required on a project like this that does not get incorporated into the final project.
The Value Engineering Study includes numerous proposals that have been analyzed by WSP for:
(1) potential risk factors; (2) to determine which potential concepts cannot be combined as some are
mutually exclusive; and (3) to incorporate the best ideas. The Council expressed interest in receiving a
copy of the VE Study and/or the consultant's draft response to the report.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019
Page 7 of 12
Recommendations
Option 1 Continue with the current design of a 4-lane road. $5 to $10 million potential cost savings
identified by VE Study.
Option 2: Incorporate value engineering proposals of a 2-lane road with no seal, if possible, and
continue design. This option would eliminate walls on one side of the structure.
$10 to $25 million potential cost savings identified. Option 2 is the recommendation of
City Administration.
Option 3. Stop work. Return grant funding and reimburse federal funds spent to date.
Possible funding scenario (page 124 of the agenda packet)
Phase 3 Funding
PE ROW ConsbucIon Total Nobs
SECURED
City of Tukwaa $607,500 S195,750 S1,196,750 $2,000,000 Secured
State Funding S276,166 S223,834 5500,000 Secured
STP(PSRC) S3,892,500 53,892,500 Secured
1) TRY TIME EXTENSION Try Extension or
2) RETURN & REAPPLY Retum & Reapply
FASTLANE 55,000,000 S5,000,000 Retum and reapply
FMSIB $5,000,000 $5,000,000 Return and reappy
STP (PSRC) $1 254,250 SO 51,254,250 Retum and reappy
POTENTIAL FUNDING SOURCES
State Legislative Funding
Transportation knpv Board
Additional PSRC (STP)
Sound Transit
S20.000,000
S7,000,000
S5.000.000
S5,000,000
S20,000,000 Potential
57,000,000 Potential
S5,000,000 Potential
S5,000,000 Potential
OTHER FUNDING SOURCES
City of Renton 54,000 S4,000,000 Possible
Additional City of Tukwi: $4,000,0ui; $4,000,000 Possible
UPRR SO SO
BNSF SO SO
BUILD Grant (formerly 11GLFr) So S0
Potential Funding 54,500,000 S1.726.166 S56,420,584 S62.646.750
Phase 3 Costs
54.500,000
S1.720.166
S55,000,000
S61.220,166
2-Lane concept Cost
Green section Existing secured funds
Red section Existing grants to be returned and reapplied for later (if the project is not ready to go to
construction by the required time)
Other sections Options for a reasonable way to do a $60 million project —versus $80 million
Third party impacts with Option 2 include pumping more groundwater, with potential for the ground to
subside around the project. That possibility will require additional study. Having the potential for more
water can be complicated on a project with federal funding and the right-of-way process. They would
need to verify the traffic benefits, and check in with permitting and regulatory agencies as it relates to the
amount of naturally -occurring groundwater. There are risks with Option 2 that need to be investigated.
Tukwila City Council Committee of the Whole Minutes
June 10,2019 Page8of12
The Councilmembers asked the following clarifying questions:
• By going with Option 2, does that imply we would go back later and add the two lanes and seal?
Mr. Fernandez stated that is possible; however, there is no cost estimate at this time. He indicated the
work would be more expensive later due to escalation, having to remobilize the construction activity,
and working in a more constrained site. It would also require determining what would have to be built
now because it could not be built later.
• What would be the differences and impacts associated with Option 2? Mr. Fernandez explained that if
Option 2 is built, the goal is to eliminate some walls and the seal. In order for traffic to work on West
Valley Highway, and to provide access for property owners, Phase 4 (at the west end of the project)
would likely have to be built much as it is now to accommodate businesses. Federal requirements for
the project would still need to be met, i.e. some or all of the items listed under "Project Purpose and
Need — Accommodates Growth" on page 5. Additional review with a traffic consultant will be needed
to make these determinations and get a cost estimate.
• Is there a possibility of getting an extension for the use of the grant funds? Mr. Hash stated the City
will be asking for an extension on use of the funding from both FMSIB and FASTLANE (approximately
$5 million each). He explained that both of these funding sources will go away if construction does not
start by the beginning of next year. An extension until September 2020, for example, would still not
allow enough time; the City would need at least a 3-year extension period for design, permitting,
regulatory issues and the right-of-way process.
• Would there be costs associated with Option 3, i.e stopping the project when some money has already
been spent, and there was an agreement with the City Renton? Mr. Hash stated that the two $5
million funding sources are "on paper" at this time. The $5.1 million received from the Puget Sound
Regional Council (PSRC) is what is currently being spent—$3.8 million for design and $1.2 million for
right-of-way. If work on the project is stopped, the funds spent to date (approximately $2 million)
would need to be returned. If the money is used to complete design work (for Option 1 or 2), the City
would have 10 years to complete construction.
• How much time do we have to make this decision? Mr. Hash stated that while a decision is not
needed tonight, if the City does decide to relinquish the money, it is best to do so before it expires
to maintain credibility with the funding agency. Another stipulation is that if the project is inactive for
6 months, the City would need to return the money. Mr. Fernandez of WSP stated that he has
experience with agencies who returned funding to the Transportation Improvement Board and they
were able to receive it again later.
• Would the 2-lane option suffice for this project? Mr. Fernandez stated that the reality is that traffic
movements such as merging have to work at intersections —whether it is the 2-lane or 4-lane option.
If the 2-lane option is preferred at this time, additional work and traffic analysis will be needed to
determine the answer. Mr. Fernandez stated that estimates for building projects are somewhat
different than for transportation projects, and WSP is confident in the numbers provided. If work was
stopped today, discussions with potential funding agencies would continue. The design work to date
would not be a waste, and would be in line for the original 4-lane project.
• Why is City Administration recommending Option 2? Mayor Ekberg stated the City's goal 4 to 5 years
ago with the TIGER and/or FASTLANE grants was to get a shovel -ready project together to have a
higher probability of receiving funds for development. Option 2 provides a road forward to get to a
shovel -ready project and allow the City to ask for federal, state and/or county funding. David Cline,
City Administrator, stated requests for federal funds have not been successful. The proposal here is to
shift the focus to be part of the next transportation package at the state level for funding as a regional
transportation project. The project is still 2 to 2-1/2 years away from the construction stage, so the
timing may align with Mr. Foster's comments earlier that any state transportation funding packages
may be several years away.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 9 of 12
Mr. Hash explained that the discussion tonight was to provide an update on the Value Engineering Study.
The purpose of the VE Study was two -fold: Validate that the consultant's work to date is doable (yes),
and determine whether there are any savings options (yes, Option 2). For Option 2, the City has the
money in place to complete design to get to a shovel -ready project. Under Option 3, the City would need
to return approximately $2 million that has already been spent to date. The $10 million from FMSIB and
FASTLANE is designated for construction costs.
The Councilmembers provided additional input on the three options:
Councilmember Robertson stated Option 1 comes with a high cost ($83 million) based on the original
design. Money already secured toward the project must be spent within a limited time period. Option 2
reduces the lanes to two, with an unsealed road, which does not meet the original goals. Option 2 also
would not provide the anticipated $65M in travel time economic benefits (2022 to 2052), which was
expected to demonstrate national economic benefits under the federal funding guidelines. There are
design and engineering questions, and expansion will likely be desired in the future. Funding issues
include the City needing to contribute $6 million, and Renton $4 million. The City would need an
extension or reapplication of grant funds already in place, plus an additional $37 million. City staff will
already be facing challenges with work for the Public Safety Plan over the next couple of years. He thinks
stopping the project and returning the $2 million in grant fund is a reasonable choice.
Councilmember Seal shares the concerns expressed by other Councilmembers. She understands the
process associated with TIGER grants (Transportation Investment Generating Economic Recovery
grants) from meetings in Washington DC. The City is also facing cost impacts related to the Public Safety
Plan bond, and potential escalation costs are alarming. She acknowledged she has advocated to take
this project to a shovel -ready stage in the past, but is now hesitant to have the added costs potentially
impact services to citizens. She appreciates the hard work done to date on the 30% design work, and
continuing would impose a lot of work for staff on reapplying and looking for funding. She feels Option 3
is the correct decision at this time.
Councilmember Quinn stated the $41 million deficit to fund Option 1 is an unanswered question, with the
most likely scenario being some type of grant. Option 2 brings less clear benefits that may affect funding
possibilities. He does not see this project fitting into the City's Six -Year Capital Improvement Program.
Councilmember Kruller noted the City has come close to receiving funds through the Transportation
Policy Board, and those grant applications have been predicated on the City's good reputation of finishing
projects that we had started. She indicated the National League of Cities has indicated it could potentially
be an issue if funds were returned. She stated smaller cities need to work harder to secure funds, and
she is starting to question the repercussions of returning funds for small cities. She suggested involving
Sound Cities in similar situations going forward as small cities cannot absorb the full impacts of a regional
project. She appreciates the honest answers to the Council's questions today.
Councilmember McLeod served as Chair of the Transportation and Infrastructure Committee last year,
which requested the VE Study. He does not feel the City is in a position to take this project on at this
time, which leads him to Option 3 (stopping work).
Councilmember Idan stated he appreciates the thoughtful presentation today. He feels Option 2 does not
meet all the goals of the original project, and leans toward Option 3.
Council President Hougardy confirmed that $2 million is the actual money already spent, which will need
to be repaid to PSRC. The Council's preferred direction seems very clear.
COUNCIL CONSENSUS EXISTED FOR OPTION 3: STOP WORK, AND RETURN THE GRANT
FUNDING AND REIMBURSE FEDERAL FUNDS SPENT TO DATE.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 10 of 12
e. 2018 4th Quarter financial report.
Councilmember McLeod indicated this item was discussed at the Finance Committee meeting on
May 28, 2019.
Vicky Carlsen, Finance Director, presented a summary of the 2018 year-end report.
Three takeaways from the General Fund are:
• Total General Fund revenues of $64 million exceeded total General Fund expenditures.
• All General Fund departments finished under budget.
• The City's reserve policy was met.
Ms. Carlsen noted that while all departments came in below budget, the savings is considered one-time
due to vacant positions.
Sales tax, which is the City's largest revenue stream, increased $1.8 million over 2017.
Property tax revenue ended the year up, with increases primarily due to new construction.
Other General Fund revenues include:
• Utility taxes were below budget. The City has been seeing a decline in the telephone tax, with trends
showing many land lines are being dropped. Data packages are also changing to unlimited vs. a set
amount of minutes.
• lnterfund utility tax was over budget primarily due to increases in funds.
• Gambling tax was a little below budget. One casino was temporarily shut down in the summer of
2018.
• Admissions tax showed an increase from 2017; one new business in the Commercial Business District
has been doing very well.
• Business licensing showed an increase in funds. Approximately the same number of licenses were
issued this year; however, the City's new fee structure took effect in 2018 with the per employee fee
(instead of RGRL).
• Building permits: A half million over budget. The same number of permits were issued compared to
2017; however, the valuation of the permits significantly increased in 2018.
General Fund expenditures:
• The Unreserved Fund Balance in the General Fund increased from $11.9 million in 2017 to $13.3
million at the end of 2018.
• Contingency fund meets the City's reserve policy.
Capital Projects Funds
Public Safety Plan:
• LTGO bonds were Issued for the Public Works Shop Facility.
• $17.6M in expenditures related to land and buildings for the Justice Center.
• $3.2 million in expenditures for fire equipment (ladder truck and two pumper trucks).
Residential Streets: Decline in fund balance as a result of spending the previous year's bond proceeds,
with planned work on 42nd Ave. S. and 53rd Ave. S.
Enterprise Funds
All Enterprise Funds met the City's reserve fund balance policy. Water and Sewer Fund balances
increased. There was a slight decline in the Sewer Fund balance. The Golf Course maintained its end
fund balance.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019 Page 11 of 12
Internal Service Funds
Equipment Rental: All planned purchases will be funded.
Employee Self -Insurance Fund is healthy. The fund balance was down from 2017 due to changes made
to reduce plan overfunding and achieve balance between annual premium charges and maintenance of
reserve levels.
The Councilmembers asked follow-up questions on the various funds discussed.
REPORTS
a. Mayor
Mayor Ekberg noted work that has taken place at the Namaste Garden behind Foster High School.
David Cline and other City staff worked to improve accessibility to disabled individuals wanting to use the
garden. He also noted the Seattle Seawolves will play to defend their rugby championship on June 16,
2019 in San Diego.
b. City Council
Councilmember Seal attended the K4C (King County -Cities Climate Collaboration) work session on
June 10, 2019, where recent actions of the State legislature were reviewed. She noted that King County
Executive Dow Constantine stated that while a lot of the progress made in recent years is being rolled
back, actions taken at the local level can still drive change. Values around climate should continue to be
discussed in relation to the City's Comprehensive Plan, zoning decisions, etc. She also noted that the
Tukwila Library Advisory Board meeting scheduled for June 11 has been cancelled.
Councilmember Quinn stated he will provide more information at a later date relating to a transformative
decision made by the Washington State Criminal Justice Training Commission. The State Attorney
General, prosecution, and law enforcement came together on this rule -making accomplishment.
Councilmember Kruller stated she attended a spring concert featuring students from fifth grade through
high school. She noted that studies have shown the importance musical education can have on multiple
skills. There will be a "See You in the Park" event on June 12, 2019 at Cascade View Park. She also
issued an advisory for citizens to prepare for the hot weather predicted for this week. The Seattle
Seawolves won their quarter finals game 30-17. The Tukwila Pride festival will take place in the vicinity
of Friendz Cafe, and is one more way Tukwila is working to be an inclusive city.
Councilmember McLeod stated the Finance Committee had a robust discussion on funding for Fire
Station 52 earlier this evening. Discussion will continue on this issue as it relates to Fire Department
service levels.
Councilmember Idan stated that he received phone calls from citizens related to 53rd Avenue South
questioning why only two speed bumps were installed, and also that with cars parking on the street there
is not enough room for vehicles to pass through.
Council President Hougardy attended the Equity and Social Justice Commission on June 6, 2019, where
there was discussion about the City's appointment process for Boards and Commissions. The group is
planning outreach on vacant Board and Commission positions, including with community -based
organizations, the faith community, and at the City's "See You in the Park" events. She reminded Council
to be aware of what openings are available for potential discussion with residents. Another suggestion of
the Equity and Social Justice Commission was to review King County's application for Boards and
Commissions, and to make citizens aware of the Community Leadership Institute through Puget Sound
Sage. The program is an opportunity to help residents become more interested in being involved in City
business.
Tukwila City Council Committee of the Whole Minutes
June 10, 2019
Page 12 of 12
c. Staff
There was no report.
d. Council Analyst
The Council Analyst was not present.
ADJOURNMENT
9:48 p.m. COUNCIL PRESIDENT HOUGARDY DECLARED THE COMMITTEE OF THE WHOLE
MEETING ADJOURNED.
Barbara Saxto , Aci
inistrative Support Coordinator
APPROVED BY THE COUNCIL PRESIDENT: 6/24/19
AVAILABLE ON THE CITY WEBSITE: 6/25/19