HomeMy WebLinkAboutTIC 2020-02-03 Item 2B - Final Acceptance - 2019 Overlay and Repair with Tucci and SonsCity of Tukwila Allan Ekberg, Mayor
Public Works Department - Henry Hash, Director
INFORMATIONAL MEMORANDUM
TO: Transportation and Infrastructure Committee
FROM: Henry Hash, Public Works Director
BY: Scott Bates, Traffic Engineering Project Manager
CC: Mayor Ekberg
DATE: January 31, 2020
SUBJECT: 2019 Overlay and Repair Project
Project No. 91910401, Contract No. 19-087
Project Completion and Acceptance
ISSUE
Accept contract as complete and authorize release of performance bond.
BACKGROUND
The Notice to Proceed for Contract No. 19-087 with Tucci and Sons, Inc. of Tacoma, Washington was
issued on June 24, 2019 for the 2019 Overlay and Repair Project. This overlay project provided hot mix
asphalt (HMA) paving at seven locations throughout the City, a portion of the parking lot at Fort Dent
Park and pavement repairs for the Andover Park East water main break. The street improvements
included: pavement grinding; asphalt paving; removing and replacing concrete curbs, gutters, sidewalks
and ADA ramps; adjusting surface utilities to grade; and installing roadway channelization.
ANALYSIS
Construction was physically completed on November 20, 2019. Two change orders were executed for a
total of $10,390.00. The budget for the 2019 Overlay & Repair construction was $1,351,102.72 and
included a 5% contingency, which was not utilized. Under -runs were primarily due to fewer quantities
needed during the roadway excavation, haul and repair phase of the project.
Construction Contract Amount $ 1,286,764.50
Additions/Change Orders 10,390.00
Under -runs (73,355.07)
Total Amount Paid $ 1,223,799.43
RECOMMENDATION
Council is being asked to formally accept and authorize the release of the performance bond, subject to
standard claim and lien release procedures, for the 2019 Overlay and Repair Project construction
contract with Tucci and Sons in the final amount of $1,223,799.43, and consider this item on the Consent
Agenda at the February 24, 2020 Special Meeting.
ATTACHMENT
Notice of Completion Contract No. 19-087
W:1PW Eng\PROJECTSIA- RW & RS Projecls'Annual Overlay 8 Repair Programs12019 Overlay & Repair Program(91910401)IConstruclionlContraclorlClose Out to TClln(o memo 2019 Overlay Closeout 120119.docx
13
BTATg
D bFp e p
.] S
6
s
may.
�N'� fRH9
Original
❑ Revised #
NOTICE OF COMPLETION OF PUBLIC WORKS CONTRACT
Date: 12-2-2019 Contractor's UBI Number: 278021315
Name & Mailing Address of Public Agency Department Use Only
City of Tukwila Assigned to:
6200 Southcenter Blvd Tukwila. WA 98188
Date Assigned:
UBI Number: 91-6001519
Notice is hereby given relative to the completion of contract or project described below
Project Name
Contract Number
Job Order Contracting
2019 Annual Overlay & Repair Program 91910401
119-087
❑ Yes VNo
Description of Work Done/Include Jobsite Address(es)
Hot Mix Asphalt (HMA) Overlay at seven sites all within the City of Tukwila
Federally funded transportation project? ❑ Yes V No (if yes, provide Contract Bond Statement below)
Contractor's Name
E-mail Address
Affidavit ID*
Tucci and Sons
kld@tucciandsons.com
1984252 (intent only)
Contractor Address
Telephone #
4224 Waller Rd Tacoma, WA 98443
253-922-6676
If Retainage is not withheld, please select one of the following and List Surety's Name & Bond Number.
VRetainage Bond ❑ Contract/Payment bond (valid for federally funded transportation projects)
Name: Travelers Casualty and Surety of America
jBond Number: 107055298
Date Contract Awarded
Date Work Commenced
Date Work Completed
Date Work Accepted
4-25-2019
6-17-2019
10-3-2019
Were Subcontracters used on this project? If so, please complete Addendum A. Wyes ❑ No
Affidavit ID* - No L&I release will be granted until all affidavits are listed.
Contract Amount
Additions ( + )
Reductions (- )
Sub -Total
Sales Tax Rate n/a Rulel-t
(If various rates apply, please send a breakdown)
Sales Tax Amount
$ 1,286,764.50
$ 10,390.00
$ 73,355.07
$ 1,223,799.43
TOTAL $ 1,223,799.43
LVVip-: inese two totals must oe
Comments:
Rule 171, sales tax included.
Liquidated Damages $ 0.00
Amount Disbursed $ 1,223,799.43
Amount Retained $ 0.00
TOTAL $ 1,223,799.43
Note: The Disbursing Officer must submit this completed notice immediately after acceptance of the work done under this contract.
NO PAYMENT SHALL BE MADE FROM RETAINED FUNDS until receipt of all release certificates.
Submitting Form: Please submit the completed form by email to all three agencies below.
Contact Name: Scott Bates
Email Address: Scott. Bates@tukwilawa.gov
Department of Revenue
Wasb1op n Stame Departmern of
Works Section
Labor & Industries
CPublic
(360) 704-5650
Contract Release
PWC@dor.wa.gov
(855) 545-8163, option # 4
ContractRelease@LN I. W A. GOV
REV 31 0020e(10/26/15) F215-038-000 10-2014
Title: Program Manager
Phone Number: 206431-2193
Employment Security
Department
Registration, Inquiry,
Standards & Coordination
Unit
(360)902-9450
publ icworks@esd.y 3.90v
Addendum A: Please List all Subcontractors and Sub -tiers Below
This addendum can be submitted in other formats.
Provide known affidavits at this time. No L&I release will be granted until all affidavits are listed.
Subcontractor's Name:
UBI Number: (Required)
Affidavit ID*
Able Industries
603542604
884125
Blackline Inc
601000623
890793
C&E transport corp
602408510
884223
Carli Trucking by Looker LLC
604280337
884025
Evergreen Concrete cutting
601605667
894249
G&G Corp
601381635
Janke Trucking
602862253
885312
Krupp LLC
602889069
888086
Moby's Sweeping
603358194
894042
Mowatt incorporated
603210502
884860
Northwest traffic
602140049
O'Bunco Engineering
602045762
897085
Pac-West Grinding
603493970
893562
Strong Trucking inc
601777166
884706
Wilson Concrete Construction
602168956
For tax assistance or to request this document in an alternate format, please call 1-800-647-7706. Teletype (TTY) users may use the
Washington Relay Service by calling 711.
REV 31 0020e Addendum (10/26/15) F215-038-000 10-2014 15