HomeMy WebLinkAboutReg 2019-07-15 Item 6E - Report - Public Safety Plan: Program Management Quality Assurance Monthly ReportJuly 9, 2019 TO: Tukwila City Council FROM: Steve Goldblatt PMQA Consultant RE: Public Safety Plan July update Fire Station 51 and Justice Center construction activities continue. Station 52's early works will soon be underway. Programming and master planning of the consolidated shops facili- ties nears completion. Boldfaced entries below are updated from last month's report. FIRE STATIONS Site acquisition The City owns the property planned for deferred Fire Station 54, and its use or disposi- tion will be a future Council decision. Lydig demolished the property's structures. De- ferred Station 54 lot consolidation is close to completion. Station 51 construction Lydig's MACC (Maximum Allowable Construction Cost) amendment was approved by Council 25 March. The Council -approved budget is $14.8 million. To follow construc- tion progress, see SOJ's Construction Management Monthly Report in the Council's first regular meeting packet each month. Absent an unexpected event, no further Council action is anticipated until project completion and acceptance next summer. Station 52 pre -construction services and mini-MACC Drive -through Station 52's revised budget of $23.49 million will be presented for Council approval 15 July. Council consensus was reached at COW 24 June over proposed sources to fund Station 52's $4.23 million increase. Lydig's $8.1 million mini-MACC contract amendment —including sales tax and contingency —to begin earthwork, site utilities, and structures was presented to Public Safety 1 July and for- warded for Council discussion and consideration 15 July. The final MACC amend- ment will follow in October/November to approve the full scope of construction. The City has agreed to timely permitting; approval is expected to enable early works as scheduled. Station 54 assessment Last year, Council asked for an estimate to make life safety improvements to existing Station 54. Staff presented four potential options —with very rough order of magnitude cost estimates —to Public Safety 5 November; see Rachel Bianchi's 30 October memo for details. Committee consensus was to revisit the options after Station 51 and Justice Center construction costs firm up. The Committee agreed that the existing station needs modest maintenance and repairs for the health of firefighters there. City staff is compiling costs for presentation to Public Safety this summer. The Fire Dept. is prepar- ing a grant application for funding. 199 FIRE STATIONS continued Stations' budget Including Station 51's and Station 52's budget growth and Station 54's substantially re- duced scope, the stations' overall revised budget of $39.83 million will be presented for Council approval 15 July. Council consensus was reached at COW 24 June over proposed sources to fund Station 52's $4.23 million increase. JUSTICE CENTER Full MACC and construction The MACC amendment to authorize BNB's full scope of work was approved by Council 3 June. The Council -approved budget is $67 million. To follow construction progress, see SOJ's Construction Management Monthly Report in the Council's first regular meet- ing packet each month. Absent an unexpected event, no further Council action is antici- pated until project completion and acceptance fall 2020. DISADVANTAGED BUSINESS ENTERPRISE AND LOCAL HIRING Council policies The Council unanimously passed Resolution 1929 April 2018, adopting DBE and local hiring policies for the Plan's projects. The DBE goal is 17% and the local hiring goal is 20%, complementing the City's 10% apprenticeship requirement of Resolution 1814. Extensive outreach efforts continue with the DBE community in this very competitive market. The first metrics that the Council sees can be expected this month. Council is receiving regular updates. Fire Station 51 Lydig has over $1 million of DBE subcontracting in process. Justice Center BNB has over $2 million of DBE subcontracting in process. CONSOLIDATED SHOPS Property acquisition The City has agreements with all three property owners. Lot consolidation on two properties is underway. Ownership of the third property will transfer in 4+ years. Programming and master planning services Having worked closely with Public Works staff, SHKS is incorporating their feedback to two test -fit master plan options. Council can expect a master plan and phasing pro- posal to be ready for Public Safety and COW next month. Renovation contracting The project team is reviewing contracting options for an initial scope of renovation work on existing facilities. PMQA update July 9, 2019 page 2 200 OTHER RESOURCES Professional services The project teams have been working through procurement of additional consultant resources for the Fire Stations and Justice Center. PROGRAM SCHEDULE Tight schedule The overall schedule remains very ambitious. With so many activities under way, there is little room for any missteps to meet the Plan's revised milestones. Fire Station 51 and Justice Center construction activities are underway. Fire Station 52 is on a tight schedule to begin its extensive earthwork this month. PROGRAM BUDGET Market conditions All program element budgets are sensitive to tight construction market conditions. These external budget pressures will continue to manifest themselves as Fire Station 52 and future consolidated shops project costs are refined. LEGEND Meeting target Proceeding as planned. Caution advised Steps needed to meet target. PMQA update Correction needed Steps needed to attempt recovery. Not meeting target No recovery plan in place. July 9, 2019 page 3 201