HomeMy WebLinkAboutTIC 2019-10-08 Item 2F - Public Safety Plan - Master Plan Next Steps for Public Works Shops Phase ICity of Tukwila
Public Works Department - Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Henry Hash, Public Works Director
BY: Hari Ponnekanti, City Engineer
CC: Mayor Allan Ekberg
DATE: October 4, 2019
SUBJECT: Public Safety Plan — Public Works Shops First Phase
Project No. 91630601
Master Plan Next Steps
Allan Ekberg, Mayor
ISSUE
Update on the Public Works Shops Master Plan and seek approval for financing the improvements to the Heiser property.
BACKGROUND
The City hired SHKS Architects to conduct a Master Planning and Programming effort for the City's Public Works
Maintenance Shops facilities in September 2018. SHKS conducted several meetings with PW staff, visited the existing
facilities, toured similar PW facilities in the region and developed a Master Planning and Programming Report. Several
options were discussed and the selected Master Plan option and the proposed tenant improvements to the Heiser site
are the most practical and least expensive option.
The completion of improvements will enable the City to move the George Long operations to the Heiser site. The current
George Long building lacks sufficient spacing for routine maintenance and is also the most seismically deficient City
building. The new site will be much safer for our employees and provides more space, therefore increasing operation
efficiency. In addition, some of the equipment from Minkler Shops can also be moved to Heiser, allowing more space at
Minkler Shops for maneuverability and productivity.
ANALYSIS
The findings from the Public Works Shops Master Plan are summarized in the attached PowerPoint presentation. The
City took possession of the two Heiser properties in July 2019 and will take possession of the UPS site in 2023.
Master Plan Summary
• The Master Plan envisions the redevelopment of over 13 acres of land, which will serve the Public Works
Department into the future with planned growth through the year 2045.
• The Master Plan comprises roughly 66,000 sf of interior program space, roughly 58,000 sf of exterior program
space, parking for 285 vehicles, and facilities for 67 employees.
• The Public Works Shops First Phase of the Master Plan focuses on relocating the PW Fleet Maintenance and
Facilities divisions from George Long Shops to the Heiser property after seismic retrofitting and upgrades. The
First Phase will also include moving the Police vehicle evidence storage and spoils from the Longacres site.
• The Public Works Final Phase will include the entire buildout of the Heiser and UPS sites.
Next Steps
Approval of $4.4 million for funding the PW Shops First Phase (to move forward with Heiser improvements)
• Demolition of two outbuildings at the Heiser site. Oct/Nov 2019
• Design of seismic retrofitting, and interior and exterior improvements. Upgrades to HVAC, mechanical,
electrical, and storm drainage. Nov 2019 — April 2020
• Advertise and award seismic retrofitting and improvements. April 2020
• Project completion. December 2020
37
W:1PW Eng1PROJECTS1A- BG Projects101 Public Safety Plan1PW Shops First PhasedukoMernontes 100419 docx
Informational Memo
Page 2
A Possession of UPS site in 2023. Staff will return to Council for further direction.
FINANCIAL IMPACT
Expenditures 2019 Budget Budget Request
Land Purchases $ 25,334,123.00 $ 30,000,000.00
Contracts & Demolition 883,221.88
PW Shops First Phase
General Fund $ 2,200,000.00
Utilities 2,200,000.00
Total $ 26,217,344.88 $ 30,000,000.00
Budget Balance $ 3,782,655.12
$ 4,400,000.00
SHKS estimates that the PW Shops First Phase's costs will be $5.8 million and soft costs at $2.4 million, for an
estimated total project cost of $8.2 million. Project soft costs include design fees, construction management fees,
construction contingency, and sales tax.
The 2019 CIP's PW Shops budget is $30 million and to date $26,217,344,88 is estimated to be spent, which leaves a
balance of $3.783 million. To complete the PW Shops First Phase at an estimated cost of $8.2 million, additional funding
of $4.4 million is needed.
Both Water and Sewer Utilities appear to have sufficient unreserved fund balance to absorb the additional costs, further
analysis is needed to determine if the Surface Water utility can absorb the additional costs within the current rate model.
FINANCING PLAN
To fund the gap of $2.2 million in the General fund, funds can come from two sources. A transfer of $1 million from the
general fund to the arterial street fund is currently budgeted in 2020. Because there is currently a healthy fund balance
due to impact fees exceeding budget, the budgeted transfer can be redirected to the PW Shops project fund.
Additionally, the 2020 general fund budget has a budgeted surplus of $1.4 million and could be utilized to fund the
remaining request of $1.2 million.
Staff will walk through the entire financing plan at the meeting on October 8, 2019,
RECOMMENDATION
Council is being asked to approve project funding of $8.2 million for the Public Works Shops First Phase and allow staff
to move forward with the negotiation of the design contract of the Heiser improvements and to consider this item at
October 14, 2019 Committee of the Whole.
attachments: PW Shops Master Plan PowerPoint
Link to PW Shops Master Plan httns://shksarchitects.sharefile,cninjd-cC633ROP59a6467c8
38
W:IPW Eng1PROJECTS1A- BG Projects101 Pubic Safety PlantPW Shops First Phasehttlemorrasturplanupdo*HP 100419 docx
TUKWILA PUBLIC WORKS FACILITY
SHKSARCHITECTS H I T E C T S
39
TUKWILA PUBLIC WORKS FACILITY: WHATWE HAVE DONE
• KICKOFF MEETINGS AND GOALS EXERCISE
• SITE VISITS OF EXISTING FACILITIES
• 2-3 ROUNDS OF INTERVIEWS
• JOB SHADOW OF OPERATIONS
• TOURS OF LOCAL PUBLIC WORKS FACILITIES
• ALL -HANDS MEETING PRESENTED (2) TEST - TO - FIT OPTIONS
• SHARED FINALIZED MASTER PLANNING OPTION AT ALL -HANDS MEETING
•
III
00 0)
bb
N CN
II
1
PROGRAM NEEDS ASSESSEMNT /
GOAL SETTING
•
II .1 I .1 • I • I
MASTER PLAN
DEVELOPMENT
•
STAFF INTERVIEWS
• TEAM MEETINGS
• SITE VISITS
• ALL - HANDS MEETING
• PUBLICWORKSTOURS
• COUNCIL MEETING
CY) o
= N
O 0
N N
• • •
NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2020
SHKSARCHITECTS
2
TUKWILA PUBLIC WORKS FACILITY: EXISTING PROGRAM
MINKLER 64'
Street, Water, Sewer, Surface Water o' 32'
FLEET MAINTENANCE
ADMIN + SHOPS
GEORGE LONG
Facilities, Fleet Maintenance
COVERED STORAGE FLEET PARKING
UNCOVERED STORAGE FLEET MAINTENANCE PARKING
SPOILS fb STAFF PARKING
50'
100' 0
LONG ACRES
Spoils
0' 100'
200'
0
SHKSARCHITECTS
3
41
TUKWILA PUBLIC WORKS FACILITY: CURRENT FACILITIES
GEORGE LONG
MINKLER
SHKSARCHITECTS
4
42
TUKWILA PUBLIC WORKS FACILITY: NEW SITES
HEISER
HEISER -OPEN SHOPS
SER -OPEN SHOPS
SHKSARCHITECTS
5
43
TUKWILA PUBLIC WORKS FACILITY: EXISTING VS 2045 PROJECTED PROGRAM AREAS
FLEET MAINTENANCE
ADMIN + SHOPS
STAFF/VISITOR PARKING
10,760 SF
20,195 SF
22,150 SF
41,650 SF
14,050 SF
12,910 SF
COVERED FLEET PARKING 3,860 SF
29,310 SF
DECANT + BRINE
WASH RACK
SPOILS
BULK BINS
COVERED STORAGE
UNCOVERED STORAGE
POLICE IMPOUND
SHKSARCHITECTS
0 SF
4,750 SF
0 SF
1,900 SF
13,260 SF
15,600 SF
3,500 SF
6,000 SF
3,620 SF
5,300 SF
12,630 SF
14,000 SF
6,250 SF
6,250 SF
EXISTING
NEW
REGIONAL PUBLIC WORKS PROGRAM SIZES
300 - 600 SQUARE FEET PER PERSON*
TUKWILA PUBLIC WORKS PROGRAM
560 SQUARE FEET PER PERSON
*RANGE OF PROGRAM SIZES DUE TO VARYING
PROGRAM REQUIREMENTS
6
TUKWILA PUBLIC WORKS FACILITY: GUIDING PRINCIPLES FROM GOAL SETTING
SAFE
The facility provides a safe environment for workers and visitors and
improves employee health and wellness.
FUNCTIONAL
The facility housesa collaborative Public Works Department with the
capacity and flexibility to support the operations of tomorrow efficiently and
effectively.
FORWARD LOOKING
The facility conveys the Department's values to its customers and
employees. It supports a long-term investment strategy to raise existing
facility standards and plans for technological advancements that improve
service to the public.
STEWARDS OF THE ENVIRONMENT
The facility will exemplify environmental and regulatory standards for a
sustainable future. It promotes human and environmental health.
SHKSARCHITECTS
7
TUKWILA PUBLIC WORKS FACILITY: MASTER PLAN
/
/
/
/
SOUTH 112TH ST
UNCOVORD
STOR-A►G
PROPERTY LINE
PROPOSED WETLAND BY KING"OUNTY
ADMIN +VISITOR
PARKING
PROGRAM LEGEND
U ADMIN + SHOPS
• FLEET MAINTENANCE
FLEET MAINTENANCE PARKING
INTERIOR FLEET PARKING
COVERED FLEET PARKING
UNCOVERED FLEET PARKING
DECANT + BRINE
SPOILS
▪ COVERED STORAGE
BULK BINS
UNCOVERED STORAGE
ESTIMATED COSTS
CONSTRUCTION COSTS:
S53,000,00
SOFT COSTS:
S21 ,200,000
TOTAL PROJECT COST:
S74,200,000
SHKSARCHITECTS
8
TUKWILA PUBLIC WORKS FACILITY: NEXT STEPS
TENANT IMPROVEMENTAND SPOILS STORAGE
SOUTH 112TH ST
L
HEISER BUILDING
PROPERTY LINE
POLICE
IMPOUND
UNCOVERED
STORAGE
UNCOVER°ED
STORAG
N
r dommb
SITE VEHICLE ACCESS
BUILDING VEHICLE ACCESS
STAFF PARKING
FLEET PARKING
SPOILS
UNCOVERED STORAGE
FLEET MAINTENANCE PARKING
SITE REGRADING
SECURITY FENCING
SHKSARCHITECTS
9
TUKWILA PUBLIC WORKS FACILITY:TENANT IMPROVEMENT TEST -TO -FIT
VEHICLE ACCESS
FLEET MAINTENANCE
OFFICE + SUPPORT
FACILITIES SHOPS
FACILITIES STORAGE
SPOILS/ORGANICS
FLEX/OVERNIGHT PARKING
SHKSARCHITECTS
TUKWILA PUBLIC WORKS FACILITY: NEXT STEPS
EXAMPLES OF COMPLETED FACILITIES
OFFICE SPACE
LOCKER ROOM
SHKSARCHITECTS
49
TUKWILA PUBLIC WORKS FACILITY: NEXT STEPS COST SUMMARY
ESTIMATED CONSTRUCTION COST - $5,800,000
ESTIMATED SOFT COSTS - $2,400,000
THESE COSTS ARE TYPICALLY PAID FOR BY THE OWNER AND ARE IN ADDITION TO THE
CONTRACTOR'S COSTS. THESE COSTS INCLUDE:
• A/E FEES- ARCHITECT AND CONSULTANTS UNDER THE ARCHITECT'S CONTRACT. (11.5%)
• ENGINEERING FEES AND STUDIES - OTHER PROJECT SPECIFIC CONSULTANTS NOT UNDER THE
ARCHITECT'S CONTRACT (EX: ENVIRONMENTAL IMPACT, GEOTECH, SURVEY, LOCATION WORK, ETC). (35%)
• PERMITS AND FEES- INCLUDES MUP, BUILDING PERMITS, FIRE DEPARTMENT REVIEW, ETC. (2%)
• COMMISSIONING- THIRD PARTY SYSTEM COMMISSIONING. (1%)
• WA STATE SALES TAX. (1O%)
• FURNITURE, FIXTURES AND EQUIPMENT ALLOWANCE. (1.5%)
• OWNER'S CONTINGENCY. (1O%)
ESTIMATED TOTAL PROJECT COST - $8,200,000
NOTE: CONSTRUCTION COSTS AND SOFT COSTS WILL BE MORE ACCURATE ONCE DESIGN PROGRESSES
SHKSARCHITECTS
P
TUKWILA PUBLIC WORKS FACILITY
QUESTIONS?